BOND PROJECTS timeline
Picnic Tables 10/1/12 - 10/1/14
Palmer Hall HVAC 1/22/12 - 1/7/13
2012
Public Restrooms (ADA/curb appeal) 5/5/12 - 8/20/14
Valve Work Hanson and Tut 10/1/12 - 1/13/13
Roofiing (6 buildings) 5/5/12 - 8/16/13
Athletics Lighting 10/1/12 - 1/7/13
Doors 1/7/12 - 8/16/13
Brick streets and sidewalk repair 11/7/12 - 8/15/14
Peterson House 4/1/13 - 10/31/13 3D Art Complex 10/11/13 - 8/15/14
2013
Energy saving system software 7/1/12 - 10/3/12
Campus Lighting 10/1/14 - 8/31/15
2014
Ground floor library restrooms 2/11/13 - 6/15/13
Water Tank Maintenance 5/15/13 - 6/26/13
Irrigation Piping 5/12/14 - 8/15/14 Brooke Hall HVAC 5/12/14 - 8/15/14
Furniture for Res. Life (Tut, Brooke and Lund) 5/13/13 - 8/16/13 Napier Hall 5/5/12 - 8/15/12 ADA equipment (truck, desks, closures, lever knobs) 5/6/12 - 8/16/14 Harman Lab upgrade 5/6/12 - 8/12/12
Physical Plant foundation repair 12/7/12 - 3/30/13 Alabama Power building 1/7/13 - 8/16/13
Main Hall upgrades 5/6/13 - 8/16/13
Other aspects Technology Contingency (scope changes, project management, estimate variations) Deferred projects High voltage wiring replacement Wills Hall ceiling (one room only)