Active House in Vietnam

Page 1


WHO WE ARE PROJECT TEAM

Dragos Todoran (Romania) Kirill Orlov (Estonia) Gina Danes (Romania) Henry Pilk (Estonia) Kristina Kalnina (Latvia) Olimpiu Androne (Romania) Viktorija Acaite (Lithuania) Yoanna Shivarova (Bulgaria)

UCN DENMARK

Carl Redmond (England) Tutor UCN

Nguyen Thi Thanh Hang ECC-HCMC

Tran Nhan Hai University Architect of HCMC

Le Thi Ho Vi

VIETNAM

University Architect of HCMC

Ly Thi Thuy Huong Ecc-HCMC

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


BRIEF*


INTRODUCTION TO THE PROJECT Active building Energy defining architecture Low energy consumption

Production of it’s own energy A healthy and comfortable indoor environment An optimized relationship with the local context Requirements : 600m² to 800m² in 2 levels. FIRST ACTIVE HOUSE- “HOME FOR LIFE”, AARHUS DENMARK

The building must include teaching facilities and 2- 3 apartments for visiting lectureres / businessmen.

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SITE ANALYSIS

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SITE ANALYSIS_WIND SPEED

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SITE ANALYSIS_RELATIVE HUMIDITY

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


FIRST THOUGHTS BRAINSTORM COMPACT DESIGN

SHADE ANALYSIS SOLAR PATH WINDOWS WIND DIRECTION DAMP ANALYSIS COMFORT ANALYSIS SOUND AND FIRE ANALYSIS ALTERNATIVE ENERGY

COMFORTABLE SPACE FOR USERS ; ENVIRONMENTLY FRIENDLY BUILDING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


PROPOSAL_SCHEME OF FUNCTION

1ST LEVEL

2ND LEVEL

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


1ST LEVEL FURNISHING PLAN

CANTEEN OPEN ED FOR STUDENTS AND OTHER GUESTS

MOVABLE WALLS IN CLASSROOMS

FOOTPRINT OF 382 m2

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


2ND LEVEL FURNISHING PLAN

CLOSED AND QUIET APARTMENTS OPEN MEETING ROOM / LIBRARY

TOTAL AREA OF 764 m2

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


WHAT WE CAME UP WITH

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SHADING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


VISUALIZATION

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


VISUALIZATION

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


CONSTRUCTION*


COMPONENT ANALYSES - WALL U- value 0.11

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


COMPONENT ANALYSES - ROOF U- value 0.11

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


COMPONENT ANALYSES - FLOOR U- value 0.2

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


COMPONENT ANALYSES - WINDOW U- value 0.44

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


MOISTURE CALCULATIONS - WALL

Moisture staying in

Max RH in the construction

Moisture through the construction

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


MOISTURE CALCULATIONS – ROOF Steel roof Moisture staying in

Max RH in the construction

Moisture through the construction

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


MOISTURE CALCULATIONS - ROOF Steel roof with ventilation gap Moisture staying in

Max RH in the construction

Moisture through the construction

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


1ST LEVEL PLAN

CLASROOMS ARE DIVIDED BY MOVABLE WALLS SYSTEM WHICH ALOWDS TO INCREASE ROOM SIZE WHEN THERE ARE MORE STUDENTS TECHNICAL ROOM IS EXPOSED TO VISITORS BY A GLASS WALL

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


2ND LEVEL PLAN

THERE ARE OPENINGS WHICH ARE MADE IN ORDER TO GET NATURAL VENTILATION AND LIGHT WHICH REACHES THE 1ST LEVEL OF THE BUILDING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SECTION 1

WE HAVE RAISED PART OF THE BUILDING IN ORDER TO GET NATURAL VENTILATION AND LIGHT THROUGH BOTH LEVELS OF THE BUILDING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SECTION 2

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


DETAIL DRAWING - ROOF

THERE IS 500 MM OF OVERHANG TO CREATE SHADING ON THE FACADE 250 MM OF INSULATION IS USED TO KEEP THE COOL AIR INSIDE THE BUILDING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


DETAIL DRAWING – STORY PARTITION

WALL IS MADE WITH 250MM OF INSULATION TO STOP HEAT COMING INTO THE BUILDING

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


DETAIL DRAWING - WINDOW

THERE ARE USED TRIPLE GLAZED WINDOWS. SPACES BETWEEN GLASS LAYERS ARE FILED WITH CRYPTON GASS . GLASS PANEL EXTERIOR COATING IS MADE OF POWDER – LACQUERED ALUMINUM PLATING. U – VALUE FOR PANEL IS 0.44

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


DETAIL DRAWING - DOOR

SEALANTS ARE USED TO AVOID LINE LOSES

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


DETAIL DRAWING - FOUNDATION

INNER PANEL OF WALL IS LOADBEARING OUTER LAEF IS MADE FROM SPECIAL RENDERING WHICH DOESN’T CRACK DURING DRYING PROCESS AND THE FINAL FINISH IS LAYER OF PAINT

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


VENTILATION Fresh air needed Canteen 78m2 x 5.6 ls/m2= 436.8 l/s 1572m3/h Class rooms 135m2 x 4.21 ls/m2= 567 l/s= 2041m3/h Rooms 51m2 x 3.5 ls/m2= 1785 l/s= 642 m3/h Offices 32 m2 x 1.41 ls/m2= 5.2 l/s= 18.6 m3/h Hall ways= 125 m3 x 3 ls/m2= 375 l/s= 1350m3/h Total of fresh air needed= 5623m3/h Second proposal Canteen 78m2 x 4 ls/m2= 436.8 l/s 1123m3/h Hall ways= 125 m3 x 1.5 ls/m2= 375 l/s= 700m3/h Total of fresh air needed= 4524m3/h Extraction needed Bathrooms 11x15 l/s=165 Kitchen 40 l/s Storage 20 l/s Total 225 l/s=810 m3/h

Need for cooling- classes 70 people – 700w 70 pc – 4200w Light – 1350w Total = 12550W =>572m3/h Actual ventilation =680 m3/h- Comfort class B

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


KEY NUMBERS (Be 10)

The Be10 calculation program gives us the overview on the buildings energy consumption during the design phase. When looking at these results we have to take into consideration that there is no input data that has the climatic details of Ho Chi Minh City. Therefore we have used the climatic details of Hanoi. The program will continue to improve in the future, but we can say for sure that it is an ACTIVE HOUSE. If we had more data, this would have been clearly seen.

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


SOLAR CELLS

Solar Cells Chosen company – Kyocera Solar Weight of Cell – 25kg Dimensions – 1600 x 1270mm Maximum power of one chosen cell - 0.315 kWh Slope of the Roof – 2 degree Slope of the Cells – 10 degree Orientation – South Approximate average amount of kWh for house (light, appliances and etc.) – 6 kWh – 12h Approximate amount of kWh for ventilation – 9 kWh – 12h 15 kWh / 0.315 = 47, 62 ~ 48 panels should be placed on the roof.

PROJECT WEEK IN VIETNAM, HO CHI MINH CITY, 2012


CONCLUSION* • • • • • • •

KEY PRINCIPLES OF ACTIVE HOUSE: INTEGRATION OF ENERGY USAGE, CLIMATE & DEMANDS FOR COMFORT WHICH MAKES IT SUSTAINABLE AND USES MODERN TECHNOLOGY USES SOURCES FOR ALTERNATIVE ENERGY (GEOTHERMAL; SOLAR) COMPACT DESIGN TAKES ADVANTAGES OF THE ENVIRONMENT AND TERRAIN (WIND; GROUND; VEGETATION) ENERGY PERFORMANCE, CONCUMPTION AND SUPPLY IS IMPORTANT ISSUE THE BEST SOLUTION FOR THE SPECIFIC CONTEXT DAYLIGHT & THERMAL CONDITIONS ARE FACTORS WHICH EFFECTS THE WELLBEING AND ABILITY TO PERFORM

ACTIVE HOUSE IS NEAR FUTURE IN ALL OVER THE WORLD. CULTURAL THINKING AND TRADITIONS NEED TO BE PUSHED A SIDE TO MAKE THE IDEA AND THE TECHNOLOGY DEVELOPMENT FASTER.


THANK YOU!!