Logbook wk07

Page 1

Week 07 Summary Gasket

Water in gutter downpipes and storm water system

Sealant

Sloping window and door sills and roof flashing

Grading roofs

Remove opening

An opening

Keep water away Sloping ground

A force to move wate in Sloping surface for drainage

Moisture

Neutralize the forces

Water presents

Gravity

Overlapping cladding and roofing element

Weatherboard

Tiles

Double cavity wall

Momentum Air pressure differentia An air barrier on internal side of ventilation drainage

Surface tension and capillary action

Drip or break

Flashing

Eaves gutters

- Previous surface - Double skin wall - Rain screen system

Parapet wall Waterproof membrane, artificial rubber

Drain


Summary 第 # 期:[日期]

折页册 Thermal insulation

Double glazing with air space

Thermal breaks

An opening

Heat in conducted through building envelope

Building envelope and elements are subjecte to radian heat

Reflective surface

Material property Type

Shading system

Air present at opening

Controlling air leakage

Heat

A force to move air through the opening

Masonry

Thermal mass used to regulate the flow of heat through bulidng envelope

Rubber Natural rubber • Rubber tree • Seals • Gaskets and control joints • Flooring • Insulation • Hosing and piping

Concrete Water bodies

Plastic Themoplastics • Mouldable when heated and become solid again • Can be recycled • PVC, polythelyne Thermosetting platic • Can only be moulded once • Cannot be recycled • Polystrene – insulation

Hardness

Sythesized rubber • Laboratory • Plastic • EPDM • Neoprene • Silicone Varied

Fragility

Low

Low – medium

Ductility

Varied

High

Flexcibility

High

High

Permeability

Waterproof

Waterproof

Density

1.5 X water

Low

Conductivity

Poor

Very poor

Durability

High

Varied

Reusability

High

Sustainability

Varied

Thermoplastics – high Thermosetting plastics – limited Varied

Cost

Effective

Effective

Damage

Exposed to weather

Exposed to weather, expansion or contraction

Elastomers • Rubber Medium – low

2


Studio Report (Off Cmapus) 第 # 期:[日期]

折页册

The first site we visited is currently under early construction, part of the soils are still in digging process. However there are shotcrete walls could be seen, Shotcrete is concrete conveyed through a hose and pneumatically projected at high velocity onto a surface, as a construction technique (Wikipedia, http://en.wikipedia.org/wiki/Shotcrete) The shotcrete wall on site is about 10-12 storeys high. There is also a precast concrete retaining wall and some reinforcements cages on site.

Shotcrete wall

Reinforcement cages Used to increase the strength of concrete, might be used as water tank or piles.

Bar Guards Yellow plastic end caps used as a protective device for reinforcing bar.

The major site we visited on Friday was the Royal Melbourne Hospital; we walked under the bridge which will be linking the Victorian Comprehensive Cancer Centre (which is under construction as well) and the site. Since under the protocol we weren’t allowed to take photos on site, I only took one picture of the bridge from outside, standing on the street. The budge of this building is around 100milion to 120 million overall, and the VCCC is one 1billion big project cross the street. 3


第 # 期:[日期] Studio Report (Off Cmapus)

折页册

On the street level of the hospital, we went into a nearly done courtyard area; we were told that there is 26 in situ piles support the structure. Precast concrete panel could be found on site due to its well-manufactured technologies. Moreover, one existing wall is built by bricks, weep hole could be identified on the brick wall, as the building might contain a lot moisture, it’s really important that the structure to be waterproofed and allow spare moisture to move out and evaporate.

Sketches are coming up.

We then access the site through the Private Hospital and went to the 4th floor, followed the original path to the site, we firstly saw the new roof which is going to be lower than the original one.

We also notice that the girders above the head were sprayed by concrete but the joist weren’t, which means that secondary member doesn’t need to be protected.

As we went higher, steel strut as the framing of the wall which separates each room could be seen, also, like timber framing, noggins made of steel were also holding spacing between each strut. In addition, most steel on site is cold-formed steel with a shape of PFC.

Some wards have foam core panels, due to it’s ability of absorb the sound and create the quiet atmosphere in the hospital.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.