9 minute read

PRECAST FACILITATES SHOPPING MALL OVER BUSY RAILWAY LINE

Precast concrete accounts for the major portion of the building materials used in the construction of a shopping mall directly above a 390m section of the KwaZulu-Natal South Coast railway line at Isipingo Station.

Built for Prasa and spanning 20 520m² over two floors (excluding the ramps and existing building), the new building is being erected on either side of and integrated with the existing Isipingo station building, which – in turn – is being modernised and upgraded. The new building comprises two floors, the first to be used for retail space and the level above for parking.

The precast portion of the mall structure, designed by specialist precast concrete contractor Bedrock Group, is being built using precast columns, beams and hollow-core slabs, as well as precast parapet walling for the upper floor.

Unimpeded traffic A major proviso for the construction of the mall was that the line remain open to normal rail traffic during construction. Insitu construction, which involves shuttering and propping, would obviously not have worked and therefore precast concrete proved the only viable building option.

All 141 columns were produced on site and were cast with corbels for beam support. However, a variation order was issued after the first 121 units had been cast, changing the building from a threeto a two-storey structure. This meant the existing columns had to be shortened from 22m to 17m.

Depending on the width of the flooring, the columns were placed in rows of either two, three or four abreast. Cast with starter bars flanking a column foot of 340mm x 600mm x 1 400mm, they were lowered onto structural blindings

PRECAST FACILITATES SHOPPING MALL OVER

of various sizes, cast over pile caps, propped with braces and adjusted into a vertical position with shims. After additional reinforcing was installed, concrete was poured around the base of the columns. The braces were removed after 14 days once the concrete had cured sufficiently.

(Above): A beam supports hollow-core slabs prior to the casting of the structural topping.

(Below): A partially completed section of the mall.

Heavy beams Of the 211 beams used on this project, 132 measured 3-9m and were cast at Bedrock’s production yard in Westmead. Up to 15m long, the remaining 79 beams were cast on site.

The beams were placed between the columns to support the 10m prestressed hollow-core slabs, which were

(Top): A beam is about to be lifted by the 460-tonne mobile crane prior to placement between the western abutment and the central pier.

(Above): Concrete pouring of the pavement.

(Left): The central diaphragm’s reinforcing prior to the pouring of concrete. The Y40s can be seen protruding from the ends of the beams in a knitting formation.

(Right): The completed bridge.

PRECAST FACILITATES SHOPPING MALL OVER BUSY RAILWAY LINE

supplied by Echo Prestress. The beams were lowered onto the column corbels by mobile crane and were “stitched” across the columns. The reinforcing involved straddling the beams and the columns with Y32 bars.

The beams were “stitched” together around the internal columns before the 60mm structural topping was poured. The 15m beams in the two-span configuration were partially stressed, in addition to some supplemental non-pre-stressed reinforcing. This offered a better solution and simplified the reinforcement and redistribution of stresses, as well as improving deflection and crack control. It was important to keep deflection to a minimum, as some of the beams were close to the railway’s overhead highvoltage cabling.

Monolithic structure Using the same concrete mix for the structural topping and the “stitching” created a seamless monolithic structure between the columns, beams and flooring. Due to the railway line being used during the day, much of the initial placement of precast elements had to be done at night during line shut-downs. But once the first-floor slab had been installed, lifting could continue during the day because the lines were protected.

“Moreover, hollow-core slab flooring was the only option for this project,” says David Kitching, general manager of the Bedrock Group, “because it doesn’t require propping or shuttering, which wouldn’t have been possible while the line was operational.”

The precast parapet walling was cast on site by Bedrock in sections up to 15,6m long and 1 510mm high. It was attached to column corbels with steel brackets and braced with in-situ stub columns cast onto the slab.

at ground level in order not to overload the pipeline and allow access for cranes and trucks from the casting beds to the building site. Some casting beds were close enough to the building for the precast elements to be lifted directly from the beds into position. However, most units had to be double-handled using cranes and trucks, either over the pipeline, across the “bridges” or from the public road.

Casting beds were used multiple times for various precast units and the sequence of casting was carefully planned so that precast elements could be stacked in the order required.

Surrounding infrastructure A public road abutting the west elevation, the existing station building, the railway lines and a fuel pipeline running parallel to the eastern side of the lines meant that space for on-site casting was limited and the casting beds were placed further from the building site than would normally have been the case.

Three “bridges” were constructed Project team The project’s professional team is as follows: principal agent and civil/structural engineering: Delca Systems; quantity surveyor: Ukuza Consulting; main contractor: GVK Siya Zama Building Contractors; specialist precast contractor: Bedrock Group; structural engineers to Bedrock responsible for the precast structure: Escongweni BPH Engineers; pre-stressed hollow-core slab supplier: Echo Prestress.

(Top, from left): An on-site casting bed; A column foundation trench prior to casting of the concrete blinding over the piles and members of the Bedrock team pose on one of the on-site casting beds: Lungile Phukani, David Kitching, Cathy Paver, Ganee Shaik and Africa Simamane.

(Left, from top): A partially completed section of the first floor prior to the “stitching” process and workers prepare the rebar and shuttering for beam and column “stitching”.

A FICK SEMENTWERKE BK TEL: (022) 913 1921 PROVINCE/COUNTRY: WC PILLAR: PB

AGW TRADING T/A KOLBE BLOCKS TEL: (041) 406 7900 PROVINCE/COUNTRY: EC PILLAR: PB

AVENG INFRASET (PTY) LTD TEL: (011) 876 5500/872 1713 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

BANZI TRADE 31 (PTY) LTD T/A BRICKIT TEL: (011) 023 6708 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

BETA TILES (PVT) LTD TEL: (263) 4333735 PROVINCE/COUNTRY: ZIM PILLAR: PB

BOSUN BRICK BRITS (PTY) LTD TEL: (012) 250 1711 PROVINCE/COUNTRY: NW

BOSUN BRICK MIDRAND (PTY) LTD TEL: (011) 310 1176 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

BOSUN BRICK PORT ELIZABETH (PTY) LTD TEL: (041) 405 0100 PROVINCE/COUNTRY: EC

C.E.L. PAVING PRODUCTS (PTY) LTD TEL: (021) 905 5998 PROVINCE/COUNTRY: WC PILLAR: PI

CEMBLOCKS (PTY) LTD TEL: (014) 538 0311 PROVINCE/COUNTRY: NW PILLAR: PB/PI

CEM BRICK MANUFACTURERS (PTY ) LTD TEL: (051) 433 4479 PROVINCE/COUNTRY: F/STATE PILLAR: PB/PI

CONCRETE UNITS (PTY) LTD TEL: (021) 386 1923/(016) 362 2236 PROVINCE/COUNTRY: WC/GAUT PILLAR: PB/PI

CONFRAMAT (PTY) LTD TEL: (0861) 33 5599 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

CORESLAB (PTY) LTD TEL: (087) 232 2462 PROVINCE/COUNTRY: LIMPOPO PILLAR: PB/PI

COROBRIK (PTY) LTD TEL: (031) 560 3252 PROVINCE/COUNTRY: KZN PILLAR: PI

DERANCO PRECAST (PTY) LTD TEL: (041) 463 3338 PROVINCE/COUNTRY: EC PILLAR: PB/PI EAGLE ROOF TILES (PTY) LTD TEL: (044) 874 0290 PROVINCE/COUNTRY: WC PILLAR: PB

HORIZON BRICK & CONCRETE TEL: (012) 943 3701 PROVINCE/COUNTRY: N/W PILLAR: PB

INCA CONCRETE PRODUCTS (PTY) LTD TEL: 072 646 4916 PROVINCE/COUNTRY: WC PILLAR: PB/PI

LATEGAN CEMENT WORKS (PTY) LTD TEL: (021) 873 1154 PROVINCE/COUNTRY: WC PILLAR: PB/PI

MANHOLES 4 AFRICA (PTY) LTD TEL: (011) 903 7023 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

MOBICAST (PTY) LTD TEL: 086 111 2346 PROVINCE/COUNTRY: WC PILLAR: PB/PI

MONIER COVERLAND (PTY) LTD TEL: (011) 222 7300/7334 PROVINCE/COUNTRY: GAUT PILLAR: PB

MVA BRICKS CC TEL: (012) 386 0050 PROVINCE/COUNTRY: GAUT PILLAR: PI

PAVECON MANUFACTURING (PT Y ) LTD TEL: 087 940 3631 PROVINCE/COUNTRY: LIMPOPO PILLAR: PI

PORTLAND HOLLOWCORE SLABS (PTY) LTD TEL: (021) 972 1111 PROVINCE/COUNTRY: WC PILLAR: PI

REMACON PRODUCTS CC TEL: (011) 393 5504 PROVINCE/COUNTRY: GAUT PILLAR: PI

REVELSTONE (CAPE) (PTY) LTD TEL: (0861) 173 835/(021) 761 9737 PROVINCE/COUNTRY WC PILLAR: PI

ROCLA (PTY) LTD TEL: (011) 670 7600 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

SHUKUMA BRICKS (PTY) LTD TEL: (041) 372 1013 PROVINCE/COUNTRY: EC PILLAR: PB

SHUKUMA FLOORING SYSTEMS T/A ZITTLAU EIENDOMME (PTY) LTD TEL: (041) 372 1933 PROVINCE/COUNTRY: EC PILLAR: PB

SMARTSTONE (PTY) LTD TEL: (011) 310 1161 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI SOLID PAVE BRICKS (PTY) LTD (CONTICRETE) TEL: (041) 365 7676 PROVINCE/COUNTRY: EC PILLAR: PB

TECHNICRETE (PTY) LTD TEL: (011) 672 1425/670 7600 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

VANSTONE PRECAST (PTY) LTD TEL: (012) 541 2056/1808 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

VIBRO BRICKS & PAVING (PTY) LTD TEL: (012) 374 5533 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

WEST END CEMENT BRICKS (PTY) LTD TEL: (011) 851 1005 PROVINCE/COUNTRY: GAUT PILLAR: PB/PI

NON-PRODUCER MEMBERS

ABEL EQUIPMENT CC TEL: (044) 874 1876 PROVINCE/COUNTRY: EC

BIRKENMAYER H (PTY ) LTD TEL: (011) 970 3880 PROVINCE/COUNTRY: GAUT

CHRYSO SOUTHERN AFRICA (PTY) LTD TEL: (011) 395 9700/ (031) 564 0325/(021) 928 1660 PROVINCE/COUNTRY: GAUT/ KZN/ WC

DICK KING LAB SUPPLIES (PTY ) LTD TEL: (011) 499 9400/(031) 700 2551 PROVINCE/COUNTRY: GAUT/DBN

FIBERTEX SOUTH AFRICA (PTY ) LTD TEL: (031) 736 7100 PROVINCE/COUNTRY: KZN

HAWKEYEPEDERSHAAB TEL: 00 459645 4193 PROVINCE/COUNTRY: DENMARK TERRAFORCE (PTY ) LTD TEL: (021) 465 1907 PROVINCE/COUNTRY: WC

ASSOCIATE MEMBERS

AF CONSULTING ENGINEERS & ASSOCIATES (PTY ) LTD PROVINCE/COUNTRY: JHB

ASPASA TEL: (011) 791 3327 PROVINCE/COUNTRY: JHB

BRITISH PRECAST CONCRETE FEDERATION TEL: +(44) 116 232 5170 PROVINCE/COUNTRY: UK

CONCRETE SOCIETY OF SOUTHERN AFRICA TEL: (012) 348 5305 PROVINCE/COUNTRY: PTA

CPI CONCRETE PLANT INTERNATIONAL TEL: (02236) 962390 PROVINCE/COUNTRY: GERMANY

JC PAVING CONSULTING TEL: (011) 431 0727 PROVINCE/COUNTRY: JHB

SEKHUKHUNE & ASSOCIATES TEL: (012) 346 1945 PROVINCE/COUNTRY: PTA

TACO VOOGT CONSULTING ENGINEER TEL: (012) 669 0125 PROVINCE/COUNTRY: PTA

YOUNG & SATHARIA CONSULTING CIVIL ENGINEERS TEL: (031) 207 7252 PROVINCE/COUNTRY: KZN

CONTRACTOR MEMBERS

DECORTON RETAINING SYSTEMS (PTY ) LTD TEL: (021) 875 5155 PROVINCE/COUNTRY: WC

KERNEOS SOUTH AFRICA (PT Y ) LTD TEL: (011) 444 3090 PROVINCE/COUNTRY: GAUT

KOBRA MOULDS B.V. TEL: 003111 356 2460 PROVINCE/COUNTRY: NETHERLANDS

MANITOU SA (PTY ) LTD TEL: (011) 975 7770 PROVINCE/COUNTRY: JHB

PAN MIXERS SA (PTY ) LTD TEL: (011) 578 8700/8600 PROVINCE/COUNTRY: JHB

QUANGONG MACHINES CO LTD TEL: +865 958 679 9557 PROVINCE/COUNTRY: CHINA

REVARO CONCRETE EQUIPMENT TEL: (011) 794 827 PROVINCE/COUNTRY: JHB

SIKA SOUTH AFRICA (PTY ) LTD TEL: (031) 792 6500 PROVINCE/COUNTRY: KZN FRICTION RETAINING STRUCTURES (PTY ) LTD TEL: (011) 608 4321 PROVINCE/COUNTRY: GAUT

POWERGATE CONSTRUCTION CC TEL: 071 603 5070 PROVINCE/COUNTRY: GAUT

VALCAL INTERNATIONAL EXPORT CC TEL: (011) 867 2471 PROVINCE/COUNTRY: GAUT

CEMENT MEMBERS

AFRISAM SOUTH AFRICA (PTY ) LTD TEL: (011) 670 5500/5752 PROVINCE/COUNTRY: GAUT

PI – Precast Infrastructure PB – Precast Building

WITH SUPERIOR QUALITY, STRENGTH AND CONSISTENCY. GREAT STRUCTURES STAND TALL

AfriSam High Strength Cement is developed for specialist concrete applications that require high early strength. Its durability, strength and workability make it the preferred product for construction and structural work. *Product specification dependent on area.

This article is from: