CONTENTS 1. Introduction
1
2. Impact
4
3. Successes and Outcomes
6
4. Activities
7
5. Challenges and Lessons Learned
9
6. Cross-Cutting Themes
12
7. Value for Money (VfM)
12
8. Other Stakeholders
12
9. Conclusion
12
10. Exit Strategy
13
11. Human Interest Story
15
1
WATER SUPPLY IN LOGA
INTRODUCTION Country:
Niger Project Location:
Badoko Village, Loga District, Dosso Region
Niger is among the least developed countries where access and utilization of basic social services of a large proportion of its population are unmet. Though access to potable water is a right and is essential for the wellbeing of every community, permanent access to it is amongst the main challenges faced by Nigeriens in rural areas. This project supported by IR Canada and implemented by IR Niger was designed to improve the access of Badoko community to permanent access to potable water through which contributing to improving their wellbeing. The key outcome to be achieved by the project was to secure improved usage of clean water for 5000 people in one village of the district of Loga. To meet the stated outcome and medium-term change, the project achieved two outputs:
O RP H A N AG E S U P P O RT FI N I NS A I DLE RSY ER P IOAR T Interim Report
1
Increased access to clean water for 5,000 people in the District of Loga.
2
2
Increased capacity of 5 people organised in committees in one village to manage water facilities.
In achieving this, the project drilled a deep borehole in
After the completion of the water supply system, a water
Badoko village and equipped it with a water supply system
management committee composed of 5 people (3 men 2
including water tank, solar generator, and reticulation
women) was set up. The committee ensures the daily
networks. Four fairly distributed water standpoints were
operation of the water points and maintenance if ever
established in strategic places across the village to provide
needed and the daily checking of the whole system. To fulfil
the population with easy access to potable water at all
this role the committee received basic training and
times, including securing supply for a school and health
equipment from the project.
centre. As such, the project has contributed to reducing the burden faced by women and girls in fetching water. Additionally, the setting of the points and the design has been established with communities with a view to reducing any potential related gender-based violence usually experienced once the water point is far from dwellers.
3
WATER SUPPLY IN LOGA
MAJOR CHANGES TO THE PROJECT
PARTNERSHIP
Two major changes occurred during the implementation of
The project was implemented in partnership with
the project:
Government Local Services in charge of Hydraulics (DDHA) to identify locations for the intervention and ensure the
The project originally intended to install 5 water points,
facilities constructed complied with national technical
this increased to 6. This was motivated by the need
standards. To establish this a written notification was made
expressed by the community to connect the health and
to Loga District along with IR Niger criteria for the project
the primary school to the water network. Resources
village identification. Based on the defined criteria, Badoko
allowed us to achieve this.
village was selected and the DDHA appointed by the district
The failure of two open tender rounds significantly delayed project implementation according to the originally agreed timeline. At first a limited offer (only one offer) was received for the work to be carried out, during the second round two offers were received that were beyond the project budget and negotiation failed to move the offers into the limit of the budget. As a result, a no cost extension request was submitted to IR Canada. This was approved and a supplier was secured, with all activities being completed within the new timeframe.
to monitor project implementation in collaboration with IR Niger. DDHA has experienced human resources with proven working experience with development agencies in the water supply sector in the Loga district. DDHA in coordination with the Loga commune assisted in the identification of Badoko village; ensuring the technical follow up of drilling activities and water supply installation, setting up and training of the water committee. IR Niger and Loga DDHA signed a formal collaboration MoU for the undertaking of all tasks. Whilst monitoring project activities, DDHA undertook quick decision making and gave quick feedback to IR Niger if any technical issues were found. DDHA supervised both borehole drilling and reticulation network installation. The service also ensured that the appropriate aquifer reached during the borehole drilling, that the borehole yield was at least 5 cubic meter per hour (minimum yield to support a water supply system), solar water pump type and capacity control, and monitored solar panel installation and the performance of the system.
FINAL REPORT
4
IMPACT Though it is early to report on significant project impact as the works have been completed only recently, beneficiaries’ testimonials and reports from the local hydraulic services allow to identify that the project has established the following changes in Badoko:
1 2
Water fetching effort and time has been reduced, especially for women. The communities of Badoko have gained capacities in managing their water system with additionally the establishment of a trained 5 person water management committee on the matter.
3
Domestic water quality has improved and allows the anticipation of the reduction of water borne disease prevalence.
5
WATER SUPPLY IN LOGA
FINAL REPORT
6
SUCCESSES & OUTCOMES Outcome 1
Improved usage of clean
Planned Targets
Actual Targets
Reason for any
Measureable
Achieved
Variation
Indicators
5000
5000
No deviation
5000 people
5000 people
No deviation
water for 5000 people in one village of the district of Loga Output 1.1 Increased access to clean
Number of people with
water for 5000 people in the
increased access to
District of Loga
potable water
Output 1.2 Increased capacity of 5 persons organised in committees in one village to manage water facilities
5 persons
5 persons (2 women and 3 men)
No deviation
Number
of
person
with ability to manage a water point
7
WATER SUPPLY IN LOGA
1.1.1 Construction of one water supply system powered with solar energy in one village.
ACTIVITIES
Prior to the intervention, the village only had two open wells for water supply, the main users of which were women, girls and herders. Around the wells, hygiene conditions were very
REPORT ON ACTIVITIES
poor and water fetching extremely strenuous for users as
To achieve all targets and changes set by the intervention,
making use of donkeys to fetch water. As the wells were
and to bring the community of Badoko access to improving
open and due to the climatic conditions in the Sahel with of
use of potable water, the project carried out the following
strong dusty winds throughout the year; the wells were
main activities as planned:
subject to pollution and such the water not being potable,
the wells were very deep. Users that could afford it were
clean or suitable for drinking. To address this situation, the project constructed a sustainable solar powered water supply system including; A 110m deep borehole with the following geographic coordinates: Longitude 3° 18 ‘38, 4’’; Latitude 13° 39’ 17,3’’ and located at 236 m above the sea level. The borehole registration number is N°IRH: 300614. A Water storage and distribution facility: The system is made up of a metallic tank/reservoir of 20 cubic meters on a pedestal of 8 meters, one of highest water tanks IR Niger has ever installed. A solar water pump with capacity to pump up to 45 cubic meter a day is also installed in the borehole. The pump is powered with 8 solar panels with a combined power of 3000 watts to ensure the quick uplift of water to the tank. A water meter is placed to monitor the volume of water used by the population.
FINAL REPORT
8
1.2.2 Set up and train one water management committee.
and facilities handover to the Badoko community.
A committee of 5 people (2 male and 3 females) was set up by
Additionally WASH sensitisation also took place within these
Loga DDHA and IR Niger. The selection process was conducted
sessions covering conservation and transport of potable
during a village general assembly where the community was
water, hygiene measures to be observed around the water
informed on the necessity and importance of the water
point and general hygiene practices such as hand washing.
management committee, its composition, the role and attribution of each member, the member’s selection procedure
This activity is completed and contributed to increasing
and the committee internal rules and procedures. Two training
Badoko village capacity on WASH practices especially
sessions were conducted for the committee members and
around water points.
covered the following; (1) water point management, (2) Roles and attributions of committee members, (3) water committee
1.1.4 Water test.
functioning, (4) repair and maintenance of water points.
A water flow rate and quality test were completed after the initial drilling of the borehole to ensure compliance with
This activity is completed and contributed to increasing
relevant standards and continuity of water supply sufficient
Badoko village capacity on water point management.
to cover the target population. The borehole yield is 30 cubic meter per hour, high above Badoko population water needs
1.1.3 Supply of water facility repair & maintenance kit.
in water. The water quality laboratory test stated that the
Under the supervision of the village water management
borehole is providing potable water to users and is certified
committee, a volunteer was trained by Loga DDHA and
by hydraulic service in charge of water analysis.
equipped by the project with a basic maintenance tool kit to ensure maintenance of the water points. The tool kit is
This activity is completed. It ensured water flow is good to
composed of a set of flat keys, a screwdriver set, short flat
reach 6 water points and the water is potable.
screwdriver, and set of adjustable wrenches, adjustable gripper, 2 keys with claw 131-18, and mechanic's hammer.
1.2.2 Set up and train one water management committee. A committee of 5 people (2 male and 3 females) was set up
1.1.5 Community mobilization and sensitization on water facility management.
by Loga DDHA and IR Niger. The selection process was conducted during a village general assembly where the
The project organized 5 community mobilization sessions
community was informed on the necessity and importance
related to informing the population on the project including
of the water management committee, its composition, the
intended outcomes, outputs, and activities to be conducted
role and attribution of each member, the member’s
and the approach of the project in these activities; borehole
selection procedure and the committee internal rules and
site identification, introduction of the drilling company to the
procedures. Two training sessions were conducted for the
community, presentation of 2nd company in charge of the
committee members and covered the following; (1) water
water system installation, the water point management
point management, (2) Roles and attributions of committee
committee and its purpose, and setting up of the
members, (3) water committee functioning, (4) repair and
management committee and their training. Valuable
maintenance of water points
sensitization were made during each of the mobilization session by the DDHA and the IR WASH officer to community
This activity is completed and contributed to increasing
that had contributed to smooth implementation of the project
Badoko village capacity on water point management.
9
WATER SUPPLY IN LOGA
CHALLENGES AND LESSONS LEARNED
KEY CHALLENGES The key challenge faced during the implementation of the project was the delay in securing a company to conduct water system installation after two rounds of open tender process of at least one month each. This caused a delay of more than two and half months. An NCE request was submitted to IR Canada and approved for an extension to the project timeframe to allow all work to be completed. To overcome the challenges in securing a supplier to carry out the full work, the work was split into two components (drilling and water system installation) to assist suppliers in meeting the budget available – this was successful and all activities were achieved within the budget planned.
FINAL REPORT
10
LESSONS LEARNED
COMMUNITY ENGAGEMENT/FEEDBACK
As a lesson learned from this project, most local drilling
IR
companies have limited capacities to construct a water
sensitization throughout project implementation and made
system. As such they sub contract part of their contract
use of this framework to highlight to beneficiaries their
which contributes to significantly increasing their cost
rights and responsibilities in project implementation and
proposed. To avoid such challenges assessment was made
how to voice out their concerns and register complaints. The
to identify specialized companies based on the tender
complaints mechanism used within this project involved
technical component and tender made accordingly. As such
sharing with the project stakeholders IR’s official phone
the project was able to contract two companies and succeed
number, including that of the CD assistant, project assistant,
to implement the project in budget time line and even made
or
a saving on some budget lines. This approach and learning
encouraged to raise their complaints if any using the shared
will be taken forward into future projects.
phone number. No phone complaint was received during
Niger
project
conducted
coordinator,
community
mobilization
Beneficiaries
were
and
actively
implementation; however, during a monitoring field visit regarding the setting of the 4 water points, a neighbour to one of the sites complained that the location was too close to his house and would damage it. To address this complaint the community was consulted and a new site was identified and agreed upon.
11
WATER SUPPLY IN LOGA
FINAL REPORT
12
CROSS-CUTTING THEMES
OTHER STAKEHOLDERS
Amongst the cross-cutting themes addressed during
The project was implemented with the participation of
project implementation include;
Badoko community, Loga DDHA and Loga commune.
Water chain management: Maintenance of cleanliness
Badoko
of potable water through application of appropriate
identification of water facility sites as well as their
management, transfer, storage and hygiene measures.
construction and installation. The community ensured
Hygiene and Sanitation: hygiene measures to be observed around the water point and general hygiene practices such as hand washing. The interrelationship
community:
participated
fully
in
the
the security of drilling material and equipment throughout construction, and will ensure appropriate management of the facilities after project close.
and
DDHA: ensured technical advice, follow-up and control
environmental hygiene. Improved hygiene cannot
of water facility construction and installation. In addition
ensure unless an environmental hygiene.
DDHA conducted training of the water committee.
Environmental protection: environmental protection
Loga Commune: are in charge of overseeing the water
sensitization related to water resource management.
facility management with regard to country’s policies. In
between
improvement
in
general
hygiene
Gender: Mainstreamed throughout implementation by giving equal opportunities to women to participate in project activities and management positions. In all
working towards ensuring sustainable management of the water system, the commune was actively involved during community mobilization.
meetings organized by the project, women were involved. It was recognized by community that women, girls and boys are primary beneficiaries of this project due cultural norms that made them responsible for domestic water mobilization.
VALUE FOR MONEY (VFM)
CONCLUSION
IR Niger gives priority to competition in the procurement
IR Niger gives priority to competition in the procurement
and implementation of project activities. Tender and bid
and implementation of project activities. Tender and bid
processes were used and providers with best offer were
processes were used and providers with best offer were
selected. To ensure project funds were used efficiently,
selected. To ensure project funds were used efficiently,
three (2 open and 1 selective) rounds of tendering
three (2 open and 1 selective) rounds of tendering
processes were undertaken before getting the best offers.
processes were undertaken before getting the best offers.
This allowed IR Niger to make some savings on the
This allowed IR Niger to make some savings on the
allocated borehole drilling budget line. These saving would
allocated borehole drilling budget line. These saving would
help to connect the secondary school to the water system if
help to connect the secondary school to the water system if
time was sufficient, however it was requested very late by
time was sufficient, however it was requested very late by
beneficiaries.
beneficiaries.
13
WATER SUPPLY IN LOGA
EXIT STRATEGY IR Niger implemented this intervention in collaboration with Badoko village community, Loga Hydraulic and Sanitation Service and Commune to ensure their effective involvement during and post-project. Community mobilization was carried out to prepare these stakeholders to take care and sustain project achievements post-IR Niger exit. IR Niger throughout the project implementation mobilized and prepared stakeholders and made them aware of their roles and responsibilities during and after the project. By so IR Niger prepared its exit. To ensure successful community management; the project organized the community by establishing a committee of 5 members and building their capacities on water system management in conjunction with the district service in charge water resources and the Loga commune. The DDHA and the commune being the technical and the communal authority in charge of the potable water service sustainable delivery in the commune will take over from IR Niger in engaging with the communities beyond the project life time.
FINAL REPORT
14
SUSTAINABILITY AFTER COMPLETION The main instruments that support sustainability of the project after completion are the following :
• Community Commitment:
• Quality of installation: The technical control and monitoring conducted by IR Niger and hydraulic service ensured the installations are of good quality and robust to resist natural hazards such as wind for years.
Badoko population has been waiting for a very long time for this kind of opportunity, and committed themselves to ensuring the security of all items such as solar panels. They also committed themselves to support the committee in facilitating its mission.
• Management committee:
• Niger public water law:
The presence of a trained water management committee
Niger has a law that regulates the management of public
will
delivery. Basic
water points. Loga commune is accountable for all water
maintenance will be performed at village level. More
facilities installed in the area. The law commands Loga
complicated issues will be raised to IR Niger during the
commune to delegate a private water manager who will be
guarantee period (up to 6 month after primary reception)
selling water to community at a discounted cost affordable
who will coordinate with the provider to fix any issue found
to them at a price set in discussion with the community.
after assessment.
Those who are unable to afford water will gain free access.
allow
rational
use
of
project
The private manager will be responsible for water facility maintenance in case of breakdown. He will be selected through open tender process. However community based management is also an option that can allowed to communities by the commune based the quality of their
• Security of installation: Water facilities are set in secure areas provided by Badoko village. A maintenance and repair focal person has been appointed by the community to watch after the installations and ensure their security. Robust metal fencing has been installed around the core water facility (i.e. borehole and accessories,
water
tank,
solar
panel).
Only
water
management committee members and DDHA have access to these installations.
management of their water system. In both cases, the commune will ensure the supervision of the water service delivery.
15
WATER SUPPLY IN LOGA
HUMAN INTEREST STORY Zakaryaou Kalilou My Name is Zakaryaou Kalilou. I am 55 years old. I have 15
On behalf of Badoko village, I present our gratitude to the
dependents. I am Badoko village Imam and village head
donor. We are very grateful to this project for installing 18
representative.
water taps in our village. Women of Badoko are very happy of that support. With tap water we expect to be healthier
Before this intervention, Badoko women suffered a lot for
than with open wells. With the open well it is possible to get
water fetching from the existing 2 open wells. They had to
diseases by drinking dust in the water. Now there is no risk.
attach a rope of at least 40m to a bucket to pull water from the wells. Also, the wells are open, so the wind can bring all
May Allah bless those who helped us in the name of our
kind of dust inside it.
loved prophet Mohamad (SAWS). May Allah bless Islamic Relief as it has supported us. We trust their support with
Now, Islamic Relief has installed a water tank and solar panels with 6 water stand points without requesting any contribution from our community. We can get clean water at any time in the village. We think they supported us as recommend by Islam.
Islam values of solidarity.
FINAL REPORT
Barira Hassane My Name is Barira Hassane. I live in Badoko village. I am a beneficiary of the borehole project in the village. I have just collected the water from the installed taps. This water is clean, safe and very tasty. Water from tap swill makes us rest and be healthier. We will take bath with clean water and have better hygiene. Many tanks to donors.
16
3501 Mainway, Burlington ON, L7M 1A9. www.islamicrelief.ca 1-855-377-4673 (HOPE)