Year in review PHYSICAL WORK ACHIEVED TO FIRST PLASMA Project share (design, component manufacturing, building construction, shipment and delivery, assembly and installation)
67.3%
Project share
IP
Physical work
PROGRESS TOWARD THE REALIZATION OF FIRST PLASMA SYSTEMS AND COMPONENTS IP
Physical work
96.4%
Manufacturing completed
PA Number Project share
of design completed
PA Value
Physical work
PA Number
77.6% of manufacturing completed
IP
Design completed
Physical work
Manufacturing completedManufacturing completed
Building construction on site
BUILDING CONSTRUCTION COMPLETED ON SITE PA Number
PA Value
73%
PA Value
Design completed Design completed
Building construction on site
First Plasma scope
All figures and graphics as of 31 December 2019 Design completed
8
2019 Year in review
Building construction on site