Looking ahead: 2021
Two poloidal field coils have been completed and a third is in fabrication in the European winding facility on site.
• Achieve first 1,200-tonne vacuum vessel sub-assembly • Finalize cryostat top lid • First central solenoid modules on site; begin structural assembly • Install poloidal field coils #6 and #5 in pit • Receive next-in-line vacuum vessel sectors • Receive next-in-line toroidal field coils • Launch cryoplant commissioning • Lower first vacuum vessel sub-assembly in pit • Start construction of ITER Control Building
LOOKING AHEAD