ATA - Costing Report

Page 1

THE LIPARI RETREAT

Costing Report

AR7022 Group_12 Frederick Mawhood Jonas Bertlind Rana Rehman Martins Silins

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT


ATA Applied Technology in Architecture Module code: AR7022 The Demountable Building 2016/2017

Group Rana Rehman Martins Silins Frederick Mawhood Jonas Bertlind

All Rights Reserved 2017c All terms apply


TABLE OF CONTENT Introduction

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

1

1.0_As Designed 1.1_Component Analysis 1.2_Schedule of Components 1.3_CNC Wastage 1.4_Schedule of Works 1.5_Schedule of Labour 1.6_Site Tools 1.7_Cost Summary 1.8_Conclusion

5 6 7 8 10 12 14 16 17

2.0_Value Engineered 2.1_Component Analysis 2.2_Proposed Changes 2.3_Schedule of Components 2.4_Schedule of Works 2.5_Schedule of Labour 2.6_Site Tools 2.7_Cost Illustrations 2.8_Cost Summary 2.9_Conclusion

18 19 21 23 25 27 29 30 35 36

_Individual Contributions

38

_Appendix _Quotes & Correspondence

39 40


Introduction Costing Report In our design report (prior to making this costing report), we have made initial presumptions (and the odd assumption) as to what the elements in our building cost. This gave us a total sum of ÂŁ17,526. However, although informed by size and weight, these numbers were not informed by through market research and the parameters for ordering them were relatively loose. It is fair to say that although we have completed an initial cost estimate purely based on raw data, we definitely need to complete a more thorough analysis of how much our building costs to construct. This cost evaluation does not only concern the elemental costs but also, the cost of manufacturing, the cost of assembly during pre-construction, the cost of transporting goods to site, the cost of construction. These outlined criteria can be split into numerous subcategories and in order to ensure we are utilising the best and cheapest modes of construction, we should analyse (and scrutinise) each cost from larger elements such as structure elements to smaller ones such as windows. Our aim is to provide the most realistic cost evaluation based on real time information and industry rates. As well, our aim is to value engineer our design, make informed modifications based on the data we have collated. This is in order to provide a potential investor and/ or client with options for cost-saving. However, it is important also that as the architects of this building, we should advise clients/investors of the ramifications for opting to cost-save. What might be cheaper, may not be aesthetically pleasing, or may pose long term issues. This surely falls under the architects duties and thus should not be neglected when reducing costs.

1


Component

Count

Dimensions (mm)

Weight (Kg)

Weight Per Element

Mass (kg/m3³)

Cost £

Green Durable Super Felt

1

7820x10218x3

196

N/a

817

690

Proof Membrane

1

7820x10218x4

21

N/a

262

47.4

Ceiling Hardwood Plywood (On Top and bottom)

96

1120x1120x18

1363.2

14.2

625

1332

Ceiling Hardwood Plywood (Sides)

14

300x2410x18

140

10

625

136

Roof Insulation Boards

48

1120x1120x100

33.12

0.69

30

946.15

Hardwood Plywood (Short Trusses)

72

2400x170x18

331.2

4.6

625

324

Hardwood Plywood (Long Trusses)

17

2400x320x18

149.6

8.8

625

146.2

Hardwood Plywood (Disk)

34

300x300x18

35

1.03

625

34

Hardwood Plywood (Disk Dimonds)

34

210x210x18

17

0.5

625

16.6

OSB Panels for Walls (Both sides)

112

575x2800x10

1389.6

13.3

323

1220.8

Wall Insulation Board

56

630x2800x120

218.4

3.9

30

2058

CLT Columns

12

150x3473x150

474

39.5

505

720

Drawing

2


Component

Count

Dimensions (mm)

Weight (Kg)

Weight Per Element

Mass (kg/m3³)

Cost £

Window Glass

20

2527x474x4

239.6

11.98

2.3

2717.4

Aluminium Sill

10

75x70x480

N/a

N/a

2800

60

Window frame (Flashed)

10

550x2629x125

150

15

625

900

External door with frame (Pull Handle, Key lock, butt hinges)

4

Structural Opening 902mm Leaf Size 826x2040

480

120

N/a

500

Hardwood Plywood Floor Panels (Top)

192

610x610x18

1209.6

6.3

625

1171.2

Hardwood Plywood floor panels (Bottom)

192

600x600x18

1170.2

6.09

625

1132

Floor Insulation Boards

96

1120x1120x120

66.6

0.69

30

1892.3

Scaffold Base Jacks

12

381x4x650

40.8

3.4

N/a

120

Non Structural hardwood Plywood (Large floor joists)

17

2500x300x22

175.1

10.3

625

391

Non Structural Hardwood Plywood (Small floor joists)

75

2500x150x22

386.25

5.15

625

862.5

Non Structural Plywood (Small supportive floor joists)

10

1300x150x22

22

2.2

625

59.8

Non Structural hardwood Plywood (Floor structure joints)

169

75x15x15

33.8

0.2

625

49

3

Drawing


Package

Weight (Kg)

Cost (£)

Inside Area (m2)

Outside Area (m2)

Full Package

4666.35

17526.35

36

33

Package

Weight (Kg)

Cost (£)

Inside Area (m2)

Outside Area (m2)

Middle Lobby Package Package

4309(Kg) Weight

16812 Cost (£)

25 (m2) Inside Area

Outside 44 Area (m2)

Full Package

4666.35

17526.35

36

33

Package

Weight (Kg)

Cost (£)

Inside Area (m2)

Outside Area (m2)

Large Terrace Package Package

3533(Kg) Weight

13957 Cost (£)

Inside 12.6 Area (m2)

Outside56.4 Area (m2)

Middle Lobby Package Package

Weight 4309(Kg)

Cost (£) 16812

Inside Area 25 (m2)

Outside 44 Area (m2)

Full Package

4666.35

17526.35

36

33

Package

Weight (Kg)

Cost (£)

Inside Area (m2)

Outside Area (m2)

Large Terrace Package Package

Weight 3533(Kg)

Cost (£) 13957

Inside 12.6 Area (m2)

Outside56.4 Area (m2)

Middle Lobby Package

4309

16812

25

44

Package

Weight (Kg)

Cost (£)

Inside Area (m2)

Outside Area (m2)

Large Terrace Package

3533

13957

12.6

56.4

4


AS DESIGNED

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

5


1.0_As Designed Component Analysis The building we have designed essentially falls into three categories. These three categories not only are prevalent in our design but are also consistent in the method adopted to cost the manufacture, transport and assembly on site of our building. These three categories are: 1. Structure - in which the floor and roof are interconnected with columns 2. Cassettes - which provide a weatherproofing skin to all sides of the building 3. Doors and Windows - providing the building with inhabit-ability

Structure

Cassettes

Doors and Windows

The structure is comprised of three main components. The floor structure, roof structure and columns. This system is rigidly interconnected through a gridded design. The columns are the essential pieces which tie the whole structure together.

For the walls we are using OSB grade 3 timber 10mm and for the floor and roof we are using grade BB 12mm plywood. The panels will be bonded to insulation boards. These items will need to be assembled during the pre-construction phase. We have decided that alongside a designated CNC mill, we will also hire a workshop space. This workshop space will primarily be used to bond wall, floor and roof cassettes.

Due to the specialist nature of these products, we have decided to order the individual parts that make these items and assemble them at the designated CNC mill/wood workshop. By ordering individual parts, we can, through design, simplify the product, reduce its cost whilst it still performs at a suitable standard.

The best suited mode for manufacturing these components would be CNC. These components, as presented in the Design Report have very specific notches and sizes. Therefore, it is imperative that the these panels are cut using the highest precision tools available to us. CNC’ing in bulk would thus limit responsibility to one party (the CNC Mill) as well as limit costs (as acquiring raw materials will be relatively inexpensive). We will use a variation of 12-22mm thick grade B plywood for the floor and roof components. The columns would be Glulam timber grade B. This would need to be produced by a specialist subcontractor. There overall column-like form can be produced and depending on the specialist subcontractors capabilities, they can be CNC’d by the same subcontractor too. If the specialist subcontractor does not have CNC capability, these columns can be notched and cut using CNC routing technology at our designated CNC mill.

6


1.0_As Designed Schedule of Components The full schedule as presented below is a complete and comprehensive breakdown of prices which meet our requirements for a quick and qualitative build. The criteria for selecting these products was that they should be easily, cheaply and quickly procured.

Total Delivery for CNC Items:

220

Total Cost: Total Delivery: Total Inc VAT and Delivery:

1

06.53 236.3 23,52 .1

Floor Component Scaffolding Screw Jacks (Foundations) Floor Joists - Primary Structure - plywood Floor Joists - Secondary Structure - plywood Floor Cassette Top and Bottom Panels Floor Structure Joints (Small) Thermafloor TF70 120mm (Insulation)

Total Cost: Total Delivery: Total Inc VAT:

Component No. C01 F01's F02's & F03's F04's F00's F04

# of CPNT 12 24 118 384 551 12

Supplier scaffoldingsupplies Latham Timber Latham Timber Latham Timber Latham Timber Kingspan

Dimensions (mm) Cost per Item (£) Per Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) 500 6.5 Unit 16.3 78 n/a 78 3050 x 1220 50.71 Board * 304.26 136.8 441.06 3050 x 1220 50.71 Board * 760.65 342 1102.65 3050 x 1220 50.71 Board * 1969.24 912 2881.24 2440 x 600 17.96 Board * 17.96 22.8 40.76 2400 x 1200 87.16 2 sheets p/pack 0 1045.92 547.2 1593.12

6136.83 16.3 7,380.50

Column Roof Component Columns - lulam Roof Structure - Primary - plywood Roof Structure - Secondary - plywood Roof Cassette Top and Bottom Panels Thermaroof TP10 (Insulation) 1000 auge Polythene DPM 300mu I Black Shed Felt Roof Flashing - plywood Roof ocking Disks - plywood alvanised tra arge Clout Nails

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No. # of CPNT Supplier Dimensions (mm) Cost per Item (£) Per Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) C03 12 Co le Timber artners 150x150x3800 93.33 column incl. 1344 600 1944 02's 03's 04's 72 Latham Timber 2440 x 1220 35.92 Board * 323.28 205.2 528.48 05's 17 Latham Timber 2440 x 1220 35.92 Board * 107.76 68.4 176.16 06 & 09 96 Latham Timber 2440 x 1220 35.92 Board * 1724.16 1094.4 2818.56 07 8 Kingspan 2400 x 1200 113.34 3 sheets p/pack 0 906.72 364.8 1271.52 1 insulation4less 250000x4000 38 Unit 0 38 n/a 38 8 ickes 10000x1000 20.99 Unit 0 100 n/a 100 08's 14 Latham Timber 2440x1220 35.92 Board * 143.68 91.2 234.88 01's 68 Latham Timber 2440x1220 35.92 Board * 71.84 45.6 117.44 1 ickes 20 2.99 ack of 400 0 2.99 n/a 2.99

7232.03 0 8,678.

alls Component SB3 Panels Inside and utside Thermawall T 55 PIR Insulation Board Sadolin Classic oodstain 2.5

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No. ll 's

# of CPNT 104 23 2

Supplier Latham Timber Kingspan adolin

Dimensions (mm) Cost per Item (£) 2997x1197 6.2 1200x2400 52.3 32m2 each 32.99

# of CPNT 2 2 1

Supplier ickes ickes ickes

Dimensions (mm) 2032x813 2000x807 /

# of CPNT 8 4 64 16

Supplier /a ickes ickes glass outlet

Dimensions (mm) 550x2629x125 950 40x40x40 2527x474x6.7

Per Board Unit Unit

Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) * 297.6 1094.4 1392 0 907.2 1573.2 2480.4 0 65.98

Cost of Item (£) 79.99 72.99 44.99

Per Full frame Unit ack of 3

Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) 0 159.98 n/a 159.98 0 145.98 n/a 145.98 0 44.99 n/a 44.99

Cost of Item (£) 90 15.99 1.49 43

Per Full Frame Unit Unit Unit

Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) 0 900 n/a 900 0 63.98 n/a 63.98 0 95.36 n/a 95.36 45 689 n/a 689

3 38.38 0 ,726.06

Doors Component ickes terior Premium Door Frame ardwood Ply Veneer Flush terior Fire Door ickes Bravo atch andle Set Polished Chrome Finish

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No.

350. 5 0 21.1

indows Component Tim er Frame Aluminium Sill Steel Brackets lass

Total Cost: Total Delivery: Total Inc VAT and Delivery: _ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

Component No.

17 8.3 0 2,0 8.01

7


1.0_As Designed CNC Wastage In addition to procuring quotes for CNC’ing, we have also calculated what the total wastage of material would be. As we have curves, we are estimating that there maybe a fair amount of offcuts which are of no further use. This will tell us how effectively have we used the money needed to buy sheet materials. The diagrams below represent the template areas. The areas in red are waste material. Total Wastage = 135.1m2 or 22% of total area

8

Components Type

Wastage

Total Wastage

31.44m2 3.1m2 0.6m2

35m2 or 15% of total area

16.7m2 1.4m2

18.1m2 or 9.7% of total area

Floor 59 x [3050 x 1220mm Ply] 02 x [2440 x 1220mm Ply] 01 x [2440 x 600mm Ply] Roof 61 x [2440 x 1220mm Ply] 03 x [2440 x 600mm Ply] Wall 48 x [2997 x 1250mm OSB] 82m2

82m2 or 45% of total area


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

9


1.0_As Designed Schedule of Work

10


1.0_As Designed Schedule of Work

Schedule of work

Project Schedule May 1, 2017

Start Week Week Starting

2

1 Mon

Tue

1

2

Wed Thu 3

4

Fri

Sat

Sun

Mon

Tue

5

6

7

8

9

Wed Thu 10

11

3 Fri

Sat

Sun

Mon

Tue

12

13

14

15

16

Wed Thu 17

18

4 Fri

Sat

Sun

Mon

Tue

19

20

21

22

23

Wed Thu 24

25

Fri

Sat

Sun

26

27

28

Action

Hours

£ Cost Action

Time

0

08:00 - 17:00

Standard - PA

Person

Phase 1

Project Architect. Free labour, 1-2 persons

Preconstruction

CNC cutting

24

1512

08:00 - 17:00

Technician

CNC cutting

16

1008

08:00 - 17:00

Carpenter

CNC cutting

12

756

08:00 - 17:00

Pilot

CNC cutting

16

1008

08:00 - 17:00

Lorry Driver

CNC cutting

24

1512

08:00 - 17:00

4 additional unskilled labour

CNC cutting

20

1260

08:00 - 17:00

Carpenter Assembly

20

857.5

08:00 - 17:00

Carpenter Assembly

12

514.5

08:00 - 17:00

Carpenter Assembly

16

686

08:00 - 17:00

Carpenter Assembly

8

343

08:00 - 17:00

0

08:00 - 17:00

PA Task PA Task

0

08:00 - 17:00

Phase 2

Lorry Transport

8

480

04:00 - 20:00

Transport

Helicopter Transport

6

2450

08:00 - 20:00

Phase 3

PA Task

0

08:00 - 20:00

Construction

Unskilled Labour Task

4x8

320

08:00 - 20:00

0

08:00 - 20:00

Phase 4

Clearing Site - PA Task/Helicopter Transport

2

175

08:00 - 10:00 10:00 - 18:00

PA Task

Windup Cost £

Work & Cost

504 504 504 504 504

504 504 567 567 567

567 567 567 567 2930

320

515

Lorry Transport

8

340

For details see Schedule of Labour

224h

13,221

Cost Tot £

Wood Workshop

164

Carpenter

2240

Transport Heli

2625

Transport Lorry

820

Unskilled Labour CNC Lab TOTAL

7052

320 13,221

By making sure CNC cutts the right piecis in the beginning, the carpenters working hours and sequences can overlap with CNC to make the process more compact, and therefor more effective in terms of time. _ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

11


1.0_As Designed Schedule of Labour

12


1.0_As Designed Schedule of Labour Shift Schedule

For the Week of: Department Name:

Week 1 Monday Standard CNC Technician

HeadcountTotal

Tuesday Standard CNC Technician

HeadcountTotal

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

Week 2 3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

2

8:00 A.M.

2

9:00 A.M.

2

10:00 A.M.

2

0

11:00 A.M.

12:00 P.M.

2

2

1:00 P.M.

2:00 P.M.

2

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

2

2

2

0

2

2

2

8:00 A.M.

Standard CNC Technician

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

HeadcountTotal

Thursday Standard CNC Technician

HeadcountTotal

Friday Standard CNC Technician

HeadcountTotal

Saturday

HeadcountTotal

Sunday

HeadcountTotal

CNC floor board CNC insulation CNC walls CNC roof board CNC floor struct. CNC roof struct.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

2

2

2

2

0

2

2

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

2

8:00 A.M.

2

9:00 A.M.

2

10:00 A.M.

2

0

11:00 A.M.

12:00 P.M.

2

2

1:00 P.M.

2:00 P.M.

2

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

2

2

2

2

0

2

2

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

CNC technician cutting boards of insulation to right formats for floor cassettes, wall cassettes & roof cassettes CNC technician cutting columns, windows, doors CNC technician cutting roof boards for roof cassettes CNC technician cutting primary and secondary floor joists CNC technician cutting primary and secondary roof beams

The schedule shows a careful deployment of labourers for particular tasks at particular times. Notes have been added to identify who the individual labourer is and what his/her particular task is.

PA Loading Lorry Load Helicopter

Project Architect, helping to load cargo onto Helicopter PA setting up amenities, safety fence around site peremises, setting up generator, cover cargo PA setting screw jacks & columns in grid, assembling /mouning floor structre & slotting in floor cassettes.

Wrapping

4:00 P.M.

Project Architect, helping to load cargo onto Lorry

Floor assembly

Sick?

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Standard CNC Technician

16

HeadcountTotal

TOTAL 8 8 0 0 0 0 16

Sick?

Sick?

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Monday

8 8 0 0 0 0

TOTAL 8 8 0 0 0 0 16 TOTAL 8 8 0 0 0 0 16 TOTAL 8 8 0 0 0 0 16 TOTAL 0 0 0 0 0 0

Tuesday Standard CNC Technician

HeadcountTotal

Sick?

TOTAL 0 0 0 0 0 0

10:00 A.M.

11:00 A.M.

1st woodstain ap

1st woodstain ap

1st woodstain ap

CNC Wall

CNC Wall

CNC Wall

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

CNC Wall

CNC Wall

CNC Wall

CNC Wall

CNC Wall

2

2

2

2

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap CNC Wall

2

CNC Wall

2

CNC Wall

2

1:00 P.M.

2

2:00 P.M.

2

3:00 P.M.

CNC roof board

0

2

CNC roof board

2

CNC roof board

4:00 P.M.

2

PA

PA

PA

PA

PA

PA

PA

CNC roof board

CNC roof board

CNC roof board

CNC roof board

CNC roof board

CNC roof board

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

HeadcountTotal

Thursday

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

3

3

3

3

0

3

3

3

3

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

Standard CNC Technician Carpenter

PA

PA

PA

PA

PA

PA

PA

PA

CNC roof board

CNC roof board

CNC roof board

CNC roof board

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

HeadcountTotal

3

3

3

3

0

3

3

3

3

11:00 A.M.

12:00 P.M.

Friday

8:00 A.M.

9:00 A.M.

10:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

Standard CNC Technician Carpenter

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

HeadcountTotal

3

3

3

3

0

3

3

3

3

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

Saturday

Sunday

Carpenter to asseble (glue) floor sandwich cassettes: Plywood - insulation - Plywood

Drive 04:00-12:00

Lorry driver to take cargo to site for helicopter pick-up

Windows, doors

Carpenter to cut & construct/asseble (glue) wall sandwich cassettes: OSB - insulation - OSB & windows & doors

Drive 10:00-18:00

Lorry driver to take extras & amenities from helicopter back to London

Roof cassettes

Carpenter to asseble (glue) roof sandwich cassettes: Plywood - insulation - Plywood

Helicopter runs

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

2

CNC roof board

11:00 A.M.

7:00 P.M.

8:00 P.M.

Sick?

CNC roof board

PA

10:00 A.M.

6:00 P.M.

2

8:00 A.M.

9:00 A.M.

5:00 P.M.

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap

CNC Wall

2

2

CNC roof board

Floor Cassette

Column

9:00 A.M.

Standard CNC Technician Carpenter

HeadcountTotal

0

8:00 A.M.

Week 3

Wednesday

HeadcountTotal

0

Project Architect, supervising project.

Site Organisation

8:00 P.M.

0

2

CNC insulation

CNC technician cutting boards for floor cassettes

7:00 P.M.

2

Wednesday

9:00 A.M.

6:00 P.M.

2

CNC floor board

2

5:00 P.M.

TOTAL hours worked

Helicopter to take cargo to construction site in three runs.

Roof structure

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

16

HeadcountTotal

3

3

3

3

0

3

3

3

3

11:00 A.M.

12:00 P.M.

TOTAL 8 8 0 0 0 0

TOTAL 8 8 8 0 0 0 24 TOTAL 8 8 8 0 0 0 24 TOTAL 8 8 8 0 0 0 24 TOTAL 0 0 0 0 0 0

Tuesday Standard CNC Technician Carpenter

HeadcountTotal

TOTAL 0 0 0 0 0 0

8:00 A.M.

9:00 A.M.

10:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

Loading Lorry

Loading Lorry

Loading Lorry

Loading Lorry

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

3

3

3

3

0

4

4

4

8:00 A.M.

Standard CNC Technician Carpenter

PA

PA

PA

PA

PA

PA

PA

PA

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

HeadcountTotal

Thursday

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

7:00 P.M.

8:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

3

0

3

3

3

3

0

0

0

0

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Loading Lorry

Loading Lorry

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

Column

Column

Column

Column

Column

Column

Column

Column

HeadcountTotal

2

2

2

2

0

2

2

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

PA

PA

PA

PA

Sick?

0

11:00 A.M.

Loading Lorry

HeadcountTotal

6:00 P.M.

3

Loading Lorry

Sunday

5:00 P.M.

10:00 A.M.

PA

Sick?

0

3

PA

Saturday

8:00 P.M.

9:00 A.M. PA

HeadcountTotal

7:00 P.M.

3

PA

Friday

6:00 P.M.

8:00 A.M.

Standard CNC Technician Carpenter

Standard Lorry Driver Pilot

5:00 P.M.

4

Wednesday

HeadcountTotal Sick?

8:00 A.M.

Standard CNC Technician Carpenter

0

4:00 P.M.

Monday

Week 4

8 8 0 0 0 0

16

0

5:00 P.M.

TOTAL hours worked

0

0

0

Sick?

Sick?

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

PA

Load Helicopter

PA

Load Helicopter

Site organisation

Site organisation

Site organisation

Helicopter run 1

Helicopter run 1

Helicopter run 2

Helicopter run 2

Helicopter run 3

Helicopter run 3

Sick?

Drive 04:00-12:00 Drive 04:00-12:00 Drive 04:00-12:00 Drive 04:00-12:00

2

2

2

2

0

3

3

3

3

3

3

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

Sick?

Standard

24

HeadcountTotal

TOTAL 12 8 8 0 0 0

TOTAL 20 8 8 0 0 0 34 TOTAL 12 8 8 0 0 0 28 TOTAL 24 8 6 0 0 0 38 TOTAL 0 0 0 0 0 0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

Tuesday Standard Unskilled labour 1 Unskilled labour 2 Unskilled labour 3 Unskilled labour 4 HeadcountTotal

Wednesday Standard

HeadcountTotal

Thursday Standard Pilot Lorry Driver

HeadcountTotal

Friday

HeadcountTotal

Saturday

HeadcountTotal

0

4:00 P.M.

Monday

8 8 8 0 0 0

28

0

Load Helicopter

TOTAL hours worked

Sick?

TOTAL 0 0 0 0 0 0

Sunday

HeadcountTotal

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

Floor assembly

Floor assembly

Floor assembly

Floor assembly

2

2

2

2

0

12:00 P.M.

PA placing second part of column, assembling/ mounting roof & applying roof felt & membrane

1st woodstain ap

PA applying first coat of Woodstain onto outer OSB wall boards. Drying time 4-6h (over night)

2nd woodstain ap

PA applying second coat of Woodstain onto outer OSB wall boards. Drying time 4-6h (over night)

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

24 0 0 0 0 0

2

2

2

2

2

2

2

2

24

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

5

5

5

5

0

2

2

2

2

12:00 P.M.

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

Windows, doors

Windows, doors

Windows, doors

Windows, doors

1

Sick?

Sick?

1

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

1

1

1

1

0

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Load Helicopter

PA

Loading Lorry

PA

PA

PA

PA

PA

Helicopter run 1

Helicopter run 1

0

0

0

0

1

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

Carpenter to drill holes in bottom of first part of columns

As these processes will be overlapping, it is important that time is kept fairly well throughout the process of preconstruction and construction.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

TOTAL 24 8 8 8 8 0 56

Sick?

TOTAL 24 0 0 0 0 0 24

Sick?

TOTAL 11 2 8 0 0 0 21

Sick?

TOTAL 0 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00 Drive 10:00-18:00

Extra - placing second part of column, assembling/ mounting roof & applying roof felt & membrane

TOTAL hours worked

1:00 P.M.

Roof structure

PA /mouning wall cassettes, windows & doors

Roof structure

12:00 P.M.

0

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

13


1.0_As Designed Site Tools Both prior to and during construction, we have scoped out costs we are likely to incur which have to with site, tools and machinery. With regards to the site, we are likely to hire a wood workshop throughout the manufacturing process. This wood workshop will be used not only to assemble cassettes, doors and windows but also, as storage up until departure date. The cost here would be the cost to hire the workshop out solely for our needs for a set number of days. The second phase of costing with regards to the site would be incurred during construction. This a more general cost and this has been outlined in the table below. This costs include securing the site and providing artificial lighting for work to commence in low natural light. With regards to tools, we have outlined the use of a general purpose hammer, of which you can have multiple. The second is standard 40-50mm round head galvanised steel nails. A box of 100 of these should suffice.

There will be no machinery used on site which has not already been costed for. All machinery used will be pre-construction but has been factored into CNC milling costs. These items have a total cost of £890.75p. As some of these items will be hired, they will also have a cost associated with transporting them back to mainland. Most items have an unconfirmed weight but it is safe to assume they would be too heavy for a quad bike to transport back to mainland. We have made a special arrangement with the helicopter company and agreed that we can add an extra trip after construction has finished to airlift these items back to mainland from where a 3.5 tonne lorry can drive them back to their various depots.

General Site Equipment

No.

Supplier

Delivery (£)

Cost Per Day (£)

Cost Per Week (£)

Time Required

Total Cost (£)

Mesh Fence Kit

16

HHS Hire

45

0.96

6.77

7 Days

108.32

Festoon Lights

2

HHS Hire

45

5.2

37.06

7 Days

74.02

Leica Disto S1 Laser Distance Meter

1

sccssurvey

0

N/A

N/A

N/A

85

Secure Tool Store

1

HHS Hire

45

N/A

65.36

7 Days

65.36

Wickes Multi Purpose Tarpaulin 4x5m

2

Wickes

0

N/A

N/A

N/A

19.98

Gorilla Glue Wood Glue 532Ml

8

ScrewFix

0

0

0

N/A

45

Multi Mode Ladder

2

HHS Hire

45

5

35.46

7 Days

70.92

Estwing Surestrike Curved Claw Hammer

4

Wickes

0

N/A

N/A

N/A

79.96

Portable Suitcase Generator

1

HHS Hire

45

N/A

77.39

7 Days

77.39

Questionable items: Site Toilet, Skip, Adjustable Trestle

625. 5 225 Delivery: Total Including VAT and Delivery: 76.1 Total Cost:

14


1.0_As Designed Site Tools

Secure Tools Storage

Portable Suitcase Generator

Multi-Mode Ladder

Feston Lights

Mesh Fence Kit

Tarpaulin

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

Surestrike Curved Claw Hammer

Gorilla Glue

Laser Site Measure

15


1.0_As Designed Cost Summary & Evaluation The date presented on this page is full summary, derived from all the information in the breakdowns on prior pages. Although we feel this cost is relatively what we had expected, there are individual costs that stand out. In particular, costs of plywood and it’s CNC is something we feel can be value-engineered and lowered. Furthermore, the cost of windows is incredibly high. This maybe due to their bespoke design. We will look to simplify this design. This may have a knock-on effect on other items such as walls. With VAT returned, the total cost of the build is £26, 015.10 (according to market research). Item Category

a

Columns Floor Structure

oints

Ply Floor Cassette Panels (Top

anu acture Cost

Delivery

Delivery Time days

anu acturing Time days

Total Cost

1344

600

1

14

1944

1082.87

501.6

3

14

1584.47

1969.24

912

3

14

2881.24

Roo Structure

431.04

273.6

3

14

704.64

Roo Flashing

143.68

91.2

3

14

234.88

1724.16

1094.4

3

14

2818.56

Ply Roo Cassette Panels (Top Wall Panels

S 3 ( nside

ottom)

aterial Cost

ottom)

297.6

1094.4

3

14

1392

nsulation

utside)

2859.87

2485.2

3

14

5345.07

Doors and Windows

2099.29

2099.29

N/A

0

2

14

Foundations

78

N/A

16.3

1

N/A

78

Roo Cover

138

N/A

0

1

N/A

138

Time equired or Days

Cost

Total

Additional Items Transport to Site Truck and Helicopter

2

2930

Labour

8

2560

Transport rom site Returns

1

515

Hiring Site Equipment

7

625.95

Hiring Wood Workshop

7

164

Total

Total Cost Delivery Total Including VAT and Delivery

16

26015.1 16.3 31,23 . 2

Structure Re ers to the gridded system o plywood which makes up the roo and loor structure as well as the glulam columns Cassette Panels Re ers to the cassette panels which make up the cassettes which go in the loor and roo Delivery Time Re ers to the average delivery times Foundation Re ers to sca olding screw jack Roo Cover Felt and Membrane


1.0_As Designed Conclusion Although we will value engineer our design to bring costs down, we would at this stage like to say that a lot of the costs we’ve incurred have not surprised us. The costs for CNC’ing is high but justified for its degree of efficiency and accuracy. The cost of material is high too but it has been carefully considered for its performance. In this initial exercise we have determined that our main focus was on Qualitiy and Time (for manufacture and build). This reflects our design aims and is somewhat portrayed in this cost report. Price has suffered and we will look to find a greater balance between these three elements.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

17


VALUE ENGINEERED

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

18


2.0_Value Engineered Component Analysis Some of the key points we have highlighted for consideration are: 1) Plywood wall, roof and floor cassette panels. These have proved to be really expensive and we have began to question in detail the pros and cons for keeping the material as is. 2) Insulation along the perimeter (external). Our initial reasoning for having insulation along the external perimeter was that the building we have designed has the scope to expand, and so, as the designers, we have designed in the provision for it’s expansion. However, this is a realistic question to be asked of the client/investor who may or may not be adamant that the building should and will always remain at 36m2 internal floor area. In this case, we think the total cost will be affected if insulation is reduced.

Floor Component Scaffolding Screw Jacks (Foundations) Floor Joists - Primary Structure - plywood Floor Joists - Secondary Structure - plywood Floor Cassette Top and Bottom Panels Floor Structure Joints (Small) Thermafloor TF70 120mm (Insulation)

Total Cost: Total Delivery: Total Inc VAT:

Component No. C01 F01's F02's & F03's F04's F00's F04

# of CPNT 12 24 118 384 551 12

Supplier scaffoldingsupplies Latham Timber Latham Timber Latham Timber Latham Timber Kingspan

Dimensions (mm) Cost per Item (£) Per Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) 500 6.5 Unit 16.3 78 n/a 78 3050 x 1220 50.71 Board * 304.26 136.8 441.06 3050 x 1220 50.71 Board * 760.65 342 1102.65 3050 x 1220 50.71 Board * 1969.24 912 2881.24 2440 x 600 17.96 Board * 17.96 22.8 40.76 2400 x 1200 87.16 2 sheets p/pack 0 1045.92 547.2 1593.12

6136.83 16.3 7,380.50

Most expensive components in floor and roof are Insulation and Plywood cassette panels Column Roof Component Columns - lulam Roof Structure - Primary - plywood Roof Structure - Secondary - plywood Roof Cassette Top and Bottom Panels Thermaroof TP10 (Insulation) 1000 auge Polythene DPM 300mu I Black Shed Felt Roof Flashing - plywood Roof ocking Disks - plywood alvanised tra arge Clout Nails

Total Cost: Total Delivery: Total Inc VAT and Delivery:

19

Component No. # of CPNT Supplier Dimensions (mm) Cost per Item (£) Per Delivery Cost (£) Raw Material (£) MFR Cost (£) Total Cost (£) C03 12 Co le Timber artners 150x150x3800 93.33 column incl. 1344 600 1944 02's 03's 04's 72 Latham Timber 2440 x 1220 35.92 Board * 323.28 205.2 528.48 05's 17 Latham Timber 2440 x 1220 35.92 Board * 107.76 68.4 176.16 06 & 09 96 Latham Timber 2440 x 1220 35.92 Board * 1724.16 1094.4 2818.56 07 8 Kingspan 2400 x 1200 113.34 3 sheets p/pack 0 906.72 364.8 1271.52 1 insulation4less 250000x4000 38 Unit 0 38 n/a 38 8 ickes 10000x1000 20.99 Unit 0 100 n/a 100 08's 14 Latham Timber 2440x1220 35.92 Board * 143.68 91.2 234.88 01's 68 Latham Timber 2440x1220 35.92 Board * 71.84 45.6 117.44 1 ickes 20 2.99 ack of 400 0 2.99 n/a 2.99

7232.03 0 8,678.


2.0_Value Engineered Component Analysis

Item Category

a

Columns Floor Structure

oints

Ply Floor Cassette Panels (Top

anu acture Cost

Delivery

Delivery Time days

anu acturing Time days

Total Cost

1344

600

1

14

1944

1082.87

501.6

3

14

1584.47

1969.24

912

3

14

2881.24

Roo Structure

431.04

273.6

3

14

704.64

Roo Flashing

143.68

91.2

3

14

234.88

1724.16

1094.4

3

14

2818.56

Ply Roo Cassette Panels (Top Wall Panels

S 3 ( nside

ottom)

aterial Cost

ottom)

297.6

1094.4

3

14

1392

nsulation

utside)

2859.87

2485.2

3

14

5345.07

Doors and Windows

2099.29

2099.29

N/A

0

2

14

Foundations

78

N/A

16.3

1

N/A

78

Roo Cover

138

N/A

0

1

N/A

138

Total

As the above schedule shows, the plywood cassettes and OSB panels have the same manufacture cost as they are the same quantity. However, there total costs vary drastically as there raw material costs are so different. It is this precise difference we wish to exploit in this value engineering exercise. Furthermore, although the total floor area is 69m2, the total inhabitable floor area is 36m2. By removing insulation from the non-inhabitable floor area, we are planning to cut the total insulation down by a third almost. This too will drastically impact the final cost. However, in doing so, this will have other design implications.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

20


2.0_Value Engineered Detail Changes Few changed have been placed in value engineering process to save some money. Most important change is the all top and bottom panels for both roof and floor have been changed to OSB. OSB is much more environmental friendly material and is much more cheaper comparing with plywood. OSB is very efficient for temporary structure solutions, but it lacks for permanent efficiency, as its not good for waterproofing and direct sun. In order to fix this issue if building is required to be permanent all the osb that faces the outside will be stained. The overhang roof and decking use to have insulation placed inside, but its use in those locations is very small and limited. Also by removing it from roof overhang and decking we have nearly saved half of the money we were originally spending for insulation. In same time we can remove the bottom plywood panels where roof overhangs.

Plywood is more expensive however, is easier to handle and poses fewer long term maintenance issues

21

As designed - Insulation throughout

Insulation omitted from external overhang and decking

OSB is considerably cheaper and although has maintenance issues, these are not very costly


2.0_Value Engineered Detail Changes

Plywood changed to OSB All top panels and bottom panels are changed in roof to OSB

Insulation taken out

Insulation taken out in overhang roof

OSB Stained Stained OSB on bottom panels where roof overhangs

Plywood taken out As there is no more insulation, plywood is no more necessary in this location.

OSB Stained Yellow indicated all the places where OSB is required to be stained.

Insulation taken out

Insulation taken out inside decking

Plywood taken out As there is no more insulation, plywood is no more necessary in this location.

Plywood changed to OSB Plywood changed for tom and bottom panels in floor to OSB.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

OSB Stained Insulation Removed Plywood changed to OSB Plywood Removed

22


2.0_Value Engineered Schedule of Components Clearly, the changes we have propsed are yielding considerable saving. From the ‘As Designed’ portion to these Value Engineered figures, our proposed changes will save approximately £7500. That is well over a third worth of savings.

Total Cost: Total Delivery: Total Inc VAT and Delivery:

1

06.53 236.3 23,52 .1

As Designed Total Cost of Components

Total Cost: Total Delivery: Total Inc VAT:

11888.3 236.3 1 ,502.26 Value Engineered Total Cost of Components

Pie chart for value engineered component costs

23


2.0_Value Engineered Schedule of Components

Taken out Cost owered Increase of cost

Floor Component Scaffolding Screw Jacks (Foundations) Floor Joists - Primary Structure Floor Joists - Secondary Structure Floor Cassette Top and Bottom Panels Floor Structure Joints (Small) Thermafloor TF70 120mm (Insulation)

Total Cost: Total Delivery: Total Inc VAT:

Component No. C01 F01's F02's & F03's F04's F00's F04

No. 12 24 118 288 551 7

Supplier scaffoldingsupplies Latham Timber Latham Timber Latham Timber Latham Timber Kingspan

Dimensions 500mm 3050 x 1220mm 3050 x 1220mm 2997 x 1197 2440 x 600mm 2.4m x 1.2m

Delivery Raw Material (£) Manufacture Cost (£) 16.3 * 304.26 136.8 * 760.65 342 * 186 684 * 17.96 22.8 0

Total Cost (£) 78 441.06 1102.65 870 40.76 360.15

No. 12 72 17 72 5 1 8 14 68 1 3 2

Supplier Co le Timber artners Latham Timber Latham Timber Latham Timber Kingspan insulation4less ickes Latham Timber Latham Timber ickes ickes ickes

Dimensions 150x150x3800mm 2440 x 1220mm l 2440 x 1220mm l 2997 x 1197 B 2.4m x 1.2m 25m x 4m 10m x 1m 2440 x 1220mm l 2440 x 1220mm l 20mm 40mm 4x 40mm

Cost per Item (£) Per Delivery Raw Material (£) Manufacture Cost (£) 93.33 column incl. 35.92 Board * 431.04 273.6 35.92 Board * 107.76 68.4 6.2 Board * 223.2 820.8 113.34 pack of 3 0 38 Unit 0 20.99 Unit 0 35.92 Board * 143.68 91.2 35.92 Board * 71.84 45.6 2.99 ack of 400 0 7.49 pack of 20 0 6.99 pack of 125 0

Total Cost (£) 1344 704.64 176.16 1044 567.7 38 100 234.88 117.44 2.99 22.47 13.98

No. 104 23 2

Supplier Latham Timber Kingspan adolin

Dimensions 2997 x 1197 B 1.2m x 2.4m 32m2 each

Cost per Item (£) 6.2 52.3 32.99

Per Board Unit Unit

Delivery Raw Material (£) Manufacture Cost (£) * 297.6 1094.4 0 0

Total Cost (£) 1392 907.2 230.93

No. 2 2 1

Supplier ickes ickes ickes

Dimensions 2032 x 813mm 2000 x 807 mm /

Cost of Item (£) 79.99 72.99 44.99

Per Full frame Unit ack of 3

Delivery Raw Material (£) Manufacture Cost (£) 0 0 0

Total Cost (£) 159.98 145.98 44.99

No. 8 4 64 16

Supplier bespoke ickes ickes glass outlet

Dimensions 550x 2629 x 125 mm 950 mm 40x40x40 mm 2527 x 474 x 6.7 mm

Cost of Item (£) 90 15.99 1.49 43

Per Full Frame Unit Unit Unit

Delivery Raw Material (£) Manufacture Cost (£) 0 0 0 45

Total Cost (£) 900 63.98 95.36 689

l l B l

Cost per Item (£) 6.5 50.71 50.71 6.2 17.96 87.16

Per Unit Board Board Board Board pack of 2

28 2.62 16.3 3, 87.

Column Roof Component Columns Roof Structure - Primary Roof Structure - Secondary Roof Cassette Top and Bottom Panels Thermaroof TP10 (Insulation) 1000 auge Polythene DPM 300mu I Black Shed Felt Roof Flashing Roof ocking Disks alvanised tra arge Clout Nails ickes 0mm inc Plated Angle Brackets Spa MDF Screws

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No. C03 02's 03's 04's 05's 06 & 09 07

08's 01's

366.26 0 523 .512

alls Component SB Panels Inside and utside Thermawall T 55 PIR Insulation Board Sadolin Classic oodstain 2.5

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No. ll 's

2530.13 0 3,036.16

Doors Component ickes terior Premium Door Frame ardwood Ply Veneer Flush terior Fire Door atch andle Set Polished Chrome Finish

Total Cost: Total Delivery: Total Inc VAT and Delivery:

Component No.

350. 5 0 21.1

indows Component Tim er Frame Aluminium Sill Steel Brackets lass

Total Cost: Total Delivery: Total Inc VAT and Delivery:

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

Component No.

17 8.3 0 2,0 8.01

24


2.0_Value Engineered Schedule of Works

25


2.0_Value Engineered Schedule of Works

Schedule of work

Project Schedule May 1, 2017

Start Week Week Starting

2

1 Mon

Tue

1

2

Wed Thu 3

4

Fri

Sat

Sun

Mon

Tue

5

6

7

8

9

Wed Thu 10

11

3

4

Fri

Sat

Sun

Mon

Tue

Wed

Thu

Fri

Sat

Sun

Mon

Tue

12

13

14

15

16

17

18

19

20

21

22

23

Wed Thu 24

25

Fri

Sat

Sun

26

27

28

Action

Hours

£ Cost per Action

Time

0

08:00 - 17:00

Standard - PA

Person

Phase 1

Project Architect. Free labour, 1-2 persons

Preconstruction

CNC cutting

18

1134

08:00 - 17:00

Technician

CNC cutting

10

630

08:00 - 17:00

Carpenter

CNC cutting

12

756

08:00 - 17:00

Pilot

CNC cutting

12

756

08:00 - 17:00

Lorry Driver

CNC cutting

24

1512

08:00 - 17:00

4 additional unskilled labour

CNC cutting

20

1260

08:00 - 17:00

Carpenter Assembly

10

423

08:00 - 17:00

Carpenter Assembly

12

503

08:00 - 17:00

Carpenter Assembly

8

343

08:00 - 17:00

Carpenter Assembly

8

343

08:00 - 17:00

PA Task

0

08:00 - 17:00

PA Task

0

08:00 - 17:00

Phase 2

Lorry Transport

8

480

04:00 - 12:00

Transport

Helicopter Transport

6

2450

12:00 - 18:00

0

08:00 - 20:00

4x8

320

08:00 - 17:00

0

08:00 - 20:00

2

175

08:00 - 10:00 10:00 - 18:00

Phase 3

PA Task

Construction

Unskilled Labour Task

Phase 4

Clearing Site - PA Task/Helicopter Transport

PA Task

Windup £ Cost per day

Work & Cost

504 504 504 567 567

567 567 521 504 504

504 504 2930

0

320

0

175 340

0

Lorry Transport

8

340

For details see Schedule of Labour

190h

Total: 11,425

Cost Tot £

Wood Workshop

115

Carpenter

1520

Transport Heli

2625

Transport Lorry

820

Unskilled Labour CNC Lab TOTAL

6044

320 11,425

By reducing material it is also clear that the amount of hours and cost spent on CNC and Carpenter is significantly reduced, which in turn further reduce the cost and time to produce building package. _ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

26


2.0_Value Engineered Schedule of Labour

27


2.0_Value Engineered Schedule of Labour

Shift Schedule

For the Week of: Department Name:

Week 1 Monday Standard CNC Technician

HeadcountTotal

Tuesday Standard CNC Technician

HeadcountTotal

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

2

8:00 A.M.

2

9:00 A.M.

2

10:00 A.M.

12:00 P.M.

Week 2

2

0

11:00 A.M.

12:00 P.M.

2

2

1:00 P.M.

2:00 P.M.

2

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

CNC floor board

2

2

2

0

11:00 A.M.

12:00 P.M.

2

2

2

Wednesday

8:00 A.M. PA

PA

PA

PA

PA

PA

PA

PA

CNC floor board

CNC floor board

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC insulation

HeadcountTotal

Thursday

2

8:00 A.M.

2

9:00 A.M.

10:00 A.M.

2

10:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

2

0

2

2

2

2

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

Standard CNC Technician Carpenter

PA

PA

PA

PA

PA

PA

PA

PA

CNC insulation

CNC insulation

CNC insulation

CNC insulation

CNC wall

CNC wall

CNC wall

CNC wall

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

Floor cassettes

HeadcountTotal

3

3

3

3

3

3

3

3

Friday Standard CNC Technician Carpenter

HeadcountTotal

Saturday

HeadcountTotal

Sunday

HeadcountTotal

CNC floor board CNC insulation CNC walls CNC roof board CNC floor struct. CNC roof struct.

8:00 A.M.

9:00 A.M.

10:00 A.M.

0

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC wall

CNC wall

CNC wall

CNC wall

CNC wall

CNC wall

CNC wall

CNC wall

Floor cassettes

Floor cassettes

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

3

8:00 A.M.

3

9:00 A.M.

3

10:00 A.M.

3

0

11:00 A.M.

12:00 P.M.

3

3

1:00 P.M.

2:00 P.M.

3

3:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

CNC technician cutting boards for floor cassettes CNC technician cutting boards of insulation to right formats for floor cassettes, wall cassettes & roof cassettes CNC technician cutting columns, windows, doors CNC technician cutting roof boards for roof cassettes CNC technician cutting primary and secondary floor joists CNC technician cutting primary and secondary roof beams

After Value Engineering we changed some material from plywood to OSB but also reduced the amount of material. This means that it became possible to compress the time schedule, which now

PA Loading Lorry Load Helicopter

PA setting up amenities, safety fence around site peremises, setting up generator, cover cargo

Wrapping

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

6:00 P.M.

7:00 P.M.

8:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

TOTAL hours worked

Monday

9:00 A.M.

10:00 A.M.

11:00 A.M.

PA

PA

PA

PA

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

CNC roof board

CNC roof board

CNC roof board

CNC roof board

Windows, Doors

Windows, Doors

Column

Column

3

3

3

Standard CNC Technician Carpenter

CNC roof board

CNC roof board

CNC roof board

CNC roof board

Windows, Doors

Windows, Doors

Windows, Doors

Windows, Doors

16

HeadcountTotal

3

3

3

3

0

3

11:00 A.M.

12:00 P.M.

TOTAL 8 8 0 0 0 0

TOTAL 8 8 0 0 0 0 16 TOTAL 8 8 8 0 0 0 24 TOTAL 8 8 8 0 0 0 24

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Tuesday

9:00 A.M.

10:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

PA

PA

PA

PA

PA

PA

PA

PA

CNC roof board

CNC roof board

CNC roof board

CNC roof board

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

Column

Column

Column

Column

Column

Column

Roof cassette

Roof cassette

HeadcountTotal

3

3

3

3

0

3

3

3

3

12:00 P.M.

Wednesday

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

Standard CNC Technician Carpenter

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

Roof cassette

HeadcountTotal

3

3

3

3

0

4

4

12:00 P.M.

Thursday

3

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

1st woodstain ap

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

CNC floor struct.

HeadcountTotal

3

3

3

3

3

3

3

3

Friday Standard CNC Technician

HeadcountTotal

Saturday

Sunday

Floor Cassette

Carpenter to asseble (glue) floor sandwich cassettes: Plywood - insulation - Plywood

Drive 04:00-12:00

Lorry driver to take cargo to site for helicopter pick-up

Windows, doors

Carpenter to cut & construct/asseble (glue) wall sandwich cassettes: OSB - insulation - OSB & windows & doors

Drive 10:00-18:00

Lorry driver to take extras & amenities from helicopter back to London

Roof cassettes

Carpenter to asseble (glue) roof sandwich cassettes: Plywood - insulation - Plywood

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

0

12:00 P.M.

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap CNC floor struct.

3

8:00 A.M.

CNC floor struct.

3

9:00 A.M.

CNC floor struct.

3

10:00 A.M.

11:00 A.M.

2:00 P.M.

3:00 P.M.

CNC roof struct.

0

12:00 P.M.

3

1:00 P.M.

CNC roof struct.

3

2:00 P.M.

CNC roof struct.

3

3:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

Helicopter runs

6:00 P.M.

7:00 P.M.

4:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

Helicopter to take cargo to construction site in three runs.

Roof structure

CNC roof struct.

3

0

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

TOTAL hours worked

Standard CNC Technician

24

HeadcountTotal

TOTAL 8 8 8 0 0 0

TOTAL 12 8 6 0 0 0 28 TOTAL 16 8 0 0 0 0 24 TOTAL 16 8 0 0 0 0 24

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Tuesday

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap CNC roof struct.

CNC roof struct.

CNC roof struct.

3

3

3

3

0

11:00 A.M.

12:00 P.M.

9:00 A.M.

10:00 A.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

2

2

2

3

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

0

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

PA

PA

PA

PA

Loading Lorry

Loading Lorry

Loading Lorry

Loading Lorry

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

CNC roof struct.

HeadcountTotal

2

2

2

2

0

3

3

3

3

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

PA

PA

PA

PA

Load Helicopter

PA

Load Helicopter

PA

Load Helicopter

Site organisation

Site organisation

Site organisation

Wednesday Standard Lorry Driver Pilot

HeadcountTotal

Thursday Standard

HeadcountTotal

Friday Standard Unskilled labour 1 Unskilled labour 2 Unskilled labour 3 Unskilled labour 4 HeadcountTotal

Saturday

Sunday

HeadcountTotal

Sick?

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap

CNC roof struct.

8:00 A.M.

1:00 P.M.

Week 4

Standard CNC Technician

HeadcountTotal

0

0

Monday

8 8 8 0 0 0

24

2nd woodstain ap 2nd woodstain ap 2nd woodstain ap 2nd woodstain ap

CNC floor struct.

3

1:00 P.M.

5:00 P.M.

3

Standard CNC Technician

HeadcountTotal

0

8:00 A.M.

Standard CNC Technician Carpenter

HeadcountTotal

0

Column

8:00 A.M.

8 8 0 0 0 0

16

0

5:00 P.M.

Project Architect, helping to load cargo onto Lorry

PA setting screw jacks & columns in grid, assembling /mouning floor structre & slotting in floor cassettes.

5:00 P.M.

4:00 P.M.

Project Architect, helping to load cargo onto Helicopter

Floor assembly

8:00 P.M.

0

3

Project Architect, supervising project.

Site Organisation

7:00 P.M.

2

Standard CNC Technician

9:00 A.M.

6:00 P.M.

2

CNC floor board

2

5:00 P.M.

Week 3

Sick?

0

Sick?

2

2

2

2

0

12:00 P.M.

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

Floor assembly

Floor assembly

Floor assembly

Floor assembly

2

2

2

2

0

Helicopter run 2

Helicopter run 2

Helicopter run 3

Helicopter run 3

3

3

3

3

3

3

2

2

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

Floor assembly

2

2

2

2

2

2

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

Roof structure

5

5

5

5

5

5

5

5

2

2

2

2

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

Helicopter run 1

0

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Sick?

Sick?

Standard

20

HeadcountTotal

TOTAL 12 8 0 0 0 0

TOTAL 24 8 6 0 0 0 38 TOTAL 24 0 0 0 0 0 24 TOTAL 24 8 8 8 8 0 56

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Tuesday Standard Pilot

HeadcountTotal

Wednesday Standard Lorry Driver

HeadcountTotal

Thursday

HeadcountTotal

Friday

HeadcountTotal

Saturday

HeadcountTotal

0

0

Monday

12 8 0 0 0 0

20

Drive 04:00-12:00 Drive 04:00-12:00 Drive 04:00-12:00 Drive 04:00-12:00 Helicopter run 1

TOTAL hours worked

Sunday

HeadcountTotal

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

Roof structure

Roof structure

Roof structure

Roof structure

2

2

2

2

0

12:00 P.M.

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

Windows, doors

Windows, doors

Windows, doors

Windows, doors

PA placing second part of column, assembling/ mounting roof & applying roof felt & membrane

1st woodstain ap

PA applying first coat of Woodstain onto outer OSB wall boards. Drying time 4-6h (over night)

2nd woodstain ap

PA applying second coat of Woodstain onto outer OSB wall boards. Drying time 4-6h (over night)

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

Windows, doors

24 0 0 0 0 0

2

2

2

2

2

2

2

2

24

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

1:00 P.M. Load Helicopter

PA

Helicopter run 1

Helicopter run 1

2

2

2

0

3

2

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

Loading Lorry

PA

PA

PA

PA

PA

PA

Sick?

Sick?

0

2

2

2

2

1

2

2

2

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

4:00 P.M.

5:00 P.M.

6:00 P.M.

7:00 P.M.

8:00 P.M.

0

0

0

0

0

0

0

0

8:00 A.M.

9:00 A.M.

10:00 A.M.

11:00 A.M.

12:00 P.M.

1:00 P.M.

2:00 P.M.

3:00 P.M.

0

0

0

0

0

0

0

0

Carpenter to drill holes in bottom of first part of columns

saves both time and expenses. The somewhat troublesome transports makes it difficult to further optimize the schedule. _ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

TOTAL 11 2 0 0 0 0 13

Sick?

TOTAL 8 8 0 0 0 0 16

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Sick?

TOTAL 0 0 0 0 0 0

Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00 Drive 08:00-16:00

Extra - placing second part of column, assembling/ mounting roof & applying roof felt & membrane

TOTAL hours worked

1:00 P.M. Windows, doors

2

PA /mouning wall cassettes, windows & doors

Roof structure

12:00 P.M.

0

0


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

28


2.0_Value Engineered Site Tools With the change in design, there were various changes made to the tools schedule. However, these were not considered to be great.

Taken out Cost owered Increase of cost General Site Equipment

No.

Supplier

Delivery (£)

Cost Per Day (£)

Cost Per Week (£) Time Required

Total Cost (£)

Mesh Fence Kit Festoon Lights

2

HHS Hire

45

5.2

37.06

7 Days

Leica Disto S1 Laser Distance Meter

1

sccssurvey

0

N/A

N/A

N/A

74.02 85

Secure Tool Store

1

HHS Hire

45

N/A

65.36

7 Days

65.36

Wickes Multi Purpose Tarpaulin 4x5m

2

Wickes

0

N/A

N/A

N/A

19.98

Multi Mode Ladder

2

HHS Hire

45

5

35.46

7 Days

70.92

Estwing Surestrike Curved Claw Hammer

2

Wickes

0

N/A

N/A

N/A

39.98

Portable Suitcase Generator

1

HHS Hire

45

N/A

77.39

7 Days

77.39

2 Speed Percussion Drill

2

HHS H ire

45

10.34

20.68

7 Days

41.36

Gorilla Glue Wood Glue 532Ml

Questionable items: Site Toilet, Skip, Adjustable Trestle

7 .01 225 Delivery: Total Including VAT and Delivery: 7 3.812 Total Cost:

29


2.0_Value Engineered Cost Illustrations The following images explain our cost based decisions in a more visual format.

CNC Technician

Our CAD files

CNC Machine - £6619.20

All CNC material has been quoted for and so the cost to manufacture would be paid in one lump sum of £6619.20

Workshop space required for 4.75 days: £115 hire

Carpenter to be paid £1520 for 38hours of work

Carpenter to work assemble cassettes in workshop. Paid hourly. Total estimated to £1520 + £115 workshop space hire = £1635 _ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

30


2.0_Value Engineered Cost Illustrations

All items to be loaded on to the truck and taken to close proximity of site. Truck hire to site: ÂŁ480

31


2.0_Value Engineered Cost Illustrations Helicopter to site: £2450 used for 6 hours

Helicopter to airlift building parts to remote site. This will be done in three trips.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

32


2.0_Value Engineered Cost Illustrations

Site tool hire: ÂŁ793.81

Site preparation - Items to be hired are specified in Site Tools section.

33


2.0_Value Engineered Cost Illustrations

Cost of four unskilled labourers : £320

Four unskilled labourers required to erect columns and roof structure. This is because two roof structures act together and are locked using a joist piece which keys in between the two. These labourers are solely required to erect the roof structure.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

34


2.0_Value Engineered Cost Summary There is a clear and drastic change which has been made to the total cost of the building as demonstrated in the tables below.

26015.1 16.3 31,23 . 2

Total Cost Delivery Total Including VAT and Delivery

‘As Designed’ final cost evaluation Item Category

a

Columns Floor Structure

oints

S 3 Floor Cassette Panels (Top

ottom)

Roo Structure Roo Flashing

aterial Cost

anu acture Cost

Delivery

Delivery Time days

anu acturing Time days

Total Cost

1344

600

1

14

1944

1082.87

501.6

3

14

1584.47

186

684

3

14

870

538.8

342

3

14

880.8 234.88

143.68

91.2

3

14

223.2

820.8

3

14

1044

297.6

1094.4

3

14

1392

nsulation

1836.65

2485.2

3

14

4321.85

Doors and Windows

2099.29

N/A

2

14

2099.29

Foundations

78

N/A

1

N/A

78

Roo Cover

174.45

N/A

1

N/A

174.45

S 3 Roo Cassette Panels (Top Wall Panels

S 3 ( nside

ottom)

utside)

16.3

Total

Additional Items

Time equired or Days

Cost

Taken out

Transport to Site Truck and Helicopter

2

2930

Cost owered

Labour

8

2560

Increase of cost

Transport rom site Returns

1

515

Hiring Site Equipment

7

625.95

Hiring Wood Workshop

7

164

Total

Total Cost Delivery Total Including VAT and Delivery

35

21 18.6 16.3 25,718.73


2.0_Value Engineered Conclusion Through this task, we were able to learn just how much time-management, material sourcing and unexpected costs are involved in the construction and fabrication of even a small de-mountable building such as the one we have designed. During the design process, we placed an emphasis on ease of on-site construction which has saved us considerable time and money on labour costs, tools, and heavy machinery, but also led to reasonably large off-site fabrication costs. However, for a building of this scale and architectural sophistication we all believe that even before conducting the value engineering exercise, the initial design and construction cost of £31,234.42 (excluding vat) is by no means outrageous. However, through a rigorous process of value engineering our design we were able to get this final value down to £25,718.73 which is an 18% decrease in price. Furthermore, if we look solely at the building itself and the material and fabrication costs, then we managed to navigate a huge 39% decrease in price down from £23,524.14 to £14,502.26 with minimal impact on the finished aesthetic quality and structural stability of the building and only a few resulted costing implications.

One of the major moves we made was to replace all non-structural plywood items in the building, one of the highest pricing material costs in our design (as much as £50.71 per sheet) with OSB3 boards which were far cheaper at £6.20 per board. This alone resulted in a saving of £3785.80, and as you can see from the final two renders in our document hasn’t had a huge impact on the aesthetic experience of our internal spaces. Nevertheless, the OSB3 panels that now existed as an external surface would have to be veneered with a weatherproofing stain to prevent damage from harmful UV rays, although we agreed that the incurred cost of £230.93 and increased off-site fabrication costs were worth the compromise. Another decision we made was to remove the need for insulation and the bottom cassette panels on the external decking and overhanging roof that exist outside our building envelope. The need here for the expensive insulation blocks is negligible and the removal of the bottom cassette panels in this section, whilst damaging to the overall aesthetic continuity of the design, saved us some further expenditure. However, this change wasn’t as straightforward as the

As existing, using plywood for floor and roof cassettes, the total price would £26, 015.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

move to OSB3, and would lengthen the construction time on-site, and involved the sourcing of brackets and screws to retain structural viability. Some of the primary roofing beams would also have to increase in size to now meet the top panels and prevent the insulation blocks being exposed but this only resulted in the minor cost implication of 3 additional plywood boards. Overall, we firmly believe that this exercise of value engineering our design has given us a tremendous insight into the complexity of the fabrication and construction of a de-mountable building and given us a far deeper understanding of our proposal. We conducted a rigorous process which we believe has yielded some incredible savings that none of us could have ever foreseen, without getting into a detailed analysis of the various costs and implications involved in the material sourcing procedure. Our building has taken one step closer to becoming a reality and we are all the wiser for it.

Value Engineered, replacing the plywood cassette panels with OSB3, the total price would be £21, 418.

36


37


Individual Contributions Introduction As designed Component Analysis - Rana + Jonas Schedule of Components - Martins + Freddy Schedule of Works - Jonas Schedule of Labour - Jonas Site, Tools, Machinery - Rana + Martins Cost Summary & Evaluation - Freddy Value-Engineered Detail & Component Analysis - Rana + Jonas Schedule of Components - Martins + Freddy Schedule of Works - Jonas Schedule of Labour - Jonas Site, Tools, Machinery - Rana + Martins Cost Summary & Evaluation - Freddy N.B. The above breakdown is a provisional breakdown of tasks devised very early on in the assignment. However, it is important to note that since commencement of work, there have be incalculable overlaps and we can all vouch that this was most certainly a joint effort. No one member contributed more than the other.

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

38


Appendix - Quotes

39


5,624.29 1,124.858 6,749.148 6.159t

40


Technical Desking Ltd

Costing CNC VARIOUS PANELS

Date:7-03-17 Costing# CNC-454-FM-C

Delivery Address:

TO:

Frederick Mawhood

From:

E1 7PF

CNCaPART

59-63 Whitechapel High Street

Technical Desking Ltd

London

6 Argall Avenue,

E1 7PF

Unit 12 London E10 7QE Tel: 020 3581 0500 e-mail: sales@cncapart.com

SALESPERSON

JOB #

SHIPPING METHOD

SHIPPING TERMS

ah

0454

Local Delivery

On receipt of payment

COLLECTION/ DELIVERY DATE tbc

QUANTITY

ITEM

DESCRIPTION

174 panels

CNC

CNC 174#(approx), Ply & OSB Panels

PAYMENT TERMS 50% deposit, balance prior to collection

LINE TOTAL £3973.00

NB-All Internal corners will have a 6.35mm min radius. No cost is included for sanding of faces or edges.

Delivery

2 deliveries to site over 2 weeks

£220.00

Costs excluding vat.

Total Costing = £5030.60

VAT No: GB 107 4463 29

Registered in England No: 7455484. This is a costing for the goods named, subject to our standard terms & conditions, a copy of which will be supplied on request. E. & O.E. (Errors and Omissions Excepted)

41

Technical Desking Ltd. Registered office: Hathaway House, Popes Drive, London N3 1QF, UK


42 Approximate Total Costing = £9,072.00


43

Approximate Total Costing = £7,800.00


44 Approximate Total Costing = £8,636.064


45


46 Approximate Total Costing = £6546.90


Good evening,

I am looking to get a general quote and timescale for cutting 4 different types of materials, as follows:

. 2440x600 . 3000 x 1220 . 2440x1220

18mm birch plywood 18mm birch plywood 18mm birch plywood

4 sheets 59 sheets 63 sheets

. 3000x1250

9mm OSB panels

48 sheets

We have sourced all the materials ourselves so we are just looking for a rough quotation for how long it would take to cut these sheets and an estimated cost for your services. None of the shapes are too complicated but I ve attached a small dwg file which shows the average shapes we would be looking to cut. We are looking to get this done as soon as possible so a quick response would be amazing. I look forward to your reply and potentially working with you. Delivery address for the finished product would be: 59-63 Whitechapel High Street London E1 7PF

Regards

Frederick Mawhood

47


Good evening,

I am looking to get a general quote and timescale for the following material panels from your website:

. 2440x600 . 3050 x 1220 . 2440x1220

18mm birch plywood Grade BB 18mm birch plywood Grade BB 18mm birch plywood Grade BB

. 2997x1197

9mm OSB3 panels

4 sheets 59 sheets 63 sheets 48 sheets

We are looking to purchase as soon as possible so a quick response would be amazing. I look forward to your reply and potentially working with you. Delivery address for the finished product would be: 59-63 Whitechapel High Street London E1 7PF

Regards

Frederick Mawhood

_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

48


3/7/2017

7.5 Tonne Dropside Truck Hire - Nationwide Hire

(https://www.nationwidehireuk.co.uk/)

Create an Account (https://www.nationwidehireuk.co.uk/customer/account/create/)

|

(https://www.nationwidehireuk.co.uk/customer/account/login/referer/aHR0cDovL3d3dy5uYXRp

Book online or call free on 0500 053 899 (tel:0500053899) Contact us (https://www.nationwidehireuk.co.uk/contact-us/)

Truck Hire in the UK

Free delivery & collection (https://www.nationwidehireuk.co.uk/beneาts/#freedelivery-collection) Free unlimited mileage (https://www.nationwidehireuk.co.uk/beneาts/#freeunlimited-mileage)

European cover (https://www.nationwidehireuk.co.uk/beneาts/#europeancover) One way rentals (https://www.nationwidehireuk.co.uk/beneาts/#one-wayrentals)

Hire Start Hire End

07 Mar, 2017 08 Mar, 2017

Purpose of rental

Private

17 17

45 45

Business

Update

7.5 Tonne Dropside Truck or similar A large 7.5 dropside truck. Great for carrying a variety of di‫ڷ‬erent items. Truck Dimensions https://www.nationwidehireuk.co.uk/trucks-for-hire/7-5-tonne-dropside-truck-4294/

49

1/3


50


3/8/2017

Bench spaces for rent furniture wood work Workshop | in South East London, London | Gumtree

Post an ad

Bench spaces for rent furniture wood work Workshop

ÂŁ700.00pm

South East London, London Images

Map

1 of 9

M Posting for 2+ years

See all ads

Contact details Email Favourite

Report

Posted

5 days ago

Seller type

Private

Date available

03 Mar 2017

Description Bench spaces for rent Workshop located in Abbey Wood (SE London) Bench spaces available in an 8000 sqĺ&#x;” modern well-equipped woodworking https://www.gumtree.com/p/other-commercial-space/bench-spaces-for-rent-furniture-wood-work-workshop-/1220555840

51

1/4


52


53


54


55


The Quarry Grantham Road Waddington Lincoln LN5 9NT Tel: 01522 720022 Fax: 01522 723681 E-mail: mail@cowleytimber.co.uk

QUOTATION - 3183

Date 07-Mar-17

Customer

Project Address

Rana Rehman

East London

Customer REF No.: Customer Contact: Rana Rehman

Quotation Date : Valid to:

Item - Measured Work

Qty

07-Mar-17 07-Apr-17

Rate

Value

Gl28H Spruce Glulam

12

160 x160 x 3800

No.

93.33

1,120.00

Delivery to East London Included

Gross Value

1,120.00

VAT @ 20%

224.00

AMOUNT DUE

1,344.00

All amounts paid are subject to VAT at the standard rate Bank Details: Lloyds Bank Sort Code: 30-63-57 Account No: 28022468 Registered Office: 41 Pear Tree Street ● London ● EC1V 3AG Registered in England No. 09445063 ● VAT No. 207 8987 64

56


57


58


59


_ATA COSTING REPORT 2016-2017 _GROUP 12 _THE LIPARI RETREAT

60