Architectural Practice_Fee proposal and Feasibility study

Page 1

Architectural Practice ABPL90140 SM2 2019
Cover
Group Number 5 Student Name Student Number KAI LIN 825663
Assignment 2 Fee Proposal
Sheet

270 423 ✉ reventarchitecture@gmail.com 219 Abbotsford St, North Melbourne VIC 3051

RE: Fee Proposal for Architectural services- 871 Swanston St, Parkville VIC 3052

Dear Mr. Peter, Thank you for the opportunity to submit our fee proposal for the architectural services of developing new student housing at the above mentioned address. Please find below our fee proposal as requested. We are delighted to work at the opportunity with you on this project and looking forward to a high-quality and most feasible outcome.

1.0 Feasible Solution for the Project :

The approximately 74% of the 12 M budget can be used on the construction based on the distribution diagram below. Therefore, we got the feasible solution to achieve the estimated project budget. There could have more student apartments, but we decided to provide students more social spaces and courtyard. The site is currently using as a open carpark area, So we purposed to build a underground car park to remain the function. The site coverage will be approx. 50%. We purposed to design a “L” shape student housing for maximum sunlight access and minimal negative effect on current conext. Should you require additional information, please do not hesitate to discuss with us.

Lot Size: 816m2

Building Type: Student accommodation

Number of Storeys: 6 x above ground 1 x underground car park

Standard: Medium standard finish with air conditioning

Occupancy: 54 X 30m2 apartments 464m2 Social space with 267m2 courtyard

2.0 Risks

• Underground Encumbrance

3.0 Proposed Fee Summary

According the scale of the project, we have prepared the following fee proposal for your consideration. We charge 6% of the total construction fee which is $648,000 plus GST & Variational cost on construction (Based on the hourly rate). The variational cost triggered when client wants to change the selected specifications and our architects need to verify the particular material to make sure it is safe to use or change designs we agreed. We have itemised our fee for each “Phase of Service”. To allow us to start work on your project a deposit of $64,800 plus GST is required. The deposit will be credited against the final invoice to you.

Included services:

• Scope of work listed below

• Feasibility exploration

• Progress report to Clients

4.0

Scope of Work and Fee

Excluded services:

• All consulting works from other subject listed below

• Reports from consultants & sub-consultant

• 3D (For marketing purpose or photo realistic rendering)

• Charges from Council/ Authorities

• Landscape Design

• Council Meeting

The following is a stage by stage breakdown of the stages, together with our fee allocation for each of these stages: Revent Architect requires clients to approval and make payment when each phase completed and then we can move to the next phase. We have the right to stop work on the project if we did not receive the payment in 14 days

• Amend the conceptual floor plans according to client request

• Prepare project brief for all specialist consultants

• Arrange, attend and record meetings with the client and any other specialist consultants.

• Prepare plans, Elevations, 3D illustrations (for design communication only)

• Develop the approved design concept and present documents and other informaion to adequately explain the developed design.

• Review and Revise the developed (up to 3 revisions)

• Provide schedule of proposed materials and finishes

• Detailed facade design

• Prepare all contract documentation including detailed working drawing, schedules and specifications as are necessary to fully describe the works and methods of construction.

• Ensure that the design and details comply with relevant regulations and codes of practice and meet the requirements of all authorities having jurisdiction.

• Coordinate the design and detailing of structure and services, etc to ensure the design is consistent between all disciplines.

• Provide copies of all drawings and specifications required for permits approvals and contracts

• Prepare documents sufficient for building approval

• Receive and report on conditions of building approval

• Preparation of final architectural documentation based on client approved designs Architecture Work:

Kai Lin (Director) ☎0401
PHASES: 4.1 Pre-design stage & feasibility study 4.2 Design development 4.3 Detailed design stage 4.4 Documentation stage & Building Permit Application 4.5 Contract preparation (Tender) stage 4.6 Contract administration & post construction services (defects) stage
PERCENTAGE 10% 25% 10% 30% 10% 15% FEES $64,800 $ 162,000 $ 64,800 $ 194,400 $ 64,800 $ 97,200 648,000+GST Approx. 300 hours 1 months
4.1. Pre-design & sketch design stage: 4.4. Construction Documentation & Building Permit
4.3. Detailed design
4.2.
Approx. 600 hours 2 months Approx. 200 hours 2 months Approx. 700 hours 3 months
Application:
stage:
Design Development stage:
Site Visit and Analysis
Confirm client’s brief and other requirements
Prepare sketches, diagrams and other information to adequately explain the design, including: design concept, floor plans and furniture layout
29th August 2019

- Plans, Elevations, Sections

- Schedules

- Construction Details - Specifications

• Develop Joinery design and preparation of joinery construction documentation

• Report to client and stakeholders on progress.

4.4. Contract preparation (Tender) stage:

• Contract Administration & Contract negotiation

• Prepare tender documents and issue to all tenderer

• Respond to inquiries from tenderer

• Receive and open the tender

• Together with the quantity consultant assess the tender.

4.5. Contract administration & post construction services (defects) stage:

• Site visit and site meeting at agreed time intervals to review work in progress regarding design quality control

• Review shop drawings submitted by the specialist contractors to ensure architectural design intent is met

• Provide supplementary details and inform where clarification of the contract documents is required including the coordination of relevant consultants when required

• Carry out a review of the works when they are deemed to have reached practical completion, and prepare a defects list to be actioned by the builder.

5.0 Exclusion

5.1

Specialist consultants fees

Approx. 200 hours 2 months Approx. 100 hours 6 months

We require professional consultants to help us on this project, but all consultant fees are excluded from the quote we provide. We have a few consultants worked with us for many years and we would like to recommend them to you. It would effectively shorten the time spend on consulting.

• Quantity surveyor

• Land surveyor

• Geotechnical Engineer

• Structural Engineer

• Town planning planner

5.2 Additional charges/ Extra Services

• Heritage Consultants

• Building surveyor

• Mechanical Engineer

• Fire Engineer

• Any other specialist consultant and sub-consultant

1. Amending the content, scope,design or details of a project upon a client’s request after approvals have been given by client at various stages.

2. Statutory fees and other disbursements

3. Preparation and / or coordination of marketing and contract plans and related documents

5.3 Hourly Rate (Excl.GST): If any additional services that is excluded from the outline of scopes of work be required, Revent Architects has right to charge the fees based on following hourly rate.

Position

Hourly Rate

Director Project Architect Graduate Architect $135/hr $200/hr $290/hr

6.0 Professional Indemnity

Revent Architecture maintains Professional Indemnity Insurance to an amount of $10,000,000.

7.0 Agreement Conditions:

a. On appointment, payment of the non-refundable mobilization deposite fee of 10% of the total fee will be required prior to commencement of service.

b. Fees for our professional services will be invoiced on a staged or progressive basis monthly and are payable within 7 days. c. All work is to be carried out during normal working hours and is besed on continous service. d. copy right and ownership.

Copy right and licence of all drawing, reports, specifications, designs and other documents provided by Revent Architecture Pty Ltd in connection with the project named above shall remain the property of Revent Architecture Pty Ltd. e. Money not pad within 30 days of the invoice date shall attract interest from the date of invoice until payment ar a rate of 18% per annum.

7.1 Termination of agreement

Termination of this agreement requires 30 days notice in writing. Revent Architectural will charge the full payment of the stage we work on. Further information can be found on the AIA website.

Revent Architecture are pleased to offer you our quote for this project, we are confident to deliver you the most feasible solution with our professional architects. If you have any questions or concerns, please do not hesitate to contact me directly.

Kind Regards, Kai Lin Kai Lin (Director) ☎0401 270 423 ✉ reventarchitecture@gmail.com 219 Abbotsford St, North Melbourne VIC 3051

Acceptance of the fee proposal

KAILIN

Director of Revent Architecture Kai Lin

St Mary’s college Client

Charge-Out Rate

Director $150,000 $90 $225 $290 Project Architect $105,000 $63 $157 $200 Draft person $68,000 $41 $102 $135

Director $150,000 $90

Project Architect $105,000 $63

Draft person $68,000 $41

Working Days Days 365 Weekends 104

Annual holidays 20 Absents 10

Public holidays 221

Hours of each day 7.5 hours

Total hours per year 1657.5 hours

1.Pre-design stage & feasibility study 1 month $290/hr 100 hours $ 2 9 , 0 0 0 $200/hr 1 150 hours $ 3 0 , 0 0 0 $135/hr 1 50 hours $ 6 , 7 5 0 $ 6 5 , 7 5 0

2.Design development 2 month $290/hr 100 hours $ 2 9 , 0 0 0 $200/hr 3 150 hours $ 9 0 , 0 0 0 $135/hr 1 50 hours $ 6 , 7 5 0 $ 1 2 5 , 7 5 0 3.Detailed design stage 1 month $290/hr 40 hours $ 1 1 , 6 0 0 $200/hr 2 120 hours $ 4 8 , 0 0 0 $135/hr $ 5 9 , 6 0 0 4.Documentation stage & Building Permit Application 3 month $290/hr 150 hours $ 4 3 , 5 0 0 $200/hr 3 200 hours $ 1 2 0 , 0 0 0 $135/hr 3 200 hours $ 2 7 , 0 0 0 $ 1 9 0 , 5 0 0 5.Contract preparation (Tender) 1.5 month $290/hr 100 hours $ 2 9 , 0 0 0 $200/hr 1 100 hours $ 2 0 , 0 0 0 $135/hr $ 4 9 , 0 0 0 6.Contract administration & post construction services (defects) 12 month $290/hr 50 hours $ 1 4 , 5 0 0 $200/hr 3 100 hours $ 6 0 , 0 0 0 $135/hr 1 50 hours $ 6 , 7 5 0 $ 8 1 , 2 5 0 $ 5 7 1 , 8 5 0 +10% contingency $ 6 2 9 , 0 3 5

CALCULATION OF THE FEASIBLE SOLUTION:

Appendix:
Annually salary Hourly Rate Overheads(2.5x) Profit (30%)
T
m e F r a m e & F E E
Project Architect
Cost
Total Cost
i
Phase: Est. time spend Director Est. time Cost
No. Est. time
Graduate Architect No. Est. time Cost
Annually salary Hourly Rate
Car park Entry Car park Exit Courtyard Underground Car Park 464 m2 Sketch Design diagrams: Feasible solution of the proejct