CROSS STREET ECO TOWNS DEVELOPMENT Code for sustainable homes level 5 development Fabric First solution to more energy efficient homes

PROJECT BRIEF Client:

Robert Woodhead Ltd

Architect: Allan Joyce Architects Sector:

Affordable Housing

Type:

New Build

A development of 4 town houses built to reflect local architecture on a small site in Gainsborough for a local authority housing project. The Buildings comprise of TEK walls and roof to provide superior thermal efficiency and air tightness, and internal walls produced using Timber Frame.

Location: Gainsborough

K-Panels Ltd, Brailwood Road, Bilsthorpe, Newark, Notts NG22 8UA T: 0845 2260 214 E: info@k-panels.co.uk W: www.k-panels.co.uk


CROSS STREET ECO TOWNS DEVELOPMENT

KEY STATISTICS • Code for Sustainable Homes Level 5 minimum, level 6 achievable • Approx £875,000 overall contract value • Positive features in local media and built in a regeneration area of Gainsborough • Efficient, on programme completion • K-Panels provided cost saving design details • Fabric first approach with renewable technologies PROJECT SOLUTION Due to the very restricted site access issues, K-Panels provided a carefully planned delivery schedule to ensure just in time deliveries for each section of the build. The sustainability demands meant that site waste allowances are minimal and as such the offsite manufacture of the TEK panels ensured a virtually waste free construction process. The build will be the subject of a study on how fabric first building can reduce energy consumption in our homes, the thermal and air tight nature of the TEK building system provides the ideal building envelope for sustainable, affordable building.

PROJECT EVALUATION A high quality local authority development, designed with sustainable living in mind which will offer real ongoing benefits to the tenants.

A carefully planned build and lifting schedule enabled K-Panels to complete the entire build from sole plate to practical completion inside a 3 week time period using a team of only 4 K-Panels installers.

K-Panels were able to work alongside the contractor to ensure minimal disruption to close neighbouring properties and engage local media and residents in the build. Our online project management portal provided fast communication and transparent planning of the delivery and construction schedule enabling all operatives and site staff to work efficiently completing the site in under 3 weeks from sole plate to completion.

K-Panels Ltd, Brailwood Road, Bilsthorpe, Newark, Notts NG22 8UA T: 0845 2260 214 E: info@k-panels.co.uk W: www.k-panels.co.uk


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.