“We Do Journalism”
the Quadrangle
Visit Our Website mcquad.org
THE STUDENT NEWSPAPER OF MANHATTAN COLLEGE | SINCE 1924
Volume XCVIII, Issue 4
FREE
NEW YORK, SEPTEMBER 18, 2018
South Campus Vision Begins to Take Shape Stephen Zubrycky Managing Editor
The 238th Street Station will be out of commission until the spring semester. JOE LIGGIO / THE QUADRANGLE
238th Street Station Renovations Underway Joe Liggio
Asst. News Editor Stair replacement at the 238th Street station is set to tie up 1 Train riders for the next few months, leaving MC students and staff to look for alternate service options. The Manhattan-bound platform closed to riders on Sept. 4, and repairs are expected to continue through the Winter, according to the MTA/New York City Transit website. In the meantime, those needing a downtown train will need to board at either the 242nd Street or 231st Street station, posing an inconvenience for many living in or near Overlook Manor and those commuting to and
from classes on South Campus. Temporary MTA signs at the site list repairs consisting of removing and replacing the old stairways entirely, along with the addition of new handrails, stair treads and risers. The stairway canopy, drain pipes and gutters will be also be updated, and new lighting is to be installed. For some, including Manhattan junior Brendan Hanney, commuting to his job via subway has gotten a bit more difficult as a result of the changes. “Now instead of getting on the subway at 238th, I have to walk to 242nd, the opposite way from where I’d be commuting to,” said Hanney. Hanney, who lives on Greystone Avenue, works at
the Disney Store in Times Square. He utilizes the 1 Train four times a week to get to and from his stop at the 50th Street station in Manhattan, and points out that the repairs have added a decent amount of time to his trip downtown. “Usually the commute is 40 minutes, but now that I have to get on at a different stop it’s closer to an hour.” His trip back to the Bronx has remained unaffected, however, as construction is only affecting downtown service. The uptown platform has remained open and accessible via MetroCard and to passengers getting __________________________ CONTINUED ON PAGE 5
Gas Leak Scare at Overlook Manor Jack Melanson & Jeremy Loffredo
News Editor & Staff Writer Last Friday at 12:40 p.m., MC Jasper 911 sent an email in regards to a potentially dangerous gas leak across the street from Overlock Manor on W238th street. “Today at approximately 1240pm there was a report of a gas odor on W.238 Street near Overlook Manor. There is ongoing construction in the streets on W.238 and Waldo Avenue. The New York Fire Department is currently onsite. As a precautionary measure W. 238 street is being closed to
IN NEWS:
Faculty dining transformed into new event space on p. 4
pedestrian traffic. Occupants of Overlook Manor should use the door located on Waldo Avenue near Dash Place if entering or exiting the building,” the initial email said. Shortly before the email, Matt Mistretta, a senior living off campus spotted the smell. “I noticed it around 12:30 and I was in my room. I knew construction was going on outside but there was a loud hissing sound that went on for about 5 minutes until I smelt gas in my room,” Mistretta said. “I went upstairs and told my roommates about it and minutes later we saw firefighters outside. We went outside to see what was going on and they told us to make sure everybody
IN FEATURES: Cortlandt Street Reopens on 1 Train Line on p. 12-13
was out and to just wait until they resolved it. By about 12:45 it was safe to re-enter the apartment.” Five minutes later, at 12:45 p.m., another MC Jasper 911 email was sent that called the incident ‘safe’. “The Fire Department has deemed this incident as SAFE. It is now safe to use the main entrance to Overlook,” the email said. David Campbell, assistant incident inspector for Con Edison was on scene. “Jr Cruz is a private contractor for Con ED, they’re normal-
Construction on the $62 million Patricia & Cornelius J. Higgins ‘62 Science and Engineering Center is underway. The new building, which will sit on the same lot as the existing Leo Engineering Building, will house new labs for Manhattan College’s science and engineering departments, and is slated to open in 2020. Following a ceremonial groundbreaking last spring, work on the site began in earnest during the summer. Construction Begins Foundation work began in early August with pile-driving, which continued until the start of classes. “Over the summer, after getting all the permits and everything, we did the site preparation. We just finished doing the installation of piles,” Andrew Ryan said. Ryan is the college’s Vice President of Facilities. The piles, which are steel tubes roughly a foot in diameter, reach depths averaging over 100 feet. All told, eighty individual piles were driven, spread out between in 45 locations. Higgins’ foundation is deep for a reason - the building sits on soft soil that is rich in organics and is not well suited for a shallower design. “That used to be Spuyten Duyvil Creek [...] and many moons ago that got relocated, rerouted,” Ryan said. “So there’s a lot of organic material that’s down there.” The concrete blocks that rest atop the piles - called pile caps - have also begun. The pile caps must first be formed, using pieces of wood arranged to form a mold, and then poured. After that, the concrete slab that will form the building’s ground floor will be poured. Ryan expects this to be done within a few weeks. By Christmas, Ryan pre-
dicts that the building’s structural steel will be fully erected. “We [will start] with the steel at the southeast corner,” Ryan said. “We’ll start there and work our way around the building.” The college is trying its best to manage construction noise issues as classes continue. “There has been some noise issues. [...] and it has disrupted things, but I think as we go forward, [Ryan] and the project managers will have those better under control,” Engineering Dean Tim J. Ward, Ph.D., said. “When you got building projects going on it gets noisy.” The c o n struction of a brand n e w building on campus has presented unique educational Andrew J. Ryan opporCOLLEGE/ tunities MANHATTAN COURTESY for the c o l lege’s engineering programs. “In terms of the pile driving, the subsurface conditions, and those types of things, Dr. [Anirban] De [of the civil engineering department] has received a lot of material from [Ryan] so Dr. De can use it in some of the geotechnical courses,” Ward said. “As the building goes up, we will be sharing the plans in terms of the structural elements with the structures folks and also we have the systems in there… so both the electrical and the mechanical folks will want to look at those to see how those are laid out.” Live video of the construction progress is available at https://leo-construction.click2stream.com/.
__________________________ __________________________
CONTINUED ON PAGE 2
CONTINUED ON PAGE 5
IN A&E:
Quadchella rocks the Jasper Backyard p. 8-9
IN SPORTS:
Inside the lives Jasper StudentAthletes
on p. 14