Timeline Ontario Greenstone Mine

Next Article
The Brief

The Brief

TIMELINE

NTARI GREENST NE MINE

Advertisement

Greenstone Mine will be one of the largest gold mines in Canada, producing more than 400,000oz of gold annually for the first five years and more than 5mn oz of gold over its initial 14-year mine life.

2021

Early construction works underway. The mine will contain a 27,000 tonnes-perday processing facility and open-pit mining operation for the Hardrock deposit

2022

Mining scheduled to start.

40% of construction capital to be spent

2023

35% of construction capital due to be spent

2024

first gold pour targeted

Remainder of construction capital spend (15%). The project anticipates two years of construction and six months of commissioning.

2024 - 2038

More than 360,000oz average annual gold production targeted over initial 14-year mine life