TIMELINE

NTARI GREENST NE MINE Greenstone Mine will be one of the largest gold mines in Canada, producing more than 400,000oz of gold annually for the first five years and more than 5mn oz of gold over its initial 14-year mine life.

2021

2022

2023

Early construction works underway. The mine will contain a 27,000 tonnes-perday processing facility and open-pit mining operation for the Hardrock deposit

Mining scheduled to start.

35% of construction capital due to be spent

14

March 2022

40% of construction capital to be spent