Progress 2021: Construction

Page 1

Minot Daily News

M AKING

SATURDAY, APRIL 3, 2021

Construction

MinotDailyNews.com • Facebook • Twitter

GOOD

PROGRESS Trinity advances Minot’s largest construction project By JILL SCHRAMM

Senior Staff Writer jschramm@minotdailynews.com he hospital and clinic under construction in southwest Minot make up one of the more impressive building projects in the city in some time. A $520 million investment by the time it opens, the Trinity Health medical complex broke ground in the fall of 2018 and construction is expected to finish by the end of 2022. “We’re making good progress,” said Randy Schwan, Trinity vice president of mission integration. “It’s been going very well.” Dave Kohlman, Trinity vice president of facilities, said the major progress over the winter was internal. “The focus right now is still the interior of the building – studding of, framing of walls on the first floor, and starting on the second floor and putting up the steel studs in the walls as well as continuing the progress on the Cen-

T

tral Energy Plant to get that completed or as close to completion as possible to be able to start providing conditioned air for the contractors as they continue to move forward with mechanical aspects of the job,” he said. The Central Energy Plant should be complete by early June to serve the buildings while construction continues. Escalators already have been placed. The main focus has been on the first and second floor of the 594,000-square-foot

hospital because of the more complex design for those critical service areas. However, similar framing work is occurring from the ground up on the connected 196,000square-foot clinic building. The 148-bed hospital will include advanced cardiac, neurosurgical and orthopedic care, state-of-the-art surgical suites, new birthing areas and an expanded emergency /Level II trauma center with 24 treatment bays. Construction workers have been creating mock-up

rooms for an emergency exam room, trauma bay, operating suite, intensive care unit room and a hospital medical/surgery patient room. Staff teams have been reviewing the mock-up rooms as construction progresses to ensure the planned layout for countertops, lights, storage, electrical outlets and other fixtures are where they need to be for the best efficiency. “Those teams can walk through the mock-up rooms during all stages of construction so that they’re fully satis-

F ROM

fied that the finished product that will be throughout the hospital will be adequate,” Schwan said. Kohlman said it is one thing to see the layout on a piece of paper but quite another thing to walk through a room as it is being formed to get a feel for how the space will work. It’s a phased process, he added. Initially, staff stick notes on studded walls to indicate where certain features See TRINITY — Page 2

TOP LEFT: Surgery Director Denise Dahl, far left, and members of her staff offer suggestions to Facilities Vice President Dave Kohlman after viewing a mockup of a surgery suite in this March 19 photo from Trinity Health. MAIN: A feature of the main floor lobby in the new Trinity hospital under construction is an escalator to the second floor. Submitted Photos

BRIDGES TO BEACHES

Construction continues throughout Minot region Jill Schramm/MDN

The new Broadway pump station, shown March 10, has been under construction for two years and is expected to be completed soon.

F LOOD

PROTECTION PROGRESS

More work planned in 2021 By JILL SCHRAMM

Senior Staff Writer jschramm@minotdailynews.com Construction on the Mouse River Enhanced Flood Protection Project will be making additional progress in 2021, particularly for Burlington and the Tierrecita Vallejo Subdivision. Ryan Ackerman, administrator for the Souris River Joint Board (SRJB), said funding is in place to advance flood protection in Burlington. Construction on levees on the south end of the community began last year and the next phase will start soon. It includes about 3,200 feet of levee, seepage cutoff, utility modifications and river bank and levee erosion protection. Funding also is in place to construct a portion of the Tierrecita Vallejo levee, which will serve as the western tieback for the city of Minot. “We’re just working through some final acquisitions on that to clear the right of way,” Ackerman said last month. Within Minot, completion of a major stormwater pump station is expected soon at the intersection of Broadway and Fourth Avenue Northwest. Efforts to push forward with more construction on the east side of Third Street Northeast, or Phase MI-5, rest on appropriations

coming out of the current legislative session. The goal is to have MI-5 ready to be bid by late fall. Ackerman said the project may be split into multiple phases. Potentially a pump station and ponding area can be built first because the land for those features has been acquired and demolition of the industrial properties has occurred. Flood wall construction would be the next phase, Ackerman said. Residential acquisitions by the city are continuing for that portion of the project. “Additionally, there’ll be some work on the south side of the tracks in the Ben’s Tavern neighborhood to basically remove some of the infrastructure that’s not going to be used anymore after all the acquisitions are complete,” Ackerman said. That area will serve as an open floodplain area that could be beneficial as a public use area, such as a park, he said. “The critical path for those projects is really twofold. One is funding. We need to get the appropriation in the current session, and then number two is the acquisitions. So, as critical masses of acquisitions get completed, then we’ll basically move forward phases of that project to complete the work,” Ackerman said. MI-5 work is expected to continue through 2022 and possibly into 2023. “We should be completing the design of the Maple Diversion within the next year or so,” Ackerman added. “When we get into the next biennium, it’s very likely that our approach will See FLOOD — Page 2

By JILL SCHRAMM

Senior Staff Writer jschramm@minotdailynews.com A pandemic and concerns about funding haven’t stopped construction in the Minot region. “For us, construction has been strong,” said Dave Schwengler, Minot office manager for Houston Engineering. “The past year was a good year for construction. That was one of the industries that kept working through the pandemic.” He expects more of the same for 2021. “There’s a lot of big projects out there right now, even some development work starting to pick back up a little bit,” he said. Houston is providing the engineering for the Northwest Area Water Supply project. The State Water Commission this winter awarded the general contractor bid on the biota treatment plant near Max to Stantec of Colorado. The electrical contract went to Main Electric of Minot and the plumbing and heating to Mowbray & Son of Minot. Groundbreaking on the three-year biota plant project is expected to begin this month, according to Tim Freije, NAWS manager with the water commission.

Jill Schramm/MDN

Children move sand last August as adults fill their shovels to toss the first ceremonial ground last October for the construction of the Magic City Discovery Center. Much of the initial work will be dirt work. Crews will be augering holes for placing 474 piles to anchor the future plant. Design work on Snake Creek modifications to provide for water intake should be completed and ready to go to bid this fall, Freije said. In the meantime, the water commission is working on getting U.S. Army Corps of Engineers’ permits and completing the design work on a hydraulic control structure and reservoir in the South Prairie area. The last 15 miles of NAWS pipeline are to be completed by fall and will enable the city of Bottineau to begin receiving water from Minot and eventually from the Missouri River/Lake Sakakawea once the other features in the works are completed.

An ongoing $28 million expansion at the Minot Water Treatment Plant is to be completed by summer. Freije said there will be a few smaller projects to create the necessary reservoir and pumping facilities to finish the distribution system. Schwengler said Houston also is working with the City of Minot on water main improvements and finishing the new southwest water tower. He foresees additional development coming to southwest Minot in the years ahead as the hospital project is completed. Already, Bremer Bank is proposing to begin construction on a new building at 1615 36th Ave. SW. Outside of Minot, projects are planned to re-gravel See MINOT — Page 3

Visit us online at www.MinotDailyNews.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.