ABPL20033 - Construction Analysis, Semester 2 - 2020 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Anastasia Sklavakis Muyan Li, 1068026, Semester 2, 2020 Lake Wendouree Residence, Tutorial 6. ASSIGNMENT 1
Cover image, photo by ...................... Peter Bennetts
FLIPBOOK SECTION AS-BUILT: assigned section and construction sequence
3A
3A
Window Systems
6
Use Double Glazed Unit-Clear comply with AS 1288 and grade A safety glass where applicable.
Block Work 90mm Series Grey Blockwork
KITCHEN
UPSTAIRS LIVING
8
Finishing Trades, Joinery, Appliances
Timber Flooring Size: 130mm x 19mm tongue and groove boards with end matched profile
Kitchen appliances are fully settled and ready to be used, including oven, drawer, sink etc.
HALL
7
Brick Wall Grampian blue dark blend (extruded) with mide grey mortar.
Internal Walls Use TL-02 Wall Tile timber flooring with 6mm thickness covering on the wall.
STORE
BATH Rm
CELLAR
Floor tile size: 600mm*300mm Grout Joint width: 2mm
External Wall Systems.
3A 01 2
Ground Floor Plan Scale 1:50 @A3
6
Brick wall (BL-01) Grampian Blue Dark Blend is constructed for this part of the building. And for cellar wall, it is three layers. Two layers of brick wall and a stud wall in the middle. The insulations are filled the space between every stud to keep the temperature stable.
3
Primary Structure above Ground Framing system is installed.
ABPL20033 - 2020, Muyan Li | 1068026 |Tutorial 6 | Anastasia Sklavakis | p. A
Timber Decking 86mm x 19mm decking boards. Flat top. Mimimal pencil round corners
STAIR
Timber treads and risers 305mm*35mm thick
3A 02 2
First Floor Plan Scale 1:50 @A3
Roof System: Roof Structure, Sheeting and Cover.
Finishing Trades, Joinery and Appliances The Kitchen Drawer is constructed. And the Bathroom utensils are ready for use.
Timber Roof structures are installed to provide ssupporting elements for roof. Joists are nailed with timber beams. Metal roofing is cover for the roof top, using Stramit Speed Deck 700 (BMT: 0.42mm).
8
5
7
Internal Partitions, Ceiling Structure, Rough in Services Internal walls and brick walls are installed. Basic service such as bathroom devices are settled.
External Wall Systems. Brick wall (BL-01) Grampian Blue Dark Blend is constructed for this part of the building. Insulations are installed between stud wall and internal brick wall.
Folded zinc capping
6
RL 460.40
FCL 459.50
100mm Zinc Standing Seam
UPSTARIS LIVING
BATH Rm
Timber screen dowel rods to back of timber drill holes in zinc clad wall and epoxy fix
FFL 456.80
Intermediate Floor Structure The spacing of joists and span of beam are checked. Timber trusses are bolted on steel beams. The gap between ceiling and steel beam is 10 mm, refer to drawings. Bracing is used.
4
FCL 456.20
Timber framed double glazed sliding windows and matching flyscreen
KITCHEN
BBQ
CELLAR
HALL
FFL 453.20
1
01 3
Section 3A Scale 1:50 @A3
Foundation Systems Excavation, Demolition and Footings Soil is tested by geotechnical engineer to ensure bearing capacity. When demolition completes, excavation commence. Trenches will dug hole for footings and keep the site to same level. Footings are foundation for the site.
Ground Floor slab The waffle slabs (Ploythylene void) and reinforcements are constructed underground. Pipework for gas, electricity and sewage is installed.
ABPL20033 - 2020, Muyan Li | 1068026 |Tutorial 6 | Anastasia Sklavakis | p. A
2
3
Isolated slab for the cellar
Vertical Structure above Ground Steel framing system is installed. Trussess and beams are bolted onto the steel columns in order to support the whole structure. Structural bracings are set to bear the load.
1. SITE PREPARATION AND FOORING
2. GROUND FlOOR SLAB
3. VERTICAL STRUCTURE ABOVE GROUND
4. INTERMEDIATE FLOOR STURCTURE
1.1 The relevant permissions are required including building permit and demolition permit before starts constructing. 1.2 Site clearing to achieve good site condition, old existing landscapes and buildings are demolished. 1.3 Site survey is done by the surveyor to identify the building blocks and helps determining the proper site boundaries. 1.4 Designing the pipes and plumbing system and other fixtures. 1.5 Site soil condition is tested and summaried in soil report. 1.6 Excavation of earthwork in trenches for foundation footings.
2.1 Depending on the soil condition, choose appropriate foundation type and contruct footings underground. 2.2 Laying underground pipework for sewage, gas and electricity. 2.3 Formwork and installation of the spacers. This is to maintain the concrete cover and garantee the durability of the building. 2.4 The reinforced steel is installed before the concreting the floor slab. 2.5 In concreting step, exposed aggregate concrete is poured and dried usually around 20 days.
3.1 Steel type is selected and painted with corrosion resistant paint. 3.2 The steel framing system is constructed both in vertical and horizontal direction. Beams and trusser are bolted onto steel columns. 3.3 Exposed finishings are dealt with covering material. 3.4 Scaffolds are constructed on the ground for workers. 3.5 Ground floor timber stud framing is installed. 3.6 Structural bracing are installed to stud frames to support the structural systems.
4.1 After the installation of the vertical structural systems, intermediate floor structure construction starts. 4.2 Joists spacing and beam span are checked refer to construction drawings. 4.3 Scaffolding extends to the first floor to achieve the construction of first floor. 4.4 Floor substrate is installed by nails. 4.5 Timber trusses are bolted on steel beams. Joist hanger are fiexed on the timber trusses.
Construction stages 1-4, summary ABPL20033 - 2020, Muyan Li | 1068026 |Tutorial 6 | Anastasia Sklavakis | p. A
5. ROOF SYSTEM: ROOF STRUCTURE, SHEETING AND COVER 5.1 The scaffolding and barriers for safety are extending to the roof level for safety purpose. 5.2 Timber roof rafters are installed on the stud wall and connected by galcanised metal straps. 5.3 Breathable sarking is constructed above the timer roof battens to improve thermal performance through decreasing the flow on the roof structure. 5.4 Metal roofings are used for cover the roof top for bathroom, living room and kitchen part, refer to Stramit Speed Deck 700 (BMT: 0.42mm). 5.5 Box gutter 600mm are installed to guide the rainwater to the ground. 5.6 Support frames required for solar panels on the roof.
6. EXTERNAL WALL, WINDOW SYSTEMS, EXTRNAL DOORS 6.1 Brick wall (BL-01) Grampian blue dark blend is selected for cellar and store construction, and stairs as internal walls. The wall of bathroom is two layers of brick wall and one lay of stud wall. 6.2 Scaffold is reassigned to external of the house. 6.3 The insulations are used between the space of every stud inside wall to keep temperature stable. 6.4 Gap between stud wall and internal brick wall is filled by foam plastic. 6.5 Crane is necessary for placing the large glazing windows on the accruate position. Windows are nailed to the internal stud wall. External windows are double glazed to reduce noises
7. INTERNAL PARTITIONS, CEILING STRUCTURE, ROUGH IN SERVICES, WALL LINING 7.1 Internal timber stud walls and brick walls are constructed in area 3. 7.2 Basic services are set inside house like air condition in the kitchen and also some electronic devices. 7.3 The thermal insulation are intalled in the roof and also on the ceiliings of house. 7.4 Intalling the cladding starts after checking the windows positions. The cladding will be cut depending on the size of windows and doors.
Construction stages 4-8, summary ABPL20033 - 2020, Muyan Li | 1068026 |Tutorial 6 | Anastasia Sklavakis | p. A
8. FINISHING TRADS, JOINERY, APPLIANCES 8.1 All basic services are well organised and well set including heating and cooling equipments such as air condition and heating system. 8.2 Joinery: Use select textured timber and intalled on site. 8.3 All the walls are painted refer to material schedule. 8.4 Furnitures are placed in the correct positions and in good condition. 8.5 Recheck the pipework like gas and electricity if they work in right way. 8.6 Clean the house and put clean carpet and ready for living.