Appendix E FDOT Mitigation Plan and St. Johns River Water Management District Permitting Process
January 26, 2015
This page is intentionally blank.
FDOT MITIGATION PLAN
2014-2015 Road Projects
2014-2015 FDOT Wetland Mitigation Plan
Page 1
CONTENTS INTRODUCTION ....................................................................................................................................................... 4 FDOT Wetland Mitigation Work Plan Measures: ................................................................................................... 5 NEW ROAD PROJECTS ............................................................................................................................................ 8 Basin 11: Project Group SJ65 ......................................................................................................................................... 8 Basin 22: Project Group SJ57 ...................................................................................................................................... 13
UPDATE OF INCOMPLETE PROJECTS FROM PREVIOUS YEARS ............................................................................. 16 Basins 14, 16: Project Group SJ56................................................................................................................................... 16 Basin 23: Project Group SJ47 .......................................................................................................................................... 18
Projects proposed for exclusion from the mitigation program ............................................................................ 20 USE OF MITIGATION BANKS.................................................................................................................................. 21 Appendix 1: 373.4137 F.S. .................................................................................................................................... 23 Appendix 2: Master List Report (FDOT Mitigation Program) ............................................................................... 27
2014-2015 FDOT Wetland Mitigation Plan
Page 2
LIST OF FIGURES Figure 1:Total FDOT Program - Mitigation (Acres) Completed through 9/30/2013 .............................................. 5 Figure 2: 2014-2015 FDOT Project Location Map ................................................................................................... 7 Figure 3: SR 20 Widening through Fowler’s Prairie and SR20, East of US 301 to Putnam County Line ................ 9 Figure 4: Regulatory Basin 11, Northern Ocklawaha River .................................................................................. 10 Figure 5: UF Greenway and Trail Segments 1 &2 ................................................................................................. 11 Figure 6: Regulatory Basin 11, Northern Ocklawaha River .................................................................................. 12 Figure 7: I-95 St. Johns Heritage Parkway/Palm Bay Parkway............................................................................. 14 Figure 8: Regulatory Basin 22 Central Indian River ............................................................................................. 15 Figure 9: Basins 14 &16: SJ Group 56 ................................................................................................................... 17 Figure 10: Basin 23 Project Group SJ47 ................................................................................................................ 19 Figure 11: Mitigation Bank Locations .................................................................................................................. 22
2014-2015 FDOT Wetland Mitigation Plan
Page 3
Wetland Mitigation Plan for Florida Department of Transportation Projects within the St. Johns River Water Management District Fiscal Year 2014-2015 INTRODUCTION This mitigation plan is developed pursuant to the provisions of section 373.4137, Florida Statutes, (F.S.), to provide wetland mitigation for the Florida Department of Transportation (FDOT). Section 373.4137, F.S., directs the water management districts to plan and implement mitigation for the FDOT projects in the adopted FDOT work program for which FDOT requests the District to provide the mitigation. Section 373.4137, F.S. directs the District mitigation plans to focus on land acquisition, restoration or enhancement, and Surface Water Improvement and Management projects where that option represents the best mitigation. In determining activities to be included in the plans, the District must also consider the purchase of credits from public and private mitigation banks. Section 373.4137, F.S., was amended in 2012. The amendments allow FDOT the option of directly providing the mitigation for their transportation projects or requesting that the District provide the mitigation (with FDOT funding). The amendments also reinstituted the requirement for FDEP approval of the mitigation plan. This is the seventeenth annual mitigation plan prepared for the FDOT Mitigation Program. An annual plan was not prepared for FY 2013-2014 as FDOT elected to purchase mitigation bank credits for their impacts. Each annual plan addresses the funded projects for the following FDOT fiscal year and necessary updates or modifications to previous plans. A Master Project List, including previously approved road projects and respective plan approval dates, is located in Appendix 2 page 27. The FY 2014-2015 plan includes five new road projects within the SJRWMD portion of FDOT Districts 2 and 5. The plan also includes an update of all mitigation projects for which the mitigation is not completed. The new projects are estimated to result in 17.50 acres of wetland and other surface water impacts. The impacts will occur in regulatory basins that do not have an US Army Corps of Engineers approved mitigation bank. All impact information in the plan is based on estimates provided by FDOT. Mitigation will be adjusted proportionally to account for permitted changes in impact acreage. The Uniform Mitigation Assessment Method will be used during permitting to confirm that sufficient mitigation has been provided. Project mitigation groups are organized by regulatory mitigation basin, and impacts are offset within the same basin unless specifically stated otherwise. During the permitting process, FDOT is required to implement practicable design modifications to reduce or eliminate impacts pursuant to subsection 373.4137(8), F.S.
2014-2015 FDOT Wetland Mitigation Plan
Page 4
FDOT WETLAND MITIGATION WORK PLAN MEASURES: Each program within the District is required to prepare a work plan with measurable goals and objectives. The work plan measure for this program is the total acreage of mitigation implemented per acre of wetland impact. For purposes of the work plan, mitigation is reported as implemented after issuance of required permits for the road project and after the District has been reimbursed by FDOT for land acquisition and management, restoration, enhancement, mitigation bank credit purchase, contracted work and/or other activities. The pie chart below provides a breakdown of the amount and distribution of wetland mitigation that has been implemented by the FDOT Wetland Mitigation program as of September 30, 2013. A total of 40,121.01 acres of mitigation has been provided to offset 1464.72 acres of wetland and other surface waters impacts. This total includes the mitigation acreage associated with 277.51 mitigation bank credits purchased to date. Some mitigation activities such as certain types of water quality improvement projects are not represented, as they are difficult to quantify as an acreage figure. These figures represent completion of mitigation for 153 road projects and partial implementation for 5 additional road projects through September 30, 2013.
Figure 1:Total FDOT Program - Mitigation (Acres) Completed through 9/30/2013
2014-2015 FDOT Wetland Mitigation Plan
Page 5
2014-2015 FDOT Road Projects and Projected Impact Acreage
Mitigation Group
Regulatory Mitigation Basin*
FDOT Project Name
Financial Management No.
County
Projected Acres
SJ65
11
SR20 through Fowler’s Prairie
210024-4
Putnam
7.50
SJ65
11
SR20, East of US 301 to Putnam County Line
207818-1
Alachua/ Putnam
0.70
SJ65
11
UF Greenway and Trails Segment 1
428896-1
Alachua
0.31
SJ65
11
UF Greenway and Trails Segment 2
430614-1
Alachua
0.02
SJ57
22
I-95 Interchange at St. Johns Heritage Parkway/Palm Bay Parkway
426904-3
Brevard
8.97
Total Acres
17.50
* Regulatory Mitigation Basins 11 – Northern Ocklawaha River 22 – Central Indian River Lagoon
2014-2015 FDOT Wetland Mitigation Plan
Page 6
Figure 2: 2014-2015 FDOT Project Location Map 2014-2015 FDOT Wetland Mitigation Plan
Page 7
NEW ROAD PROJECTS
BASIN 11: PROJECT GROUP SJ65
This is a new mitigation group, which will include the following projects: SR20 through Fowler’s Prairie SR20, East of US 301 to Putnam County Line UF Greenway and Trail, Segment 1 UF Greenway and Trail, Segment 2
FM #210024-4 FM #207818-1 FM #428896-1 FM #430614-1
The proposed projects will impact an estimated 8.53 acres of freshwater herbaceous and mixed forested wetlands associated with Fowler’s Prairie, Little Orange Creek, and Lake Alice. The proposed mitigation for this project is the preservation and enhancement of additional conservation lands in Regulatory Basin 11. The impacts will primarily occur to high quality wetlands which were acquired for conservation purposes as part of the Little Orange Creek Preserve and priority will be given to mitigation that would benefit the wetland systems and waterbodies that will be impacted by the roadway projects. Basin 11 does not have a mitigation bank. Figures 2 and 3 depict the location of the road widening projects and the existing public lands within Basin 11.
2014-2015 FDOT Wetland Mitigation Plan
Page 8
Figure 3: SR 20 Widening through Fowler’s Prairie and SR20, East of US 301 to Putnam County Line
2014-2015 FDOT Wetland Mitigation Plan
Page 9
Figure 4: Regulatory Basin 11, Northern Ocklawaha River
2014-2015 FDOT Wetland Mitigation Plan
Page 10
Figure 5: UF Greenway and Trail Segments 1 &2 2014-2015 FDOT Wetland Mitigation Plan
Page 11
Figure 6: Regulatory Basin 11, Northern Ocklawaha River
2014-2015 FDOT Wetland Mitigation Plan
Page 12
BASIN 22: PROJECT GROUP SJ57
One new road project is proposed for addition to this existing mitigation group which currently includes the following projects;
I-95 from N. of CR514 to SR 514 SR 5 (US1) S. of Highlands Dr. to S. of Oslo Rd. I-95 from Indian River C/L to SR 60 I-95 SR 60 to N. of CR 514 I-95 N. of CR514 to Brevard/Indian River C/L
FM# 413072-1 FM# 228583-4 FM# 413048-1 FM# 413050-1 FM# 413049-1
The new project is: I-95 Interchange at St. Johns Heritage Parkway/Palm Bay Parkway
FM# 426904-3
The new project is anticipated to impact 8.97 acres of wetlands, primarily consisting of wet prairie, freshwater marsh, hydric flatwoods and cypress. The previously approved mitigation plan for this group is preservation and enhancement as additions to existing conservation lands in basin 22 or restoration and enhancement on existing public lands. Current mitigation projects include wetland enhancement and restoration at the Wheeler Groves parcel to restore habitat connectivity between the St. Sebastian River Buffer Preserve State Park and the floodplain of the North Prong of the St. Sebastian River. Regulatory Basin 22, which has two banks CGW Mitigation Bank and Basin 22 Mitigation Bank. CGW Mitigation Bank has received both state and federal approval. CGW provides only saltwater mitigation credits, which would not offset the freshwater wetland impacts of the road projects in this group. Basin 22 Mitigation Bank received state approval in December 2013, but not federal approval. Additionally, no release of credits have been authorized by the state at this time.
2014-2015 FDOT Wetland Mitigation Plan
Page 13
Figure 7: I-95 St. Johns Heritage Parkway/Palm Bay Parkway 2014-2015 FDOT Wetland Mitigation Plan
Page 14
Figure 8: Regulatory Basin 22 Central Indian River
2014-2015 FDOT Wetland Mitigation Plan
Page 15
UPDATE OF INCOMPLETE PROJECTS FROM PREVIOUS YEARS
BASINS 14, 16: PROJECT GROUP SJ56
This is an existing mitigation group, which currently includes the following road projects: SR 15 (US 17) DeLeon Springs to SR 40 US 1 @ Black Branch Bridge Commuter Rail Transit Project 92 Multiuse Path US17 to Kepler Sunrail/Commuter Rail –Deland Station, Sunrail/Commuter Rail –Debary to Deland
FM# 4102511 FM# 4110921 FM# 4129944 FM# 4172051 FM# 4234469 FM# 4234469
(2008) (2008) (2009) (2009) (2011) (2011)
The mitigation approved for this group in 2008 is wetland and upland preservation and enhancement as additions to the Heart Island Conservation Area or other adjacent conservation lands. The new 2009 and 2011 impacts were approved to be alternatively offset by purchase of credits from either Blackwater Creek Mitigation Bank or Wekiva River Mitigation Bank to the extent that credit purchase is the more cost-effective option. The majority of the impacts for this group are associated with the US 17 widening project which will be located, in part, on the District’s Heart Island Conservation Area. The widening project has the likelihood of severing a significant wildlife corridor between the Ocala National Forest and conservation lands to the east such as Tiger Bay State Forest, Relay Wildlife Management Area and the Volusia Conservation Corridor. To address this concern FDOT is incorporating wildlife crossings in the design. As part of the mitigation, the District and Volusia County purchased the Strawn parcel addition to Heart Island which in part borders the road project and will facilitate use of the crossing structures. Preservation and management of the parcel will also enhance the long-term value of Deep Creek, which is a significant feature of the parcel. Approximately 14.27 acres of the projected impact of 24.94 acres have been offset to date. FDOT is currently designing the SR 40 widening project immediately east of US 17 widening. Part of the mitigation for the remaining impacts in this mitigation group is acquisition, either by easement or fee simple, of parcels that would complement new crossing structures on SR 40 and potentially reduce the secondary impact of the roadway project. The balance of the mitigation could be provided by credits from either Blackwater Creek Mitigation Bank or Wekiva River Mitigation Bank.
2014-2015 FDOT Wetland Mitigation Plan
Page 16
Figure 9: Basins 14 &16: SJ Group 56 2014-2015 FDOT Wetland Mitigation Plan
Page 17
BASIN 23: PROJECT GROUP SJ47 This is an existing mitigation group that currently includes the following road projects in the Lake Jesup regulatory basin: I-4 S. of Ivanhoe to N. of Kennedy Blvd SR 426, Mitchell Hammock to Winter Spgs SR 419/SR 436 west of Jetta Pt. to SR 426/CR426
FM# 242484-5 FM# 404525-1 FM# 422015-1
The previously approved mitigation plan for this group is preservation and enhancement as additions to existing conservation lands in this basin. Priority will be given to parcels which can provide both water quality and wildlife benefits within this rapidly urbanizing basin. There are no mitigation banks in basin 23 and the District is currently evaluating potential mitigation sites. Figure 10 shows existing conservation lands in basin 23.
2014-2015 FDOT Wetland Mitigation Plan
Page 18
Figure 10: Basin 23 Project Group SJ47 2014-2015 FDOT Wetland Mitigation Plan
Page 19
PROJECTS PROPOSED FOR EXCLUSION FROM THE MITIGATION PROGRAM Section 373.4137(4)(b), F.S., provides that “[s]pecific projects may be excluded from the mitigation plan, in whole or in part, and are not subject to this section upon election by the Department of Transportation, a transportation authority if applicable, or the appropriate water management district.“ The District proposes to exclude the following previously approved projects that were approved as part of the 2012-2013 plan from the provisions of 373.4137, F.S. The previously approved plan for these projects was purchase of mitigation bank credits and FDOT has elected to complete the credit purchase. Sunrail/Commuter Rail – DeBary to DeLand SR 200, Still Quarters to West of Rubin I-295 Auxilliary Lanes SR 16, Green Acres to SR 5A SR 13 at SR 16 US 1 at CR 210
2014-2015 FDOT Wetland Mitigation Plan
FM #423446-9 FM #210712-3 FM #213345-7 FM #424481-1 FM #424454-1 FM #210420-7
Page 20
USE OF MITIGATION BANKS
Subsection 373.4137(4), F.S., requires the District to consider the use of permitted mitigation banks in developing the FDOT mitigation plan. Please reference Figure 11 for the location of mitigation banks that have received both state and federal approval. Bank credits are proposed as an option for one of the incomplete mitigation groups in this plan, SJ 56, page 16. Mitigation group SJ 57 is located in Regulatory Basin 22, which has two banks. CGW Mitigation Bank has received both state and federal approval. CGW provides only saltwater mitigation credits which would not offset the freshwater wetland impact of the road projects in this group. Basin 22 Mitigation Bank received state approval in December 2013, but not federal approval. Additionally, no release of credits have been authorized by the state at this time. An alternative mitigation plan is proposed due to these circumstances. A new mitigation group, SJ65, is created as a part of this plan to provide mitigation primarily for the widening of SR 20 through a portion of Fowler’s Prairie. All of the roadway impacts occur in Regulatory Basin 11, which does not have an approved mitigation bank. In order to meet the cumulative impact criteria an in-basin mitigation option is proposed. The preferred option will also directly benefit the wetlands and waterbodies that will have the most significant impact. Previously approved mitigation group SJ 47 is located in the Lake Jesup Basin (Basin 23) which does not have an approved mitigation bank. An in-basin mitigation option was selected.
2014-2015 FDOT Wetland Mitigation Plan
Page 21
Figure 11: Mitigation Bank Locations 2014-2015 FDOT Wetland Mitigation Plan
Page 22
APPENDIX 1: 373.4137 F.S.
373.4137 Mitigation requirements for specified transportation projects. (1) The Legislature finds that environmental mitigation for the impact of transportation projects proposed by the Department of Transportation or a transportation authority established pursuant to chapter 348 or chapter 349 can be more effectively achieved by regional, long-range mitigation planning rather than on a project-by-project basis. It is the intent of the Legislature that mitigation to offset the adverse effects of these transportation projects be funded by the Department of Transportation and be carried out by the use of mitigation banks and any other mitigation options that satisfy state and federal requirements. (2) Environmental impact inventories for transportation projects proposed by the Department of Transportation or a transportation authority established pursuant to chapter 348 or chapter 349 shall be developed as follows: (a) By July 1 of each year, the Department of Transportation, or a transportation authority established pursuant to chapter 348 or chapter 349 which chooses to participate in the program, shall submit to the water management districts a list of its projects in the adopted work program and an environmental impact inventory of habitats addressed in the rules adopted pursuant to this part and s. 404 of the Clean Water Act, 33 U.S.C. s. 1344, which may be impacted by its plan of construction for transportation projects in the next 3 years of the tentative work program. The Department of Transportation or a transportation authority established pursuant to chapter 348 or chapter 349 may also include in its environmental impact inventory the habitat impacts of any future transportation project. The Department of Transportation and each transportation authority established pursuant to chapter 348 or chapter 349 may fund any mitigation activities for future projects using current year funds. (b) The environmental impact inventory shall include a description of these habitat impacts, including their location, acreage, and type; state water quality classification of impacted wetlands and other surface waters; any other state or regional designations for these habitats; and a list of threatened species, endangered species, and species of special concern affected by the proposed project. (3)(a) To fund development and implementation of the mitigation plan for the projected impacts identified in the environmental impact inventory described in subsection (2), the Department of Transportation shall identify funds quarterly in an escrow account within the State Transportation Trust Fund for the environmental mitigation phase of projects budgeted by the Department of Transportation for the current fiscal year. The escrow account shall be maintained by the Department of Transportation for the benefit of the water management districts. Any interest earnings from the escrow account shall remain with the Department of Transportation. (b) Each transportation authority established pursuant to chapter 348 or chapter 349 that chooses to participate in this program shall create an escrow account within its financial structure and deposit funds in
2014-2015 FDOT Wetland Mitigation Plan
Page 23
the account to pay for the environmental mitigation phase of projects budgeted for the current fiscal year. The escrow account shall be maintained by the authority for the benefit of the water management districts. Any interest earnings from the escrow account shall remain with the authority. (c) Except for current mitigation projects in the monitoring and maintenance phase and except as allowed by paragraph (d), the water management districts may request a transfer of funds from an escrow account no sooner than 30 days before the date the funds are needed to pay for activities associated with development or implementation of the approved mitigation plan described in subsection (4) for the current fiscal year, including, but not limited to, design, engineering, production, and staff support. Actual conceptual plan preparation costs incurred before plan approval may be submitted to the Department of Transportation or the appropriate transportation authority each year with the plan. The conceptual plan preparation costs of each water management district will be paid from mitigation funds associated with the environmental impact inventory for the current year. The amount transferred to the escrow accounts each year by the Department of Transportation and participating transportation authorities established pursuant to chapter 348 or chapter 349 shall correspond to a cost per acre of $75,000 multiplied by the projected acres of impact identified in the environmental impact inventory described in subsection (2). However, the $75,000 cost per acre does not constitute an admission against interest by the state or its subdivisions and is not admissible as evidence of full compensation for any property acquired by eminent domain or through inverse condemnation. Each July 1, the cost per acre shall be adjusted by the percentage change in the average of the Consumer Price Index issued by the United States Department of Labor for the most recent 12-month period ending September 30, compared to the base year average, which is the average for the 12-month period ending September 30, 1996. Each quarter, the projected acreage of impact shall be reconciled with the acreage of impact of projects as permitted, including permit modifications, pursuant to this part and s. 404 of the Clean Water Act, 33 U.S.C. s. 1344. The subject year’s transfer of funds shall be adjusted accordingly to reflect the acreage of impacts as permitted. The Department of Transportation and participating transportation authorities established pursuant to chapter 348 or chapter 349 are authorized to transfer such funds from the escrow accounts to the water management districts to carry out the mitigation programs. Environmental mitigation funds that are identified for or maintained in an escrow account for the benefit of a water management district may be released if the associated transportation project is excluded in whole or part from the mitigation plan. For a mitigation project that is in the maintenance and monitoring phase, the water management district may request and receive a one-time payment based on the project’s expected future maintenance and monitoring costs. Upon disbursement of the final maintenance and monitoring payment, the escrow account for the project established by the Department of Transportation or the participating transportation authority may be closed. Any interest earned on these disbursed funds shall remain with the water management district and must be used as authorized under this section. (d) Beginning in the 2005-2006 fiscal year, each water management district shall be paid a lump-sum amount of $75,000 per acre, adjusted as provided under paragraph (c), for federally funded transportation projects that are included on the environmental impact inventory and that have an approved mitigation plan. Beginning in the 2009-2010 fiscal year, each water management district shall be paid a lump-sum amount of $75,000 per acre, adjusted as provided under paragraph (c), for federally funded and nonfederally funded
2014-2015 FDOT Wetland Mitigation Plan
Page 24
transportation projects that have an approved mitigation plan. All mitigation costs, including, but not limited to, the costs of preparing conceptual plans and the costs of design, construction, staff support, future maintenance, and monitoring the mitigated acres shall be funded through these lump-sum amounts. (4) Before March 1 of each year, each water management district, in consultation with the Department of Environmental Protection, the United States Army Corps of Engineers, the Department of Transportation, participating transportation authorities established pursuant to chapter 348 or chapter 349, and other appropriate federal, state, and local governments, and other interested parties, including entities operating mitigation banks, shall develop a plan for the primary purpose of complying with the mitigation requirements adopted pursuant to this part and 33 U.S.C. s. 1344. In developing such plans, the districts shall use sound ecosystem management practices to address significant water resource needs and shall focus on activities of the Department of Environmental Protection and the water management districts, such as surface water improvement and management (SWIM) projects and lands identified for potential acquisition for preservation, restoration, or enhancement, and the control of invasive and exotic plants in wetlands and other surface waters, to the extent that the activities comply with the mitigation requirements adopted under this part and 33 U.S.C. s. 1344. In determining the activities to be included in the plans, the districts shall consider the purchase of credits from public or private mitigation banks permitted under s. 373.4136 and associated federal authorization and shall include the purchase as a part of the mitigation plan when the purchase would offset the impact of the transportation project, provide equal benefits to the water resources than other mitigation options being considered, and provide the most cost-effective mitigation option. The mitigation plan shall be submitted to the water management district governing board, or its designee, for review and approval. At least 14 days before approval, the water management district shall provide a copy of the draft mitigation plan to any person who has requested a copy. The plan may not be implemented until it is submitted to and approved, in part or in its entirety, by the Department of Environmental Protection. (a) For each transportation project with a funding request for the next fiscal year, the mitigation plan must include a brief explanation of why a mitigation bank was or was not chosen as a mitigation option, including an estimation of identifiable costs of the mitigation bank and nonbank options and other factors such as time saved, liability for success of the mitigation, and long-term maintenance. (b) Specific projects may be excluded from the mitigation plan, in whole or in part, and are not subject to this section upon the election of the Department of Transportation, a transportation authority if applicable, or the appropriate water management district. (c) When determining which projects to include in or exclude from the mitigation plan, the Department of Transportation shall investigate using credits from a permitted mitigation bank before those projects are submitted for inclusion in the plan. The investigation shall consider the cost-effectiveness of mitigation bank credits, including, but not limited to, factors such as time saved, transfer of liability for success of the mitigation, and long-term maintenance. (5) The water management district shall ensure that mitigation requirements pursuant to 33 U.S.C. s. 1344 are met for the impacts identified in the environmental impact inventory described in subsection (2), by implementation of the approved plan described in subsection (4) to the extent funding is provided by the 2014-2015 FDOT Wetland Mitigation Plan
Page 25
Department of Transportation, or a transportation authority established pursuant to chapter 348 or chapter 349, if applicable. During the federal permitting process, the water management district may deviate from the approved mitigation plan in order to comply with federal permitting requirements. (6) The mitigation plans shall be updated annually to reflect the most current Department of Transportation work program and project list of a transportation authority established pursuant to chapter 348 or chapter 349, if applicable, and may be amended throughout the year to anticipate schedule changes or additional projects which may arise. Each update and amendment of the mitigation plan shall be submitted to the governing board of the water management district or its designee for approval. However, such approval shall not be applicable to a deviation as described in subsection (5). (7) Upon approval by the governing board of the water management district or its designee, the mitigation plan shall be deemed to satisfy the mitigation requirements under this part for impacts specifically identified in the environmental impact inventory described in subsection (2) and any other mitigation requirements imposed by local, regional, and state agencies for these same impacts. The approval of the governing board of the water management district or its designee shall authorize the activities proposed in the mitigation plan, and no other state, regional, or local permit or approval shall be necessary. (8) This section shall not be construed to eliminate the need for the Department of Transportation or a transportation authority established pursuant to chapter 348 or chapter 349 to comply with the requirement to implement practicable design modifications, including realignment of transportation projects, to reduce or eliminate the impacts of its transportation projects on wetlands and other surface waters as required by rules adopted pursuant to this part, or to diminish the authority under this part to regulate other impacts, including water quantity or water quality impacts, or impacts regulated under this part that are not identified in the environmental impact inventory described in subsection (2). (9) The process for environmental mitigation for the impact of transportation projects under this section shall be available to an expressway, bridge, or transportation authority established under chapter 348 or chapter 349. Use of this process may be initiated by an authority depositing the requisite funds into an escrow account set up by the authority and filing an environmental impact inventory with the appropriate water management district. An authority that initiates the environmental mitigation process established by this section shall comply with subsection (6) by timely providing the appropriate water management district with the requisite work program information. A water management district may draw down funds from the escrow account as provided in this section. History.—s. 1, ch. 96-238; s. 36, ch. 99-385; s. 1, ch. 2000-261; s. 93, ch. 2002-20; s. 39, ch. 2004-269; s. 30, ch. 2005-71; s. 12, ch. 2005-281; s. 1, ch. 2009-11; s. 3, ch. 2012-174
2014-2015 FDOT Wetland Mitigation Plan
Page 26
APPENDIX 2: MASTER LIST REPORT (FDOT MITIGATION PROGRAM) Mit. ID
FDOT Proct Name
SJ23
Basin 4. Western Basin 4 Conservation Areas (Jackson, Timber Forest, Bull Creek North, Longleaf Timber, Longbranch Farms)
FM Number County
Basin Impact Acres Plan Index
Branan Field/Chaffee
209250-1
Duval
4
69.45
97:p23, 00:p7closed
Branan Field/Chaffee Rd
208225-1
Clay
4
5.6
97:p23, 00:p7closed
CR-209 over Black Creek Bridge Replacement
211560-2
Clay
4
3.7
07:p5
Highway Ave./Cedar Creek bridge replacement
212109-1
Duval
4
0
I-10 Marietta Interchange (Hammond Blvd)
213301-2
Duval
4
1.29
09:p8
I-295 @ Collins/Blanding
213345-1
Duval
4
25.33
08:p8closed
I-95 Overland Bridge
213304-3
Duval
4
0
SR 228 SCLRR Bridge #720045
209484-1
Duval
4
2.47
SR-21 from CR-218 to CR-220B
208211-1
Clay
4
0
closed
SR-23 (BFC) - I-10 Interchange
213258-2
Duval
4
45
closed/assoc./2096595
SR-23 (BFC)from SR-134 to I-10
209659-5
Duval
4
83.53
05:p8closed
SR23/BFC (Clay CL to Argyle Forest Blvd.)
209250-3
Duval
4
0
08:p8closed
SR23/BFC Overpass, Plantation Oaks Blvd.
208166-2
Clay
4
0
08:p8nomitreq
SR21, From SR 23 to Old Jennings Road
208211-7
Clay
4
4.5
I-295 at Commonwealth
213259-4
Duval
4
1.75
2012-2013:p8
I-295 Auxiliary Lanes
213345-7
Duval
4
2.58
2012-2013:p8
Branan Field Frontage Roads and Lane Additions
429304-2
Clay/Duval
4
53.79
2012-2013:p8
SJ38
08:p8nomitreq
10:p5 97:p23, 00:p7closed
Basin 12. Southern Ocklawaha River Basin SWIM projects (Emeralda Marsh, North Shore Lake Apopka)
CR 44B (US 441 to SR 44)
409870-1
Lake
12
0.025
SR 19 (Juniper Springs Run Bridge)
238770-2
Marion
14
0
closed
SR 500 (Lake Ella Rd to Avienda)
238395-5
Lake
12
0
07:p16nomitreq
SR 500 (M.L.K. to Lake Ella Rd)
238395-4
Lake
12
4.29
SR 500 (Picciola Rd. to Sumter Co.)
238395-1
Lake
12
0
SR 500 SR 44 to College Rd.
238315-1
Lake
12
4.65
SR 500 SR44toPicciola(Perkins to Griffin)
238394-1
Lake
12
0
Turnpike/CR 470 Interchange
404214-1
Lake
12
11.5
01:p38
US 441 Perkins to SR 44
238394-3
Lake
12
0.56
07:p16
US-27 (SR-25)Sblane/Leesburg
413950-1
Lake
12
0.54
05:p.19closed
US441 Griffen to MLK
238394-4
Lake
12
0.03
07:p16
SJ47
08:p14app 1/09
07:p16 03:p11closed 99:p14 03:p11closed
Basin 23. Preservation, habitat enhancement and/or stormwater retrofit in Lake Jesup basin
I-4 S. of Ivanhoe to No of Kennedy Blvd
242484-5
Orange
23
5.14
06:p20includes2424846
SR 426 (Mitchell Hammock to Winter Sprgs.) SR 419/SR 434 from west of Jetta Pt. to SR 426/CR426
404525-1
Seminole
23
1.1
02:p52
422015-1
Seminole
23
0
SJ52
2012-2013:p33
Basin 17. Mitigation Bank credits, preservation and enhancement (Krol, Paredes, Nordstrom, Dan Paul, Ford)
Amaral Plaza (US 1/SR 5)
428918-1
Volusia
17
0.182
11:p5
I-4, SR 44 to I-95 (Flyover Ramp)
408464-1
Volusia
17
1
12:p5
I-95 Brevard C/L to SR 44
406869-4
Volusia
17
16.52
07:25assocSJ46,53
I-95 So of I-4 to US 92
242715-2
Volusia
17
16.06
09:p19
I-95 SR 44 to I-4
406869-6
Volusia
17
76.5
07:p25
SR 483 (Clyde Morris) Beville Rd. to US 92
408178-1
Volusia
17
0
12:p5
SJ56
Basins 14,16. Preservation as additions to Heart Island CA or other adjacent conservation lands (Strawn)
Commuter Rail Transit Phase 1
4129944P1
Volusia
14
1.55
09:p11
Sunrail/Commuter Rail-Debary to Deland
423466-9
Volusia
14
1.46
12:p10 27
Sunrail/Commuter Rail-Deland Station
423446-9
Volusia
14
2.98
US 1 @ Black Branch Bridge
411092-1
Flagler
16
0
US 92 Multiuse Path US 17 to Kepler
417205-1
Volusia
16
0.99
09:p11
US17/SR15 DeLeon Springs to SR 40
410251-1
Volusia
14
17.96
08:p17
SJ57
08:p17closed
Basin 22. Preservation/enhancement and/or District water quality improvement or restoration project (Herndon/Wheeler, Sembler)
I-95 No of CR 512 to SR 514
413072-1
SR 5 (US 1) S. of Highlands Dr. to S of Oslo Rd.
228583-4
SR 9 (I-95) Indian River C/L to SR 60
413048-1
I-95/SR 9 from N of R 512 to Brevard Co. Line
413049-1
I-95/SR 9 from SR 60/Osceola Blvd to N. of CR 512
413050-1
SJ58
12:p10
Brevard Indian River Indian River Indian River Indian River
22
21.128
08:p30
22
2.2
12:p17
22
0.36
12:p17
22
5.18
2012-2013:p29
22
0.08
2012-2013:p29
Basin 12. Pres/enhance as additions to existing conservation lands in Basin 12 and/or rest./enh.(Lake Apopka, Lewis, & Emeralda Marsh)
Fla. Turnpike (I-4 to Beulah) Fla. Turnpike (SR-429 to SR-50 North)
406148-1 406146-1
Orange Orange
12 12
0.42 18.82
SR 50 Avalon Road to SR 429
410983-1
Orange
12
0
08:p33 08:p33 08:p33impacts prev mitigated
SR 50 Hancock Road to Orange/Lake CL
238429-4
Lake
12
0
08:p33 closed
SR 50 Turnpike to Avalon Road
239535-2
Orange
12
0.391
08:p33
18
0.64
12:p14
3
1
2012-2013:p5
SJ60
Basin 18. Mitigation Bank credits, preservation and enhancement
Sunrail/Commuter Rail- Debary to Deland
SJ61
Volusia
Basin 3. Mitigation bank credits or pre/enh project in Basin 3
SR 200, Still Quarters to West of Rubin
SJ62
423446-9 210712-3
Nassau
Basin 5. Mitigation Bank credits and/or pres/enh in Basin 5
I-295 Auxiliary Lanes
213345-7
Duval
5
22.88
2012-2013:p14
US 1 at CR210
210420-7
St. Johns
5
7.3
2012-2013:p14
SR 13 @ SR 16
424454-1
St. Johns
5
0.25
2012-2013:p14
SR 16, From Green Acres Road to SR 5A
424481-1
St. Johns
5
0.07
2012-2013:p14
SJ63
Basin 9. Mitigation Bank Credits or pres/enh within basin
SR 16, From Green Acres Road to SR 5A
424481-1
St. Johns
9
0
2012-2013:p20
US 1 Bunnell Weigh Station
425529-1
Flagler
9
0
2012-2013:p20
SJ64
Basin 11, 12. Pres/enh within areas identified by SR40 Task Force
SR 40 from CR 314 to CR 314A
410674-3
Marion
11
14.55
2012-2013:p24
SR40 Project A
410674-2
Marion
11
0.67
2012-2013:p24
SR40 Project B
410674-3
Marion
11
4.17
2012-2013:p44
SJ01
Basins 1,2. Preservation and enhancement in the greater St. Mary's River basin (Baker State Forest)
CR 121 Brandy Branch Bridge
212595-1
Nassau
2
3.1
97:p5, 01:p5closed
CR 121 Mill Creek Bridge
212606-1
Nassau
2
4.6
97:p5, 01:p5closed
I-10 Rest Areas
213317-1
Duval
1
0
SR 200 fromUS-90 to Nassau CL
209537-3
Duval
1
23.86
01:p5
SR 200 Thomas Creek to Callahan
210683-3
Nassau
1
22.06
01:p5
US 17 Bridge over St. Mary's River
210676-1
Nassau
2
0
US 90 SCLRR Deep Creek Bridge
210693-1
Nassau
1
0.71
SJ06
02:p5 closed
97:p5, 01:p5 closed 97:p5, 99:p12, 01:p5closed
Basins 3,4. Purchase of purchase of credits at Northeast Florida Wetland Mitigation Bank
I-95 from I-295 to Nassau Co.
213271-1
Duval
3,4
12.35
97,p11, 00:p11
I-95 Nassau County
213469-1
Nassau
3
14.1
97:p11, 99:p11, 00:p11
2014-2015 FDOT Wetland Mitigation Plan
Page 28
SJ10
Basins 4,5. Preservation in 12-mile Swamp (Cummer Trust parcel)
I-95 (Int'l Golf Parkway to Duval Co.)
213516-2
St. Johns
5
1.79
01:p13
I-95 (SR 16 to International Golf Parkway)
213515-2
St. Johns
5
8.24
01:p13
I-95 from I-295 south to St. Johns Co.
213274-1
Duval
5
3.71
00:p12
I-95 Rest Area in St. Johns Co.
213506-1
St. Johns
5
0.54
00:p12
Racetrack Rd./Durbin Creek Bridge
212367-1
St. Johns
5
3.8
97:p14, 00:p12
Southside Blvd. I-95 to JTB
211510-7
Duval
4,5
SR 13 Clair Ln. to Sunbeam
211478-4
Duval
SR 13 Cunningham Creek Bridge
210213-1
St. Johns
SR 13 Robert Rd. to Davis Pond
210223-1
St. Johns
US 1 (St. Johns Co. to Judith Ave.)
209641-1
Duval
US 1 Durbin Creek Bridge
210281-1
St. Johns
SJ12
0
97:p14
4
0
closed
4
2.67
97:p14, 00:p12
4
0
97:p14, 00:p12
5
1.73
00:p12
5
0.67
98:p7, 00:p12
Basins 8,9. Pres & enhancement of uplands and wetlands in the Deep Creek basin (TCAA, Yarborough & Edgefield)
CR 13 @ Sixteen Mile Creek Bridge (mod1)
2123821A 2123821B
St. Johns
8
0.069
closed
Deep Creek Mitigation
211699-8
(blank)
(blank)
(blank)
closed
SR 207 (CR 206 to CR 305)
St. Johns
8
5.97
01:p17 closed
St. Johns
8,9
26.64
01:p17
St. Johns
8,9
6.39
01:p17
SR 207 (CR 305 to I-95)(mod2)
210409-1 2102531A 2102531B 2102531C
St. Johns
8,9
2.12
01:p17
SR 207 at Cracker Branch Bridge
210283-1
St. Johns
8
0.83
97:p20, 01:p17closed
SR 207 from CR 207 to St. Johns Co.
210016-1
Putnam
8
1.92
97:p20, 01:p17closed
SR 207 from SR100 to CR 207
209965-1
Putnam
8
3.04
97:p20, 01:p17 closed
SR 207 Putnam Co. to SR 206
210410-1
St. Johns
8
9.68
97:p20, 01:p17closed
CR 13 @ Sixteen Mile Creek Bridge
SR 207 (CR 305 to I-95) SR 207 (CR 305 to I-95)(mod1)
SJ16
St. Johns
8
1.61
07:p10
Basin 16. Crescent Lake Basin preservation and long-term management (Plum Crk/Volusia/Rayonier, WT Ranch)
CR305 Bridges
407463-1
Flagler
16
0
closed
SR 100 (US 1 to Belle Terre Pkwy.)
237965-1
Flagler
16
6.54
02:p27
SR 100 Bridges Flagler Co.
237921-1
Flagler
16
2.96
00:p20, 02:p27
SR 11 ( Little Haw Creek Bridge)
408639-1
Flagler
16
0.44
05:p25
SR 11 Bridge Replacement (1)
237915-1
Flagler
16
0
closed
SR 11 Bridge Replacement (2)
237916-1
Flagler
16
0
closed
SR 11 Bridge Replacement (3)
237917-1
Flagler
16
0
closed
SJ18
Basins 18, 23. Gemini Springs additions (Empire Cattle Co)
SR 417 I-4 Interchange
242593-1
Seminole
18
8.05
98:p7, 99:p13
SR 417 Old Lake Mary to Rinehart
240259-1
Seminole
23
1.41
98:p7, 99:p13
SR 417 US 17/92 to Old Lake Mary
240258-1
Seminole
23
1.74
98:p7, 99:p13
SJ19
Basins 10,12. Lake Apopka SWIM program at the North Shore Area or Clay Island ( see also SJ38 & SJ58)
CR 325 A Bridge (near CR 448)
407165-1
Lake
12
SR 500 CR 464 to CR 225A
238679-1
Marion
SR 500 Lake Eustis to CR 44B
238314-1
Lake
SR 500 Lake Shore to Lake Eustis
238358-1
SR 500 SR 44 to College Rd. SR500 College Rd. to Lake Shore
SJ22
0
closed
10
1.09
99:p18
12
0.184
99:p14
Lake
12
0.57
99:p14
238315-1
Lake
12
2.3
99:p14
238412-1
Lake
12
2.16
99:p14
Basin 6. South Shore Pablo Creek preservation and long-term management (Hodges II)
9A Butler to Beach 2014-2015 FDOT Wetland Mitigation Plan
209301-1
Duval
6
15.18
99:p17 Page 29
9A JTB Interchange
209278-1
Duval
6
13.87
99:p17
9A SJB to Beach
209168-1
Duval
6
22.65
99:p17
SJ24
Basin 3. Upper Nassau River basin preservation (Four Creeks) and mitigation bank credits (NEFWMB)
SR 200 Griffin Rd. to I-95
210687-2
Nassau
3
22.6
00:p1
SR 200 Griffin Rd. to StrattonRoad
210687-3 21068703
Nassau
3
33.38
00:p1
Nassau
3
1.03
00:p1closed
SR 200 Griffin Rd. to StrattonRoad(mod)
SJ25
Basin 4. Preservation at Pumpkin Hill/Timucuan Preserve (Birchfield, Fanning Island)
Cedar River Bridge
209655-1
Duval
4
0
closed
I-295 (Commonwealth to Trout River Brdg.)
213259-2
Duval
4
0.42
02:p8
I-95 (Lem Turner to Heckscher Dr.)
213245-1
Duval
4
3.262
01:p10
I-95 from Heckscher Dr. to I-295
213273-1
Duval
4
0.2
00:p9, 01:p10
JIA Access Road
209399-1
Duval
4
10.35
00:p9, 01:p10
JIA Interchange
209399-2
Duval
4
0.51
00:p9, 01:p10
SJ26
Basin 6. Project withdrawn. Water quality enhancement and vegetation control at Guana River State Park
AIA from CR 210 to Duval Co.
SJ27
210404-1
St. Johns
6
0
00:p15
Basin 8. Etoniah Creek CARL Project (Rice Creek) and Murphy Island
CR 309 Access Road
403855-1
Putnam
8
1.72
02:p14
SR 100 Little Rice Creek Culvert Replacement
210014-2
Putnam
8
0.85
10:p11
SR 15 (Dunn Creek Turn Lane)
210034-2
Putnam
8
0
closed
SR 20 (Francis to SR 19)
210004-1
Putnam
8
2.28
01:p20, 02:p14
SR 20 (Rowland Ave. to Francis)
209999-1
Putnam
8
40.63
SR 20 Rice and Sweetwater Creek Bridges
209962-1
Putnam
8
6.17
01:p20, 02:p14 97:p26, 00:p17, 00a:p13, 01:p20
SJ28
Basin 17. Stormwater retrofit by City of So. Daytona. Preservation (Paul smith, Volusia 44, Krol)
I-4 (SR 44 to I-95)
408464-1
Volusia
17
I-95 SR 40 to Flagler Co.
242696-1
Volusia
17
1.9
00a:p9, 01:p24, 02:p30closed
I-95 Volusia County to Palm Coast
242340-1
Flagler
9,17
9.68
00:p22, 01:p24, 02:p30closed
SR 100 (Belle Terre Parkway to I-95)
237925-1
Flagler
17
9.3
01:p24, 02:p30closed
SR 40 (Cone Rd. to Tymber Creek)
241009-1
Volusia
17
14.83
SJ29
58.22
02:p30closed
02:p30closed
Basin 11. Northern Ocklawaha River Basin Group (Lybass, Rayonier/River Styx, Orange Crk, Crones Cradle, Bloom/Frank)
SR 20 (CR 315 to Roland Ave.)(2)
2099691A 2099691B
SR 20 (Hawthorne to CR 315)
210024-1
Putnam
11
0
SR 20 (SR 325 to Hawthorne)
207714-1
Alachua
11
12.7
SR-20 from US-301 to Putnam CL
207818-2
Alachua
11
0
05:p11closed
SR-26/US-301
207831-1
Alachua
11
20.58
05:p11closed
SR-26@ 222 &234
207796-3
Alachua
11
0.63
07:13closed
SR-26A from SR-26 to SR-26
207790-1
Alachua
11
0.88
05:p11closed
SW 20th Ave. (75th St. to SW 34th St.)
211335-1
Alachua
11
0
closed
SR 20 (CR 315 to Roland Ave.)
SJ30
Putnam
11
6.15
01:p34closed
Putnam
11
0.22
01:p34(mod)closed closed 00:p24, 01:p34closed
Basins 21,22. Blueway acquisition and/or restoration at Pine Island
SR 5 (Post Rd. to SR 404-Pineda)
237550-1
Brevard
22
0.98
99:p15
SR 518 Causeway repairs
237724-1
Brevard
21,22
0.28
00a:p5
SR 518 Causeway repairs (mod1)
237724-1
Brevard
21,22
0.44
00a:p5
SR 528 (WB lane Indian River Bridge)
404601-1
Brevard
21
0.5
02:p42
US 1 Goat Creek Bridge
237674-1
Brevard
22
0
00a:p5 closed
US 192 Causeway repairs
237723-1
Brevard
22
0
00a:p5closed
2014-2015 FDOT Wetland Mitigation Plan
Page 30
SJ32
Basin 4. Jacksonville West Project Group - Mitigation Bank credits (NEFWMB)
!-95/I-10 Interchange
213243-1
Duval
4
1.8
03:p8
Old Kings Road Bridge replacement
212079-1
Duval
4
0.37
00a:p11
US 90 McGirts Creek Bridge
209568-1
Duval
4
0.86
00:p6, 00a:p11
SJ34
Basin 3. Nassau River basin preservation (Logan, Four Creeks) and Mitigation Bank credits
SR 200 (Duval Co. to Thomas Creek)
210683-4
Nassau
3
51.812
01:p8
SR 200 (Thomas Creek to Callahan)
210683-3
Nassau
3
22.567
01:p8;
SJ35
Basins 5,9. Preservation and enhancement at Matanzas Marsh parcel (Rayonier/MatanzasMarsh)
I-95 (Equestrian crossing)
242345-1
Flagler
9
0.24
01:p13
I-95 (FECRR to SR 207)
213503-1
St. Johns
9
20.53
01:p13
I-95 (Flagler Co. to FEC RR)
213502-1
St. Johns
9
1.48
02:p17
I-95 (SR 207 to SR 16)
213505-1
St. Johns
9
2.78
01:p13
I-95 Palm Coast to St. Johns Co.
242341-1
Flagler
9
3.94
00:p22, 01:p24
SR 207 (Permit modification in St. Johns Co.)
210224-1
St. Johns
9
0.35
01:p13
SJ36
Basin 17. Stormwater retrofit by City of Port Orange, acquisition in Spruce Creek Preserve (Eubanks), and saltmarsh restoration (Parades)
SR 5A (Flomich to Wilmette)
240719-1
Volusia
17
0
01:p27see2407581closed
SR 5A (US 1 to Village Trail)
240757-1
Volusia
17
14.9
SR 5A (Village Trail to Herbert)
240720-1
Volusia
17
0
01:p27includes2407201 01:p27see240757impactsclsd
SR 5A (Wilmette to US 1)
240758-1
Volusia
17
2.33
SJ37
01:p27
Basin 19. Preservation and enhancement in the Econlockhatchee River basin (LeFevre, Dietrich, Yarborough Ranch)
SR 436 (SR 528 to SR 552)
239454-2
Orange
19
11.97
01:p31closed
SR 50 (Dean Rd. to Old Cheney Rd.)
239203-4
Orange
19
16.76
01:p31closed
SR 50 (SR 417 to Dean Rd.)
239203-3
Orange
19
2.34
01:p31closed
SR 50 (SR 436 to SR 417)
239203-2
Orange
19
0
01:p31closed
SR 520 (SR 50 to SR 528)
239292-1
Orange
19
8.26
02a:p2closed
SJ40
Basin 13. Preservation & enhancement of wetlands/uplands preferably as additions to other conservation lands within Basin 13
SR 25 (Highland Ave. to Pearl St.)
238424-1
Lake
13
SR 25 (Lake Louisa to SR 50)
238423-1
Lake
12,13
SR 25 (SR 530 to Boggy Marsh)
238421-1
Lake
13
0.07
02:p20
SR 27 Boggy Marsh to L.Louisa
238422-1
Lake
12,13
1.42
04:p10
US 27 (SB Palatlakaha River Bridge)
408638-1
Lake
13
SJ41
0
01:p4; closed
0
04:p10 closed
0
03:p15closed
Basins 15. Restoration/preservation in the Wekiva River basin (Hubler, Sutton)
Commuter Rail Transit Phase 1
4129944P1
Volusia
15
1.026
09:p15(see SJ53,56)
Fla. Turnpike (I-4 to Beulah)
406148-1
Orange
14
0.16
05:p22
I-4 (Saxon to SR 472)
242716-1
Volusia
14
0.44
02:p23closed
I-4 From Central Parkway to SR 434
242592-3
Seminole
15
0.01
10:p14
I-4 N of Kennedy to N of Maitland Blvd.
242484-6
Orange
23
0.28
06:p20g/w2424845
I-4 Orange Co. to Central Pkwy
242592-2
Seminole
15
3.71
07:p22app 5/09
Lake Norris Rd. Bridge
241444-1
Lake
15
0
02:p2closed
SR 408 Interchange
406102-1
Orange
15
0
03:p18 closed
SR 423 (Shader Rd. to SR 424)
239496-2
Orange
15
0
closed
SR 434 @ Little Wekiva Outfall
423513-1
Seminole
15
0
09:p15
SR 438 (Clark to Hiawassee)
239289-1
Orange
15
SR 50 (SR 429 to Good Homes Road)
239535-3
Orange
12,15
3.31
04:p14closed
SR 50 Good Homes to Pine Hills
239535-4
Orange
15
2.98
06:p8
US 441 By-pass (CR 437 to CR 424)
239414-1
Orange
12,15
0
closed
2014-2015 FDOT Wetland Mitigation Plan
0
closed
Page 31
SJ42
Basin 18. Mitigation Bank credits, pres/enh in Volusia Corridor & Tiger Bay connector (Menard, Fore, Fore, WT Ranch, Plum Crk, Volusia 44)
I-4 (SR 472 to SR 44and interchange)
408463-1
Volusia
18
19.66
02:p34closed
I-4 (SR44 to I-95)
408464-1
Volusia
18
38.44
02:p34closed
SR 415 (Reed Ellis to Acorn)
407355-4
Volusia
18
5.54
06:p11closed
SR 415 (Seminole Co. to Reed Ellis Rd.)
407355-3
Volusia
18
36.09
06:p11closed
SR 415 (SR 46 to Volusia Co.)
407355-1
Seminole
18
6.96
06:p11closed
SJ43
Basins 18, 20. Marsh restoration at Lake Harney by Seminole County government
SR 46 (Volusia Co. to Carpenter)
SJ44
I-4/East-West Interchange
SJ45
237711-1
Brevard
18
2.1
02:p36
Basin 18. Project withdrawn. City of Orlando - Southeast Lake Basin Restoration Project 242484-2
Orange
18
0
02:p39closed
Basin 18 Preservation and enhancement in Basin 18 (Maytown Tract) and mitigation bank credits
I-4 West of OBT to So. of Ivanhoe
242484-4
Orange
18
3.95
05:p28,09:p.24
I-95 (SR 528 to SR 50)
405506-2
Brevard
18
21.33
05:p28,09:p.24
I-95 SR 519 to SR 528
405506-5
Brevard
18
17.32
03:p.21,09:p.24
SR 5 (Barnes to SR 520)
237576-1
Brevard
20
0
02:p47
SR 5 (SR 520 to Cidco Rd.)
237592-1
Brevard
20
0
02:p47
SJ46 Basin 21. Restoration/preservation at Turnbull Hammock (Peters, Hart, Cape Atlantic Estates) I-95 Brevard C/L to SR 44
406869-4
Volusia
21
36.74
SR 442 ( I-95 to Air Park Rd.)
240812-1
Volusia
21
0
02:p49closed
SR 442 (US 1 to Air Park Rd.)
240811-1
Volusia
21
16.1
02:p49closed
US 1 (Turnbull Creek Bridge)
241043-1
Volusia
21
0
US 1 @ Barnes Blvd.
237576-3
Brevard
21
2.1
08:p24closed
SJ48
07:p35assocSJ52,53
closed
Basin 20. BCWMA enhancement, Fellsmere Farms restoration
I-95 @ Pineda Interchange
405506-6
Brevard
20
14.1
06:p14
I-95 SR 514 to SR 518
405506-3
Brevard
20
20.358
03:p.21
I-95 SR 518 to SR 519
405506-4
Brevard
20
6.89
03:p.21
I-95 SR 519 to SR 528
405506-5
20
12.59
03:p.21
SR 60 west of 82nd Ave to 66th Ave
228627-1
22
1.76
08:p27
SR 60 Fla. Turnpike to I-95
228596-1
20
2.84
05:p31
SR 60 west of I-95 to 82nd Ave
228628-1
Brevard Indian River Indian River Indian River
22
0.13
08:p27
(blank)
closed
SJ49
Basin 12. Mitigation Bank Credits (changed to SJ58; see 2008 Plan)
no projects
SJ50
9999999
(blank)
Basin 4. Mitigation Bank Project Group (Bull Crk, Longbranch Crossing)
Dr.'s Inlet Bridge
208207-1
Clay
4
0.62
05:p5closed
I-10 BFC to I-295
213272-4
Duval
4
11.88
07:p8closed
I-295 (Blanding Blvd. Ramps)
213351-5
Duval
4
6.13
02:p11closed
I-95/I-295 North interchange
213323-4
Duval
4
0.75
05:p5closed
SR 21 Old Jennings Rd to Knight Boxx Rd.
208211-2
Clay
4
1.68
06:p6closed
SJ51
Basin 22. Restoration and enhancement (Herndon Swamp/Wheeler Groves, Sembler)
Apollo Sarno to Eau Gallie
241241-1
Brevard
22
1.93
07:p38 (06)
Babcock St. (Malabar to Hunter)
237650-4
Brevard
22
0
closed (06)
Babcock St. (Malabar to US 192) - see Inv. 0044
237650-3
Brevard
22
0
06:p17closednomitreq (06)
Babcock St. (SR 507 Melbourne Av. To Fee)
237650-2
Brevard
22
0
03:p.21closed (06)
Gradick Dr. @Goat Creek Bridge
241210-1
Brevard
22
0
02:p42closed (06)
I-95 (Palm Bay Rest Areas)
242318-1
Brevard
22
7.18
02:p42;03:p.21closed (06)
I-95 SR 514 to SR 518
405506-3
Brevard
22
0.552
03:p.21 (06)
2014-2015 FDOT Wetland Mitigation Plan
Page 32
Palm Bay Road (Minton to Conlin)
241221-1
Brevard
22
6.06
Port Malabar Rd. @ Turkey Creek Bridge
241211-1
22
0
closed (06)
Vero Beach Municipal Airport
409842-1
Brevard Indian River
22
0
05:p31closed (06)
Wickham Rd. @ NASA/Ellis Rd.
404667-1
Brevard
22
0.494
SJ53
02:p42;04:p.7 (06)
04:p19 (06)
Basin 18. Preservation and enhancement (Maytown, Yarborough, Kemcho) and mitigation bank credits
Commuter Rail stations
4129944P1 4129944S
Seminole
18
6.5
I-95 Brevard C/L to SR 44
406869-4
Volusia
18
22.45
07:p29assocSJ46,52
I-95 SR 46 to Volusia C/L
406869-5
Brevard
18
7.14
07:p29
I-95 SR 50 to SR 46
406869-3
Brevard
18
5.84
07:p29
SR 46 Mellonville to SR 415
240216-2
Seminole
18
7.38
07:p29
Commuter Rail Phase 1
SJ54
Volusia
18
5.147
08:p21 08:p21
Basin22. Central Indian River Lagoon restoration and enhancement
US1 Emergency Slope Repairs
420930-1
Brevard
22
1
07:p41
CR 125 St. Mary's River (S. Prong) Bridge
211448-1
Baker
1
0.924
09:p5
Lessie RoadBridge/culvert replacement
212594-1
Nassau
2
0.98
08:p5
213516-5
St. Johns
5
35.4
10:p8
SJ55
Basins 1,2. Mitigation Bank Credits
SJ59 Basin 5. Preservation & enhancement of wetlands/uplands in Basin 5; preferably as additions to other conservation lands within basin
2014-2015 FDOT Wetland Mitigation Plan
Page 33
1/27/2015
Permitting
Permitting
An overview of water management district permitting The two most common types of permits issued by Florida’s five water management districts address how much water may be used and address the impact of new development and construc tion activities on water resources. The first type of permit, which authorizes water use, is a con sumptive use permit (CUP). A CUP typically allows water to be withdrawn from ground water or surface water for reasonablebeneficial uses — such as public supply (drinking water), agricultural and land scape irrigation, commercial use, and power generation — in a manner that does not inter fere with other existing legal water uses and protects water resources from harm (such as saltwater intrusion and drying up of wetlands, lakes and springs). CUPs require water conservation to prevent wasteful uses, such as the reuse of reclaimed water (treated wastewater) or storm water instead of higher quality groundwater, and set limits on how much water can be withdrawn at each location in the aquifer or from surface water. These limits protect existing residents’ water supplies and protect aquifers, lakes and rivers from harm. The second permit is an environmental resource permit (ERP), which authorizes new development or construction activities to occur in a manner that will prevent adverse flooding, manage surface water, and protect water quality, wetlands, and other surface waters. ERPs prevent flooding, protect the water quality of Florida’s lakes and streams from stormwater http://www.sjrwmd.com/permitting/#handbooks
1/3
1/27/2015
Permitting
pollution, and protect wetlands and other surface waters.
Who needs a CUP? Consumptive use permitting regulations have many thresholds, but the three situations which most frequently require a permit are: You want to withdraw water from a well that measures six inches or more in diameter You use or want to use an annual average of 100,000 gallons of water or more per day You have the capacity to pump 1 million gallons of water or more per day
Large water users, such as agricultural users, are required to obtain a consumptive use permit.
How do you obtain a CUP? To make certain that water users meet the criteria, District engineers and hydrologists review permit applications and conduct site inspections. Each permit applicant is required to: Submit a water conservation plan, providing measures to reduce water use and preserve water resources for other beneficial uses Investigate and use the lowest acceptable quality source of water. For example, golf courses and other large users of water for landscape irrigation are required to use reclaimed water or storm water when available instead of higher quality potable groundwater.
What happens after a CUP is issued? Each permit authorizes water use for a particular purpose and contains a number of permit conditions that must be followed by the water user. All water users are responsible for implementing their approved water conservation plan and reporting their total monthly water use every six months. Each permit has a limited duration and must be renewed upon expiration. At that time, the District reviews the permit again.
Who needs an ERP?
Golf courses and other large users of water are required to use the lowest acceptable quality source of water for irrigation.
ERPs were first required in 1995. They combine the former wetland dredge and fill permit issued by the Florida Department of Environmental Protection and the Management and Storage of Surface Waters permit issued by the water management districts. Anyone proposing construction of new facilities, including governmental agencies, developers building new residential or commercial areas, or anyone who wants to fill in wetlands must have an ERP. http://www.sjrwmd.com/permitting/#handbooks
2/3
1/27/2015
Permitting
How do you obtain an ERP? ERP applications may be obtained online, or by calling or writing the District. If you need help in preparing the application, you can arrange a preapplication conference with a District engineer or environmental specialist, or you can call if you have questions that can be answered by phone. Most ERP applications involve a site visit by a District environmental specialists.
What happens after an ERP is issued? A permit is issued for a specific purpose and contains a number of conditions that must be followed. Permit holders are responsible for implementing these conditions and filing whatever reports may be necessary, including an asbuilt certification upon completion of construction. Each permit has a limited duration for construction, usually five years. On the St. Johns River Water Management District’s website, you can search for application and permit information and regulatory rules, forms and meeting information. You can also create and maintain a login ID that enables you to submit permit applications, submit permit compliance information, and subscribe to electronic noticing of application receipt and intended permit issuance decisions. Online applications that are currently available include the contractor licensing (new and renewals); water well construction permits (WWCs); consumptive use permits (CUPs), new, renewal and modifications; CUP notice of general permits; environmental resource permits (ERPs), new and modifications; and ERPagriculture (silviculture) permits. All compliance submittals may also be submitted on this site. St. Johns River Water Management District 4049 Reid Street, Palatka, FL 32177 (800) 725-5922
http://www.sjrwmd.com/permitting/#handbooks
© 2015 St. Johns River Water Management District
3/3