Appendix K Needs Plan Project Costs, Purpose and Need
February 7, 2015
This page is intentionally blank.
Path Forward 2040 Long Range Transportation Plan
PURPOSE AND NEED STATEMENTS
The Needs Plan included a six county area consisting of Baker, Clay, Duval, Nassau, Putnam and St. Johns counties. The Needs Plan is not a prioritized list of projects, nor is it constrained by financial resources. The Needs Plan leveraged prior studies development by the Florida Department of Transportation, the North Florida Transportation Planning Organization and local governments. Maintaining the public consensus continuity of these efforts was essential to the credibility of the planning process. Because of the level of visioning and planning that occurred within these studies, the known needs greatly exceeded the resources anticipated to be available. Building on the community consensus that was achieved, the development of the Needs Plan began with a review and confirmation of these studies. The following sources were used to define the needs.
2035 Envision Long Range Transportation Plan City of Jacksonville Mobility Plan Committed Development Projects Provided by Local Governments Coordination with local governments and stakeholders on additional needs FDOT’s Strategic Intermodal Systems Needs Plan and Cost Feasible Plan (includes 1st Five Year and 2nd Five Year) FDOT’s Adopted Work Program First Coast Regional Greenways and Trails Plan Jacksonville Transportation Authority Blueprint 2020 Local Government Comprehensive Plans North Florida TPO Congestion Management Plan North Florida TPO Freight, Logistics and Intermodal Planning Framework Plan North Florida TPO ITS Master Plan North Florida TPO Regional Bicycle and Pedestrian Plan North Florida TPO Strategic Safety Plan North Florida TPO Transportation Improvement Program
As part of the planning process, these needs were confirmed through an analysis of the safety, congestion, mobility and emergency evacuation needs. The following tables summarize the needs plan costs in present day dollars and provide a summary of the purpose and need for each project of the road and transit capacity projects.
1
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type New 2 Lane Road Widen to 4 Lanes Widen to 5 Lanes New 4 Lane Road Widen to 4 Lanes* Widen to 6 Lanes New 2 Lane Road New 2 Lane Road Widen to 4 Lanes New 2 Lane Bridge New 2 Lane Road New 2 Lane Road New 2 Lane Road New 2 Lane Bridge Reconstruct 2 Lanes New 2 Lane Road New 2 Lane Road New 2 Lane Road Widen to 5 Lanes New 4 Lane Road New 2 Lane Road New 3 Lane Road Widen to 6 Lanes New 4 Lane Road Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New Interchange New 4 Lane Road, Two Overpass and New Interchange
Abaco Island Drive Extension Alta Drive Alta Drive / Yellow Bluff Road Alta Drive Realignment Amelia Island Parkway Argyle Forest Boulevard Arrigo‐Parliament Reconnection Barnwell‐0' Neil Scott Connector Baxley Road Blount Island Boulevard Extension Braddock Parkway Brady Point‐Clements Connector Brinkhoff Road Buffalo Road Cahoon Road Cardinal Street North Extension Cardinal Street South Extension Cecil Field Connector Chaffee Road Cheswick Oak Avenue Extension Christian Way Extension Clark Road Extension College Drive College Drive Extension Collins Road Collins Road Collins Road Collins Road Collins Road Realignment
Nassau Duval Duval Duval Nassau Duval Nassau Nassau Clay Duval Duval Nassau St. Johns Putnam Duval Nassau Nassau Duval Duval Clay Nassau Duval Clay Clay Duval Duval Duval Duval Duval
988 3 2 1 704 936 980 1001 900 1006 939 1002 801 503 1016 976 975 972 971 13 995 1020 902 14 930 932 15 16 16B
Abaco Island Drive SR 105 Heckscher Drive I‐295 SR 105 Zoo Parkway South 14th Street SR 23 First Coast Expressway Arrigo Boulevard Barnwell Road CR 220 Doctors Inlet Road Spoil Island SR 115 Lem Turner Road Brady Point Road SR 207 Buffalo Road west Lenox Avenue Cardinal Avenue Spring Meadow Avenue Commerce Center SR 228 Normandy Boulevard Oakleaf Plantation Parkway Christian Way Broward Road CR 220 Doctors Inlet Road SR 21 Blanding Boulevard Shindler Drive Old Middleburg Road S SR 21 Blanding Boulevard at US 17 Roosevelt Boulevard Pine Verde
Zion Court I‐295 New Berlin Road (north ) North of New Berlin Road (south) CR 105A Buccaneer Trail Old Middleburg Road Parliament Drive O'Neil Scott Road SR 21 Blanding Boulevard Jacksonville Port Authority Pecan Park Road Clements Road Wildwood Drive Buffalo east US 90 Beaver Street SR 200 SR AIA Yulee Backage Roads William Burgess Boulevard SR 23 First Coast Expressway Crystal Springs Road Savannah Glen Boulevard Hampton Club Way Clark Road SR 21 Blanding Boulevard Challenger Drive (Branan Field Road) Rampart Road Shindler Drive Pine Verde
Comfort Road Commodore Point Drive Extension Concourse Loop Road Connector Road CR 105A Buccaneer Trail CR 16A CR 16A Extension CR 209 Russell Road CR 209 South CR 210 CR 210 CR 210 W CR 214 CR 218 CR 218 CR 218 CR 218 CR 218 Extension CR 218 Extension CR 220 Doctors Inlet Road CR 220 Doctors Inlet Road CR 2209 CR 2209 CR 2209 CR 2209 CR 2209 CR 2209 CR 2209 CR 2209 CR 305
Putnam Nassau Nassau Putnam Nassau St. Johns St. Johns Clay Clay St. Johns St. Johns St. Johns St. Johns Clay Clay Clay Clay Clay Clay Clay Clay St. Johns St. Johns St. Johns St. Johns St. Johns St. Johns St. Johns St. Johns St. Johns
505 996 501 502 705 803 802 905 906 805 807 849 809 1026 1027 24 909 25 26 33 34 810 811 812 813 814 815 816 843 818
Port Road Commodore Point Drive License Road US 17 South Fletcher Avenue SR 16 Connector CR 16A CR 739 Henley Road Decoy Road I‐95 Greenbriar Road Longleaf Pine Parkway Holmes Boulevard US 301 Cosmos Avenue SR 21 Blanding Boulevard SR 16 CR 739 Henley Road SR 23 First Coast Expressway SR 21 Blanding Boulevard College Drive SR 23 First Coast Expressway SR 16 Connector International Golf Parkway CR 214 SR 207/CR 305 SR 16 CR 208 at CR 210 CR 204
US 17 Blackrock Road Amelia Concourse Distribution Center Canopy Drive SR 13 Leo Maguire Parkway US 17 US 17 near US 1 Cimarrone Road Greenbriar Road US 1 Cosmos Avenue Pine Tree Lane CR 739 Henley Road CR 739 Henley Road SR 23 First Coast Expressway CR 315 Knight Boxx Road US 17 CR 210 SR 23 First Coast Expressway SR 16 Connector CR 208 CR 214 International Golf Parkway SR 16
US 17 Roosevelt Boulevard
SR 206
Page 1 of 13
Widen to 4 Lanes New 2 Lane Road New 2 Lane Road New 2 Lane Road Turn Lane Improvements* Widen to 4 Lanes New 2 Lane Road Widen to 4 Lanes Reconstruct 2 Lanes Widen to 6 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 3 Lanes* Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 4 Lane Road New 4 Lane Road Widen to 4 Lanes Widen to 6 Lanes New 6 Lane Road New 6 Lane Road New 6 Lane Road New 4 Lane Road New 4 Lane Road New 4 Lane Road New 4 Lane Road New Interchange New 2 Lane Road
2013 Cost O&M Cost (millions) (millions) $0.72 $0.00 $8.85 $0.21 $14.50 $0.15 $15.15 $0.10 $4.17 $0.10 $8.49 $0.48 $0.59 $0.00 $2.89 $0.02 $4.61 $0.05 $80.21 $0.08 $47.68 $0.24 $2.89 $0.02 $4.32 $0.04 $34.71 $0.05 $10.20 $0.07 $1.44 $0.01 $0.48 $0.00 $12.57 $0.07 $30.00 $0.39 $23.08 $0.30 $6.49 $0.04 $0.90 $0.04 $16.29 $0.31 $30.08 $0.23 $11.30 $0.22 $4.10 $0.15 $4.30 $0.15 $36.00 $0.19 $104.84 $0.07 $5.86 $3.61 $3.17 $0.95 $1.41 $24.85 $1.41 $71.88 $68.15 $10.10 $19.90 $10.08 $0.92 $90.98 $7.50 $42.39 $31.33 $33.40 $26.00 $36.86 $40.74 $20.30 $17.75 $11.50 $27.13 $39.51 $11.50 $26.22 $35.23 $10.00
$0.07 $0.02 $0.03 $0.95 $0.05 $0.72 $0.02 $0.77 $0.30 $0.44 $0.22 $0.29 $0.13 $0.96 $0.25 $0.45 $0.33 $0.20 $0.30 $0.30 $0.77 $0.52 $0.45 $0.42 $0.42 $0.61 $0.06 $0.41 $0.19 $0.16
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
CR 305 CR 315 CR 315 CR 739B Sandridge Road Crosby Avenue Extension Davis / 9B Parcel Decoy Road Dixie Highway / Pellicer Lane
St. Johns Clay Clay Clay Nassau Duval Clay St. Johns
850 31 32 904 993 1036 907 1025
SR 206 SR 16 CR 315B CR 739 Henley Road US 17 SR 5 SR 9B US 17 SR 207
SR 207 CR 315B US 17 CR 209 Russell Road Pinewood Drive SR 152 Baymeadows Road CR 209 South CR 214 West of King Street
Dove Road Extension {west} Durbin Parkway Durbin Parkway Duval Station Road east Dove Road Extension East Nassau Connector East Nassau Connector Eastport Road Flora Parke‐Wal Mart Connector Florida Boulevard Future Corridor Initiative
991 819 844 942 974 36 969 37 986 1021 721
Harper Chapel Road Extension 9B Extension at US 1/SR 5 Dixie Highway US 17/SR 5 Main Street Harper Chapel Road I‐95 at I‐95 SR 105 Heckscher Drive Flora Parke Boulevard Penman Road Tampa Bay
Mentoria Road Nocatee Parkway
Pulaski Road Walmart Supercenter SR 10 Atlantic Boulevard Northeast Florida
Gator Bowl Boulevard
Nassau St. Johns St. Johns Duval Nassau Nassau Nassau Duval Nassau Duval Baker/Clay/Duv al Duval
Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 2 Lane Road Widen to 4 Lanes Reconstruct 2 Lanes Reconstruct 2 Lanes and Widen to add Sidewalks and Bike Lanes New 2 Lane Road New 4 Lane Road Modify Interchange Widen to 4 Lanes New 2 Lane Road New 4 Lane Road New Interchange Widen to 3 Lanes New 2 Lane Road Widen to 3 Lanes Future Corridor
Liberty Street
Hart / Mathews Bridge
Widen to 6 Lanes and Remove Ramps
Gene Lasserre Boulevard Extension Goodbread Road Reconstruction Governors Park Road Hamilton Street Extension Harlow Boulevard Harper Chapel Extension Hart Expressway Ramps Hartley Road Harts Road Holmes Boulevard I‐10 I‐10 I‐10 I‐10 I‐10 I‐10 I‐10 I‐10 I‐10 I‐10/US 90 Parallel Reliever I‐295 I‐295 I‐295
Nassau Nassau Clay Nassau Duval Nassau Duval Duval Duval St. Johns Duval Nassau Duval Baker Baker Duval Duval Baker Duval Baker Duval/Clay Duval Duval
985 977 46 1000 943 989 43B 49 963 821 401 402* 403* 404* 405* 406 432 453 454 720 57 119 407
Gene Lassere Boulevard US 17 SR 5 US 17 Goodbread Circle SR 134 103rd Street Harper Chapel Road Liberty Street SR 13 San Jose Boulevard SR 104 Dunn Avenue CR 214 SR 23 First Coast Expressway Baker/Nassau County Line Nassau/Duval County Line W of CR 125 W of SR 121 US 301 I‐295 Baker/Columbia County Line at I‐295 South Mac Clenny SR 13 San Jose Boulevard SR 9B I‐95 North
SR 200A Pages Dairy Road Hamilton Street SR 16
I‐295 I‐295 I‐295 I‐295 I‐295 I‐295 I‐295 I‐295 I‐295 I‐95 I‐95 I‐95 I‐95
Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval St. Johns St. Johns Duval
408 409 410 411 431 964 1022 1023 121 68 138 400 413
North of Trout River US 1 New Kings Road SR 134 103rd Street I‐10 US 17 Roosevelt Boulevard at US 17 Roosevelt Boulevard I‐95 South SR 202 J. T. Butler Boulevard SR 113 Southside Connector at SR 102 Airport Road at US 1/SR 5 Ponce De Leon Boulevard and at SR St. Johns/Flagler County Line SR 104 Dunn Avenue
43
Starratt Road William Burgess Boulevard Chester Road
Lane Avenue Dove Road Extension Hart / Mathews Bridge Old St. Augustine Road I‐295 Four Mile Road I‐295 Nassau/Duval County Line US 301 W of SR 121 Baker/Nassau County Line SR 23 First Coast Expressway I‐95 CR 125
Page 2 of 13
East Baldwin W of US 17 Roosevelt Boulevard I‐295 SR 105 Dames Point Bridge/Heckscher Drive I‐95 North of Trout River I‐10 US 1 South of New Kings Road SR 134 103rd Street SR 13 San Jose Boulevard SR 9B SR 202 J. T. Butler Boulevard
SR 206 SR 102 Airport Road
2013 Cost O&M Cost (millions) (millions) $13.39 $0.39 $29.50 $0.30 $7.10 $0.10 $34.10 $0.36 $0.72 $0.00 $3.15 $0.42 $3.37 $0.02 $2.27 $0.03 $2.78 $52.52 $35.23 $14.48 $0.30 $93.40 $35.23 $11.80 $1.44 $5.30 $2,000.00
$0.03 $0.43 $0.19 $0.13 $0.00 $0.82 $0.19 $0.18 $0.01 $0.14 $5.10
$40.50
$0.00
New 2 Lane Road and Roundabout New 2 Lane Road New 4 Lane Road New 2 Lane Road Widen to 3 Lanes New 2 Lane Road Remove Ramps Widen to 3 Lanes Widen to 4 Lanes Widen to 6 Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Modify Interchange Future Corridor Add 4 Express Lanes on Bridge Add 4 Express Lanes Add 4 Express Lanes
$1.44 $1.98 $71.80 $2.37 $1.89 $0.49 $6.30 $8.40 $18.83 $5.08 $219.54 $4.58 $56.25 $50.57 $16.96 $101.87 $372.32 $155.61 $131.63 $144.00 $177.64 $12.30 $123.30
$0.01 $0.04 $0.59 $0.02 $0.02 $0.01 ‐$0.19 $0.09 $0.22 $0.10 $7.00 $0.71 $3.28 $1.17 $3.28 $6.32 $5.58 $18.49 $0.19 $0.37 $5.20 $3.00 $6.08
Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Modify Interchange Add 2 Express Lanes Add 2 Express Lanes Add 4 Express Lanes Modify Interchange Modify Interchange Add 4 Express Lanes Add 4 Express Lanes
$87.38 $28.17 $180.57 $66.47 $52.45 $34.10 $0.85 $0.85 $176.80 $9.00 $13.18 $92.49 $456.58
$5.18 $1.16 $6.22 $5.47 $6.31 $0.19 $4.46 $4.86 $8.39 $0.19 $0.19 $8.00 $3.62
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From I‐95 I‐95 I‐95 I‐95 I‐95 I‐95 I‐95 I‐95 I‐95 International Golf Parkway Jones Road Kernan Boulevard Kernan Boulevard Knight Boxx Road Lake Asbury East West 1 Lake Asbury North South Road 3 Lofton Creek Crossing Long Bay Road Extension North Macaw Avenue Extension McDuff Avenue / 5th Street Mentoria‐Wm Burgess Connector Merrill Road Mickler Road Monument Road Monument Road National Cemetery Road New Berlin Road New Berlin Road New World Avenue New World Avenue Norfolk Southern Railroad Overpass Northern Cross Town Corridor Northern Outer Beltway Oakleaf Village Parkway Extension Old Kings Road Old Middleburg Road Old St. Augustine Road Old St. Augustine Road
Duval Duval St. Johns Duval St. Johns Duval Duval St. Johns Duval St. Johns Duval Duval Duval Clay Clay Clay Nassau Clay Nassau Duval Nassau Duval St. Johns Duval Duval Duval Duval Duval Duval Duval Duval Baker Duval/Nassau Clay Duval Duval Duval Duval
414 418A 418B 419 420 433 434 846 962 823 944 73 933 901 915 914 710 911 982 1019 990 945 825 946 947 1033 948 949 1034 1035 85 500 88 913 951 1015 90 1010
North of Fuller Warren Bridge Duval/St. Johns County Line International Golf Parkway at US 1/SR 15 MLK SR 206 SR 202 J. T. Butler Boulevard I‐295 at CR 210 at SR 115 Southside Boulevard I‐95 US 90 Beaver Street SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard CR 220 Doctors Inlet Road NS3 CR 739B Sandridge Road Hendricks Road Old Jennings Road Cardinal Street Melson Avenue William Burgess Boulevard Hartsfield Road Palm Valley Road Tredinick Parkway I‐295 Lannie Road Pulaski Road Yellow Bluff Road SR 23 First Coast Expressway SR 23 First Coast Expressway West 12th Street CR 125 I‐10 Oakleaf Plantation Parkway SR 111 Edgewood Avenue Argyle Forest Boulevard Bartram Park Boulevard at Greenland Road
Outer Loop Facility Pages Dairy Road East Extension Pages Dairy Road South Extension Palm Valley Road Pecan Park Road Pecan Park Road Pulaski Road Pulaski Road / Starratt Road Race Track Road Race Track Road Race Track Road Connector Ramona Boulevard Rampart / Firestone Road Ranch Road Ricker Road Salisbury Road Extension San Pablo Road Shindler Drive SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard
Baker/Duval Nassau Nassau St. Johns Duval Duval Duval Duval St. Johns St. Johns St. Johns Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval
91 987 983 826 952 92 953*** 97 827 828 851 935 98 1038 934 99 1009 101 714 715 716
SR 228 Normandy Boulevard Chester Road SR 200 SR A1A Intracoastal Waterway Braddock Boulevard I‐95 Eastport Road I‐295 St. Johns Parkway Bartram Park Boulevard Durbin Parkway / 9B Extension Hammond Boulevard Collins Road Tradeport Road Morse Avenue SR 152 Baymeadows Boulevard US 90 Beach Boulevard Collins Road at Girvin Road at Hodges Boulevard at San Pablo Boulevard
To
Improvement Type
SR 104 Dunn Avenue I‐295 St. Johns/Duval County Line
Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Modify Interchange Add 4 Express Lanes Add 4 Express Lanes Add 4 Express Lanes Modify Interchange Modify Interchange Widen to 4 Lanes* Intersection Improvements Widen to 6 Lanes Widen to 6 Lanes Widen to 6 Lanes New 2 Lane Road New 2 Lane Road New 2 Lane Bridge New 2 Lane Road New 2 Lane Road Widen to 3 Lanes New 2 Lane Road Widen to 6 Lanes Widen to 4 Lanes Widen to 6 Lanes Widen to 6 Lanes New 2 Lane Road Widen to 4 Lanes Widen to 4 Lanes New 2 Lane Road Widen to 4 Lanes New 3 Lane Road / Bridge New 2 Lane Road Future Corridor New 2 Lane Road Intersection Improvements Widen to 4 Lanes Widen to 6 Lanes and Overpass Intersection Improvements / Add 1 Lane
2013 Cost O&M Cost (millions) (millions) $2,167.51 $11.00 $67.16 $5.47 $106.25 $8.64 $59.50 $0.19 $850.86 $18.00 $301.38 $5.16 $361.45 $6.21 $36.00 $0.19 $35.23 $0.19 $0.43 $0.09 $5.40 $0.18 $4.50 $0.29 $7.50 $0.55 $12.22 $0.23 $15.15 $0.08 $18.51 $0.10 $70.03 $0.12 $5.05 $0.03 $4.69 $0.03 $25.09 $0.04 $1.44 $0.01 $5.03 $0.30 $12.10 $0.13 $6.15 $0.05 $6.15 $0.25 $25.00 $0.12 $42.67 $0.28 $42.67 $0.10 $4.30 $0.07 $4.30 $0.17 $24.90 $0.07 $6.65 $6.65 $787.90 $4.08 $10.10 $0.05 $12.96 $0.30 $23.10 $0.39 $458.55 $0.36 $0.60 $0.05
Future Corridor New 2 Lane Road New 2 Lane Road Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 2 Lane Road Widen to 5 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 3 Lanes New 3 Lane Road Widen to 3 Lanes Widen to 3 Lanes Intersection Improvements Intersection Improvements Intersection Improvements
$1,600.00 $7.22 $1.70 $11.43 $22.43 $5.40 $3.09 $25.10 $40.80 $30.00 $3.99 $2.70 $26.24 $2.10 $9.40 $16.10 $35.19 $11.40 $7.57 $7.57 $7.57
International Golf Parkway SR 10 Atlantic Boulevard SR 202 J. T. Butler Boulevard
Turn/Bend Pritchard Road Glen Kernan Parkway SR 116 McCormick Road SR 21 Blanding Boulevard CR 209 Russell Road CR 209 Russell Road Avant Road Long Bay Road US 17 SR 5 Huron Street Harper Chapel Road SR 113 Southside Connector SR A1A I‐295 Lee Road Arnold Road Yellow Bluff Road Cedar Point Road Chaffee Road Chaffee Road US 23 New Kings Road SR 121 I‐95 Oakleaf Village Parkway Plummer Road SR 134 103rd Street US 1/SR 5 Phillips Highway
SR 228 Normandy Boulevard Blackrock Road Sowell Road Mickler Road JIA North Access Road US 17 Main Street I‐295 Duval Station Road Bartram Park Boulevard Bartram Springs Race Track Road Cahoon Road South SR 134 103rd Street SR 102 North of Airport Road Old Middleburg Road Belfort Road SR 10 Atlantic Boulevard SR 134 103rd Street
Page 3 of 13
$4.08 $0.04 $0.01 $0.13 $0.09 $0.06 $0.03 $0.28 $0.17 $0.15 $0.03 $0.07 $0.30 $0.03 $0.21 $0.13 $0.18 $0.21 $0.05 $0.05 $0.05
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From SR 100 SR 100 SR 101 Mayport Road SR 101 Mayport Road SR 102 Airport Road SR 104 Dunn Avenue SR 104 Dunn Avenue SR 115 Arlington Expressway SR 115 Arlington Expressway * SR 115 Lem Turner Road SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 152 Baymeadows Road SR 152 Baymeadows Road SR 16 SR 16 SR 16 SR 16 SR 16 SR 16 Connector SR 19 Connector SR 20 SR 20 SR 200 Overpass SR 200 William Burgess Connector SR 200 Yulee Backage Roads SR 200 SR A1A SR 200 SR A1A SR 200A Pages Dairy Road SR 207 SR 207 SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 228 Hart Bridge SR 228 Normandy Boulevard SR 228 Normandy Boulevard SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 23 First Coast Expressway SR 243 JIA North Access Road SR 312 SR 313 SR 313 SR 313 SR 9B
Clay Putnam Duval Duval Duval Duval Duval Duval Duval Duval/Nassau Duval Duval Duval Duval Duval Duval Duval Duval Duval Clay St. Johns Clay St. Johns St. Johns St. Johns Putnam Putnam Putnam Nassau Nassau Nassau Nassau Nassau Nassau St. Johns St. Johns Duval Clay Duval Duval Duval Duval Duval Duval Clay Clay Clay Clay Clay Clay/Duval Clay/St. Johns St. Johns St. Johns St. Johns Duval St. Johns St. Johns St. Johns St. Johns Duval
450 451 152B 152 421 940 941 100 153 74 102 103 104 960 966 967 968 937 938 106 110 908 835 836 829 965 422 423 1003 998 992 427 703 979 113 830 9 114 957A 957B 957C 47 86 87 41 8202 1011 1012 1013 8201 8203 840 841 847 701 115 831 832 839 1024
Clay/Bradford County Line Clay/Putnam County Line SR 116 Wonderwood Drive at SR 116 Wonderwood Drive Airport Entrance US 1/SR 15 New Kings Road Old Kings Road SR 109 University Boulevard at SR 109 University Boulevard I‐295 US 1/SR 5 Philips Highway SR 202 J. T. Butler Boulevard US 90 Beach Boulevard Hogan Road at SR 202 J. T. Butler Boulevard at SR 152 Baymeadows Road at SR 10 Atlantic Boulevard I‐95 US 1 /SR 5 Philips Highway CR 218 I‐95 US 17 South Francis Road CR 208 Outlet Mall SR 16/CR 16A SR 19 Putnam/Alachua County Line SW 56th Avenue at US 17 SR 5 and Railroad Tracks William Burgess Boulevard Cardinal Street North Extension at US 17 Amelia Island Parkway at Felmor Road I‐95 Holmes Boulevard I‐295 SR 16 at Collins Road at SR 134 103rd Street at Cedar Hills Boulevard SR 228 Hart Expressway ‐ Downtown US 301 SR 23 First Coast Expressway at CR 218 SR 21 Blanding Boulevard at SR 21 Blanding Boulevard at CR 739 at SR 16 I‐10 US 17 at I‐95 at CR 16 A at CR 2209 SR 102 Airport Road US 1/SR 5 Dixie Highway SR 207 SR 16 at US 1/SR 5 Dixie Highway US 1/SR 5 Philips Highway
Page 4 of 13
To
Improvement Type
Clay/Putnam County Line US 17 SR 5 Mayport Main Gate
Widen to 4 Lanes Widen to 4 Lanes Add 2 Northbound Lanes Intersection Improvements Widen to 6 Lanes Widen to 4 Lanes Intersection Improvements Widen to 6 Lanes* Modify Interchange Widen to 4 Lanes Widen to 6 Lanes* Widen to 6 Lanes* Widen to 6 Lanes* Intersection Improvements Modify Interchange Underpass Intersection Improvements Widen to 6 Lanes Widen to 6 Lanes* Widen to 4 Lanes Widen to 6 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 4 Lane Road New 4 lane road / bridge Widen to 4 Lanes Widen to 4 Lanes Overpass New 2 Lane Road New 2 Lane Road Intersection Improvements Widen to 6 Lanes Roundabout Projects Widen to 6 Lanes Widen to 6 Lanes Widen to 6 Lanes Widen to 4 Lanes Intersection Improvements Intersection Improvements Intersection Improvements New 6 Lane Bridge Widen to 4 Lanes Widen to 6 Lanes New Interchange New 4 Lane Road New Interchange New Interchange New Interchange Widen to 6 Lanes New 6 Lane Road New Interchange New Interchange New Interchange Widen to 4 Lanes Widen to 6 Lanes New 6 Lane Road New 4 Lane Road New Interchange Add 2 Auxiliary Lanes
I‐95 I‐295 US 23 New Kings Road SR 10 Atlantic Boulevard US 1 / Callahan S Kings Road I‐95 Ramps US 90 Beach Boulevard SR 10 Atlantic Boulevard Gate Parkway
SR 115 Southside Boulevard I‐95 SR 15A Oakridge Avenue SR 313 Shands Bridge International Golf Parkway South Francis Road CR 2209 Putnam County Boulevard SW 56th Avenue CR 315 Interlachen SR 200 SR A1A Old Yulee Road Sadler Road South Holmes Boulevard SR 312 Wilson Boulevard CR 215 Blanding Boulevard
SR 10 Atlantic Boulevard Bell Road (Equestrian Park ) SR 111 Cassat Avenue US 17
SR 21 Blanding Boulevard I‐95
Pecan Park Road SR A1A SR 16 US 1 Dixie Highway I‐295
2013 Cost O&M Cost (millions) (millions) $20.59 $0.49 $96.87 $2.06 $0.49 $0.12 $0.50 $0.05 $8.47 $0.39 $25.71 $0.23 $3.00 $0.05 $31.66 $0.64 $12.50 $0.19 $87.00 $1.56 $0.97 $0.37 $8.50 $0.50 $1.22 $0.47 $25.50 $0.05 $35.23 $0.19 $12.50 $0.19 $10.30 $0.05 $10.52 $0.20 $0.43 $0.16 $54.70 $0.69 $20.25 $0.50 $37.78 $0.40 $5.90 $0.17 $15.59 $0.45 $26.00 $0.16 $198.93 $0.34 $57.95 $0.72 $44.68 $0.34 $83.20 $0.19 $4.14 $0.03 $4.26 $0.02 $3.00 $0.05 $3.79 $0.19 $0.80 $0.02 $26.00 $0.65 $26.00 $0.08 $75.18 $1.01 $34.30 $0.39 $5.80 $0.05 $5.80 $0.05 $5.80 $0.05 $198.00 $0.23 $54.70 $0.66 $69.30 $1.66 $42.19 $42.19 $518.83 $518.83 $35.43 $35.43 $35.43 $35.43 $35.43 $35.43 $123.66 $123.66 $706.26 $706.26 $35.43 $35.43 $35.43 $35.43 $42.19 $42.19 $32.40 $0.34 $22.80 $0.50 $39.26 $0.82 $34.35 $0.58 $35.23 $0.19 $0.85 $3.22
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
I‐295 Race Track Road
Widen to 6 Lanes Widen to 6 Lanes New Interchange Widen to 6 Lanes* Turn Lane Improvements* Intersection Improvements Widen to 4 Lanes Widen to 4 Lanes* CSS Ferry Slip Replacement Widen to 6 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 2 Lane Road Modify Interchange Widen to 6 Lanes Widen to 6 Lanes Intersection Improvements Widen to 6 Lanes Widen to 6 Lanes Widen to 6 Lanes Widen to 6 Lanes Widen to 6 Lanes* Widen to 6 Lanes* Widen to 6 Lanes Widen to 6 Lanes Intersection Improvements Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New Interchange New 2 Lane Road and Roundabout
2013 Cost O&M Cost (millions) (millions) $31.20 $1.06 $23.87 $0.48 $35.23 $0.19 $0.99 $0.38 $3.00 $0.06 $3.00 $0.05 $27.00 $0.27 $3.00 $0.16 $2.10 $0.06 $8.00 $11.12 $0.23 $27.26 $0.25 $7.00 $0.07 $34.10 $0.36 $6.60 $0.06 $11.78 $0.06 $17.53 $0.19 $24.50 $0.61 $40.10 $1.05 $1.08 $0.06 $47.50 $1.27 $22.20 $0.56 $60.90 $1.58 $19.90 $0.50 $6.56 $0.58 $7.00 $0.94 $31.60 $0.70 $18.10 $0.39 $2.97 $0.09 $79.74 $0.91 $7.15 $0.05 $69.80 $0.40 $78.50 $0.39 $21.41 $0.19 $3.55 $0.03
New 2 Lane Road Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes Widen to 4 Lanes New 2 Lane Road Context Sensitive Solutions (CSS) Context Sensitive Solutions (CSS) Widen to 4 Lanes Widen to 6 Lanes Intersection Improvements Widen to 6 Lanes New 6 Lane Bridge and Transit Widen to 4 Lanes Widen to 4 Lanes Intersection Improvements
$4.26 $50.70 $19.07 $66.47 $6.72 $0.85 $3.15 $7.15 $146.09 $28.05 $7.16 $25.08 $1,175.00 $60.71 $40.82 $8.00
$0.06 $0.20 $0.28 $1.28 $0.46 $0.00 $0.04 $0.07 $0.43 $1.16 $0.05 $1.35 $0.34 $0.58 $0.46 $0.05
$36.37 $0.31 $1.44 $33.06
$0.30 $0.00 $0.01 $0.28
SR 9B SR 9B Extension SR 9B Extension SR A1A SR A1A SR A1A SR A1A SR A1A SR A1A Anastasia Boulevard SR A1A St Johns River Ferry St. Johns Parkway Starratt Road Touchton Road Town Center Boulevard Trout River Boulevard Tynes Road US 1 SR 5 US 1/SR 15 New Kings Road US 1/SR 15 New Kings Road US 1/SR 15 New Kings Road US 1/SR 5 Dixie Highway US 1/SR 5 Dixie Highway US 1/SR 5 Dixie Highway US 1/SR 5 Philips Highway US 1/SR 5 Philips Highway US 1/SR 5 Philips Highway US 1/SR 5 Philips Highway US 17 US 17 US 17 US 17 US 17 Main Street US 17 Main Street US 17 Main Street US 17 Pages Dairy Connector w/roundabout
Duval St. Johns St. Johns St. Johns Nassau St. Johns St. Johns Duval St. Johns Duval St. Johns Duval Duval Clay Duval Clay St. Johns Duval Duval Duval St. Johns St. Johns St. Johns Duval Duval Duval Duval Clay Nassau Nassau Clay Duval/Nassau Duval Duval Nassau
18 833 842 128 706 1008 800 151 1031 2331 848 954 129 903 955 912 845 82 83 950 130 131 132 93 94 95 96 133 707 709 1037 78 1017 959 984
US 1/SR 5 Philips Highway St. Johns Parkway at Durbin Parkway Solana Road South Fletcher Avenue at Red Cox/Coquina Rd Mickler Road SR 116 Wonderwood Drive Casanova Road
US 17 Powerline Corridor US 17 SR 15 US 17 SR 15 US 17 SR 15 US 17 SR 15 US 17 Yulee Backage Roads US 1B King Street US 1B San Marco Avenue US 301 SR 200 US 301 SR 200 US 301 SR 200 US 301 SR 201 US 90 / SR 115 Mathews Bridge US 90 Beaver Street US 90 Beaver Street Various SR 200 Intersections Modifications
Nassau Putnam Putnam Putnam Putnam Nassau St. Johns St. Johns Duval Clay Nassau Duval Duval Duval Duval Nassau
994 428 429 430 452 999 1029 1030 123 424 708 425 79 6 7 981
Vegas Boulevard West of Dunn Creek Bridge CR 309 Satsuma Putnam/Volusia County Line Pomona Park/Feagle Avenue US 17 SR 5 US 1 Ponce de Leon Boulevard Bridge of Lions US 90 Clay/Bradford County Line US 1 at S Kings Road Duval/Clay County Line Alt. US 1 MLK Jr. Parkway SR 23 First Coast Expressway Cahoon Road
Radio Avenue Horse Landing Road West of Dunn Creek Bridge Pomona Park/Feagle Avenue CR 309 Satsuma North of Koen Lane Avenida Menendez SR 16 Duval/Nassau County Line Duval/Clay County Line
Veterans Parkway Wells Road Woodbridge Parkway Extension Yellow Bluff Road * Candidates for context sensitive solutions
St. Johns Clay Nassau Duval
834 910 997 956
Greenbriar Road Aquarius Concourse Woodbrigde Parkway Starratt Road
Longleaf Pine Parkway SR 21 Blanding Boulevard Clements Road New Berlin Road (north)
SR 202 J. T. Butler Boulevard Amelia Island Parkway Palm Valley Road Naval Station Mayport North Gate Bridge of Lions
CR 2209 Duval Station Road Belfort Road US 17 Old Kings Road Pipit Place at CR 210 Soutel Drive I‐295 SR 111 Edgewood Avenue SR 206 SR 313 International Golf Parkway Nocatee Parkway / Race Track Road SR 9B I‐95 at the Avenues SR 202 J. T. Butler Boulevard CR 315 Nassau/Duval County Line SR 200 SR A1A Governor Street Pecan Park Road New Berlin Road at Eastport Road US 17 SR 5
9B Extension Yellow Bluff Road SR 115 Southside Boulevard CR 220 Doctors Inlet Road US 23 New Kings Road Oakleaf Plantation Parkway I‐295 Old Kings Road Soutel Drive Lewis Point Road International Golf Parkway Race Track Road SR 9B I‐295 SR 202 J. T. Butler Boulevard SR 126 Emerson Street Town Center Boulevard Harts Road Georgia State Line Haven Avenue SR 200 / SR A1A Pecan Park Road SR 200A Pages Dairy Road
I‐10 SR 109 University Boulevard Cahoon Road McDuff Avenue
Page 5 of 13
New 4 Lane Road Reconstruct and New 2 Lane Road New 2 Lane Road Widen to 4 Lanes
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
Anastasia Island (Amphitheatre) Area wide Area wide Area wide Area wide Area wide Area wide Center Street CR 210 CR 220 Doctors Inlet Road Cumberland Island Ferry Downtown ‐ Sports Complex Downtown Facility Drew Street Duval Road East First Coast Flyer Five Points/Core/Brooklyn Five Points/Core/Brooklyn I‐95 I‐95 La Villa/Core Mayport Road North (CSX) North Extension (CSX) Northwest (CSX) Racetrack Road Riverside/Avondale South of Glen St. Mary Southbank/San Marco Southbank/San Marco Southeast (FEC) Southeast Extension (FEC) Southwest (CSX) Southwest Extension (CSX) Southwest First Coast Flyer Springfield SR 115 Lem Turner Road SR 115 Lem Turner Road SR 115 Lem Turner Road SR 115 Southside Boulevard SR 134 103rd Street SR 134 103rd Street SR 16*** SR 200 SR A1A SR 200 SR A1A SR 207*** SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 228 Normandy Boulevard
St. Johns Baker Clay Duval Nassau Putnam St. Johns Duval St. Johns Clay Nassau Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Nassau Duval St. Johns Duval Baker Duval Duval Duval St. Johns Duval Clay Duval Duval Duval Duval Duval Duval Duval Duval St. Johns Nassau Nassau St. Johns Clay Clay Clay Clay Clay Clay Clay Duval Duval Duval Duval Duval Duval
2380 2303 2310 2332 2370 2374 2378 2304 2381 2316 2369 2349 2355 2305 2336 2385 2347 2350 2326 2330 2351 2338 2356 2366 2357 2382 2352 2306 2348 2353 2327 2377 2358 2319 2386 2354 2337 2361 2362 2325 2321 2334 2385 2371 2372 2386 2308 2311 2312 2313 2314 2315 2318 2335 2340 2341 2360 2364 2322
To
Improvement Type
Transit Capacity Projects Park and Ride Lots Local Bus Service Local Bus Service Local Bus Service Local Bus Service Local Bus Service Local Bus Service North of Drew Street (Baldwin) Park and Ride Lots east of US 1 Park and Ride Lots at Hollow Road Park and Ride Lots Fernandina Cumberland Island Ferry Service Downtown Jacksonville (Bay Street & Main Street) Jacksonville Municipal Stadium Streetcar Transportation Center at Center Street (Baldwin) Park and Ride Lots at I‐95 Park and Ride Lots Downtown Jacksonville (Duval County) 3rd Street (Jacksonville Beach) BRT Central Station Brooklyn Station Skyway Extension Five Points Downtown Jacksonville (Bay Street & Ma Streetcar Gateway Mall Jacksonville International Airport BRT Downtown Jacksonville (Duval County) Yulee (Nassau County) Express Bus Service Transportation Center Duval Street & Monroe Street to Ocean Streetcar at SR A1A Park and Ride Lots Downtown Jacksonville (Duval County) Yulee (Nassau County) Commuter Rail Yulee Fernandina Beach Commuter Rail Downtown Jacksonville (Duval County) Callahan (Nassau County) Commuter Rail at US 1 Park and Ride Lots Riverside (King Street) Five Points Streetcar Park and Ride Lots Kings Avenue Station Southwest of Railroad Tracks (SouthbankSkyway Extension Kings Avenue Station Baptist Hospital / MOSH & Atlantic Boule Streetcar St. Augustine (St. Johns County) Downtown Jacksonville (Duval County) Commuter Rail Palm Coast (Flagler County) City of St. Augustine Commuter Rail Green Cove Springs (Clay County) Downtown Jacksonville (Duval County) Commuter Rail Palatka (Putnam County) Green Cove Springs (Clay County) Commuter Rail Wells Road Downtown Jacksonville (Duval County) BRT FSCJ Station 8th Street/ Medical Complex Streetcar at SR 104 Dunn Avenue Park and Ride Lots at Soutel Park and Ride Lots at I‐295 Park and Ride Lots Avenues Mall Regency Square Mall BRT SR 228 Normandy Boulevard SR 21 Blanding Boulevard BRT at SR 228 Normandy Boulevard Park and Ride Lots Park and Ride Lots at I‐95 Park and Ride Lots east of Yulee Park and Ride Lots Park and Ride Lots CR 218 Wells Road BRT at Tanglewood Park and Ride Lots at Old Jennings Road Park and Ride Lots at Edson Drive Park and Ride Lots at Wells Road Park and Ride Lots at SR 224 Kingsley Avenue Park and Ride Lots North and South of Bolton Road Park and Ride Lots at Weconnett Boulevard Park and Ride Lots North and South of Wilson Boulevard Park and Ride Lots North and South of SR 134 103rd Street Park and Ride Lots at 105th Street Park and Ride Lots North of I‐295 Park and Ride Lots SR 134 103rd Street Downtown Jacksonville (Duval County) BRT
Page 6 of 13
2013 Cost O&M Cost (millions) (millions) $0.25
$0.25 $0.25 $0.25 $5.00 $38.50 $60.00 $0.25 $0.25 $28.00 $26.60 $85.00 $12.20 $31.50 $0.25 $271.69 $122.90 $179.60 $0.25 $26.25 $0.25 $52.50 $52.50 $0.00 $255.20 $294.01 $236.30 $19.00 $46.17 $0.25 $0.25 $0.25 $18.00 $38.35 $0.25 $0.25 $0.25 $0.25 $0.25 $37.50 $0.25 $0.25 $0.25 $0.25 $0.25 $0.25 $0.25 $0.09 $0.25 $0.25 $0.25 $97.45
$0.00 $1.00 $1.00 $69.00 $1.00 $1.00 $1.10 $0.00 $0.00 $0.00 $1.00 $0.41 $2.55 $0.00 $0.00 $7.08 $6.37 $0.41 $3.89 $1.71 $0.41 $0.00 $0.00 $4.49 $15.96 $0.00 $0.41 $0.00 $4.24 $0.41 $0.00 $14.97 $0.00 $14.97 $4.96 $0.41 $0.00 $0.00 $0.00 $2.83 $2.16 $0.00 $0.00 $0.00 $0.00 $0.00 $3.01 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5.49
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
SR A1A SR A1A SR A1A St Johns River Ferry SR A1A St Johns River Ferry SR A1A St Johns River Ferry SR A1A St Johns River Ferry SR A1A St Johns River Ferry SR A1A St Johns River Ferry St. Augustine Airport US 1 US 1 US 1 US 1/SR 15 New Kings Road US 1/SR 15 New Kings Road US 17 Roosevelt Boulevard US 17 Roosevelt Boulevard US 90 US 90 Beach Boulevard US 90 Beach Boulevard West (CSX) West Extension (CSX) Yellow Water Road Youngerman Circle
Duval St. Johns Duval Duval Duval Duval Duval Duval St. Johns St. Johns Duval St. Johns Duval Duval Clay Duval Baker Duval Duval Duval Baker Duval Clay
2343 2379 2329 2331 2333 2344 2345 2346 2383 2384 2324 2375 2323 2363 2320 2342 2302 2339 2359 2328 2301 2307 2317
North and South of SR 202 J. T. Butler Boulevard at Palm Valley Road Ft. George/Mayport JPA Property Mayport Ft. George/Mayport at Lewis Speedway Road Lewis Speedway (St. Johns County) Lewis Speedway (St. Johns County) Downtown Jacksonville (Duval County) Timucuan DRI at Wells Road at SR 128 San Juan Avenue MacClenny (Baker County) West and East of Kernan Boulevard at San Pablo Road Baldwin (Duval County) MacClenny (Baker County) North of I‐10 at Argyle Forest Boulevard
Mayport Terminal Ft. George Island Avenues Mall (Duval County) Avenues Mall (Duval County) Edgewood Avenue Downtown Jacksonville (Duval County) Downtown Jacksonville (Duval County) Baldwin (Duval County)
Park and Ride Lots Park and Ride Lots Drydock / Ferry Repairs Ferry Slip Replacement Long Term Site Improvements Relocation of Ferry offices Service & Capital Improvements Site Improvements Park and Ride Lots Park and Ride Lots BRT BRT BRT Park and Ride Lots Park and Ride Lots Park and Ride Lots Local Bus Service Park and Ride Lots Park and Ride Lots Commuter Rail Commuter Rail Park and Ride Lots Park and Ride Lots
SR 121 Rail Trail Corridor Cecil Field Conservation Corridor CR 218 CR 220 Doctors Inlet Road CR 220 Doctors Inlet Road Long Bay Road Old Jennings Road US 17 US 17 Roosevelt Boulevard / Park Avenue US 17 Park Avenue SR 16 5th Street Arlington Road Arlington Road West Bay Street Baymeadows Road Beauclerc Road Boulevard Street Bowden Road Bowden Road Broad Street Cecil Field Conservation Corridor Clark Road Commonwealth Avenue CSX Corridor North Deerwood Area Downtown Jacksonville Downtown Neptune/Atlantic Beach Duval Road Duval Street East Coast Greenway ‐ Duval County Corridor Edgewood Avenue Forest Street Forsyth Street Gate Parkway East
Baker Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay / St. Johns Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval
2000 2001 2002 2004 2003 2005 2006 2007 2009 2008 2010 2012 2013 2014 2019 2020 2023 2026 2028 2027 2029 2031 2032 2033 2034 2035 2036 2037 2039 2040 2041 2043 2045 2046 2047
Bicycle and Pedestrian Projects Baker/Union County Line Baker/Nassau County Line CR 218 Duval/Clay County Line SR 16 SR 21 College Drive US 17 SR 21 College Drive SR 21 Blanding Boulevard Old Jennings Road Long Bay Road SR 23 First Coast Expressway at CR 220 (Fleming Island Area) Palatka Clay/Duval County Line at Kingsley Avenue (Orange Park) Kingsley Lake Drive SR 13 San Jose Boulevard Lane Avenue Melson Avenue Lone Star Road King Arthur Road Cesery Road King Arthur Road Myrtle Avenue Lee Street SR 115 at Southside Boulevard I‐295 SR 13 San Jose Boulevard 5th Street 12th Street Spring Park Road Southpoint Parkway US 1 Philips Highway Spring Park Road Water Street 5th Street Duval/Clay County Line US 90 Beaver Street Broward Road US 17 Main Street Imeson Road Lane Avenue US 17 Main Street / S Rail Line US 17 Main Street / Trout River Drive Deerwood Park Boulevard Gate Parkway at Sherry Drive, 2nd Street, Ocean Street, Cherry Stre Airport Road Airport Center Drive Lee Street Georgia Street St. Johns/ Duval County Line Nassau/Duval County Line St. Johns Avenue Post Street Acosta Street Lime Street Myrtle Avenue Lee Street Gate Parkway St. Johns Town Center Boulevard
Page 7 of 13
Florida Greenway Land Trail Opportunities Florida Greenway Multi‐Use Trail Florida Greenway Multi‐Use Trail Multi‐Use Trail Accommodate Pedestrians and Bicyclist Florida Greenway Accommodate Pedestrians and Bicyclist Florida Greenway ‐ Multi‐Use Trail Bike Lane Bike Lane Bike Lane Bike Lane Accommodate Pedestrians and Bicyclist Bi‐directional 12 ft. Shared Use Path Bike Lane Bike Lane Bike Lane Bike Lane Florida Greenway Bike Lane Bike Lane Multi‐Use Path Multi‐Use Path Accommodate Pedestrians and Bicyclist Accommodate Pedestrians and Bicyclist Bike Lane Bike Lane Florida Greenway Bike Lane Bike Lane Bike Lane Multi‐Use Path
2013 Cost O&M Cost (millions) (millions) $0.25 $0.00 $0.25 $0.00 $13.00 $13.00 $8.00 $8.00 $0.29 $7.00 $0.80 $0.89 $0.25 $0.00 $0.25 $0.00 $132.03 $7.43 $29.55 $0.25 $0.25 $0.25 $1.08 $0.25 $170.10 $85.10 $0.25 $0.25
$1.66 $0.00 $0.00 $0.00 $2.14 $0.00 $0.00 $9.48 $5.49 $0.00 $0.00
$3.08 $2.54 $1.73 $0.93 $1.62 $1.28 $0.46 $0.34 $18.14 $0.04 $6.48 $0.40 $0.01 $0.11 $0.09 $0.03 $0.64 $0.15 $0.06 $0.14 $0.27 $2.78 $0.19 $0.30 $0.71 $0.17 $1.45 $0.07 $0.15 $0.41 $11.30 $0.32 $0.13 $0.09 $0.05
$0.12 $0.10 $0.07 $0.04 $0.06 $0.03 $0.02 $0.00 $0.72 $0.00 $0.26 $0.02 $0.00 $0.00 $0.00 $0.00 $0.03 $0.01 $0.00 $0.01 $0.01 $0.11 $0.01 $0.01 $0.03 $0.01 $0.02 $0.00 $0.01 $0.02 $0.21 $0.01 $0.01 $0.00 $0.00
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From Gate Parkway South East Hogan's Creek Greenway Hubbard Street Imeson Road Jacksonville Baldwin / East Coast Corridor Jacksonville Beach Area Jefferson Street Kernan Boulevard Laura Street Laura Street Lee Street Lone Star Road Mandarin Road Mary Street McCoys Creek Boulevard / Fitzgerald Street McCoys Creek Boulevard / Fitzgerald Street Moncrief Road Monument Road and SR 10 Atlantic Boulevard Myrtle Avenue Newnan Street Old Kings Road Old Middleburg Road Old St Augustine Road Riverplace Boulevard Riverside/Five Point Area Southpoint Parkway SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard SR 104 Dunn Avenue SR 105 Zoo Parkway SR 105 Zoo Parkway SR 109 University Boulevard North SR 109 University Boulevard North SR 111 Cassat Avenue SR 111 Edgewood Avenue SR 111 Tallulah Avenue SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 115 Southside Boulevard SR 126 Emerson Street SR 128 San Juan Avenue SR 13 Hendricks Avenue SR 13 San Jose Boulevard SR 13 San Jose Boulevard SR 13 San Jose Boulevard SR 13 San Jose Boulevard SR 13 San Jose Boulevard SR 134 103rd Street SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 211 Riverside Avenue SR 211 St. Johns Avenue SR 228 Normandy Boulevard SR A1A SR A1A UNF East
Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval
2048 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061 2062 2065 2089 2067 2066 2068 2069 2070 2071 2073 2074 2075 2078 2080 2090 2017 2016 2018 2015 2038 2049 2050 2102 2103 2030 2042 2099 2094 2095 2093 2092 2091 2044 2088 2051 2086 2085 2084 2087 2083 2011 2024 2025 2079 2098 2072 2096 2097 2100
To
Improvement Type
Deerwood Parkway St. Johns Town Center Boulevard Bike Lane Market Street North Riverbank Multi‐Use Path Orange Street 14th Street Bike Lane Commonwealth Avenue Baldwin Rail Trail Bike Lane Bulls Bay Highway (Jacksonville Baldwin Corridor) St Johns River Ferry (East Coast GreenwayFlorida Greenway at 3rd Avenue, Ocean Street, 2nd Avenue, South 10t Accommodate Pedestrians and Bicyclist Water Street 1st Street Bike Lane Baymeadows Road (SR 152) SR 116 Fort Caroline Road Florida Greenway 8th Street S‐Line Pavement Markings and Signage Bay Street 8th Street Pavement Markings and Signage Water Street Duval Street Bike Lane Mill Creek Road SR 113 Southside Connector Bike Lane San Jose Boulevard (SR 13) I‐295 Bi‐directional 12 ft. Shared Use Path San Marco Boulevard US 17 Main Street Bridge Bike Lane Nixon Street Forest Street Multi‐Use Path McDuff Avenue Leland Street Bike Lane 13th Street Golfair Boulevard Bike Lane SR 113 Southside Boulevard N Regency Square Boulevard Bike Lane Forest Street Kings Road Bike Lane Bay Street Orange Street Pavement Markings and Signage S‐line Martha Street Bike Lane Herlong Road Lenox Avenue Bike Lane Losco Road SR 13 San Jose Boulevard Bike Lane Prudential Drive US 1 Main Street Bike Lane at Stockton Street, Rossell Street, I‐95, St. Johns Rive Accommodate Pedestrians and Bicyclist Belfort Road Bowden Road Bike Lane Kings Road US 90 Beach Boulevard Bike Lane US 90 Beach Boulevard SR 228 Alt. US 1 Hart Expressway Bike Lane SR 228 Hart Expressway SR 109 University Boulevard Bike Lane Hart Expressway (SR 228 Alt. US 1) SR A1A Bi‐directional 12 ft. Shared Use Path Biscayne Avenue US 17 Main Street Bike Lane Busch Drive I‐295 Bike Lane US 17 Main Street SR A1A Multi‐Use Path SR 10 Atlantic Boulevard Cesery Boulevard Bike Lane University Boulevard / Cesery Boulevard Gable Lane Bike Lane SR 21 Blanding Boulevard SR 111 Edgewood Avenue Bike Lane SR 111 Cassat Avenue US 1/SR 15 New Kings Road Bike Lane US 17 Main Street 68th Street Bike Lane Gate Parkway Touchton Road Sidewalk Improvements US 1 Philips Highway Belle Rive Boulevard Sidewalk Improvements Deerwood Park Boulevard US 90 Beach Boulevard Sidewalk Improvements US 1 Philips Highway Belle Rive Boulevard Multi‐Use Path Avenues Mall (US 1) SR 10 Atlantic Boulevard / Regency SquarBi‐directional 12 ft. Shared Use Path Hendricks Avenue US 1 Philips Highway Bike Lane SR 21 Blanding Boulevard SR 211 Herschel Street Bike Lane SR 13 San Jose Boulevard San Marco Boulevard Bike Lane Julington Creek Road Plummers Cove Road Bike Lane Old St. Augustine Road SR 152 Baymeadows Road Bike Lane SR 152 Baymeadows Road Hendricks Avenue Bike Lane Loretto Road SR 152 Baymeadows Road Accommodate Pedestrians and Bicyclist Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path Old Middleburg Road Old Middleburg Road North Bike Lane Blackburn Road Appleton Avenue Bike Lane Harlow Boulevard Wilson Boulevard Bike Lane St. Johns Avenue Forest Street Bike Lane Woodmere Street Talbot Avenue Bike Lane SR 103 Lane Avenue SR 111 Cassat Avenue Bike Lane SR 202 J. T. Butler Boulevard SR 10 Atlantic Boulevard Bi‐directional 12 ft. Shared Use Path St. Johns River Ferry Duval/Nassau County Line Bi‐directional 12 ft. Shared Use Path Kernan Boulevard UNF West Bike Lane
Page 8 of 13
2013 Cost O&M Cost (millions) (millions) $0.11 $0.00 $0.23 $0.01 $0.11 $0.01 $0.08 $0.00 $17.47 $0.26 $0.23 $0.00 $0.21 $0.01 $3.05 $0.12 $0.06 $0.00 $0.06 $0.00 $0.07 $0.00 $0.11 $0.00 $1.50 $0.06 $0.03 $0.00 $0.03 $0.00 $0.10 $0.00 $0.30 $0.01 $0.33 $0.01 $0.29 $0.01 $0.07 $0.00 $0.05 $0.00 $0.28 $0.01 $0.05 $0.00 $0.08 $0.00 $0.67 $0.01 $0.38 $0.02 $0.18 $0.01 $0.23 $0.01 $0.29 $0.01 $3.16 $0.12 $0.37 $0.02 $0.12 $0.01 $0.14 $0.01 $0.11 $0.00 $0.36 $0.01 $0.77 $0.03 $0.77 $0.03 $0.22 $0.01 $0.14 $0.00 $0.48 $0.00 $0.72 $0.00 $0.43 $0.02 $2.30 $0.09 $0.25 $0.01 $0.20 $0.01 $0.50 $0.02 $0.07 $0.00 $0.22 $0.01 $1.07 $0.04 $3.18 $0.04 $3.10 $0.12 $0.19 $0.01 $0.09 $0.00 $0.15 $0.01 $0.36 $0.01 $0.22 $0.01 $0.30 $0.01 $1.09 $0.04 $2.27 $0.09 $0.20 $0.01
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From UNF West Duval 2101 US 1 Philips Highway Duval 2077 US 1 Philips Highway Duval 2076 US 17 Main Street Duval 2064 US 17 Main Street Duval 2063 US 17 Roosevelt Boulevard Duval 2082 US 17 Roosevelt Boulevard Duval 2081 US 17 Roosevelt Boulevard Duval 2104 US 90 Beach Boulevard Duval 2022 US 90 Beach Boulevard Duval 2021 Water Street Duval 2105 Jacksonville Baldwin Corridor Duval / Nassau 2106 8th Street Nassau 2107 Amelia Island Parkway Nassau 2108 Amelia Island Parkway Path Segment 1 Nassau 2109 Amelia Island Parkway Path Segment 2 Nassau 2110 Amelia Island Parkway Path Segment 3 Nassau 2111 Amelia Island Parkway Path Segment 4 Nassau 2112 Amelia Island Trial ‐ Central (1st Ave) Nassau 2113.1 Amelia Island Trial ‐ South (Buccaneer Trail) Nassau 2113 Amelia Island Trial‐ North ( Friendly/Clinch) Nassau 2113.2 American Beach Loop Nassau 2114 American Beach Loop Nassau 2116 American Beach Loop Nassau 2115 Crandall Parkway Corridor Nassau 2117 East Coast Greenway ‐ Nassau County Corridor Nassau 2118 ENCPA DSAP 1‐ Central (Old Yulee Vicinity) Nassau 2120.1 ENCPA DSAP 1‐ North (Owens Rd Vicinity) Nassau 2120.2 ENCPA DSAP 1‐ South (Harper Chapel Vicinity) Nassau 2120 Highland Broom Street Nassau 2121 Maxine Street Nassau 2123 Ocklawaha Trail Nassau 2124 Orange Avenue Nassau 2125 Simmons Connector Nassau 2126 SR 200 SR A1A Nassau 2127 US 17 Nassau 2129 US 17 / SR A1A East Coast Greenway Nassau 2119 Nassau 2128 US 301/ SR 200 Trans Nassau Trail Corridor William Burgess Boulevard Nassau 2130 CR 121/CR 119 Jacksonville Baldwin Rail Trail Northern Extension CorridNassau / Duval 2122 CR 216 Putnam 2131 Cross Florida Greenway Corridor Putnam 2132 SR 100 Putnam 2133 SR 20 Putnam 2134 US 17 Putnam 2135 US 17 Crescent City (parallel facilities) Putnam 2136 SR 207 Putnam / St. Joh 2137 County Road 214 Corridor St. Johns 2138 CR 13 Spuds Palmo Trail Corridor St. Johns 2149 CR210 St. Johns 2139 Deep Creek to ECG Corridor St. Johns 2140 Downtown and Uptown St. Augustine St. Johns 2141 East Coast Greenway ‐ St. Johns County Corridor St. Johns 2142 Nocatee Corridor St. Johns 2143 Race Track Road St. Johns 2147 Racetrack Corridor St. Johns 2148 SR 13 San Jose Boulevard St. Johns 2150 SR 13 William Bartram Trail Corridor St. Johns 2155 SR 16 St. Johns 2151 SR A1A St. Johns 2152
To
Improvement Type
I‐295 UNF East Bike Lane Southside Boulevard (SR 115) Southbank Riverwalk Rails‐W‐Trails Racetrack Road Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path Trout River Bridge New Berlin Road Rails‐W‐Trails Eastport Road Pecan Park Road Bi‐directional 12 ft. Shared Use Path Duval/Clay County Line Forest Street Rails‐W‐Trails I‐295 Edison Avenue Bi‐directional 12 ft. Shared Use Path Duval/Clay County Line Forest Street Florida Greenway at Hodges Boulevard Accommodate Pedestrians and Bicyclist San Pablo Boulevard Downtown (Southbank) Bi‐directional 12 ft. Shared Use Path Lee Street Pearl Street Bike Lane West of Baldwin Bulls Bay Highway Florida Greenway at Sadler Road Accommodate Pedestrians and Bicyclist at Amelia Road Accommodate Pedestrians and Bicyclist Bailey Road 8th Street/ SR A1A Multi‐Use Trail 14th Street Bailey Road Multi‐Use Trail Via Del Rey 14th Steet Multi‐Use Trail SR A1A Fletcher Avenue / Amelia Island Trail Via Del Rey Multi‐Use Trail Bill Melton Matanzas Way Trail Fletcher Avenue Amelia Island Pkwy Trail Bailey Road Atlantic Avenue Trail American Beach Loop Julia Street Segment American Beach Bike Lane American Beach Loop Ocean Avenue Segment American Beach Multi‐Use Path American Beach Loop Burney Road Segment American Beach Multi‐Use Path East Coast Greenway (US 17) SR A1A East Coast Greenway Corridor Florida Greenway Nassau/Duval County Line Fernandina Beach Florida Greenway East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path East Nassau Community Planning Area East Nassau Community Planning Area Multi‐Use Path Proposed Highland Broom Street Multi‐use Trail Proposed Highland Broom Street Multi‐Use Path Maxine Street Path Maxine Street Path Multi‐Use Path Via Del Rey / Bill Melton Road Sadler Road Multi‐Use Trail Orange Avenue Path Orange Avenue Path Multi‐Use Path Simmons/AIP Connector Simmons/AIP Connector Multi‐Use Trail at SR 200 Bridge Accommodate Pedestrians and Bicyclist Nassau/Duval County Line SR 200 SR A1A Bi‐directional 12 ft. Shared Use Path Fernandina Beach Georgia State Line Florida Greenway CR 119 US 17 Main Street / Yulee Florida Greenway SR 200 SR A1A US 17 Multi‐Use Trail Beaver Street (US 90) US 301/SR 200 Trans Nassau Trail Corrid Florida Greenway SR 100 US 17 Multi‐Use Path Existing Cross Florida Greenway Trail Palatka Florida Greenway Clay/Putnam County Line Palatka Florida Greenway Hawthorne Palatka Florida Greenway Putnam/Volusia County Line Palatka Florida Greenway Prospect Street CR 308 Multi‐Use Path Palatka St. Augustine Florida Greenway SR 13 San Jose Boulevard SR 207 Florida Greenway Spuds (SR 207) SR 13 San Jose Boulevard Florida Greenway at SR A1A Accommodate Pedestrians and Bicyclist SR 207 SR A1A Florida Greenway at US 1, Park Avenue, River, South Street, Riberia Str Accommodate Pedestrians and Bicyclist St. Johns/Flagler County Line St. Johns/Duval County Line Florida Greenway San Jose Boulevard (SR 13) SR A1A Florida Greenway San Jose Boulevard (SR 13) US 1 Philips Highway Bi‐directional 12 ft. Shared Use Path San Jose Boulevard (SR 13) Nocatee Corridor Florida Greenway Roberts Road Julington Creek Bi‐directional 12 ft. Shared Use Path CR 13 St. Johns/Duval County Line Florida Greenway I‐95 Collins Avenue Bi‐directional 12 ft. Shared Use Path at SR 312 Accommodate Pedestrians and Bicyclist
Page 9 of 13
2013 Cost O&M Cost (millions) (millions) $0.43 $0.02 $2.46 $0.11 $4.39 $0.17 $0.98 $0.04 $2.30 $0.09 $2.28 $0.10 $2.28 $0.09 $4.13 $0.16 $0.00 $0.00 $1.97 $0.08 $0.10 $0.00 $1.40 $0.15 $0.00 $0.00 $0.01 $0.00 $0.63 $0.01 $0.63 $0.01 $0.63 $0.01 $0.63 $0.01 $0.16 $0.01 $0.29 $0.01 $0.96 $0.04 $0.11 $0.00 $0.36 $0.00 $0.60 $0.01 $1.75 $0.07 $2.02 $0.11 $4.03 $0.16 $0.78 $0.03 $0.66 $0.03 $0.36 $0.01 $0.13 $0.01 $0.94 $0.03 $0.25 $0.01 $1.72 $0.02 $0.71 $0.01 $3.13 $0.12 $30.08 $0.19 $6.58 $0.26 $0.79 $0.03 $3.09 $0.12 $0.58 $0.02 $6.05 $0.08 $9.43 $0.23 $15.23 $0.24 $38.54 $0.25 $0.58 $0.02 $10.48 $0.23 $2.74 $0.11 $5.10 $0.20 $0.02 $0.00 $3.21 $0.13 $1.13 $0.01 $27.88 $0.41 $5.10 $0.20 $2.14 $0.08 $2.14 $0.09 $0.65 $0.03 $3.76 $0.15 $0.77 $0.03 $0.03 $0.00
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
St. Augustine Bike Plan US 1 Dixie Highway US 1 Dixie Highway US 1 Dixie Highway / Ponce De Leon Boulevard US 1 St. Augustine to Nocatee Corridor
St. Johns St. Johns St. Johns St. Johns St. Johns
2153 2146 2145 2144 2154
Areawide at SR 312 Putnam/Flagler County Line San Marco Avenue (US 1 B) (St. Augustine) St. Augustine
Areawide SR 207 Racetrack Road Nocatee Corridor
Bicycle accommodations Accommodate Pedestrians and Bicyclist Bi‐directional 12 ft. Shared Use Path Bi‐directional 12 ft. Shared Use Path Florida Greenway
CSX Transportation CSX Transportation CSX Transportation CSX Transportation CSX Transportation CSX Transportation CSX Transportation Florida East Coast Railway Florida East Coast Railway Jacksonville International Airport Jacksonville International Airport Jacksonville International Airport Jacksonville International Airport Jacksonville International Airport Norfolk Southern Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority Jacksonville Port Authority CSX Transportation CSX Transportation CSX Transportation Florida East Coast Railway CSX Transportation CSX Transportation Port of Fernandina Port of Fernandina Port of Fernandina Port of Fernandina City of Palatka County CSX Transportation City of Saint Augustine Florida East Coast Railway
Clay Clay Duval Nassau Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval/Baker Duval/Clay Duval/Nassau Duval/St. Johns Duval Nassau Nassau Nassau Nassau Nassau Putnam Putnam Putnam St. Johns Statewide
2200 2201 2202 2203 2204 2205 2206 2207 2208 2209 2210 2211 2212 2213 2214 2215 2216 2217 2218 2219 2220 2221 2222 2223 2224 2225 2226 2227 2228 2229 2230 2231 2232 2233 2234 2235 2236 2237 2238 2239 2240 2241 2242 2243 2244 2245 2246 2247 2248 2249 2250 2251 2252
Multimodal Freight Projects at Wells Road at SR 224 Kingsley Avenue at SR 104 Busch Drive at SR A1A (SR 200) / Yulee Beaver Street Interlocking North Rail Corridors Phase 1 Westlake Cecil Commerce Connector at Bowden Intermodal at Jacksonville Bridge Construction of Runway 7R/25L Air Cargo Ramp Improvements Air Cargo Surface Storage Design & Construct By‐Pass Taxiways Intermodal Terminal Facility Development at Norfolk Southern Railway (Near Simpson Yard) Blount Island / Dames Point Marine Terminals Rail Blount Island Marine Terminal Berth Upgrades Blount Island Marine Terminal Facility Upgrades Dames Point Marine Terminal Berth Upgrades Dames Point Marine Terminal Facility Upgrades New Cranes for Talleyrand and Blount Island Marine Terminals Talleyrand Marine Terminal Berth Upgrades Talleyrand Marine Terminal Facility Upgrades Talleyrand Marine Terminal Rail Blount Island Marine Terminal Facility Upgrades Dames Point Marine Terminal Facility Upgrades New Cranes for Talleyrand and Blount Island Marine Terminals Talleyrand Marine Terminal Facility Upgrades Blount Island / Dames Point Terminals ‐ Rail and Bridge Blount Island Marine Terminal Berth Upgrades Blount Island Marine Terminal Facility Upgrades Dames Point Marine Terminal Berth Upgrades Dames Point Marine Terminal Facility Upgrades Harbor Deepening New Cranes for Talleyrand and Blount Island Marine Terminals Talleyrand Marine Terminal Berth Upgrades Talleyrand Marine Terminal Facility Upgrades Talleyrand Marine Terminal Rail MacClenny to Jacksonville Green Cove Springs to Jacksonville Jacksonville to Yulee St. Augustine to Jacksonville at US 301 (SR 200) / Baldwin at US 301 / Crawford Diamond Berth Improvements Cruise / Cargo Berth Rail Track Improvements at Fernandina Port SR 100 CR 309D Barge Port at SR 15 Reid Street Historic Commercial Areas Amtrak Service Miami to Jacksonville
Page 10 of 13
Grade Separation Grade Separation Grade Separation Grade Separation Capacity Upgrade Multi Modal Corridor Multi Modal Corridor Capacity Upgrade Bridge Construct Runway Expand Apron Expand Apron Construct Taxiway Terminal Development Grade Separation Internal Rail Docks Intermodal Transfer Improvement Docks Intermodal Transfer Improvement Intermodal Transfer Improvement Docks Intermodal Transfer Improvement Internal Rail Intermodal Transfer Improvement Intermodal Transfer Improvement Intermodal Transfer Improvement Intermodal Transfer Improvement Internal Rail Docks Intermodal Transfer Improvement Docks Intermodal Transfer Improvement Dredging Harbor Intermodal Transfer Improvement Docks Intermodal Transfer Improvement Internal Rail Upgrade to Accommodate Freight and Passenger Service* Upgrade to Accommodate Freight and Passenger Service Upgrade to Accommodate Freight and Passenger Service Upgrade to Accommodate Freight and Passenger Service Grade Separation Grade Separation Docks Docks Internal Rail Access Improvements Runway expansion Operational and Capital Improvements Grade Separation Mobility & Distribution Improvements New Passenger Service
2013 Cost O&M Cost (millions) (millions) $1.17 $0.00 $0.00 $0.00 $3.77 $0.15 $3.88 $0.15 $3.79 $0.15
$56.74 $56.74 $90.78 $68.08 $6.00 $40.00 $30.00 $14.36 $8.84 $53.50 $2.82 $0.54 $8.65 $99.42 $14.75 $32.42 $32.42 $97.26 $54.04 $97.26 $86.45 $43.23 $32.42 $21.62 $81.05 $37.82 $43.23 $21.62 $270.18 $43.23 $81.50 $32.42 $32.42 $648.42 $32.42 $27.02 $21.61 $10.81 $294.00 $271.69 $0.00 $53.33 $32.42 $0.86 $10.81 $0.65 $5.00 $15.00 $15.00 $49.75 $10.00 $162.16
$0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $85.10
$0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Florida East Coast Railway Intercity Passenger Rail Intercity Passenger Rail Intercity Passenger Rail Norfolk Southern CSX Transportation Florida East Coast Railway Downtown Transportation Center* Jacksonville Port Authority Florida East Coast Railway * Project costs are identified in the Transit Capacity Needs table.
Statewide Statewide Statewide Statewide Duval Duval Duval Duval Duval Duval
2253 2254 2255 2256 2257 2258 2259 2355 1006 2260
Miami to Jacksonville Upgrade Bolt and Clip System New Orleans to Jacksonville Jacksonville to Savannah Orlando to Jacksonville Soutel Drive to Norfolk Southern Intermodal Yard North Rail Corridors Phase 2 at Sunbeam Road Downtown Facility Spoil Island Connector Bridge at Shad Road
SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard CR 215 CR 218 CR 220 Doctors Inlet Road CR 220A Long Bay Road CR 209 Russell Road US 17 SR 15 SR 134 103rd Street SR 134 103rd Street SR 134 103rd Street SR 134 103rd Street SR 134 103rd Street SR 134 103rd Street SR 134 103rd Street SR 13 Acosta Bridge SR 115 Arlington Expressway SR 10 Atlantic Boulevard SR 10 Atlantic Boulevard US 90 Beach Boulevard US 90 Beach Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 21 Blanding Boulevard SR 109 Cesery Boulevard Collins Road SR 126 Emerson Street Firestone Road SR 23 First Coast Expressway SR 116 Fort Caroline Road Harlow Boulevard Alt US 1 Hart Bridge Expressway I‐295
Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Clay Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval Duval
209 212 215 219 221 231 605 606 241 202 203 608 204 201 327 207 218 222 225 226 311 603 310 301 650 651 223 652 230 232 242 317 653 200 304 205 213 654 206 300 607
at Arora Boulevard at SR 16 at Youngerman Circle at Argyle Forest Boulevard at Wells Road at CR 215 Everett Avenue Old Jennings Road SR 16 SR 16 N Mimosa Avenue SR 21 Blanding Boulevard CR 220 Doctors Inlet Road Old Ferry Road CR 315 at New World Avenue at Firestone Road , I‐295 Interchanges at Harlow Boulevard at SR 21 Blanding Boulevard at Shindler Drive , Old Middleburg Road SR 228 Normandy Boulevard SR 228 Normandy Boulevard I‐95 US 17 / US 17 SR 228 State Street Monument Road Hart Bridge Expressway at Forest Boulevard Parental Home Road at Collins Road at I‐295 NB Off Ramp Argyle Forest Boulevard Collins Road SR 109 University Boulevard Shindler Drive I‐95 Morse Avenue at US 90 , I‐10 Beaver Street Merrill Road SR 134 103rd Street Monroe Street Old St Augustine Road
Improvement Type Track Upgrade New Passenger Service New Passenger Service New Passenger Service New Connector Multi Modal Corridor Grade Separation Transportation Center New 2 Lane Bridge Grade Separation
2013 Cost O&M Cost (millions) (millions) $21.67 $0.10 TBD $0.10 TBD $0.10 TBD $0.10 $14.65 $0.10 $5.00 $0.10 $52.82 $60.00 $80.21 $40.00
Safety and Operations Improvements
Page 11 of 13
Old Jennings Road Argyle Forest Boulevard CR 218 SR 21 Blanding Boulevard CR 739 Henley Road CR 224 College Drive Old Jennings Road CR 220 Doctors Inlet Road Kingsley Avenue I‐295 Wesconnett Boulevard Broad Street SR 10 Atlantic Boulevard Intracoastal Waterway SR 109 University Boulevard San Pablo Road US 17 Roosevelt Boulevard US 17 Roosevelt Boulevard SR 115 Arlington Expressway Rampart Road Bedford Road SR 208 Wilson Boulevard McCormick Road SR 21 Blanding Boulevard US 90 Beach Boulevard SR 228 Normandy Boulevard
Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Arterial Management System Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Corridors Freeway Management System Freeway Management System Arterial Management System Arterial Management System Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Intersections Safety Projects ‐ Intersections Safety Projects ‐ Corridors Arterial Management System Arterial Management System Safety Projects ‐ Corridors Traffic Operations Improvements Safety Projects ‐ Corridors Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Corridors Freeway Management System Safety Projects ‐ Corridors
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$7.05
$0.46
$11.10
$0.73
$11.85
$0.78
$9.30
$0.61
$9.90
$0.65
$8.25
$0.54
$2.85
$0.19
$2.85
$0.19
$1.37
$0.08
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$1.50
$0.05
$0.77
$0.04
$13.20
$0.87
$0.28
$0.01
$1.77
$0.06
$1.04
$0.06
$0.23
$0.01
$1.50
$0.05
$1.16
$0.07
$1.50
$0.05
$1.50
$0.05
$9.00
$0.59
$1.07
$0.06
$0.27
$0.02
$3.00
$0.20
$2.42
$0.08
$4.65
$0.31
$1.50
$0.05
$0.15
$0.01
$2.70
$0.18
$0.91
$0.03
$33.00
$2.16
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
I‐295 SR 202 J. T. Butler Boulevard SR 202 J. T. Butler Boulevard Jammes Road SR 115 Lem Turner Road US 17 Main Street US 1 Main Street Bridge SR 106 Merrill Road US 1 MLK Parkway Monument Road Morse Avenue Mt. Pleasant Road US 1/SR 15 New Kings Road US 1/SR 15 New Kings Road SR 228 Normandy Boulevard SR 228 Normandy Boulevard SR 228 Normandy Boulevard SR 228 Normandy Boulevard SR 228 Normandy Boulevard Old Middleburg Road Old Middleburg Road Old St. Augustine Road US 1/SR 5 Philips Highway Rampart Road Ricker Road Ricker Road Shindler Drive US 17 / US 17 SR 228 State Street SR 134 Timuquana Road US 17 / US 17 SR 228 Union Street SR 109 University Boulevard SR 109 University Boulevard SR 109 University Boulevard US 301 SR 200 Wesconnett Boulevard SR 208 Wilson Boulevard SR 116 Wonderwood Connector SR 116 Wonderwood Connector SR 116 Wonderwood Connector US 301 SR 200 SR 9B SR 200 SR A1A SR 200 SR A1A US 1/SR 5 Dixie Highway US 1/SR 5 Dixie Highway US 1/SR 5 Dixie Highway/Ponce De Leon Boulevard International Golf Parkway International Golf Parkway CR 214 King Street/Anastasia Boulevard CR 210 Palm Valley Road US 1/SR 5 Ponce De Leon Boulevard Race Track Road
SR 115 Lem Turner Road SR A1A Hodges Boulevard San Juan Avenue I‐295 I‐295 Bay Street SR 113 Southside Connector I‐95 Fort Caroline Road Jammes Road Girvin Road I‐295 I‐295 SR 111 Cassat Avenue I‐295 SR 134 103rd Street Lenox Avenue US 1/ SR 5 Philips Highway Park City Drive SR 134 103rd Street Old Middleburg Road SR 134 103rd Street Liberty Street US 17 Roosevelt Boulevard Liberty Street US 90 Beach Boulevard Merrill Road SR 109 Cesery Boulevard US 90 Beaver Street SR 21 Blanding Boulevard SR 103 Lane Avenue Mt. Pleasant Road Fort Caroline Road East SR 101 Mayport Road Mickler Street (Callahan) I‐295 Fernandina Beach Chester Road SR 16 SR A1A SR A1A SR 16 US 1
Safety Projects ‐ Corridors Freeway Management System Safety Projects ‐ Corridors Safety Projects ‐ Corridors Arterial Management System Arterial Management System Arterial Management System Arterial Management System Freeway Management System Arterial Management System Safety Projects ‐ Corridors Arterial Management System Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Intersections Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Arterial Management System Safety Projects ‐ Intersections Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Safety Projects ‐ Corridors Arterial Management System Safety Projects ‐ Corridors Arterial Management System Arterial Management System Arterial Management System Arterial Management System Rural ITS Safety Projects ‐ Corridors Safety Projects ‐ Corridors Arterial Management System Arterial Management System Arterial Management System Rural ITS Freeway Management System Arterial Management System Safety Projects ‐ Corridors Safety Projects ‐ Intersections Safety Projects ‐ Intersections Arterial Management System Safety Projects ‐ Intersections Safety Projects ‐ Intersections Arterial Management System Rural ITS Access Management Plan Arterial Management System
Duval 610 Duval 315 Duval 712 Duval 233 Duval 305 Duval 326 Duval 324 Duval 663 Duval 325 Duval 306 Duval 234 Duval 657 Duval 224 Duval 307 Duval 208 Duval 220 Duval 318 Duval 609 Duval 611 Duval 235 Duval 236 Duval 658 Duval 229 Duval 237 Duval 238 Duval 239 Duval 240 Duval 322 Duval 602 Duval 323 Duval 659 Duval 660 Duval 661 Duval 313 Duval 600 Duval 601 Duval 655 Duval 656 Duval 662 Duval / Nassau314 Duval / St. Joh319 Nassau 320 Nassau 604 St. John's 210 St. John's 214 St. John's 328 St. John's 216 St. John's 217 St. John's 303 St. John's 302 St. John's 329 St. John's 308
SR 228 Normandy Boulevard US 1/SR 5 Philips Highway SR 115 Southside Boulevard Morse Avenue I‐95 Bay Street I‐95 SR 109 University Boulevard SR 115 Arlington Expressway SR 10 Atlantic Boulevard Ricker Road McCormick Road at Moncrief Road I‐95 at Fouraker Road at Blair Road South SR 134 103rd Street I‐295 SR 23 First Coast Expressway Argyle Forest Boulevard SR 134 103rd Street I‐95 at Bowden Road Argyle Forest Boulevard Morse Avenue SR 134 103rd Street Collins Road I‐95 Wesconnett Boulevard I‐95 St. Augustine Road Arlington Road SR 10 Atlantic Boulevard SR 228 Normandy Boulevard SR 21 Blanding Boulevard Fouraker Road Fort Caroline Road East SR 113 Southside Connector Mt. Pleasant Road US 90 Beaver Street CR 2209 I‐95 I‐95 at SR 312 at SR 206 SR 312 at SR 16 at US 1/SR 5 Dixie Highway I‐95 SR 13 SR 5A King Street SR 13 San Jose Boulevard
Page 12 of 13
2013 Cost O&M Cost (millions) (millions) $18.30 $1.20 $65.06
$2.16
$7.65
$0.50
$5.85
$0.38
$1.20
$0.07
$1.29
$0.07
$0.28
$0.01
$0.37
$0.02
$18.69
$0.62
$0.82
$0.05
$2.25
$0.15
$0.14
$0.01
$1.50
$0.05
$2.07
$0.12
$1.50
$0.05
$1.50
$0.05
$0.79
$0.04
$3.90
$0.26
$12.90
$0.85
$7.20
$0.47
$6.15
$0.40
$0.03
$0.00
$1.50
$0.05
$1.50
$0.10
$1.50
$0.10
$2.10
$0.14
$4.50
$0.30
$0.16
$0.01
$3.90
$0.26
$0.16
$0.01
$0.28
$0.01
$0.17
$0.01
$0.04
$0.00
$0.36
$0.01
$2.85
$0.19
$2.25
$0.15
$0.32
$0.02
$0.07
$0.00
$0.40
$0.02
$0.97
$0.04
$1.13
$0.03
$0.82
$0.04
$19.80
$1.30
$1.50
$0.05
$1.50
$0.05
$0.34
$0.02
$1.50
$0.05
$1.50
$0.05
$0.69
$0.04
$1.65
$0.08
$0.19
$0.01
$0.83
$0.04
Path Forward 2040 Long Range Transportation Plan
Table 1. Summary of the Need Plan Project Cost and Operating and Maintenance Costs (in millions of present day dollars) Facility County Map ID From
To
Improvement Type
SR 13 SR 16 SR 16/SR 13 SR 207/SR 312 SR A1A US 1, A1A & SR 5A
Julington Creek Road US 1 SR A1A CR 214
Arterial Management System Arterial Management System Safety Projects ‐ Intersections Rural ITS Rural ITS Transportation Management Plan
St. John's St. John's St. John's St. John's St. John's St. John's
309 312 211 316 321 330
Shands Bridge CR 13 at CR 13 I‐95 SR 206
Page 13 of 13
2013 Cost O&M Cost (millions) (millions) $0.87 $0.04 $1.26
$0.07
$1.50
$0.05
$0.92
$0.05
$1.20
$0.06
$37.50
$1.23
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
County
Map ID
From
To
Improvement Type
Source
Purpose
Need
Road Capacity Projects
Abaco Island Drive Extension
Alta Drive
Alta Drive / Yellow Bluff Road
Alta Drive Realignment
Amelia Island Parkway
Nassau
Duval
Duval
Duval
Nassau
988
3
2
1
704
Abaco Island Drive
SR 105 Heckscher Drive
I‐295
SR 105 Zoo Parkway
South 14th Street
Zion Court
I‐295
New Berlin Road (north )
North of New Berlin Road (south)
CR 105A Buccaneer Trail
New 2 Lane Road
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen Alta The project need was established in Drive to four lanes from SR 105 the 2035 Needs Plan and confirmed Heckscher Drive to I‐295 to address as part of the planning process. congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen to Alta Drive / Yellow Bluff Road to five lanes from I‐295 to New Berlin Road (north) to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 4 Lane Road
2035 Needs Plan
The project's purpose is to construct a new four‐lane road and realign Alta Drive from SR 105 Zoo Parkway to North of New Berlin Road (south) to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Widen to 4 Lanes*
The project's purpose is to widen Amelia Island Parkway to four lanes from South 14th Street to CR 105A Local government Buccaneer Trail to address congestion coordination needs and improve mobility. This project was also identified as candidate for context sensitive solutions.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
Widen to 5 Lanes
1
The project's purpose is to construct a new two‐lane road called Abaco Island Local government Drive Extension from Abaco Island Drive coordination to Zion Court to address congestion needs and improve mobility.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Argyle Forest Boulevard
Arrigo‐Parliament Reconnection
Barnwell‐0' Neil Scott Connector
Baxley Road
Blount Island Boulevard Extension
County
Duval
Nassau
Nassau
Clay
Duval
Map ID
936
980
1001
900
1006
From
SR 23 First Coast Expressway
Arrigo Boulevard
Barnwell Road
To
Old Middleburg Road
Parliament Drive
O'Neil Scott Road
CR 220 Doctors Inlet Road SR 21 Blanding Boulevard
Spoil Island
Jacksonville Port Authority
Improvement Type
Source
Purpose
Need
Widen to 6 Lanes
Argyle Traffic Circulation Study
The project's purpose is to widen Argyle Forest Boulevard to six lanes from SR 23 First Coast Expressway to Old Middleburg Road to address congestion needs and improve mobility.
The project need was established during a corridor planning study performed by the North Florida TPO to address congestion, mobility and safety needs.
New 2 Lane Road
The project's purpose is to construct a new two lane road called Arrigo‐ Local government Parliament Reconnection from Arrigo coordination Boulevard to Parliament Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Barnwell‐0' Local government Neil Scott Connector from Barnwell coordination Road to O'Neil Scott Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen Baxley Road to four lanes CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Other Local Government Priority
The project's purpose is to New two Lane Bridge along Blount Island Boulevard Extension from Spoil Island to Jacksonville Port Authority to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Bridge
2
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Braddock Parkway
Brady Point‐Clements Connector
Brinkhoff Road
Buffalo Road
Cahoon Road
County
Duval
Nassau
St Johns
Putnam
Duval
Map ID
939
1002
801
503
1016
From
SR 115 Lem Turner Road
Brady Point Road
SR 207
Buffalo Road west
Lenox Avenue
To
Pecan Park Road
Clements Road
Wildwood Drive
Buffalo east
US 90 Beaver Street
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new tow lane road called Braddock Local government Parkway from SR 115 Lem Turner Road coordination to Pecan Park Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Brady Point‐ Local government Clements Connector from Brady Point coordination Road to Clements Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Brinkhoff Road from SR 207 to Wildwood Drive to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Bridge
Other Local Government Priority
The project's purpose is to construct new two‐lane bridge along Buffalo Road from Buffalo Road West to Buffalo East to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to reconstruct two lanes of Cahoon Road from Lenox Avenue to US 90 Beaver Street to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Reconstruct 2 Lanes
3
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Cardinal Street North Extension
Cardinal Street South Extension
Cecil Field Connector
Chaffee Road
Cheswick Oak Avenue Extension
County
Nassau
Nassau
Duval
Duval
Clay
Map ID
976
975
972
971
13
From
Cardinal Avenue
Spring Meadow Avenue
Commerce Center
SR 228 Normandy Boulevard
Oakleaf Plantation Parkway
To
SR 200 SR AIA Yulee Backage Roads
William Burgess Boulevard
SR 23 First Coast Expressway
Crystal Springs Road
Savannah Glen Boulevard
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Cardinal Local government Street North Extension from Cardinal coordination Avenue to SR 200 SR AIA Yulee Backage Roads to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Cardinal Local government Street South Extension from Spring coordination Meadow Avenue to William Burgess Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
Widen to 5 Lanes
New 4 Lane Road
4
Source
Local Government CIP
The project's purpose is to construct a new two‐lane road called Cecil Field Connector from Commerce Center to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Local Government CIP
The project's purpose is to widen Chaffee Road to five lanes from SR 228 Normandy Boulevard to Crystal Springs Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Cost Feasible Plan
The project's purpose is to construct a new four‐lane road called Cheswick Oak Avenue Extension from Oakleaf Plantation Parkway to Savannah Glen Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Christian Way Extension
Clark Road Extension
College Drive
College Drive Extension
Collins Road
County
Nassau
Duval
Clay
Clay
Duval
Map ID
995
1020
902
14
930
From
Christian Way
Broward Road
To
Hampton Club Way
Clark Road
CR 220 Doctors Inlet Road SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
Shindler Drive
Challenger Drive (Branan Field Road )
Rampart Road
Improvement Type
New 2 Lane Road
New 3 Lane Road
Widen to 6 Lanes
New 4 Lane Road
Widen to 4 Lanes
5
Source
Purpose
The project's purpose is to construct a new two‐lane road called Christian Way Local government Extension from Christian Way to coordination Hampton Club Way to address congestion needs and improve mobility.
Need
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Local Government CIP
The project's purposes to construct a new three‐lane road called Clark Road Extension from Broward Road to Clark Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen College Drive to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Cost Feasible Plan
The project's purpose is to construct a new four‐lane road called College Drive Extension from SR 21 Blanding Boulevard to Challenger Drive (Branan Field Road) to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to widen Collins Road to four lanes from Shindler Drive to Rampart Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Collins Road
Collins Road
Collins Road
Collins Road Realignment
Comfort Road
County
Duval
Duval
Duval
Duval
Putnam
Map ID
932
From
Old Middleburg Road S
15
SR 21 Blanding Boulevard
16
at US 17 Roosevelt Boulevard
16B
505
Pine Verde
Port Road
To
Shindler Drive
Pine Verde
Improvement Type
Widen to 4 Lanes
Widen to 4 Lanes
Purpose
Need
Local Government CIP
The project's purpose is to widen Collins Road to four lanes from Old Middleburg Road S to Shindler Drive to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen Collins Road to four lanes from SR 21 Blanding Boulevard to Pine Verde to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a The project need was established in new interchange along Collins Road at the 2035 Needs Plan and confirmed US 17 Roosevelt Boulevard to address as part of the planning process. congestion needs and improve mobility.
New Interchange
US 17 Roosevelt Boulevard
Local government coordination and New 4 Lane Road, Two the project was Overpass and New Interchange part of the Better Jacksonville Plan
US 17
Widen to 4 Lanes
6
Source
Other Local Government Priority
The project's purpose is to construct a new four‐lane road, two overpasses and a new interchange along the Collins Road Realignment from Pine Verde to US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
The project's purpose is to widen Comfort Road to four lanes from Port Road to US 17 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Commodore Point Drive Extension
Concourse Loop Road
Connector Road
CR 105A Buccaneer Trail
CR 16A
County
Nassau
Nassau
Putnam
Nassau
St Johns
Map ID
996
501
502
705
803
From
Commodore Point Drive
License Road
US 17
South Fletcher Avenue
SR 16 Connector
To
Blackrock Road
Amelia Concourse
Distribution Center
Canopy Drive
SR 13
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Commodore Local government Point Drive Extension from Commodore coordination Point Drive to Blackrock Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Concourse Loop Road from License Road to Amelia Concourse to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Road
SIS CFP
The project's purpose is to construct a new two‐lane road called Connector Road from US 17 to Distribution Center to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Turn Lane Improvements*
The project's purpose is to construct turn lane improvements along CR 105A Buccaneer Trail from South Fletcher Local government Avenue to Canopy Drive to address coordination congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions.
Widen to 4 Lanes
Other Local Government Priority
7
Source
The project's purpose is to widen CR 16A to four lanes from SR 16 Connector to SR 13 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 16A Extension
CR 209 Russell Road
CR 209 South
CR 210
CR 210
County
St Johns
Clay
Clay
St Johns
St Johns
Map ID
802
905
906
805
807
From
CR 16A
CR 739 Henley Road
Decoy Road
I‐95
Greenbriar Road
To
Leo Maguire Parkway
US 17
US 17
near US 1
Cimarrone Road
Improvement Type
New 2 Lane Road
Purpose
The project's purpose is to construct a new two‐lane road called CR 16A Local government Extension from CR 16A to Leo Maguire coordination Parkway to address congestion needs and improve mobility.
Need
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to CR 209 The project need was established in Russell Road to four lanes from CR 739 the 2035 Needs Plan and confirmed Henley Road to US 17 to address as part of the planning process. congestion needs and improve mobility.
Reconstruct 2 Lanes
Other Local Government Priority
The project's purpose is to reconstruct two lanes along CR 209 South from Decoy Road to US 17 to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 6 Lanes
Other Local Government Priority
The project's purpose is to widen CR 210 to six lanes from I‐95 to near US 1 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen CR The project need was established in 210 to four lanes from Greenbriar Road the 2035 Needs Plan and confirmed to Cimarrone Road to address as part of the planning process. congestion needs and improve mobility.
Widen to 4 Lanes
Widen to 4 Lanes
8
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 210 West
CR 214
CR 218
CR 218
CR 218
County
St Johns
St Johns
Clay
Clay
Clay
Map ID
849
809
1026
1027
24
From
Longleaf Pine Parkway
Holmes Boulevard
US 301
Cosmos Avenue
SR 21 Blanding Boulevard
To
Greenbriar Road
US 1
Cosmos Avenue
Pine Tree Lane
CR 739 Henley Road
Improvement Type
Purpose
Need
Other Local Government Priority
The project's purpose is to widen CR 210 West to four lanes from Longleaf Pine Parkway to Greenbriar Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 3 Lanes*
Other Local Government Priority
The project's purpose is to widen CR 214 to three lanes from Holmes Boulevard to US 1 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
Local Government CIP
The project's purpose is to widen CR 218 to four lanes from US 301 to Cosmos Avenue to address congestion needs and improve mobility.
The project need was established in the Local Government CIP and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen to CR The project need was established in 218 to four lanes from Cosmos Avenue the 2035 Needs Plan and confirmed to Pine Tree Lane to address congestion as part of the planning process. needs and improve mobility.
Local Government CIP
The project's purpose is to widen CR 218 to dour lanes from SR 21 Blanding Boulevard to CR 739 Henley Road to address congestion needs and improve mobility.
Widen to 4 Lanes
Widen to 4 Lanes
Widen to 4 Lanes
9
Source
The project need was established in the Local Government CIP and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 218
CR 218 Extension
CR 218 Extension
CR 220 Doctors Inlet Road
CR 220 Doctors Inlet Road
County
Clay
Clay
Clay
Clay
Clay
Map ID
909
25
26
33
34
From
SR 16
CR 739 Henley Road
SR 23 First Coast Expressway
SR 21 Blanding Boulevard
College Drive
To
CR 739 Henley Road
SR 23 First Coast Expressway
CR 315
Knight Boxx Road
US 17
Improvement Type
Widen to 4 Lanes
New 4 Lane Road
New 4 Lane Road
Widen to 4 Lanes
Widen to 6 Lanes
10
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to widen CR 218 to four lanes from SR 16 to CR 739 Henley Road to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to construct a The project need was established in new four‐lane road called CR 218 the 2035 Needs Plan and confirmed Extension from CR 739 Henley Road to SR 23 First Coast Expressway to address as part of the planning process. congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 218 The project need was established in the 2035 Needs Plan and confirmed Extension from SR 23 First Coast as part of the planning process. Expressway to CR 315 to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen CR The project need was established in 220 Doctors Inlet Road to four lanes the 2035 Needs Plan and confirmed from SR 21 Blanding Boulevard to Knight Boxx Road to address congestion as part of the planning process. needs and improve mobility.
2035 Needs Plan
The project's purpose is CR 220 Doctors Inlet Road from College Drive to US 17 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 2209
CR 2209
CR 2209
CR 2209
CR 2209
County
St Johns
St Johns
St Johns
St Johns
St Johns
Map ID
810
811
812
813
814
From
SR 23 First Coast Expressway
SR 16 Connector
International Golf Parkway
CR 214
SR 207/CR 305
To
CR 210
SR 23 First Coast Expressway
SR 16 Connector
CR 208
CR 214
Improvement Type
New 6 Lane Road
New 6 Lane Road
New 6 Lane Road
New 4 Lane Road
New 4 Lane Road
11
Source
Purpose
Need
2035 Cost Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from SR 23 First Coast Expressway to CR 210 to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
2035 Cost Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from SR 16 Connector to SR 23 First Coast Expressway to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
2035 Cost Feasible Plan
The project's purpose is to construct a new six‐lane road called CR 2209 from International Golf Parkway to SR 16 Connector to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from CR 214 to CR 208 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a The project need was established in new four‐lane road called CR 2209 from the 2035 Needs Plan and confirmed SR 207/CR 305 to CR 214 to address as part of the planning process. congestion needs and improve mobility.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 2209
CR 2209
CR 2209
CR 305
CR 305
County
St Johns
St Johns
St Johns
St Johns
St Johns
Map ID
815
816
843
818
850
From
SR 16
CR 208
at CR 210
CR 204
SR 206
To
International Golf Parkway
SR 16
SR 206
SR 207
Improvement Type
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from SR 16 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called CR 2209 from CR 208 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a new interchange along CR 2209 at CR 210 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 2 Lane Road
2035 Needs Plan
The project's purpose is to construct a The project need was established in new two‐lane road called CR 305 from the 2035 Needs Plan and confirmed CR 20four to SR 206 to address as part of the planning process. congestion needs and improve mobility.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen CR 305 to four lanes from SR 206 to SR 207 to address congestion needs and improve mobility.
New 4 Lane Road
New 4 Lane Road
New Interchange
12
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 315
CR 315
CR 739B Sandridge Road
Crosby Avenue Extension
Davis / 9B Parcel
County
Clay
Clay
Clay
Nassau
Duval
Map ID
31
32
904
993
1036
From
SR 16
CR 315B
CR 739 Henley Road
US 17 SR 5
SR 9B
To
CR 315B
US 17
CR 209 Russell Road
Pinewood Drive
SR 152 Baymeadows Road
Improvement Type
Purpose
Need
2035 Needs Plan
The project's purpose is to widen CR The project need was established in 315 to four lanes from SR 16 to CR 315B the 2035 Needs Plan and confirmed to address congestion needs and as part of the planning process. improve mobility.
Widen to 4 Lanes
2035 Needs Plan
The project's purpose is to widen CR The project need was established in 315 to four lanes from CR 315B to US 17 the 2035 Needs Plan and confirmed to address congestion needs and as part of the planning process. improve mobility.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen CR 739B Sandridge Road to four lanes from CR 739 Henley Road to CR 209 Russell Road to address congestion needs and improve mobility.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Crosby Local government Avenue Extension from US 17 SR 5 to coordination Pinewood Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
The project's purpose is to widen Davis / 9B Parcel Road to four lanes from SR Local government 9B to SR 152 Baymeadows Road to coordination address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
13
Source
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Decoy Road
Dixie Highway / Pellicer Lane
Dove Road Extension {west}
Durbin Parkway
Durbin Parkway
County
Clay
St Johns
Nassau
St Johns
St Johns
Map ID
907
1025
991
From
US 17
SR 207
Harper Chapel Road Extension
819
SR 9B Extension
844
at US 1 SR 5 Dixie Highway
To
CR 209 South
CR 214 West of King Street
Mentoria Road
Nocatee Parkway
Improvement Type
Purpose
Need
Other Local Government Priority
The project's purpose is to reconstruct two lanes of Decoy Road from US 17 to CR 209 South to address congestion needs and improve mobility and provide bicycle and pedestrian accommodations.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Reconstruct 2 Lanes and Widen to add Sidewalks and Bike Lanes
2035 Needs Plan
The project's purpose is to reconstruct two lanes and widen Dixie Highway / The project need was established in Pellicer Lane to add sidewalks and bike the 2035 Needs Plan and confirmed lanes from SR 207 to CR 214 West of as part of the planning process. King Street to address congestion needs and improve mobility.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Dove Road Local government Extension {west} from Harper Chapel coordination Road Extension to Mentoria Road to address congestion needs and improve mobility.
New 4 Lane Road
Other Local Government Priority
The project's purpose is to construct a new four‐lane road called Durbin Parkway from the SR 9B Extension to Nocatee Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Modify Interchange
Other Local Government Priority
The project's purpose is to modify the interchange of Durbin Parkway at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Reconstruct 2 Lanes
14
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Duval Station Road
East Dove Road Extension
East Nassau Connector
East Nassau Connector
Eastport Road
County
Duval
Nassau
Nassau
Nassau
Duval
Map ID
942
974
36
969
37
From
US 17 SR 5 Main Street
Harper Chapel Road
I‐95
at I‐95
SR 105 Heckscher Drive
To
Starratt Road
William Burgess Boulevard
Chester Road
Pulaski Road
Improvement Type
Purpose
Need
Widen to 4 Lanes
The project's purpose is to widen Duval Station Road to four lanes from US 17 Local government SR 5 Main Street to Starratt Road to coordination address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called east Dove Local government Road Extension from Harper Chapel coordination Road to William Burgess Boulevard to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 4 Lane Road
Local Government CIP
The project's purpose is to construct a new four‐lane road called East Nassau Connector from I‐95 to Chester Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
New Interchange
The project need was established in The project's purpose is to construct a through requests by local Local government new interchange along East Nassau governments for consideration in coordination Connector at I‐95 to address congestion the plan and confirmed as part of needs and improve mobility. the planning process.
Widen to 3 Lanes
15
Source
Local Government CIP
The project's purpose is to widen Eastport Road to three lanes from SR 105 Heckscher Drive to Pulaski Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Flora Parke‐Wal‐Mart Connector
Florida Boulevard
Future Corridor Initiative
Gator Bowl Boulevard
Gene Lassere Boulevard Extension
County
Nassau
Duval
Baker/Clay/Duval
Duval
Nassau
Map ID
986
1021
721
43
985
From
Flora Parke Boulevard
Penman Road
Tampa Bay
Liberty Street
Gene Lassere Boulevard
To
Walmart Supercenter
SR 10 Atlantic Boulevard
Northeast Florida
SR 228 Hart Bridge Expressway and SR 115 Mathews Bridge
SR 200A Pages Dairy Road
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Flora Parke‐ Local government Wal‐Mart Connector from Flora Parke coordination Boulevard to Walmart Supercenter to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 3 Lanes
Local Government CIP
The project's purpose is to widen Florida Boulevard to three lanes from Penman Road to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to construct a new limited‐access roadway from Tampa Bay to Northeast Florida to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Widen to 6 Lanes and Remove Ramps
2035 Needs Plan
The project's purpose is to widen Gator Bowl Boulevard to six lanes and remove The project need was established in the 2035 Needs Plan and confirmed ramps from Liberty Street to Hart SR as part of the planning process. 115 Mathews Bridge to address congestion needs and improve mobility.
New 2 Lane Road and Roundabout
The project's purpose is to construct a new two lane road and roundabout Local government called Gene Lassere Boulevard coordination Extension from Gene Lassere Boulevard to SR 200A Pages Dairy Road to address congestion needs and improve mobility.
Future Corridor
16
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Goodbread Road Reconstruction
Governors Park Road
Hamilton Street Extension
Harlow Boulevard
Harper Chapel Extension
County
Nassau
Clay
Nassau
Duval
Nassau
Map ID
977
46
1000
943
989
From
US 17 SR 5
US 17
Goodbread Circle
SR 134 103rd Street
Harper Chapel Road
To
Hamilton Street
SR 16
Lane Avenue
Dove Road Extension
Improvement Type
New 2 Lane Road
Purpose
The project's purpose is to construct a new two‐lane road called Goodbread Local government Road Reconstruction from US 17 SR 5 to coordination Hamilton Street to address congestion needs and improve mobility.
Need
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 4 Lane Road
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called Governors Park Road from US 17 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Hamilton Local government Street Extension from Goodbread Circle coordination to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 3 Lanes
The project's purpose is to widen Harlow Boulevard to three lanes from Local government SR 134 103rd Street to Lane Avenue to coordination address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Harper Local government Chapel Extension from Harper Chapel coordination Road to Dove Road Extension to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
17
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Hart Expressway Ramps
Hartley Road
Harts Road
Holmes Boulevard
I‐10
County
Duval
Duval
Duval
St Johns
Duval
Map ID
43B
49
963
821
401
From
Liberty Street
SR 13 San Jose Boulevard
SR 104 Dunn Avenue
CR 214
SR 23 First Coast Expressway
To
SR 228 Hart Expressway and SR 115 Mathews Bridge
Old St. Augustine Road
I‐295
Four Mile Road
I‐295
Improvement Type
Purpose
Need
Phases in TIP or Work Program
The project's purpose is to remove Ramps along SR 228 Hart Expressway ramps from Liberty Street to the SR 228 Hart Bridge and SR 115 Mathews Bridge to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
Widen to 3 Lanes
Local Government CIP
The project's purpose is to widen Hartley Road to three lanes from SR 13 San Jose Boulevard to Old St. Augustine Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen Harts Road to four lanes from SR 104 Dunn Avenue to I‐295 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 6 Lanes
Other Local Government Priority
The project's purpose is to widen Holmes Boulevard to six lanes from CR 214 to Four Mile Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
SIS CFP
The project's purpose is to add four express lanes along I‐10 from SR 23 First Coast Expressway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Remove Ramps
Add 4 Express Lanes
18
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐10
I‐10
I‐10
I‐10
I‐10
County
Nassau
Duval
Baker
Baker
Duval
Map ID
402*
403*
404*
405*
406
From
To
Baker/Nassau County Line Nassau/Duval County Line
Nassau/Duval County Line US 301
W of CR 125
W of SR 121
US 301
W of SR 121
Baker/Nassau County Line
SR 23 First Coast Expressway
Improvement Type
Purpose
Need
SIS CFP
The project's purpose is to add four express lanes along I‐10 from The project need was established in Baker/Nassau County Line to the SIS CFP and confirmed as part of the planning process. Nassau/Duval County Line to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four express lanes along I‐10 from Nassau/Duval County Line to US 301 to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four The project need was established in express lanes along I‐10 from west of the SIS CFP and confirmed as part CR 125 to west of SR 121 to address of the planning process. congestion needs and improve mobility.
Add 4 Express Lanes
SIS CFP
The project's purpose is to add four express lanes along I‐10 from west of SR The project need was established in the SIS CFP and confirmed as part 121 to Baker/Nassau County Line to address congestion needs and improve of the planning process. mobility.
Add 4 Express Lanes
Phases in TIP or Work Program
The project's purpose is to add four express lanes along I‐10 from US 301 to SR 23 First Coast Expressway to address congestion needs and improve mobility.
Add 4 Express Lanes
Add 4 Express Lanes
Add 4 Express Lanes
19
Source
The project need was established in the SIS CFP and confirmed as part of the planning process.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐10
I‐10
I‐10
I‐10/US 90 Parallel Reliever
I‐295
County
Duval
Baker
Duval
Baker
Duval/Clay
Map ID
432
453
454
720
57
From
I‐295
Baker/Columbia County Line
at I‐295
South MacClenny
SR 13 San Jose Boulevard
To
I‐95
CR 125
East Baldwin
W of US 17 Roosevelt Boulevard
Improvement Type
Purpose
Need
SIS CFP
The project's purpose is to add four express lanes along I‐10 from I‐295 to I‐ 95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Add 4 Express Lanes
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐10 from Baker/Columbia County Line to CR 125 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Modify Interchange
SIS Unfunded Needs
The project need was established in The project's purpose is to modify the the SIS Unfunded Needs and interchange of I‐10 at I‐295 to address confirmed as part of the planning congestion needs and improve mobility. process.
2035 Needs Plan
The project's purpose is to construct a new roadway called the I‐10 US 90 Parallel Reliever from South MacClenny to East Baldwin to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SIS CFP
The project's purpose is to add four express lanes on the Buckman Bridge along I‐295 from SR 13 San Jose Boulevard to west of US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Add 4 Express Lanes
Future Corridor
Add 4 Express Lanes on Bridge
20
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐295
I‐295
I‐295
I‐295
I‐295
County
Duval
Duval
Duval
Duval
Duval
Map ID
119
407
408
409
410
From
SR 9B
I‐95 North
North of Trout River
US 1 New Kings Road
SR 134 103rd Street
To
I‐295
SR 105 Dames Point Bridge/Heckscher Drive
I‐95
North of Trout River
I‐10
Improvement Type
Add 4 Express Lanes
Add 4 Express Lanes
Add 4 Express Lanes
Add 4 Express Lanes
Add 4 Express Lanes
21
Source
Purpose
Need
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐295 from SR 9B to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Phases in TIP or Work Program
The project's purpose is to add four express lanes along I‐295 from I‐95 North to SR 105 Dames Point Bridge/Heckscher Drive to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
SIS CFP
The project's purpose is to add four The project need was established in express lanes along I‐295 from north of the SIS CFP and confirmed as part the Trout River to I‐95 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four express lanes along I‐295 from US 1 New Kings Road to north of Trout River to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four The project need was established in express lanes along I‐295 from SR 134 the SIS CFP and confirmed as part 103rd Street to I‐10 to address of the planning process. congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐295
I‐295
I‐295
I‐295
I‐295
County
Duval
Duval
Duval
Duval
Duval
Map ID
411
From
I‐10
431
US 17 Roosevelt Boulevard
964
at US 17 Roosevelt Boulevard
1022
I‐95 South
1023
SR 202 J. T. Butler Boulevard
To
US 1 South of New Kings Road
SR 134 103rd Street
SR 13 San Jose Boulevard
SR 9B
Improvement Type
Purpose
Need
SIS CFP
The project's purpose is to add four express lanes along I‐295 from I‐10 to US 1 South of New Kings Road to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Add 4 Express Lanes
SIS CFP
The project's purpose is to add four express lanes along I‐295 from US 17 Roosevelt Boulevard to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Modify Interchange
Phases in TIP or Work Program
The project's purpose is to modify the interchange of I‐295 at US 17 Roosevelt Boulevard to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
SIS CFP
The project's purpose is to add two express lanes along I‐295 from I‐95 South to SR 13 San Jose Boulevard to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SIS CFP
The project's purpose is to add two The project need was established in express lanes along I‐295 from SR 202 J. the SIS CFP and confirmed as part T. Butler Boulevard to SR 9B to address of the planning process. congestion needs and improve mobility.
Add 4 Express Lanes
Add 2 Express Lanes
Add 2 Express Lanes
22
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐295
I‐95
I‐95
I‐95
I‐95
County
Duval
Duval
St Johns
St Johns
Duval
Map ID
121
From
SR 113 Southside Connector
68
at SR 102 Airport Road
138
at US 1/SR 5 Ponce De Leon Boulevard and at SR 206
400
413
St. Johns/Flagler County Line
SR 104 Dunn Avenue
To
SR 202 J. T. Butler Boulevard
SR 206
SR 102 Airport Road
Improvement Type
Purpose
Need
The project need was established in the SIS CFP and confirmed as part of the planning process.
Add 4 Express Lanes
SIS CFP
The project's purpose is to add four express lanes along I‐295 from SR 113 Southside Connector to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
Modify Interchange
2035 Cost Feasible Plan
The project's purpose is to modify the interchange of I‐95 at SR 102 Airport Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to modify the interchange of I‐95 from US 1 SR 5 Ponce De Leon Boulevard to SR 206 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from St. Johns/Flagler County Line to SR 206 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from SR 104 Dunn Avenue to SR 102 Airport Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Modify Interchange
Add 4 Express Lanes
Add 4 Express Lanes
23
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐95
I‐95
I‐95
I‐95
I‐95
County
Duval
Duval
St Johns
Duval
St Johns
Map ID
From
414
North of Fuller Warren Bridge
418A
Duval/St. Johns County Line
418B
419
420
International Golf Parkway
at US 1/SR 15 MLK
SR 206
To
SR 104 Dunn Avenue
I‐295
St. Johns/Duval County Line
International Golf Parkway
Improvement Type
Purpose
Need
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from North of Fuller Warren Bridge to SR 104 Dunn Avenue to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four The project need was established in express lanes along I‐95 from Duval/St. the SIS CFP and confirmed as part Johns County Line to I‐295 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to add four express lanes along I‐95 from The project need was established in the SIS CFP and confirmed as part International Golf Parkway to St. of the planning process. Johns/Duval County Line to address congestion needs and improve mobility.
Modify Interchange
SIS CFP
The project's purpose is to modify the interchange of I‐95 at US 1/SR 15 MLK to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Add 4 Express Lanes
SIS Unfunded Needs
The project's purpose is to add four express lanes along I‐95 from SR 206 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Add 4 Express Lanes
Add 4 Express Lanes
Add 4 Express Lanes
24
Source
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
I‐95
County
Duval
Map ID
433
From
SR 202 J. T. Butler Boulevard
To
SR 10 Atlantic Boulevard
Improvement Type
Purpose
Need
The project need was established in the SIS CFP and confirmed as part of the planning process.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Add 4 Express Lanes
SIS CFP
The project's purpose is to add four express lanes along I‐95 from SR 202 J. T. Butler Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project's purpose is to add four express lanes along I‐95 from I‐295 to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
I‐95
Duval
434
I‐295
SR 202 J. T. Butler Boulevard
Add 4 Express Lanes
SIS Unfunded Needs
I‐95
St Johns
846
at CR 210
Modify Interchange
2035 Needs Plan
The project's purpose is to modify the The project need was established in interchange of I‐95 at CR 210 to address the 2035 Needs Plan and confirmed congestion needs and improve mobility. as part of the planning process.
962
at SR 115 Southside Boulevard
Modify Interchange
SR 115 Southside Boulevard Corridor Study
The project's purpose is to modify the interchange of I‐95 at SR 115 Southside Boulevard to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen International Golf Parkway to four from The project need was established in I‐95 to Turn/Bend to address congestion needs and improve mobility. the 2035 Needs Plan and confirmed as part of the planning process. This corridor was also identified as a candidate for context sensitive solutions in lieu of widening.
I‐95
International Golf Parkway
Duval
St Johns
823
I‐95
Turn/Bend
Widen to 4 Lanes*
25
Source
The project need was established in the SR 115 Southside Boulevard Corridor Study and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jones Road
Kernan Boulevard
Kernan Boulevard
Knight Boxx Road
Lake Asbury East West 1
County
Duval
Duval
Duval
Clay
Clay
Map ID
944
73
933
901
915
From
US 90 Beaver Street
SR 202 J. T. Butler Boulevard
SR 10 Atlantic Boulevard
To
Pritchard Road
Glen Kernan Parkway
SR 116 McCormick Road
CR 220 Doctors Inlet Road SR 21 Blanding Boulevard
NS3
CR 209 Russell Road
Improvement Type
Purpose
Need
The project's purpose is to construct intersection improvements along Jones Local government Road from US 90 Beaver Street to coordination Pritchard Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Local Government CIP
The project's purpose is wide Kernan Boulevard to six lanes from SR 202 J. T. Butler Boulevard to Glen Kernan Parkway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Widen to 6 Lanes
Local Government CIP
The project's purpose is to widen Kernan Boulevard to six lanes from SR 10 Atlantic Boulevard to SR 116 McCormick Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Widen to 6 Lanes
Other Local Government Priority
The project's purpose is to widen Knight Boxx Road to six lanes from CR 220 Doctors Inlet Road to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Lake Asbury Local government East West 1 from NS3 to CR 209 Russell coordination Road to address congestion needs and improve mobility.
Intersection Improvements
Widen to 6 Lanes
26
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Lake Asbury North South Road 3
Lofton Creek Crossing
Long Bay Road Extension North
Macaw Avenue Extension
McDuff Avenue / 5th Street
County
Clay
Nassau
Clay
Nassau
Duval
Map ID
914
710
911
982
1019
From
CR 739B Sandridge Road
Hendricks Road
Old Jennings Road
Cardinal Street
Melson Avenue
To
CR 209 Russell Road
Avant Road
Long Bay Road
US 17 SR 5
Huron Street
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Lake Asbury Local government North South Road 3 from CR 739B coordination Sandridge Road to CR 209 Russell Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Bridge
Other Local Government Priority
The project's purpose is to construct a new two‐lane bridge called the Lofton Creek Crossing from Hendricks Road to Avant Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Long Bay Road Extension North from Old Jennings Road to Long Bay Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Macaw Local government Avenue Extension from Cardinal Street coordination to US 17 SR 5 to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 3 Lanes
27
Source
Local Government CIP
The project's purpose is to widen 5th Street to three lanes from Melson Avenue to Huron Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Mentoria‐William Burgess Connector
Merrill Road
Mickler Road
Monument Road
Monument Road
County
Nassau
Duval
St Johns
Duval
Duval
Map ID
990
945
825
946
947
From
William Burgess Boulevard
Hartsfield Road
Palm Valley Road
Tredinick Parkway
I‐295
To
Harper Chapel Road
SR 113 Southside Connector
SR A1A
I‐295
Lee Road
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Mentoria‐ Local government William Burgess Connector from coordination William Burgess Boulevard to Harper Chapel Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 6 Lanes
The project's purpose is to widen Merrill Road to six lanes from Hartsfield Local government Road to SR 113 Southside Connector to coordination address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
The project's purpose is to widen The project need was established in Mickler Road to four lanes from Palm the 2035 Needs Plan and confirmed Valley Road to SR A1A to address as part of the planning process. congestion needs and improve mobility.
Widen to 4 Lanes
2035 Needs Plan
Widen to 6 Lanes
The project need was established in The project's purpose is to widen through requests by local Local government Monument Road to six lanes from governments for consideration in coordination Tredinick Parkway to I‐295 to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
Widen to 6 Lanes
The project's purpose is to widen Local government Monument Road to six lanes from I‐295 coordination to Lee Road to address congestion needs and improve mobility.
28
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
National Cemetery Road
New Berlin Road
New Berlin Road
New World Avenue
New World Avenue
County
Duval
Duval
Duval
Duval
Duval
Map ID
1033
948
949
1034
1035
From
Lannie Road
Pulaski Road
Yellow Bluff Road
SR 23 First Coast Expressway
SR 23 First Coast Expressway
To
Arnold Road
Yellow Bluff Road
Cedar Point Road
Chaffee Road
Chaffee Road
Improvement Type
Purpose
The project's purpose is to construct a new two‐lane road called National Cemetery Road from Lannie Road to Arnold Road to address congestion needs and improve mobility.
Need
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
New 2 Lane Road
2035 Cost Feasible Plan
Widen to 4 Lanes
The project need was established in The project's purpose is to widen New through requests by local Local government Berlin Road to four lanes from Pulaski governments for consideration in coordination Road to Yellow Bluff Road to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
Widen to 4 Lanes
The project's purpose is to widen New Berlin Road to four lanes from Yellow Local government Bluff Road to Cedar Point Road to coordination address congestion needs and improve mobility.
The project's purpose is to construct a new two‐lane road called New World Avenue from SR 23 First Coast Expressway to Chaffee Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
New 2 Lane Road
Local Government CIP
Widen to 4 Lanes
The project need was established in The project's purpose is to widen New through requests by local Local government World Avenue from SR 23 First Coast governments for consideration in coordination Expressway to Chaffee Road to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
29
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Norfolk Southern Railroad Overpass
County
Duval
Northern Cross Town Corridor Baker
Northern Outer Beltway
Oakleaf Village Parkway Extension
Old Kings Road
Duval/Nassau
Clay
Duval
Map ID
85
500
88
913
951
From
West 12th Street
CR 125
I‐10
Oakleaf Plantation Parkway
SR 111 Edgewood Avenue
To
US 23 New Kings Road
SR 121
I‐95
Oakleaf Village Parkway
Plummer Road
Improvement Type
Purpose
Need
New 3 Lane Road / Bridge
2035 Needs Plan
The project's purpose is to construct a new three lane road and bridge called The project need was established in the Norfolk Southern Railroad Overpass the 2035 Needs Plan and confirmed from West 12th Street to US 23 New as part of the planning process. Kings Road to address congestion needs and improve mobility.
New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Northern Cross Town Corridor from CR 125 to SR 121 to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a new limited‐access facility called the Northern Outer Beltway from I‐10 to I‐ 95 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 2 Lane Road
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Oakleaf Village Parkway Extension from Oakleaf Plantation Parkway to Oakleaf Village Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Intersection Improvements
The project's purpose is to construct intersection improvements along Old Local government Kings Road from SR 111 Edgewood coordination Avenue to Plummer Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Future Corridor
30
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Old Middleburg Road
Old St. Augustine Road
Old St. Augustine Road
Outer Loop Facility
Pages Dairy Road East Extension
County
Duval
Duval
Duval
Baker/Duval
Nassau
Map ID
1015
90
1010
91
987
From
Argyle Forest Boulevard
Bartram Park Boulevard
at Greenland Road
SR 228 Normandy Boulevard
Chester Road
To
SR 134 103rd Street
US 1/SR 5 Phillips Highway
SR 228 Normandy Boulevard
Blackrock Road
Improvement Type
Purpose
Need
Local Government CIP
The project's purpose is to widen Old Middleburg Road from Argyle Forest Boulevard to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen Old St. Augustine Road to six lanes and construct an overpass of US 1 SR 5 Philips Highway from Bartram Park Boulevard to US 1 SR 5 Phillips Highway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to construct intersection improvements and add one lane along Old St. Augustine Road at Greenland Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Future Corridor
2035 Needs Plan
The project's purpose is to construct a new roadway called the Outer Loop Facility from SR 228 Normandy Boulevard to SR 228 Normandy Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Pages Dairy Local government Road East Extension from Chester Road coordination to Blackrock Road to address congestion needs and improve mobility.
Widen to 4 Lanes
Widen to 6 Lanes and Overpass
Intersection Improvements / Add 1 Lane
31
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Pages Dairy Road South Extension
Palm Valley Road
Pecan Park Road
Pecan Park Road
Pulaski Road
County
Nassau
St Johns
Duval
Duval
Duval
Map ID
983
826
952
92
From
SR 200 SR A1A
Intracoastal Waterway
Braddock Boulevard
I‐95
953*** Eastport Road
To
Sowell Road
Mickler Road
JIA North Access Road
US 17 Main Street
I‐295
Improvement Type
Purpose
Need
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Pages Dairy Local government Road South Extension from SR 200 SR coordination A1A to Sowell Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen Palm Valley Road from Intracoastal Waterway to Mickler Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
The project need was established in The project's purpose is to widen Pecan through requests by local Local government Park Road from Braddock Boulevard to governments for consideration in coordination JIA North Access Road to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
The project's purpose is to widen Pecan Park Road from I‐95 to US 17 Main Street to address congestion needs and improve mobility.
Widen to 4 Lanes
2035 Needs Plan
Widen to 4 Lanes
The project's purpose is to widen Local government Pulaski Road from Eastport Road to I‐ coordination 295 to address congestion needs and improve mobility.
32
Source
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Pulaski Road / Starratt Road
Race Track Road
Race Track Road
Race Track Road Connector
Ramona Boulevard
County
Duval
St Johns
St Johns
St Johns
Duval
Map ID
97
827
828
851
935
From
I‐295
St. Johns Parkway
Bartram Park Boulevard
Durbin Parkway / 9B Extension
Hammond Boulevard
To
Duval Station Road
Bartram Park Boulevard
Bartram Springs
Race Track Road
Cahoon Road South
Improvement Type
Purpose
Need
2035 Needs Plan
The project's purpose is to widen The project need was established in Pulaski Road / Starratt Road from I‐295 the 2035 Needs Plan and confirmed to Duval Station Road to address as part of the planning process. congestion needs and improve mobility.
Widen to 4 Lanes
2035 Needs Plan
The project's purpose is to widen Race The project need was established in Track Road from St. Johns Parkway to the 2035 Needs Plan and confirmed Bartram Park Boulevard to address as part of the planning process. congestion needs and improve mobility.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen Race Track Road from Bartram Park Boulevard to Bartram Springs to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Other Local Government Priority
The project's purpose is to construct a new two‐lane road called Race Track Road Connector from Durbin Parkway and 9B Extension to Race Track Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to widen Ramona Boulevard to five lanes from Hammond Boulevard to Cahoon Road South to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Widen to 4 Lanes
New 2 Lane Road
Widen to 5 Lanes
33
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Rampart / Firestone Road
Ranch Road
Ricker Road
Salisbury Road Extension
San Pablo Road
County
Duval
Duval
Duval
Duval
Duval
Map ID
98
1038
934
99
1009
From
Collins Road
Tradeport Road
Morse Avenue
SR 152 Baymeadows Boulevard
US 90 Beach Boulevard
To
SR 134 103rd Street
SR 102 North of Airport Road
Old Middleburg Road
Belfort Road
SR 10 Atlantic Boulevard
Improvement Type
Widen to 4 Lanes
Widen to 4 Lanes
Widen to 3 Lanes
New 3 Lane Road
Widen to 3 Lanes
34
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to widen Rampart / Firestone Road to four lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to widen Ranch Road to four lanes from Tradeport Road to SR 102 North of Airport Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to widen Ricker Road to three lanes from Morse Avenue to Old Middleburg Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a new three‐lane road called Salisbury Road Extension from SR 152 Baymeadows Boulevard to Belfort Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to widen San Pablo Road to three lanes from US 90 Beach Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Shindler Drive
SR 10 Atlantic Boulevard
SR 10 Atlantic Boulevard
SR 10 Atlantic Boulevard
SR 100
County
Duval
Duval
Duval
Duval
Clay
Map ID
101
714
715
716
450
From
Collins Road
at Girvin Road
at Hodges Boulevard
at San Pablo Boulevard
To
SR 134 103rd Street
Clay/Bradford County Line Clay/Putnam County Line
Improvement Type
Purpose
Need The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Widen to 3 Lanes
Local Government CIP
The project's purpose is to widen Shindler Drive to three lanes from Collins Road to SR 134 103rd Street to address congestion needs and improve mobility.
Intersection Improvements
Phases are currently included in a local government capital improvement program.
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Girvin Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Intersection Improvements
Local Government CIP
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at Hodges Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Intersection Improvements
Phases are currently included in a local government capital improvement program.
The project's purpose is to construct intersection improvements along SR 10 Atlantic Boulevard at San Pablo Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to widen SR 100 to four lanes from Clay/Bradford County Line to Clay/Putnam County Line to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Widen to 4 Lanes
35
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 100
SR 101 Mayport Road
SR 101 Mayport Road
SR 102 Airport Road
SR 104 Dunn Avenue
County
Putnam
Duval
Duval
Duval
Duval
Map ID
451
152B
152
421
940
From
Clay/Putnam County Line
SR 116 Wonderwood Drive
at SR 116 Wonderwood Drive
Airport Entrance
US 1/SR 15 New Kings Road
To
US 17 SR 5
Mayport Main Gate
I‐95
I‐295
Improvement Type
Purpose
Need
Widen to 4 Lanes
SIS Unfunded Needs
The project's purpose is to widen SR 100 to four lanes from Clay/Putnam County Line to US 17 SR 5 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Add 2 Northbound Lanes
Through coordination with Mayport Naval Station
The project's purpose is to add two northbound lanes along SR 101 Mayport Road from SR 116 Wonderwood Drive to Mayport Main Gate to address congestion needs and improve mobility.
The project need was established in the through coordination with Mayport Naval Station and local government coordination.
Intersection Improvements
The project's purpose is to construct Through intersection improvements along SR coordination with 101 Mayport Road at SR 116 Mayport Naval Wonderwood Drive to address Station congestion needs and improve mobility.
The project need was established in the through coordination with Mayport Naval Station and local government coordination.
Widen to 6 Lanes
SIS Unfunded Needs
The project's purpose is to widen SR102 Airport Road to 6 lanes from the Airport Entrance to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR 104 Dunn Avenue to four lanes from US 1/SR 15 New Kings Road to I‐295 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Widen to 4 Lanes
36
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 104 Dunn Avenue
SR 115 Arlington Expressway
SR 115 Arlington Expressway
SR 115 Lem Turner Road
SR 115 Southside Boulevard
County
Duval
Duval
Duval
Duval/Nassau
Duval
Map ID
941
100
153
74
102
From
Old Kings Road
SR 109 University Boulevard
at SR 109 University Boulevard
I‐295
US 1/SR 5 Philips Highway
To
US 23 New Kings Road
SR 10 Atlantic Boulevard
US 1 / Callahan S Kings Road
I‐95 Ramps
Improvement Type
Purpose
Need
2035 Needs Plan
The project's purpose is to construct intersection improvements along SR The project need was established in 104 Dunn Avenue from Old Kings Road the 2035 Needs Plan and confirmed as part of the planning process. to US 23 New Kings Road to address congestion needs and improve mobility.
Widen to 6 Lanes*
New need identified in the 2040 LRTP.
The project's purpose is to widen SR 115 Arlington Expressway to six lanes from SR 109 University Boulevard to SR 10 Atlantic Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project was identified as a candidate for context sensitive solutions through the planning process based on the lack of accessibility and mobility within the corridor.
Modify Interchange
Established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE.
The project's purpose is to modify the interchange of SR 115 Arlington Expressway at SR 109 University Boulevard to address congestion needs and improve mobility.
The project need was established as part of the SR 115 Mathews Bridge Replacement PD&E Study and included in the Duval County LOGT program for PE. The need for this project was confirmed as part of the planning process.
2035 Cost Feasible Plan
The project's purpose is to widen SR 115 Lem Turner Road to four lanes from I‐295 to US 1 / Callahan S Kings Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
SR 115 Southside Boulevard Corridor Study
The project's purpose is to widen SR 115 Southside Boulevard to six lanes from US 1/SR 5 Philips Highway to the I‐ 95 Ramps to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 0 and confirmed as part of the planning process.
Intersection Improvements
Widen to 4 Lanes
Widen to 6 Lanes*
37
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 115 Southside Boulevard
SR 115 Southside Boulevard
SR 115 Southside Boulevard
SR 115 Southside Boulevard
SR 115 Southside Boulevard
County
Duval
Duval
Duval
Duval
Duval
Map ID
103
104
960
966
967
From
SR 202 J. T. Butler Boulevard
US 90 Beach Boulevard
Hogan Road
at SR 202 J. T. Butler Boulevard
at SR 152 Baymeadows Road
To
US 90 Beach Boulevard
SR 10 Atlantic Boulevard
Gate Parkway
Improvement Type
Purpose
Need
SR 115 Southside Boulevard Corridor Study
The project's purpose is to widen SR 115 Southside Boulevard to six lanes from SR 202 J. T. Butler Boulevard to US The project need was established in 90 Beach Boulevard to address the 0 and confirmed as part of the congestion needs and improve mobility. planning process. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
2035 Needs Plan
The project's purpose is to widen SR The project need was established in 115 Southside Boulevard to six lanes the 2035 Needs Plan and confirmed from US 90 Beach Boulevard to SR 10 as part of the planning process. Atlantic Boulevard to address congestion needs and improve mobility.
Intersection Improvements
Local Government CIP
The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard from Hogan Road to Gate Parkway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Modify Interchange
SR 115 Southside Boulevard Corridor Study
The project's purpose is to modify the interchange of SR 115 Southside Boulevard at SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility.
The project need was established in the 0 and confirmed as part of the planning process.
Underpass
SR 115 Southside Boulevard Corridor Study
The project's purpose is to construct an underpass where SR 152 Baymeadows Road would go under SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 0 and confirmed as part of the planning process.
Widen to 6 Lanes*
Widen to 6 Lanes*
38
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 115 Southside Boulevard
SR 152 Baymeadows Road
SR 152 Baymeadows Road
SR 16
SR 16
County
Duval
Duval
Duval
Clay
St Johns
Map ID
968
937
938
106
110
From
at SR 10 Atlantic Boulevard
I‐95
US 1 /SR 5 Philips Highway
CR 218
I‐95
To
SR 115 Southside Boulevard
I‐95
SR 15A Oakridge Avenue
SR 313
Improvement Type
Intersection Improvements
Widen to 6 Lanes
Widen to 6 Lanes*
Widen to 4 Lanes
Widen to 6 Lanes
39
Source
Purpose
Need
Local Government CIP
The project's purpose is to construct intersection improvements along SR 115 Southside Boulevard at SR 10 Atlantic Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR 152 Baymeadows Road to 6 lanes from I‐95 to SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR 152 Baymeadows Road to six lanes from US 1 SR 5 Philips Highway to I‐95 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR 16 to four lanes from CR two18 to SR 15A Oakridge Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR 16 to six lanes from I‐95 to SR 313 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 16
SR 16
SR 16
SR 16 Connector
SR 19 Connector
County
Clay
St Johns
St Johns
St Johns
Putnam
Map ID
908
835
836
829
965
From
US 17
South Francis Road
CR 208 Outlet Mall
SR 16/CR 16A
SR 19
To
Shands Bridge
International Golf Parkway
South Francis Road
CR 2209
Putnam County Boulevard
Improvement Type
Purpose
Need
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from US 17 to Shands Bridge to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from South Francis Road to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen SR 16 to four lanes from CR 208 Outlet Mall to South Francis Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 4 Lane Road
2035 Needs Plan
The project's purpose is to construct a new four‐lane road called SR 16 Connector from SR 16/CR 16A to CR 2209 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
New 4 lane road / bridge
Other Local Government Priority
The project's purpose is to construct a new four‐lane road / bridge called SR 19 Connector from SR 19 to Putnam County Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
40
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 20
SR 20
SR 200 Overpass
SR 200 William Burgess Connector
SR 200 Yulee Backage Roads
County
Putnam
Putnam
Nassau
Nassau
Nassau
Map ID
422
From
Putnam/Alachua County Line
To
SW 56th Avenue
423
SW 56th Avenue
1003
at US 17 SR 5 and Railroad Tracks
998
992
William Burgess Boulevard
Cardinal Street North Extension
CR 315 Interlachen
SR 200 SR A1A
Old Yulee Road
Improvement Type
Purpose
Need
Widen to 4 Lanes
Phases in TIP or Work Program
The project's purpose is to widen SR 20 to four lanes from Putnam/Alachua County Line to SW 56th Avenue to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
Widen to 4 Lanes
Phases in TIP or Work Program
The project's purpose is to widen SR20 to four lanes from SW 56th Avenue to CR 315 in Interlachen to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
Overpass
2035 Needs Plan
The project's purpose is to construct an The project need was established in overpass along SR 200 at US 17 SR 5 the 2035 Needs Plan and confirmed and the railroad tracks to address as part of the planning process. congestion needs and improve mobility.
New 2 Lane Road
The project's purpose is to construct a new two‐lane Road called SR 200 Local government William Burgess Connector from coordination William Burgess Boulevard to SR 200 SR A1A to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called SR 200 Yulee Local government Backage Roads from the Cardinal Street coordination North Extension to Old Yulee Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
41
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 200 SR A1A
SR 200 SR A1A
SR 200A Pages Dairy Road
SR 207
SR 207
County
Nassau
Nassau
Nassau
St Johns
St Johns
Map ID
427
703
979
113
830
From
at US 17
Amelia Island Parkway
at Felmor Road
I‐95
Holmes Boulevard
To
Sadler Road
South Holmes Boulevard
SR 312
Improvement Type
Purpose
Need
The project's purpose is to construct The project need was established in intersection improvements along SR the SIS CFP and confirmed as part 200 SR A1A at US 17 to address of the planning process. congestion needs and improve mobility.
Intersection Improvements
SIS CFP
Widen to 6 Lanes
The project's purpose is to widen SR 200 SR A1A to six lanes from Amelia Local government Island Parkway to Sadler Road to coordination address congestion needs and improve mobility.
Roundabout Projects
The project need was established in The project's purpose is to construction through requests by local Local government a roundabout along SR 200A Pages governments for consideration in coordination Dairy Road at Felmor Road to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
Widen to 6 Lanes
Widen to 6 Lanes
42
Source
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to SR 207 The project need was established in widen to six lanes from I‐95 to South the 2035 Needs Plan and confirmed Holmes Boulevard to address as part of the planning process. congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR 207 to 6 lanes from Holmes Boulevard to SR 312 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
County
Duval
Clay
Duval
Duval
Duval
Map ID
9
114
957A
957B
957C
From
I‐295
SR 16
at Collins Road
at SR 134 103rd Street
at Cedar Hills Boulevard
To
Wilson Boulevard
CR 215 Blanding Boulevard
Improvement Type
Widen to 6 Lanes
Widen to 4 Lanes
Intersection Improvements
Intersection Improvements
Intersection Improvements
43
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to widen SR 21 The project need was established in Blanding Boulevard to six lanes from I‐ the 2035 Needs Plan and confirmed 295 to Wilson Boulevard to address as part of the planning process. congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR 21 Blanding Boulevard to four lanes from SR 16 to CR two15 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Collins Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at SR 134 103rd Street to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Local Government CIP
The project's purpose is to construct intersection improvements along SR 21 Blanding Boulevard at Cedar Hills Boulevard to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 228 Hart Bridge
SR 228 Normandy Boulevard
SR 228 Normandy Boulevard
SR 23 First Coast Expressway
SR 23 First Coast Expressway
County
Duval
Duval
Duval
Clay
Clay
Map ID
47
86
87
41
8202
From
SR 228 Hart Expressway ‐ Downtown
US 301
SR 23 First Coast Expressway
at CR 218
SR 21 Blanding Boulevard
To
SR 10 Atlantic Boulevard
Bell Road (Equestrian Park )
SR 111 Cassatt Avenue
US 17
Improvement Type
New 6 Lane Bridge
Widen to 4 Lanes
Widen to 6 Lanes
New Interchange
New 4 Lane Road
44
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to construct a replace the SR 228 Hart Bridge from SR The project need was established in 228 Hart Expressway ‐ Downtown to SR the 2035 Needs Plan and confirmed as part of the planning process. 10 Atlantic Boulevard to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR 228 Normandy Boulevard to four lanes from US 301 to Bell Road (Equestrian Park) to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR The project need was established in 228 Normandy Boulevard to six lanes from SR 23 First Coast Expressway to SR the 2035 Needs Plan and confirmed as part of the planning process. 111 Cassatt Avenue to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at CR two18 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new four‐lane road called SR 23 First the SIS CFP and confirmed as part Coast Expressway from SR 21 Blanding of the planning process. Boulevard to US 17 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 23 First Coast Expressway
SR 23 First Coast Expressway
SR 23 First Coast Expressway
SR 23 First Coast Expressway
SR 23 First Coast Expressway
County
Clay
Clay
Clay
Clay/Duval
Clay/St. Johns
Map ID
1011
1012
1013
8201
8203
From
at SR 21 Blanding Boulevard
at CR 739
at SR 16
I‐10
US 17
To
SR 21 Blanding Boulevard
I‐95
Improvement Type
New Interchange
New Interchange
New Interchange
Widen to 6 Lanes
New 6 Lane Road
45
Source
Purpose
Need
SIS CFP
The project's purpose is to construct a new interchange along SR 23 First Coast The project need was established in Expressway at SR 21 Blanding Boulevard the SIS CFP and confirmed as part of the planning process. to address congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at CR 739 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at SR 16 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to widen SR 23 The project need was established in First Coast Expressway from I‐10 to SR the SIS CFP and confirmed as part 21 Blanding Boulevard to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a new six‐lane road called SR 23 First Coast Expressway from US 17 to I‐95 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 23 First Coast Expressway
SR 23 First Coast Expressway
SR 23 First Coast Expressway
SR 243 JIA North Access Road
SR 312
County
St Johns
St Johns
St Johns
Duval
St Johns
Map ID
840
841
847
701
115
From
at I‐95
at CR 16 A
at CR 2209
SR 102 Airport Road
US 1/SR 5 Dixie Highway
To
Pecan Park Road
SR A1A
Improvement Type
New Interchange
New Interchange
New Interchange
Widen to 4 Lanes
Widen to 6 Lanes
46
Source
Purpose
Need
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at I‐95 to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at CR 16 A to address of the planning process. congestion needs and improve mobility.
SIS CFP
The project's purpose is to construct a The project need was established in new interchange along SR 23 First Coast the SIS CFP and confirmed as part Expressway at CR 2209 to address of the planning process. congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR 243 JIA North Access Road to four lanes from SR 102 Airport Road to Pecan Park Road to address congestion needs and improve mobility.
2035 Needs Plan
The project's purpose is to widen SR The project need was established in 312 to six lanes from US 1/SR 5 Dixie the 2035 Needs Plan and confirmed Highway to SR A1A to address as part of the planning process. congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 313
SR 313
SR 313
SR 9B
SR 9B
County
St Johns
St Johns
St Johns
Duval
Duval
Map ID
831
832
839
1024
18
From
SR 207
SR 16
at US 1/SR 5 Dixie Highway
US 1/SR 5 Philips Highway
US 1/SR 5 Philips Highway
To
SR 16
US 1 Dixie Highway
I‐295
I‐295
Improvement Type
New 6 Lane Road
New 4 Lane Road
New Interchange
Add 2 Auxiliary Lanes
Widen to 6 Lanes
47
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to construct a new six lane road called SR 313 from SR 207 to SR 16 to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a The project need was established in new four‐lane road called SR 313 from the 2035 Needs Plan and confirmed SR 16 to US 1 Dixie Highway to address as part of the planning process. congestion needs and improve mobility.
Other Local Government Priority
The project's purpose is to construct a new interchange along SR 313 at US 1 SR 5 Dixie Highway to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
SIS CFP
The project's purpose is to add two auxiliary lanes along SR 9B from US 1/SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
SIS CFP
The project's purpose is to widen SR 9B to six lanes from US 1 SR 5 Philips Highway to I‐295 to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 9B Extension
SR 9B Extension
SR A1A
SR A1A
SR A1A
County
St Johns
St Johns
St Johns
Nassau
St Johns
Map ID
833
842
128
706
1008
From
St. Johns Parkway
at Durbin Parkway
Solana Road
South Fletcher Avenue
at Red Cox/Coquina Road
To
Race Track Road
SR 202 J. T. Butler Boulevard
Amelia Island Parkway
Improvement Type
Purpose
Need
Other Local Government Priority
The project's purpose is to widen the SR 9B Extension to six lanes from St. Johns Parkway to Race Track Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to construct a The project need was established in new interchange along the SR 9B the 2035 Needs Plan and confirmed Extension at Durbin Parkway to address as part of the planning process. congestion needs and improve mobility.
Widen to 6 Lanes*
2035 Needs Plan
The project's purpose is to widen SR A1A to six lanes from Solana Road to SR The project need was established in 202 J. T. Butler Boulevard to address congestion needs and improve mobility. the 2035 Needs Plan and confirmed as part of the planning process. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
Turn Lane Improvements*
The project's purpose is to construct turn lane improvements along SR A1A from South Fletcher Avenue to Amelia Local government Island Parkway to address congestion coordination needs and improve mobility. This project was also identified as a candidate for context solutions.
Intersection Improvements
Other Local Government Priority
Widen to 6 Lanes
New Interchange
48
Source
The project's purpose is to construct intersection improvements along SR A1A at Red Cox/Coquina Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR A1A
SR A1A
SR A1A Anastasia Boulevard
SR A1A St Johns River Ferry
St. Johns Parkway
County
St Johns
Duval
St Johns
Duval
St Johns
Map ID
800
151
1031
2331
848
From
Mickler Road
SR 116 Wonderwood Drive
Casanova Road
CR 2209
To
Palm Valley Road
Naval Station Mayport North Gate
Bridge of Lions
9B Extension
Improvement Type
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to widen SR A1A to four lanes from Mickler Road to Palm Valley Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen SR A1A to four lanes from SR 116 Wonderwood Drive to Naval Station The project need was established in Mayport North Gate to address the 2035 Needs Plan and confirmed congestion needs and improve mobility. as part of the planning process. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
CSS
St. Augustine Mobility Institute
The project's purpose is to construct context sensitive solutions along SR A1A Anastasia Boulevard from Casanova Road to Bridge of Lions to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
Ferry Slip Replacement
2035 Cost Feasible Plan
The project's purpose is to replace the St. Johns River ferry slip to maintain service, address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
Widen to 6 Lanes
Other Local Government Priority
The project's purpose is to widen the St. Johns Parkway to six lanes from CR 2209 to 9B Extension to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
Widen to 4 Lanes*
49
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Starratt Road
Touchton Road
Town Center Boulevard
Trout River Boulevard
Tynes Road
County
Duval
Duval
Clay
Duval
Clay
Map ID
954
129
903
955
912
From
Duval Station Road
Belfort Road
US 17
Old Kings Road
Pipit Place
To
Yellow Bluff Road
SR 115 Southside Boulevard
CR 220 Doctors Inlet Road
US 23 New Kings Road
Oakleaf Plantation Parkway
Improvement Type
Purpose
Need
Widen to 4 Lanes
The project's purpose is to widen Starratt Road to four lanes from Duval Local government Station Road to Yellow Bluff Road to coordination address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
2035 Needs Plan
The project's purpose is to widen Touchton Road to four lanes from Belfort Road to SR 115 Southside Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Widen to 4 Lanes
Other Local Government Priority
The project's purpose is to widen Town Center Boulevard to four lanes from US 17 to CR 220 Doctors Inlet Road to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Widen to 4 Lanes
The project's purpose is to widen Trout River Boulevard to four lanes from Old Local government Kings Road to US two3 New Kings Road coordination to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
Other Local Government Priority
50
Source
The project's purpose is to construct a new two‐lane road called Tynes Road from Pipit Place to Oakleaf Plantation Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1 SR 15 New Kings Road
US 1 SR 15 New Kings Road
US 1 SR 15 New Kings Road
US 1 SR 5
US 1 SR 5 Dixie Highway
County
Duval
Duval
Duval
St Johns
St Johns
Map ID
82
83
950
845
130
From
Soutel Drive
I‐295
SR 111 Edgewood Avenue
at CR 210
SR 206
To
I‐295
Old Kings Road
Soutel Drive
Lewis Point Road
Improvement Type
Purpose
Need
2035 Needs Plan
The project's purpose is to widen US 1 The project need was established in SR 15 New Kings Road to six lanes from the 2035 Needs Plan and confirmed Soutel Drive to I‐295 to address as part of the planning process. congestion needs and improve mobility.
Widen to 6 Lanes
2035 Needs Plan
The project's purpose is to widen US 1 The project need was established in SR 15 New Kings Road to six lanes from the 2035 Needs Plan and confirmed I‐295 to Old Kings Road to address as part of the planning process. congestion needs and improve mobility.
Intersection Improvements
The project's purpose is to construct intersection improvements along US 1 Local government SR 15 New Kings Road at SR 111 coordination Edgewood Avenue to Soutel Drive to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Modify Interchange
Phases in TIP or Work Program
The project's purpose is to modify the interchange of US 1 SR 5 at CR 210 to address congestion needs and improve mobility.
The project need was established in the Phases in TIP or Work Program and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen US 1 The project need was established in SR 5 Dixie Highway to six lanes from SR the 2035 Needs Plan and confirmed 206 to Lewis Point Road to address as part of the planning process. congestion needs and improve mobility.
Widen to 6 Lanes
Widen to 6 Lanes
51
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1 SR 5 Dixie Highway
US 1 SR 5 Dixie Highway
US 1 SR 5 Philips Highway
US 1/SR 5 Philips Highway
US 1/SR 5 Philips Highway
County
St Johns
St Johns
Duval
Duval
Duval
Map ID
131
132
93
94
95
From
SR 313
International Golf Parkway
Nocatee Parkway / Race Track Road
SR 9B
I‐95 at the Avenues
To
International Golf Parkway
Race Track Road
SR 9B
I‐295
SR 202 J. T. Butler Boulevard
Improvement Type
Widen to 6 Lanes
Widen to 6 Lanes
Widen to 6 Lanes
Widen to 6 Lanes*
Widen to 6 Lanes*
52
Source
Purpose
Need
2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Dixie Highway to six lanes from SR 313 to International Golf Parkway to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen US 1 The project need was established in SR 5 Dixie Highway to six lanes from the 2035 Needs Plan and confirmed International Golf Parkway to Race Track Road to address congestion needs as part of the planning process. and improve mobility.
2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from Nocatee Parkway / Race Track Road to SR 9B to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen US 1 SR 5 Philips Highway to six lanes from SR 9B to I‐295 to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from I‐95 at the Avenues to SR 202 J. T. Butler Boulevard to address congestion needs and improve mobility. This project was also identified as a candidate for context sensitive solutions in lieu of widening.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1/SR 5 Philips Highway
US 17
US 17
US 17
US 17
County
Duval
Clay
Nassau
Nassau
Clay
Map ID
96
133
707
709
1037
From
SR 202 J. T. Butler Boulevard
CR 315
To
SR 126 Emerson Street
Town Center Boulevard
Nassau/Duval County Line Harts Road
SR 200 SR A1A
Governor Street
Georgia State Line
Haven Avenue
Improvement Type
Purpose
Need
2035 Needs Plan
The project's purpose is to widen to US 1 SR 5 Philips Highway to six lanes from The project need was established in the 2035 Needs Plan and confirmed SR 202 J. T. Butler Boulevard to SR as part of the planning process. 1two6 Emerson Street to address congestion needs and improve mobility.
Widen to 6 Lanes
2035 Needs Plan
The project's purpose is to widen US 17 The project need was established in to six lanes from CR 315 to Town Center the 2035 Needs Plan and confirmed Boulevard to address congestion needs as part of the planning process. and improve mobility.
Intersection Improvements
The project's purpose is to construct intersection improvements along US 17 Local government from Nassau/Duval County Line to Harts coordination Road to address congestion needs and improve mobility.
Widen to 6 Lanes
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
I‐95 Parallel Corridor Study
The project need was established in The project's purpose is to widen US 17 through requests by local to four lanes from SR 200 SR A1A to governments for consideration in Georgia State Line to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
Widen to 4 Lanes
2035 Cost Feasible Plan
The project's purpose is to widen US 17 to four lanes from Governor Street to Haven Avenue to address congestion needs and improve mobility.
53
Source
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 17 Main Street
US 17 Main Street
US 17 Main Street
US 17 Pages Dairy Connector w/roundabout
US 17 Powerline Corridor
County
Duval/Nassau
Duval
Duval
Nassau
Nassau
Map ID
78
1017
959
984
994
From
Pecan Park Road
New Berlin Road
at Eastport Road
US 17 SR 5
Vegas Boulevard
To
SR 200 / SR A1A
Pecan Park Road
SR 200A Pages Dairy Road
Radio Avenue
Improvement Type
Source
Purpose
Need
Widen to 4 Lanes
2035 Needs Plan
The project's purpose is to widen US 17 Main Street to four lanes from Pecan Park Road to SR 200 / SR A1A to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Widen to 4 Lanes
2035 Cost Feasible Plan
The project's purpose is to widen US 17 to four lanes from New Berlin Road to Pecan Park Road to address congestion needs and improve mobility.
The project need was established in the 2035 Cost Feasible Plan and confirmed as part of the planning process.
New Interchange
Local Government CIP
The project's purpose is to construct a new interchange along US 17 Main Street at Eastport Road to address congestion needs and improve mobility.
The project need was established based on project phases being programmed in a local government capital improvement program. The project needs were confirmed as part of the planning process.
New 2 Lane Road and Roundabout
The project's purpose is to construct a new road called US 17 Pages Dairy Local government Connector from US 17 SR 5 to SR 200A coordination Pages Dairy Road and roundabout at SR 200A Paiges Dairy Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called US 17 Local government Powerline Corridor from Vegas coordination Boulevard to Radio Avenue to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
54
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 17 SR 15
US 17 SR 15
US 17 SR 15
US 17 SR 15
US 17 Yulee Backage Roads
County
Putnam
Putnam
Putnam
Putnam
Nassau
Map ID
428
429
430
452
999
From
West of Dunn Creek Bridge
CR 309 Satsuma
Putnam/Volusia County Line
Pomona Park/Feagle Avenue
US 17 SR 5
To
Horse Landing Road
West of Dunn Creek Bridge
Pomona Park/Feagle Avenue
CR 309 Satsuma
North of Koen Lane
Improvement Type
Purpose
Need
Widen to 4 Lanes
SIS Unfunded Needs
The project's purpose is to widen US 17 SR 15 to four lanes from West of Dunn Creek Bridge to Horse Landing Road to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Widen to 4 Lanes
SIS Unfunded Needs
The project's purpose is to widen US 17 SR 15 from CR 309 Satsuma to West of Dunn Creek Bridge to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
SIS Unfunded Needs
The project's purpose is to widen to US 17 SR 15 to four lanes from the Putnam/Volusia County Line to Pomona Park/Feagle Avenue to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
Widen to 4 Lanes
SIS CFP
The project's purpose is to widen US 17 SR 15 to four lanes from Pomona Park/Feagle Avenue to CR 309 Satsuma to address congestion needs and improve mobility.
The project need was established in the SIS CFP and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called the US 17 Local government Yulee Backage Roads from US 17 SR 5 to coordination North of Koen Lane to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
55
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1B King Street
US 1B San Marco Avenue
US 301 SR 200
US 301 SR 200
US 301 SR 200
County
St Johns
St Johns
Duval
Clay
Nassau
Map ID
1029
1030
123
424
708
From
US 1 Ponce de Leon Boulevard
Bridge of Lions
US 90
To
Avenida Menendez
SR 16
Duval/Nassau County Line
Clay/Bradford County Line Duval/Clay County Line
US 1 at S Kings Road
Improvement Type
Source
Purpose
Need
St. Augustine Mobility Institute
The project's purpose is to construct context sensitive solutions along US 1B King Street from US 1 Ponce de Leon Boulevard to Avenida Menendez to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
St. Augustine Mobility Institute
The project's purpose is to construct context sensitive solutions along US 1B San Marco Avenue from Bridge of Lions to SR 16 to address congestion needs and improve mobility.
The project need was established in the St. Augustine Mobility Institute and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen US The project need was established in 301 SR 200 to four lanes from US 90 to the 2035 Needs Plan and confirmed Duval/Nassau County Line to address as part of the planning process. congestion needs and improve mobility.
Widen to 6 Lanes
SIS Unfunded Needs
The project's purpose is to widen US 301 SR 200 to six lanes from the Clay/Bradford County Line to Duval/Clay County Line to address congestion needs and improve mobility.
Intersection Improvements
The project's purpose is to construct intersection improvements along US Local government 301 SR 200 from US 1 at South Kings coordination Road to address congestion needs and improve mobility.
Context Sensitive Solutions
Context Sensitive Solutions
Widen to 4 Lanes
56
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 301 SR 200
US 90 / SR 115 Mathews Bridge
US 90 Beaver Street
US 90 Beaver Street
Various SR 200 Intersections Modifications
County
Duval
Duval
Duval
Duval
Nassau
Map ID
425
79
6
7
981
From
Duval/Clay County Line
Alt. US 1 MLK Jr. Parkway
SR 23 First Coast Expressway
Cahoon Road
To
I‐10
SR 109 University Boulevard
Cahoon Road
McDuff Avenue
Improvement Type
Purpose
Need
SIS Unfunded Needs
The project's purpose is to widen US 301 SR 200 to six lanes from Duval/Clay County Line to I‐10 to address congestion needs and improve mobility.
The project need was established in the SIS Unfunded Needs and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to reconstruct the US 90 / SR 115 Mathews Bridge as a six lane bridge and provide transit accommodations from Alt. US 1 MLK Jr. Parkway to SR 109 University Boulevard to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
2035 Needs Plan
The project's purpose is to widen US 90 Beaver Street to four lanes from SR 23 First Coast Expressway to Cahoon Road to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Widen to 4 Lanes
2035 Needs Plan
The project's purpose is to widen US 90 Beaver Street to four lanes from Cahoon Road to McDuff Avenue to address congestion needs and improve mobility.
The project need was established in the 2035 Needs Plan and confirmed as part of the planning process.
Intersection Improvements
The project need was established in The project's purpose is to construct through requests by local Local government intersection improvements along SR governments for consideration in coordination 200 at various locations to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
Widen to 6 Lanes
New 6 Lane Bridge and Transit
Widen to 4 Lanes
57
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Veterans Parkway
Wells Road
Woodbridge Parkway Extension
Yellow Bluff Road
County
St Johns
Clay
Nassau
Duval
Map ID
834
910
997
956
From
Greenbriar Road
Aquarius Concourse
Woodbrigde Parkway
Starratt Road
To
Improvement Type
Longleaf Pine Parkway
Purpose
Need
Other Local Government Priority
The project's purpose is to construct a new four‐lane road called Veterans Parkway from Greenbriar Road to Longleaf Pine Parkway to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
Reconstruct and New 2 Lane Road
Other Local Government Priority
The project's purpose is to reconstruct Wells Road and construct new two‐lane road extension of Wells Road from Aquarius Concourse to SR 21 Blanding Boulevard to address congestion needs and improve mobility.
The project need was established in the Other Local Government Priority and confirmed as part of the planning process.
New 2 Lane Road
The project's purpose is to construct a new two‐lane road called Woodbridge Local government Parkway Extension from Woodbrigde coordination Parkway to Clements Road to address congestion needs and improve mobility.
The project need was established in through requests by local governments for consideration in the plan and confirmed as part of the planning process.
Widen to 4 Lanes
The project need was established in The project's purpose is to widen through requests by local Local government Yellow Bluff Road from Starratt Road to governments for consideration in coordination New Berlin Road (north) to address the plan and confirmed as part of congestion needs and improve mobility. the planning process.
New 4 Lane Road
SR 21 Blanding Boulevard
Clements Road
New Berlin Road (north)
Source
Transit Capacity Projects
East First Coast Flyer
Duval
2385
Downtown Jacksonville (Duval County)
3rd Street (Jacksonville Beach)
BRT
58
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Southwest First Coast Flyer
SR 134 103rd Street
SR 21 Blanding Boulevard
County
Duval
Duval
Clay
SR 228 Normandy Boulevard Duval
US 1
Duval
Map ID
From
2386
Wells Road
2321
SR 228 Normandy Boulevard
2308
To
Downtown Jacksonville (Duval County)
SR 21 Blanding Boulevard
CR 218
Wells Road
2322
SR 134 103rd Street
Downtown Jacksonville (Duval County)
2324
Lewis Speedway (St. John's County)
Avenues Mall (Duval County)
Improvement Type
Purpose
Need
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
59
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1
US 1/SR 15 New Kings Road
SR 115 Southside Boulevard
I‐95
North (CSX)
County
St. John's
Duval
Duval
Duval
Duval
Map ID
From
2375
Lewis Speedway (St. John's County)
2323
Downtown Jacksonville (Duval County)
2325
Avenues Mall
2326
Gateway Mall
2356
Downtown Jacksonville (Duval County)
To
Avenues Mall (Duval County)
Edgewood Avenue
Regency Square Mall
Jacksonville International Airport
Yulee (Nassau County)
Improvement Type
Purpose
Need
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
BRT
Blueprint 2020 and 2035 LRTP
This project's purpose is to provide higher quality bus services throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
60
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
North Extension (CSX)
Northwest (CSX)
Southeast (FEC)
Southeast Extension (FEC)
Southwest (CSX)
County
Nassau
Duval
Duval
St. John's
Duval
Map ID
From
To
2366
Yulee
Fernandina Beach
2357
Downtown Jacksonville (Duval County)
Callahan (Nassau County)
2327
St. Augustine (St. John's County)
Downtown Jacksonville (Duval County)
2377
Palm Coast (Flagler County)
City of St. Augustine
2358
Green Cove Springs (Clay County)
Downtown Jacksonville (Duval County)
Improvement Type
Purpose
Need
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
61
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Southwest Extension (CSX)
West (CSX)
West Extension (CSX)
I‐95
Cumberland Island Ferry
County
Clay
Duval
Baker
Duval
Nassau
Map ID
2319
From
To
Palatka (Putnam County)
Green Cove Springs (Clay County)
2328
Baldwin (Duval County)
Downtown Jacksonville (Duval County)
2301
MacClenny (Baker County)
2330
Downtown Jacksonville (Duval County)
2369
Fernandina
Baldwin (Duval County)
Yulee (Nassau County)
Cumberland Island
Improvement Type
Purpose
Need
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Commuter Rail
Blueprint 2020 and 2035 LRTP
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Blueprint 2020
The project's purpose is the provide accessibility to additional mobility options for longer commuter trips throughout the region.
The need for this project was identified through the JTA's Blueprint 2020 study and confirmed as part of the planning process.
Nassau County
The project's purpose is to provide direct access to Cumberland Island from Florida allowing travelers to avoid crossing the St. Mary's River to access this National Park.
The need for this project was identified based on the Florida East Coast Greenway study and confirmed as part of the planning process.
Express Bus Service
Ferry Service
62
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR A1A St Johns River Ferry
SR A1A St Johns River Ferry
SR A1A St Johns River Ferry
SR A1A St Johns River Ferry
SR A1A St Johns River Ferry
County
Duval
Duval
Duval
Duval
Duval
Map ID
2331
2329
2333
2344
2345
From
Ft. George/Mayport
JPA Property
Mayport
To
Mayport Terminal
Ft. George Island
Improvement Type
Purpose
Need
Ferry Slip Replacement
This project's purpose is to provide St. Johns River safer and more efficient operations of Ferry Commission the St. Johns River Ferry. The project will replace the ferry slips.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Drydock / Ferry Repairs
This project's purpose is to provide St. Johns River safer and more efficient operations of Ferry Commission the St. Johns River Ferry.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Long Term Site Improvements
This project's purpose is to provide St. Johns River safer and more efficient operations of Ferry Commission the St. Johns River Ferry by improving the vehicular access and storage.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Relocation of Ferry offices
This project's purpose is to provide St. Johns River safer and more efficient operations of Ferry Commission the St. Johns River Ferry by improving the vehicular access and storage.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Service & Capital Improvements
This project's purpose is to provide safer and more efficient operations of St. Johns River the St. Johns River Ferry by improving Ferry Commission the vehicular access and storage and long‐term service.
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
63
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR A1A St Johns River Ferry
Area wide ****
US 90
Area wide ****
Area wide ****
County
Duval
Putnam
Baker
Baker
Clay
Map ID
2346
2374
2302
2303
2310
From
Ft. George/Mayport
MacClenny (Baker County)
To
Downtown Jacksonville (Duval County)
Improvement Type
Site Improvements
Local Bus Service
Local Bus Service
Local Bus Service
Local Bus Service
64
Source
Purpose
This project's purpose is to provide safer and more efficient operations of St. Johns River the St. Johns River Ferry by improving Ferry Commission the vehicular access and storage with short‐term enhancements.
Need
The need for this project was identified through coordination with the St. Johns River Ferry Commission and confirmed as part of the planning process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Area wide ****
Area wide ****
Area wide ****
Anastasia Island (Amphitheatre)
Center Street
County
Duval
Nassau
St. John's
St. John's
Duval
Map ID
2332
2370
2378
From
2380
2304
North of Drew Street (Baldwin)
To
Improvement Type
Local Bus Service
Local Bus Service
Local Bus Service
Park and Ride Lots
Park and Ride Lots
65
Source
Purpose
Need
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The need for this project was This project's purpose is to provide local identified through coordination bus service throughout the region to with local governments and enhance accessibility and mobility confirmed as part of the planning choices. process.
Blueprint 2020
The project's purpose is to provide off‐ site parking for the Amphitheatre to provide additional transit access.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CR 210
CR 220 Doctors Inlet Road
Drew Street
Duval Road
Mayport Road
County
St. John's
Clay
Duval
Duval
Duval
Map ID
2381
2316
2305
2336
2338
From
east of US 1
at Hollow Road
at Center Street (Baldwin)
at I‐95
at SR A1A
To
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
66
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Racetrack Road
South of Glen St. Mary
SR 115 Lem Turner Road
SR 115 Lem Turner Road
SR 115 Lem Turner Road
County
St. John's
Baker
Duval
Duval
Duval
Map ID
2382
2306
2337
2361
2362
From
at US 1
at SR 104 Dunn Avenue
at Soutel
at I‐295
To
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
67
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 134 103rd Street
SR 16***
SR 200 SR A1A
SR 200 SR A1A
SR 207***
County
Duval
St. John's
Nassau
Nassau
St. John's
Map ID
2334
2385
2371
2372
2386
From
at SR 228 Normandy Boulevard
at I‐95
east of Yulee
To
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
68
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
County
Clay
Clay
Clay
Clay
Clay
Map ID
2311
2312
2313
2314
2315
From
at Tanglewood
at Old Jennings Road
at Edson Drive
at Wells Road
To
at SR 224 Kingsley Avenue
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
69
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
SR 21 Blanding Boulevard
County
Clay
Duval
Duval
Duval
Duval
Map ID
2318
From
North and South of Bolton Road
2335
at Weconnett Boulevard
2340
North and South of Wilson Boulevard
2341
North and South of SR 134 103rd Street
2360
To
at 105th Street
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
70
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
SR 21 Blanding Boulevard
SR A1A
SR A1A
St. Augustine Airport
US 1
County
Duval
Duval
St. John's
St. John's
St. John's
Map ID
From
2364
North of I‐295
2343
North and South of SR 202 J. T. Butler Boulevard
2379
2383
2384
at Palm Valley Road
at Lewis Speedway Road
To
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
71
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
US 1/SR 15 New Kings Road
US 17 Roosevelt Boulevard
US 17 Roosevelt Boulevard
US 90 Beach Boulevard
US 90 Beach Boulevard
County
Duval
Clay
Duval
Duval
Duval
Map ID
2363
From
Timucuan DRI
2320
at Wells Road
2342
at SR 128 San Juan Avenue
2339
West and East of Kernan Boulevard
2359
at San Pablo Road
To
Improvement Type
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
Park and Ride Lots
72
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Yellow Water Road
Youngerman Circle
Five Points/Core/Brooklyn
Southbank/San Marco
Downtown ‐ Sports Complex
County
Duval
Clay
Duval
Duval
Duval
Map ID
From
2307
North of I‐10
2317
at Argyle Forest Boulevard
2347
2348
2349
Central Station
Kings Avenue Station
To
Brooklyn Station
Southwest of Railroad Tracks (Southbank)
Downtown Jacksonville Jacksonville Municipal Stadium (Bay Street & Main Street)
Improvement Type
Park and Ride Lots
Park and Ride Lots
Skyway Extension **
Skyway Extension **
Streetcar **
73
Source
Purpose
Need
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
Blueprint 2020
The project's purpose is to provide park‐and‐ride lots to promote ridesharing and use of transit options such as BRT.
The project was identified in the Blueprint 2020 Plan and the need was confirmed as part of the planning process.
The project's purpose is to provide an extension of the Automated Skyway Express to the Five Points and Brooklyn neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Blueprint 2020 and 2035 LRTP
The project's purpose is to provide an extension of the Automated Skyway Express to the Southbank and San Marco neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Blueprint 2020 and 2035 LRTP
The need for enhanced transit service to these areas was The project's purpose is to provide a confirmed through the planning streetcar or other fixed‐guideway process. ** The specific technology transit service to the Downtown Sports that will be the efficient and cost Complex neighborhoods from the urban effective to provide this service will core. be determined in subsequent Alternatives Analysis phases.
Blueprint 2020 and 2035 LRTP
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Five Points/Core/Brooklyn
La Villa/Core
Riverside/Avondale
Southbank/San Marco
Springfield
County
Duval
Duval
Duval
Duval
Duval
Map ID
2350
2351
2352
2353
2354
From
Five Points
Transportation Center
Riverside (King Street)
Kings Avenue Station
FSCJ Station
To
Improvement Type
Downtown Jacksonville (Bay Street Streetcar ** & Main Street)
Duval Street & Monroe Street to Ocean
Five Points
Streetcar **
Streetcar **
Baptist Hospital / MOSH & Atlantic Streetcar ** Boulevard
8th Street/ Medical Complex
Streetcar **
74
Source
Purpose
Need
The project's purpose is to provide a new streetcar service to the Five Points and Brooklyn neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
The project's purpose is to provide a new streetcar service to the La Villa neighborhood from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Mobility 2030 Plan
The project's purpose is to provide a new streetcar service to the Riverside and Avondale neighborhoods from the urban core.
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Mobility 2030 Plan
The need for enhanced transit service to these areas was The project's purpose is to provide a confirmed through the planning new streetcar service to the Southbank process. ** The specific technology and San Marco neighborhoods from the that will be the efficient and cost effective to provide this service will urban core. be determined in subsequent Alternatives Analysis phases.
Mobility 2030 Plan
The need for enhanced transit service to these areas was confirmed through the planning process. ** The specific technology that will be the efficient and cost effective to provide this service will be determined in subsequent Alternatives Analysis phases.
Mobility 2030 Plan
Mobility 2030 Plan
The project's purpose is to provide a new streetcar service to the Springfield neighborhood from the urban core.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Downtown Facility
County
Duval
Map ID
2355
From
To
Improvement Type
Transportation Center
Source
Blueprint 2020 and 2035 LRTP
Purpose
Need
The need for the construction of a This project's purpose is to construct a new Downtown transit hub was new Downtown Transit hub to integrate confirmed during the planning services between all modes. process.
Transit Capacity Projects
CSX Transportation
CSX Transportation
CSX Transportation
CSX Transportation
Clay
Clay
Duval
Nassau
2200
2201
2202
2203
at Wells Road
at SR 224 Kingsley Avenue
at SR 104 Busch Drive
at SR A1A (SR 200) / Yulee
Grade Separation
Grade Separation
Grade Separation
Grade Separation
75
SIS Multimodal Needs Plan
SIS Multimodal Needs Plan
SIS Multimodal Needs Plan
SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CSX Transportation
CSX Transportation
CSX Transportation
Florida East Coast Railway
Florida East Coast Railway
County
Duval
Duval
Duval
Duval
Duval
Map ID
2204
2205
2206
2207
2208
From
Beaver Street Interlocking
To
North Rail Corridors Phase 1
at Jacksonville Bridge
Capacity Upgrade
Multi Modal Corridor
Westlake Cecil Commerce Connector
at Bowden Intermodal
Improvement Type
Multi Modal Corridor
Capacity Upgrade
Bridge
76
Source
Purpose
Need
SIS Multimodal Needs Plan
This project's purpose is to improve capacity at the Beaver Street interlock to enhance service reliability.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
North Rail Corridor Feasibility Study
This project's purpose is the construct a new rail connector to reduce rail traffic through downtown which will improve safety. The project will also enhance rail access to the Dames Point and Blount Island terminals.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project's purpose is the enhance access to the Westlake and Cecil Commerce center to support economic development.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project's purpose is to improve track capacity near the Bowden Intermodal Yard to reduce rail crossing blockings and enhance service quality.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
The project will provide repairs and train control technologies on the St. Johns River bridge.
The need for this project was identified based on coordination with railroads during the development of the SIS Multimodal Plan. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jacksonville International Airport
Jacksonville International Airport
Jacksonville International Airport
Jacksonville International Airport
Jacksonville International Airport
County
Duval
Duval
Duval
Duval
Duval
Map ID
2209
2210
2211
2212
2213
From
To
Construction of Runway 7R/25L
Air Cargo Ramp Improvements
Air Cargo Surface Storage
Design & Construct By‐Pass Taxiways
Intermodal Terminal Facility Development
Improvement Type
Construct Runway
Expand Apron
Expand Apron
Construct Taxiway
Terminal Development
77
Source
Purpose
Need
SIS Multimodal Needs Plan
The project need was identified as part of the Jacksonville This project will construct a new International Airport's planning parallel runway to meet future demand. process. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project will construct by‐pass taxiways to improve the operational efficiencies.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
This project will construct additional air cargo capacity to meet future demand.
The project need was identified as part of the Jacksonville International Airport's planning process. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Norfolk Southern
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
County
Duval
Duval
Duval
Duval
Duval
Map ID
2214
2215
2216
2217
2218
From
To
at Norfolk Southern Railway (Near Simpson Yard)
Blount Island / Dames Point Marine Terminals Rail
Blount Island Marine Terminal Berth Upgrades
Blount Island Marine Terminal Facility Upgrades
Dames Point Marine Terminal Berth Upgrades
Improvement Type
Grade Separation
Internal Rail
Docks
Intermodal Transfer Improvement
Docks
78
Source
Purpose
Need
NS CSX SIS Intermodal Connector PD&E
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional on‐ dick rail capacity to meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
County
Duval
Duval
Duval
Duval
Duval
Map ID
2219
2220
2221
2222
2223
From
To
Dames Point Marine Terminal Facility Upgrades
New Cranes for Talleyrand and Blount Island Marine Terminals
Talleyrand Marine Terminal Berth Upgrades
Talleyrand Marine Terminal Facility Upgrades
Talleyrand Marine Terminal Rail
Improvement Type
Intermodal Transfer Improvement
Intermodal Transfer Improvement
Docks
Intermodal Transfer Improvement
Internal Rail
79
Source
Purpose
Need
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the Talleyrand marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
County
Duval
Duval
Duval
Duval
Duval
Map ID
2224
2225
2226
2227
2228
From
To
Blount Island Marine Terminal Facility Upgrades
Dames Point Marine Terminal Facility Upgrades
New Cranes for Talleyrand and Blount Island Marine Terminals
Talleyrand Marine Terminal Facility Upgrades
Blount Island / Dames Point Terminals ‐ Rail and Bridge
Improvement Type
Intermodal Transfer Improvement
Intermodal Transfer Improvement
Intermodal Transfer Improvement
Intermodal Transfer Improvement
Internal Rail
80
Source
Purpose
Need
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
County
Duval
Duval
Duval
Duval
Duval
Map ID
2229
2230
2231
2232
2233
From
To
Blount Island Marine Terminal Berth Upgrades
Blount Island Marine Terminal Facility Upgrades
Dames Point Marine Terminal Berth Upgrades
Dames Point Marine Terminal Facility Upgrades
Harbor Deepening
Improvement Type
Docks
Intermodal Transfer Improvement
Docks
Intermodal Transfer Improvement
Dredging Harbor
81
Source
Purpose
Need
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will deepen the St. Johns River main channel to 48‐ft to meet demand for post‐Panamax ships.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
Jacksonville Port Authority
CSX Transportation
County
Duval
Duval
Duval
Duval
Duval/Baker
Map ID
2234
2235
2236
2237
2238
From
To
New Cranes for Talleyrand and Blount Island Marine Terminals
Talleyrand Marine Terminal Berth Upgrades
Talleyrand Marine Terminal Facility Upgrades
Talleyrand Marine Terminal Rail
MacClenny to Jacksonville
Improvement Type
Intermodal Transfer Improvement
Docks
Intermodal Transfer Improvement
Internal Rail
Purpose
Need
JAXPORT Master Plan
This project will provide new cranes to meet future demand at the port.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
JAXPORT Master Plan
The need for the project was This project will provide gates and other defined during the development of facilities within the marine terminal to the JAXPORT Master Plan. The need improve efficiencies and meet future was confirmed as part of this demand. planning process.
JAXPORT Master Plan
This project will provide on‐dock rail capacity at berths in the Blount Island marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the JAXPORT Master Plan. The need was confirmed as part of this planning process.
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
Upgrade to Accommodate Blueprint 2020 Freight and Passenger Service*
82
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
CSX Transportation
CSX Transportation
Florida East Coast Railway
CSX Transportation
CSX Transportation
County
Duval/Clay
Duval/Nassau
Duval/St. Johns
Duval
Nassau
Map ID
2239
2240
2241
2242
2243
From
To
Green Cove Springs to Jacksonville
Jacksonville to Yulee
Upgrade to Accommodate Freight and Passenger Service
Upgrade to Accommodate Freight and Passenger Service
Upgrade to Accommodate Freight and Passenger Service
St. Augustine to Jacksonville
at US 301 SR 200 Baldwin
Improvement Type
at US 301 Crawford Diamond
Grade Separation
Grade Separation
83
Source
Blueprint 2020
Blueprint 2020
Blueprint 2020
Purpose
Need
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need for additional track capacity to accommodate freight and transit operations was identified in the SIS Multimodal Needs Plan and confirmed through the Blueprint 2020 and Commuter Rail feasibility studies.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Port of Fernandina
Port of Fernandina
Port of Fernandina
Port of Fernandina
City of Palatka
County
Nassau
Nassau
Nassau
Nassau
Putnam
Map ID
2244
2245
2246
2247
2248
From
Berth Improvements
Cruise / Cargo Berth
Rail Track Improvements
at Fernandina Port
SR 100 CR 309D
To
Improvement Type
Docks
Docks
Internal Rail
Access Improvements
Runway expansion
84
Source
Purpose
Need
Port Master Plan
This project will provide additional capacity at berths in the marine terminal to improve efficiencies and meet future demand.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port Master Plan
The project will construct new berths needed to accommodate cruise and larger cargo ships.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port Master Plan
This project will enhance near‐dock and on‐dock rail services.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
Port Master Plan
This project's purpose is to improve truck access to the port within the context of the historic district in Fernandina.
The need for the project was defined during the development of the OHPA Master Plan. The need was confirmed as part of this planning process.
This project's purpose is to expand the runway.
The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Nassau County
CSX Transportation
City of Saint Augustine
Florida East Coast Railway
Florida East Coast Railway
County
Putnam
Putnam
St. Johns
Statewide
Statewide
Map ID
2249
2250
2251
2252
2253
From
Barge Port
at SR 15 Reid Street
To
Historic Commercial Areas
Amtrak Service Miami to Jacksonville
Miami to Jacksonville Upgrade Bolt and Clip System
Improvement Type
Operational and Capital Improvements
SIS Multimodal Needs Plan
Purpose
Need
This project's purpose is to construct capital improvements to improve the operations at the port.
The need for the project was defined during the development of airport master plan. The need was confirmed as part of this planning process.
Grade Separation
SIS Multimodal Needs Plan
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion.
Mobility & Distribution Improvements
SIS Multimodal Needs Plan
This project's purpose is to develop strategies to improve parking management within the historic district of St. Augustine.
The need was identified by the City of St. Augustine. The need was confirmed as part of this planning process.
New Passenger Service
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
Track Upgrade
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
85
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Intercity Passenger Rail
Intercity Passenger Rail
Intercity Passenger Rail
Norfolk Southern
CSX Transportation
County
Statewide
Statewide
Statewide
Duval
Duval
Map ID
2254
2255
2256
2257
2258
From
To
New Orleans to Jacksonville
Jacksonville to Savannah
Orlando to Jacksonville
Soutel Drive to Norfolk Southern Intermodal Yard
North Rail Corridors Phase 2
Improvement Type
Purpose
Need
New Passenger Service
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
New Passenger Service
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
New Passenger Service
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the SIS Multimodal Needs Plan. The need was confirmed as part of this planning process.
SIS Multimodal Needs Plan
This project will improve track capacity to accommodate future passenger rail and meet freight capacity needs.
The need was identified through the NS CSX SIS Connector study performed by FDOT to improve access and operations of the Norfolk Southern intermodal yard.
North Rail Corridor Feasibility Study
The purpose of this project is to consider extensions of the North Rail corridor and to construct a two‐lane roadway within the corridor right of way.
This need was identified through the freight capacity analysis performed in the LRTP to address future rail and truck access needs. The need was confirmed as part of this planning process.
New Connector
Multi Modal Corridor
86
Source
Table 2. Project Purpose and Need Statements for Major Capacity Projects Facility
Florida East Coast Railway
Downtown Transportation Center
Jacksonville Port Authority
Florida East Coast Railway
Intermodal Logistics Center
County
Duval
Duval
Duval
Duval
Map ID
2259
2355
1006
2260
From
at Sunbeam Road
Downtown Facility
To
Spoil Island Connector Bridge
at Shad Road
Intermodal Logistics Center
Improvement Type
Purpose
Need
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through the SIS Multimodal Needs Planning process which included an analysis of the safety record and crossroad congestion. The need was confirmed as part of this planning process.
Transportation Center
SIS Multimodal Needs Plan
This project's purpose is to construct a downtown intermodal facility where multiple transit modes can be connected.
This project's need was identified in the 2035 LRTP and confirmed as part of the Blueprint 2020 plan to provide greater systems integration of the transit modes. The need was confirmed as part of this planning process.
New 2 Lane Bridge
New need identified in the 2040 LRTP by JAXPORT.
This project's purpose is to construct a new bridge for the management and distribution of spoil material associated with dredging the St. Johns River.
The need for this project was identified by JAXPORT as an opportunity to better manage spoil and reduce environmental impacts.
Grade Separation
New need identified in the 2040 LRTP.
This project's purpose is to construct a highway‐rail grade separation to improve safety and traffic flow.
The need for this project was identified through a process which included an analysis of the safety record and crossroad congestion.
New need identified in the 2040 LRTP.
This project's purpose is to construct an intermodal logistics center in North Florida to improve rail efficiencies and the interchange of intermodal traffic between railroads and over the road trucking.
The need for this project was identified as part of the rail system capacity analysis performed during the planning process.
Grade Separation
New capacity
87
Source
SIS Multimodal Needs Plan
This page is intentionally blank.