Five Year Capital Program
Looking Forward: Alpha Street Reconstruction
This Multi-year project involves reconstructing Alpha Street from 6th Avenue to 9th Avenue West. It includes reconstructing the road and replacing all underground infrastructure, curbs/gutters, sidewalks, and possibly streetlights.
Advertisement
Budget: $9,330,000
Strategic Plan Priority: A City that Moves
2023 Funding Source: 50% funded through debenture, and 50% funded through utility rates
2022: Engineering
In 2022, the City issued an RFP and retain an engineering consultant to produce a detailed design for the entire multi-phase project, with construction anticipated to start in 2023.
Timeline: Multi-year project, ending in 2025.
2023: Phase 1
Construction will begin on Phase 1 of the project, which includes the reconstruction and replacement of underground infrastructure on Alpha Street from 6th Avenue West to 8th Avenue West - 260 metres.
2024: Phase include and replacement underground on Alpha Avenue West
2024: Phase 2
Phase 2 of the project will include the reconstruction replacement of underground infrastructure Alpha Street from 8th Avenue West to 11th Street West - 325 metres.
2025: Phase 3
Phase 3 of the project will include reconstruction and replacement of underground infrastructure on Alpha Street from 11th Street West to 9th Avenue West - 190 metres.
2026+: Completion and Maintenance
The full project will be completed, and the road will be maintained as per the City’s Asset Management Plan.