Century 21 Garden Suburb st
social housing on toronto’s edge the BLACK CREEK case study
Century 21 Garden Suburb st
social housing on toronto’s edge the BLACK CREEK case study
Nando Micale, Adjunct Assistant Professor Meng Cao, Miseon Kim, Mark J Kieser, Ke Lin, Zhen Qin, Hao Sun, Xin Tan, Simona Uzaite, Rui Zhang Department of City and Regional Planning, Spring 2014
foreword The University Pennsylvania students took on the challenge of studying the state of social housing in 3 cities on 3 continents as a way to understand and advance the physical, social and financial solutions for social housing in the 21st Century. This course of study included a broad survey of social housing models in recent history and current global trends, as a way to synthesis new approaches for their respective contexts. The students I was fortunate to guide studied social housing in the context of Canada’s open immigration policy, expanding economy, recent policies of disinvesting in their national housing stock, and suburban concentrations of poverty and social housing needs. While policy makers, planners and designers during the later part of the 20th Century focused on revitalizing inner-city neighborhoods blighted by concentrations of poverty and disinvestment, the challenge in many cities is poverty in
suburban locations. In Canada, this is exactly the challenge facing local governments, as they seek public-private models for revitalizing outer-fringe neighborhoods, which are plagued by crime and social isolation. For the City of Toronto, the second largest provider of social housing in North America, the challenge is how market-driven economics can be addressed in suburban, low-value locations. The work presented in this studio report sets forth a model for Toronto, North America, and potentially other developed nations, as they grapple with the future of suburbia and evolving social housing needs in a global economy. Nando Micale, FAIA, AICP / Principal WRT
9
section i
15
section ii
Background
Existing Condition
TABLE OF CONTEXT
Regional Trian Station
Town center: Commercial and institutional b Central park Engagement of surrounding de
To the City
Highway Transit
43 rd
Landscape Plan
Self-sustaining agriculture
leva
en
Be
lt
Localized industry
e tiv uc od Pr
nd La
Range of housing income level
sc ap e
MASTER PLAN
Overall Plan
67
73 Stormwater Management
Green Energy
21st Century Garden Suburb Model
NTRO
59
Greenbelt and boulevards
rd
e Gr
4. Phasing/Relocation Plan
Master Plan
r te en
ry
3. Core Area Plan
4
va
ule
Bo
C wn To
t Indus
21st Century Garden Suburb 2. Landscape Plan 1. Overall Plan
53
section v
Central Park
Bou
section iv
31 5
Introduction to the Studio
section iii
Mixed-use development
77
Efficient Spatial transporta Design tion Sustainability
Housing | 21 Century Garden Subur to Social Studio Approachsection vii Section viii
section vi
Phasing
99
109
Financing
119
Conclusion
SECTION I
What? Where? And Why?
INTRODUCTION TO THE STUDIO
Torontonians seek ideas on adaptive reuse, densification strategies, flexible housing models, site systems and social and civic realm design.
introduction to the studio What? Where? And Why?
While US cities have focused on dedensification, Toronto has identified the re-
Known as “apartment neighborhoods”, these 1960s and 1970s communities represent this next step and Torontonians seek ideas on adaptive reuse, densification strategies, flexible h o u s ing “re-development and models, site densification of the systems and “towers in the park” s o c i al and c i v i c re alm design, as well as sustainable building, green infrastructure, and construction technologies. Having already embarked on model programs both in the urban core and some close in suburbs, the sites that the TCH (who will serve as the client) has identified are in the Jane and Finch Corridor. This area has a diversity that is reflective of an immigrant and minority lower income demographic, found throughout the GTA.
section i | introduction to the studio
Much of the historical social housing models in Toronto are common to North American cities, with low-rise “different apartment blocks market and buil t af ter t he economic depression and a proliferation of forces” high-rises built following WWII. Unlike the US, the Canadian housing market is not deeply subsidized by mortgage interest deductions on income taxes or through Federally sponsored tax credits, and therefore are subject to different market and economic forces and are facing significant end of life-cycle financial and social pressures. These policy and market forces, coupled with Toronto’s growth economy (growing by 40% in the next 25 years) and a legacy of social housing in key locations near the expansion of their Metro, provide for a unique studio exploration for new models of social housing.
development and densification of the “towers in the park” model as the best approach to drive environmental, social, economic and cultural change. Specifically, the Toronto government and the Toronto Community Housing Corporation (TCH) seek to address climate change and economic opportunities in planned growth areas through the re-use of the buildings and underutilized land in these suburban neighborhoods. Regent Park represents Toronto’s most recent mixedincome redevelopment effort, but the shear number of high-rises and dispersion in the GTA will require Toronto to develop a variety of models tailored to a diverse suburban landscape.
11
Growth communities around the globe are addressing affordability and innovation in sustainable development, for which the provision of social housing is key. The US can learn from each of these communities and through a comparison of their approaches. In North America, the greater Toronto Area (GTA) is addressing these issues in an economy fueled by immigration (250 million a year), global investment, and strategic infrastructure projects.
SECTION II
Social Housing Structure
Background
background
background | section ii
16
Social Housing Structure Currently, Toronto is suffering from a Social Housing Crisis, due in part to the disinvestment from national and provincial government policies that do not account for the creation of new social housing development. The waiting list for social housing units has reached approximately 200,000 families in the past 10 years, and will grow in the future according to research. In addition, the existing social
“The waiting list for social housing units has reached approximately 200,000 families in the past 10 years” housing communities lack adequate living conditions for residents due to aging housing stock. The lack of regular maintenance in these social housing communities is a contributing factor to poor living conditions, which may result in a concentration of criminal activity. Unlike the United States, the trend of the housing market in Canada is more focused on market-rate condominiums. Only 5% of the entire housing market in the country is geared towards rental housing, which includes all the social housing units. This rental housing market in Canada is very limited, making it difficult for tenants to find affordable rental housing. This issue becomes more serious as there are growing numbers of immigrants in the country.
These families are more likely to find small-unit rental housing in the city. Additional complications arise due in part to Canada not having adequate national housing programs “projects are not on the government financially viable” level; comparable programs in the U.S. include HOPE VI and Choice Neighborhood. Currently, new social housing projects are mostly managed and initiated by local governments, but the affordable unit numbers are not guaranteed as the projects are not financially viable. Looking back at the timeline of social housing, certain events can explain the reason for the current crisis. After WWII, it was the trend to develop social housing communities all across North America. The federal government was involved in these developments in order to replace the slums. Many social housing communities were built during this time as there were needs of housing for manufacturing labor. Later in the 1970s, the federal government became involved less by removing federal funds for social housing developments. This is due to the Urban Renewal trends as well as the decline of manufacturing market. Finally, the
“removing federal funds for social housing developments” federal government passed responsibilities to provincial governments in early 90s. In 1998, the right was passed to City of Toronto, which resulted in very limited funds from city government.
Assessment of Social Housing in Toronto Social Housing Crisis crisis Waged by labor Federal Government unions & community invoved more organizers
1960
1970
1990
Financial responsibility passed to city of Toronto
1998
2002
INTROCommunity Housing Corporation located in the outer ring suburbs of the city, 1 Toronto inTro: PoSiTion Social HouSinG 1 Timeline | Where Does the Crisis Come from? INTRO on (TCHC) was established in 2002 by the City of Toronto. The City brought together the Toronto Housing Company and the Metropolitan Toronto Housing Corporation. TCHC currently is the largest social housing provider in Canada and the second largest in North America. It provides homes to about 58,500 low and moderate-income households, “TCHC currently is i n c l u d i n g the largest social s e n i o r s , housing provider in families, singles, refugees, recent Canada” immigrants to Canada and people with special needs. Their core business is to provide safe, wellmaintained, affordable homes for residents. So far they have completed and planned a number of revitalization plans for new social housing communities. Their approach to social housing is to create sustainable mixed communities with modern design. Currently, TCHC has either completed or planned a number of new social housing projects all across Toronto. Priority large sites that they plan to work on are mostly
which includes our site. Edgely Village, also known as Black “concentration of Creek , is a properties with priority site for public ownership” social housing revitalization because of its location: adjacent to York University and near a newly planned subway station. There is also a concentration of properties with public ownership, either by TCHC, the city or school board that has potential for redevelopment. By planning through revitalization, TCHC has come up with their own model for social housing projects that are both financially beneficial and can provide RGI (Rent-Gear-to-Income) units.
One of the successful revitalization cases is St. Lawrence. It is located in a historic neighborhood along the waterfront with culturally viable assets. The social housing revitalization plan in St. Lawrence is known for its mixed income, mixed financing, and mixed partnership strategy.
section ii | background
1
Federal Government Feferal SODFHG ÀQDQFLDO responsibility to ontario Government
17
WWii
Federal Government involved less
18
background | section ii
Building | Modular, Rehabilitation, Standard
Regent Park, also located in downtown area, is TCHC’s first and largest social housing project. It is famous for being a successful social housing revitalization plan. One of the most “average successful strategies rate between for Regent Park is market rate its self financing; condo and by creating marketsocial housing rate condos and selling land to private is 4” developers, TCHC can acquire money and construct more social housing. In Regent Park, the rate between market condos and social housing is 5 to 1. This revitalization plan has increased the land value of Regent Park dramatically and has helped the neighborhood change in socially positive ways. Lawrence Heights, located in a suburb within the Greater Toronto Area, is another TCHC social housing project. It is still within its planning phase and is based on Regent Park model. The rate between market-rate condos and social housing units is 3.5 to 1, which means the portion of social housing
Regent Park 2005-2025
1
INTRO
in Lawrence Height is higher than that in Regent Park. From the last three projects that utilized TCHC’s model, we can conclude that their revitalization plan largely focuses on financial, physical, and replacement strategies. The average rate between market rate condo and social housing is 4, which means that they take advantage of a self-financing structure and are able to create mixed income communities. The FAR rate is 1.2 due to their de-concentration and intensification strategy. The communities
“The FAR rate is 1.2” are designed to be more pedestrian friendly after the implementation of revitalization. For the replacement of units, they follow a “One for One” replacement policy. This means that for each demolished unit, a similar unit must be replaced for the current resident. This strategy ensures the relocation process for the current residents on the sites. It should be noted however, that the existing model does not completely solve the problem of the city’s social housing crisis. This model
Alexandra Park 2014
Lawrence Heights 2014
Current TCHC Model
Allenbury Gardens 2015
TRO
• Private-Public Partnership • Relocation on Site
Assessment of Social Housing in Current TCHC Model | St. Lawrence
Regent Park: • 87% self-financing • Market Condo:Social = 5:1 • Public-Private Partnership • Relocation on Site (new construction)
Assessment of Social Housing in Current TCHC Model | Regent Park
Lawrence Heights: • Based on Regent Park Model • Market Condo:Social = 3.5:1 • Public-Private Partnership • Relocation - multiple options
Assessment of Social Housing in Current TCHC Model | Lawrence Heights
section ii | background
NTRO
• Mixed financing
19
RO
St. Lawrence:
Edgeley Village (Black Creek)
background | section ii
20
Lawrence Heights
Regent Park St. Lawrence Downtown
1
does not increase the social housing unit than Black Creek. As a result, it is important number or Assessment lower the city’s of waiting list Housing to create ain new social housing model. Social Current TCHCsuburb Model because of the financial problem. TCHC has to build enough market rate condos to TCHC’s affordable housing development is get the money needed to cover the costs expanding from center city to the outer ring associated with new social housing units. suburbs, which has followed the growth pattern TCHC’s current solution is to cover only of the city of Toronto - radial expansion. The the replacement unit (RGI units) instead of old town is near the waterfront. The original creating more for people on the waiting list.
INTRO
“$110 million financial gap”
We have calculated that if we follow the current TCHC model, there will be a $110 million financial gap for the Black Creek neighborhood; the main reason is due to the low land price in our site. Compared with the three models described above, Black Creek has very low land value. Even in Lawrence Heights, which is also located in suburb area, its land price is 3 times more
blocks were fully planned from scratch, deeply influenced by British Garden City movement. The key pieces of ideas include town center with a park surrounded by commercial and public buildings, boulevard and greenbelt with institutional buildings, localized industry and agriculture in the fringe of the city to make it self-sustaining, and reliable transportation system. The early community developments were pretty successful, and many of them included mixed-income communities.
T
Growth of Toronto Suburbs
Edgeley Village Outer Ring Suburb
section ii | background
As Toronto city continued to expand to the outer ring as we see today, problems
emerged. Because different from the urban area that facilitates mixed-income communities, the outer ring suburb is where affordable housing is concentrated. Our site is a typical suburban affordable housing model in the outer ring of the city. It has poor location, poverty, and underserved services. In 2004, it was ranked as the least livable neighborhood in Toronto area. Other serious issues include aging building stock and crime.
21
The city has been expanding with the construction of transit and extension of the greenbelt along the watersheds. In the inner ring suburbs, housing developments have been inspired from the Garden Suburb model, derived from the Garden City. These developments successfully incorporated social housing.
Inner Ring Suburb
Center City
Major T
Old Town
1
Growth of Toronto Suburbs
INTRO
Planning History on Toronto
Major G sion
22
background | section ii
Building | Modular, Rehabilitation, Standard
Suburban Affordable Housing Model in 1960s: Up Edgeley Village in 1958 Down Edgeley Village in 1964
Regional Trian Station
rd
Bouleva
vard
leva rd
en
rm Fa
Bou le
e Gr
en
nd
y str
lt
ard
lev
e tiv uc od Pr
e tur Na
rm Fa
rm Fa
or
Be lt
r te en
ry
u Bo
C wn To
t Indus
e Gr
a Gr
u Ind
ge Lar
ry Dia
Be
To the City
Central Park
r te en
rd
C wn To
va
ule
Bo
ue
Regional Trian Station
Highway Transit
Central Park
Central Park
Av en
To the City
Highway
leva rd
Garden
Bou
Public Buildings
Bou
Regional Trian Station
nd La
sc ap e
• Tow C C E
• Gree
• Self
• Loca 23
• Ran
• Mix
11
section ii | background
Ebenezer Howard GardenCity CityModel Model Ebenezer Howard Garden
PlanSuburb Town of York (Toronto),1788 • Effic Garden Suburb Movement InnerRing Ringofofthe theCity City Model 21st Century Garden Suburb Model Garden Suburb Model Garden Suburb Movement ininInner Plan forGarden Town offorYork (Toronto), 1788
11
1
History Toronto INTRO History Toronto INTRO INTRO planning History on | Toronto planning History on | Toronto INTRO Planning INTRO Planning
Responding to those stigmas and issues, we take from the Garden City, and propose a 21st century Garden Suburb paradigm that incorporates key elements and improvement of the original Garden City model. We’d like to highlight here a range of housing income levels and self-sustaining agriculture. We distilled two typical suburban housing development models in Toronto: conventional single-family housing neighborhood and high-density housing,which is particularly developed for concentrated affordable housing. “a 21st Century Our proposal is to Garden Suburb” blend those two models in density, and establish a set of frameworks to foster a socially integrated and diversified community. By doing so, we will create levels of public space that bridge productive landscapes and main civic green spaces, as well as public and semi-public spaces. This is a step away from the highly-privatized conventional suburb and underutilized “open field” as a result of “towers in the park”. We will have
•Sust
studio Approach to social Housing | 21 Century G
a series of spatial axis, paths, and nodes, and create hierarchy of them. Mobility for vehicles and pedestrians will be improved by small block size. Main communal spaces “a step away from will be easy to access. the highly-privatized Through the conventional suburb” provision of different housing typologies, the orientation of the buildings, open spaces, and inner block courtyard, safety issues will be addressed. Suitable density will ensure the provision and financial feasibility of affordable housing construction. The public realm will benefit from the density gradient. Public spaces will organize main community services and facilitate mixed-use development. We intend to follow TCHC’s model of separating affordable and market-rate units. However, for the sake of community cohesion, affordable units will be indistinguishable and phase-in the whole development process. A wide range of social programs will be proposed as well.
24
background | section ii
?
++
Conventional Suburb Conventional Suburb
single family housing community Single family housing community
1 1
INTRO INTRO
?
Density Suburb High High Density Suburb
An example: A example: Jamestown high-rise affordable community St.st. Jamestown high-rise affordable community
CenturyNew NewGarden Garden Suburb Suburb 2121Century socially integrated, diversified Socially integrated, diversifiedcommunity community
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
Density Density
Very low density Very low density Close relationship to natural features Close relationship to natural features
Conventional Suburb Conventional Suburb
1 1
INTRO INTRO
Very high density Very high density Highest buildings adjacent to valueHighest buildings adjacent to valuegenerated sites or natural features generated sites or natural features
Density Suburb High High Density Suburb
Gradient density Gradient density Close relationship to features natural features Close relationship to natural High-riseHigh-rise buildings adjacentadjacent to central buildings to communal central space communal space
CenturyNew NewGarden Garden Suburb Suburb 2121Century
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
Open Space Structure: Spatial Organization Open Space Structure: Spatial Organization Sightseeing axis along natural feature
1 1
INTRO INTRO
Hireachical axis to and along open spaces
Almost no spatial nodes Sightseeing axis along natural feature Almost no spatial nodes
Hierarchical and along Functional axisaxis andtopath open spaces spatial nodes Functional axis and path Spatial nodes
Density Suburb High High Density Suburb
CenturyNew NewGarden Garden Suburb 2121Century Suburb
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
Open Space Structure: Levels of Public Spaces Open Space Structure: Levels of Public Spaces
Poor engagement with natural feature Poor engagement with natural Very little hireachical open spaces feature Well maintained major open space Very little hierarchical open spaces Well maintained major open space Highly privatized block spaces Highly privatized block spaces
Conventional Suburb Conventional Suburb
1 1
INTRO INTRO
Poor engagement with natural feature Poor engagement with natural Few hireachical open spaces feature
nature asas productive landscape Nature productive landscape Hierarchical open spaces Hireachical open spaces Great connections between Great connections between different level of spaces different level of spaces Sense of spatial definition sense of spatial definition
“tower the park” open spaces Few in hierarchical “Tower in the park” “open field” in each block “Open field” in each block
Density Suburb High High Density Suburb
CenturyNew NewGarden Garden Suburb Suburb 2121Century
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
section ii | background
Conventional Suburb Conventional Suburb
Sightseeing axis along natural feature
25
Few spatial nodes Sightseeing axis along natural feature Few spatial nodes
background | section ii
26
Street Pattern: Block Street Pattern: Block no block pattern
Huge blocks
Small blocks
dead-end street
Vehicle-friendly
Small blocks both vehicle and pedestrian friendly Both vehicle and pedestrian Street oriented towards natural features friendly
No block pattern “T“ intersections Dead-end street Curved street “T“ intersections Very vehicle-friendly Curved street Very vehicle-friendly
Conventional Suburb Conventional Suburb
1 1
INTRO INTRO
Huge blocks Vehicle-friendly
Density Suburb High High Density Suburb
Street oriented towards natural features
CenturyNew NewGarden Garden Suburb 2121Century Suburb
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
Street Pattern: Surveylability Street Pattern: Surveillability Moderate surveillability on streets
Low surveillability on streets
privatized lotssurveillability with great surveillability Moderate on streets lots with greatspaces LowPrivatized surveillability on public surveillability Low surveillability on public spaces
Moderate surveillability inner blocks Low surveillability on in streets Moderate surveillability inner Low surveillability on publicinspaces blocks Low surveillability on public spaces
Conventional Suburb Conventional Suburb
1 1
INTRO INTRO
Density Suburb High High Density Suburb
Good surveylability on streets, inner blocks, and open spaces Good surveillability on streets, inner blocks, and open spaces
CenturyNew NewGarden Garden Suburb Suburb 2121Century
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
Land Use Land Use Relatively large lot
Highly mixed use
Large lot Unified land use Location Large lotnear street intersections
Location near street intersections Relatively large lot Large surface parking Location near street space intersections Large surface parking space
Highly mixed use or major open space Location near center Location near center or major Garage parking open space P P Garage parking
Location near parking street intersections Large surface space Large surface parking space
1 1
INTRO INTRO
Density Suburb High High Density Suburb
CenturyNew NewGarden Garden Suburb Suburb 2121Century
Studio Approach to Social Housing | 21 Century Garden Suburb
Very few social housing provision Developed mostly for high income people Few social programs Very few social housing provision Few social programs
ConventionalSuburb Garden Suburb Conventional
INTRO INTRO
P
studio Approach to social Housing | 21 Century Garden suburb
Social Housing Integration Social Housing Integration developed mostly for low and moderate developed mostly for high income people
1 1
P
P
income people Developed mostly for low and moderate Distinguishable affordable buildings income people Distinguishable affordable buildings Very few social programs Very few social programs
Density Suburb High High Density Suburb
Mixed income community separated affordable and market-rate units Mixed income community Indistinguishable affordable buildings Separated affordable and market-rate units Affordable units distributed through all Indistinguishable affordable buildings housing typologies Affordable units distributed through all housing typologies Vibrant social activities Vibrant social activities
CenturyNew NewGarden Garden Suburb Suburb 2121Century
studio Approach to social Housing | 21 Century Garden suburb
Studio Approach to Social Housing | 21 Century Garden Suburb
section ii | background
ConventionalSuburb Garden Suburb Conventional
P
P
P
27
unified land use
SECTION III
On the Edge of Toronto
Existing Condition
From 1961 to 1971, the population increased from 1,300 to 33,000. But From 2001
to 2011, the population
decreased from 24,375 to 22,030.
existing condition In the Outskirts of Toronto
Black Creek is located in the outer ring suburb of Toronto, which is about 15 kilometers to downtown (approximately 30 min drive). It is bounded by Jane St., Finch St. and Highway 400.
York. However, due to crime issues, the population decreased by 10 % from 2001 to 2011.
ter
urb
Sub
SITE Jane St
Ou
g Rin
Finch St 5 km
15 km 10 Km DOWNTOWN
2
Black Creek is located about 15 kilometers to downtown. It is on the axis intersection of major roads - Jane St. and Finch St.
bLACk CReek
Existing Condition | Regional Location
section iii | existing condition
Black Creek was first developed as a model for suburb community in the 1960s in response to the rapid urban growth of Toronto. The community was planned to accommodate a socially diverse population and included a substantial amount of public housing. Known for its series of high-rise buildings and, concomitantly, its above average population density. Black Creek experienced astronomical growth from 1961 to 1971 when the population went from 1,300 to 33,000, accounting for more than 40% of the growth in North
33
The site is known for its cultural diversity. Between 1981 and 2001, the number of racialized individuals also increased by 219%. Over 120 languages are spoken in the neighborhood. Being one of the most ethnically diverse communities in the City of Toronto, the community hosts a number of cultural activities, such as “Over 120 Palisade Media languages are Ar ts Academy, International spoken in the neighborhood” Women’s D ay, International Day for the Elimination of Racial Discrimination, Toronto Caribbean Carnival Parade, Canadian
existing condition | section iii
34
Hispanic Day Parade and Driftwood’s Annual Multicultural Festival.
The target area that this plan focuses on is 75.4 acres, which is defined according to land ownership. The land in the target area is mostly public owned, either by school, city, or TCHC. This plan will also propose some suggested implementations in the surrounding area. The site consists a number of physical features that are important to study for a revitalization plan. Jane and Finch Mall is the major commercial center in Black Creek, located at the corner of Jane St. and Finch St. York University is the major institutional center, which is to the east of Black Creek. As the major and largest job center around the target site, it is important to consider staffs, students
HIGHWAY 400
and other people working at York as one of the target demography of this revitalization plan. There is also a utility corridor to the south that has large open space under it. This feature has potential for urban farming and energy production implementation. Black Creek pioneer village is a historical asset. In collaboration with the local conservancy, it functions as a museum where people can experience 19th century lifestyle in Canada.
“potential for urban farming and energy production” The Black Creek itself is the major natural feature in the area. It is a mid-size creek in the Golden Horseshoe region of Ontario, Canada. It flows from the city of Vaughan in Regional Municipality of York to the Humber River in Toronto. On August 19, 2005, Black Creek
JANE ST STEELES ST
SCHOOL OWNED CITY OWNED
BLACK CREEK
TCHC OWNED PRIVATELY OWNED
2
FINCH ST
bLACk CReek
The target area of 75.4 acres is primarily publicly owned land.
HIGHWAY 400
JANE ST STEELES ST
York University is the major institutional center.
YORK UNIVERSITY BLACK CREEK
35
2
FINCH ST
bLACk CReek
HIGHWAY 400
JANE ST
The utility corridor has potential for urban farming and energy production implementation.
BLACK CREEK
UTILITY CORRIDOR
2
FINCH ST
bLACk CReek
HIGHWAY 400
JANE ST STEELES ST
BLACK CREEK PIONEER VILLAGE
Black Creek pioneer village is a historical asset.
BLACK CREEK
2
FINCH ST
bLACk CReek
HIGHWAY 400 HIGHWAY
JANE ST JANE ST
400
Landscape & Hydrology
STEELES ST
STEELES ST
BLACK BLACK CREEK
iMGS, DiaGraMS CREEK BLACK CREEK BRANCH 7RURQWR·V -XO\ ÁRRG OLVWHG DV 2QWDULR·V PRVW FRVWO\ QDWXUDO GLVDVWHU
2
Insurance Bureau of Canada says property damage caused by storm that swamped the GTA on July 8 is more than $850 million.
BLACK CREEK
Ravine
BLACK CREEK BRANCH
2 analySiS
2
FINCH ST
bLACk CReek
Ravine as an opportunity
The Black Creek itself is the major natural feature that has experienced some severe flooding issues and happens to be one of the most polluted waterways.
section iii | existing condition
STEELES ST
existing condition | section iii
36
Transit Connection The transit system within Black Creek is also not pedestrian friendly, partially due to the complicated street pattern and undeveloped public realm. Currently, most of Black Creek does not have “eyes on the street.” The area along the creek is known as the most dangerous place because it is isolated from major streets. The bus stations are currently concentrated around Jane St. and Steeles St., which are the main commercial corridors of the area. There is potential to extend the bus lines into the target area and bring more bus stops into the new neighborhood. The regional bus route shows that the current major transit center is York University, which means connecting to the campus is our opportunity. HIGHWAY 400
JANE ST STEELES ST
20 MIN. WALKING DISTANCE 10 MIN. WALKING DISTANCE STATION
2
bLACk CReek
Transit
The new subway stations, completed in 2016, are within 15-20 minutes walking distance to our target site. The stations are our opportunity to take advantage of and make connection to the greater region. It is believed that the extension of subway can bring in more opportunity around the subway station and raise the land value in the surrounding area.
was the site of heavy flooding as a result of extremely heavy rains that afternoon. Its overflow destroyed a culvert on Finch Avenue. It is also one of the most polluted waterways as much of the Toronto section runs through industrial areas and industrial run off often enters the creek. This plan sees it as both threat and opportunity that we can develop on. It serves as a barrier between the target site and York University. In order to connect our site to York, opening up this divider and bringing in more activities is another opportunity. The current land use shows that the site is mostly residential, with industrial use on the west and institutional and commercial on the east. The major commercial corridor is Jane St. The zoning ordinance basically overlaps with the land use but has stricter requirements. The existing number of units in the site shows that the current residential development concentrates around Jane St. The number of units that allowed by zoning, which represent the capacity of the site, shows the parcels around the new subway station have large capacity of units. By comparing two of them, it is easy to tell that there are a lot of opportunities around the new subway stations. However, “a lot of opportunities our si te i s already built around the new to its capacity; subway stations” t here are fewer opportunities for new developments. As a result, it is important to make connections between our site and the new subway stations area, and up-zone certain parcels accordingly can also be another suggestion.
37
section iii | existing condition
ng | Existing Landoverlaps Usewith Designations The zoning ordinance the current land use. The area shows the concentration of high density along Jane St., especially high rise buildings. By comparing the skylines, there is a high transition of building scales between high rises along Jane St. and townhouses in other parts of the site. As the 21st result, to increase“The the density andCentury minimize
Rebranding Neighborhood
Livable Neighborhood
Public Realm
the impact of the building typology could be another potential for Black Creek. After looking at the existing condition of Black Creek and comparing with the 21st century Garden Suburb approach, the goal of this social Garden Suburb� housing revitalization plan is to:
Community Involvement
Cultural Diversity
Financial Responsible
38
• re-brand the distressed neighborhood existing condition | section iii
• create new livable community through sustainable public realm • involve the culturally diverse community by creating integrated social programs
SKYLINE &STREET VIEW
Jane Street
Shoreham Dr
Jan
eS tre
et
Sho
reha
mD
r
Spatial
• create a financially responsible model for the revitalization plan Analysis
Skyline
SUBWAY
St re e
G
Ja ne
Yo rk
2 analySiS
Drif
t
at e
BL VD
Ja ne
St re et
JANE ST
FINCH ST
twoo d
Ave
Finch Ave
Existing key opportunities in Black Creek neighborhood.
2
bLACk BLACK CReek CREEK
existing density
Existing Density
CREEK
39
Zoningof|Units Capacity: number of units Number (per parcel) Difference.
(per parcel) difference
1,764
SUBWAY STATION AREA
ďźŒ222 125 954
2
section iii | existing condition
bLACk CReek
SUBWAY 967 592
1,042
960
1,374
498 512
191
186 687 224
186 106
43
JANE ST
BLACK CREEK
728
505 655 209 203 146
666
488
112 179
15-20 min walk
Capacity: Number (per Allowed It Zoning| is important to make connections betweenof theUnits target site and parcel) the new subway stations area.
TION ANALYSIS
SECTION IV
Implying General Concept
21st Century Garden Suburb
21st Century Garden Suburb Implying General Concept
• Town center: - Commercial and institutional buildings; - Central park; - Engagement of surrounding developments; • Greenbelt and boulevards • Self sustaining agriculture • Localize industry • Range of housing income levels • Mixed-use development • Efficient Transportation • Sustainability
In our study area, we identified a town center, which is connected to the natural feature, employment center, “take transit station, and advantage of institution by boulevards the existing and green ways. The natural feature existing Jane Street commercial corridor and utility will be enhanced. corridor” We also fully take advantage of the existing natural feature and utility corridor to create productive landscape, as a key component of self-sustained living community. We studied various aspects enabling us to finalize most suitable approaches for the study area.
Highway 400
STATION
INDUSTRIAL
Shoreham St
CENTER Driftwood St
BLACK CREEK
COMMERCIAL GREEN PRODUCTIVE LANDSCAPE EW CONNECTION
3 3
UTILITY CORRIDOR
GeneRAL ConCept General Concept
Steeles St
INSTITUTIONAL
Jane St
21st century garden suburb | section iv
44
After listing the issues to be addressed, let’s move on to applying our Garden Suburb approaches to the physical design. These are the key elements we extract from new Garden Suburb paradigm:
deploy of 21 Century Garden suburb Model The deploy of 21 Century Garden Suburb Model. Deploy of 21st Century Garden Suburb Model
t on
Wa ter fr
Sights eeing St
Driftwood St
Core Area Master Plan tre Area Master Plan Core Area Master Plan.
First, besides preserving the existing ecological corridor, we designed a recreational and productive buffer zone that provides valuable amenities and food to the residents. The landscape belt is further extended into the community through the “green fingers”, which are connected through our green spine to the central park.
the community center. Together with a set of “a main gathering institutional and g re en s p ac e space and destination for nodes along the creek, these community” nodes provide places for community activities and social services.
Building on the green open space structure, a series of axis and nodes are established. Jane St will remain a strategic commercial axis. The central park will serve as a main gathering space and destination for community members with high level of accessibility, it also extend down to
Restructuring the road system, the average street blocks size is about 70 meters by 100 meters. Stores, restaurants and other businesses are located within the walking distance makes the neighborhood vibrant and fun to walk around.
section iv | 21st century garden suburb
Jane St
45
Shoreham St
There are four main types of street: green spine and the waterfront street as boulevards, Jane St as commercial corridor, East-West connections to the periphery as green streets, and waterfront access as a secondary green road.
21st century garden suburb | section iv
Building | Modular, Rehabilitation, Standard
ef ficiency and site responsiveness “the central consideration, park and block orientation ‘green fingers’ is determined by facilitate a lot three aspects: of commercial green features, services and main roads and social programs” solar access. Having more people supervising public space, can help reduce crime and make our streets safer.
Meanwhile, the central park and “green fingers” facilitate a lot of commercial services and social programs.
energ y
Because we have diverse immigrants in our neighborhood, we try to get them involved by introducing some social programs and rebrand the neighborhood by including features as follows: • Welcome Center • Community Kitchen • Trash-Can Art • Community Watch • Mural Arts • Food Stands • Job Training
In general, the highest buildings are concentrated around the central park and grading down to the creek to maximizing
Green Fingers
t on
Wa ter fr
Sights
eeing St North Promenade
Jane St
46
For
the view of creek and university campus for the residents. Medium density development is aligned along Jane St commercial corridor.
Shoreham St
Central park
3 3
Driftwood St
Open Space Structure - “green fingers”. open space structure GeneRAL ConCept Open Space Structure General Concept
South Promenade
s
Axis and Nodes
t on
Wa ter fr
t on
Wa ter fr
GREEN SECONDARY COMMERCIAL
WATERFRONT ACCESS
OPEN SPACE NODE
OPEN SPACE NODE
Jane St
WATERFRONT ACCESS
INSTITUTIONAL NODE
INSTITUTIONAL NODE
Jane St
SECONDARY COMMERCIAL
eeing St
COMMERCIAL
eeing St
GREEN
Sights
Sights
COMMERCIAL
Shoreham St
Shoreham St
Driftwood St
Driftwood St
47
3
open space structure nCept Open Space Structure pt
open space structure GeneRAL ConCept Open Space Structure General Concept
Street and Block Size
Wa ter fr
t on
t on
Wa ter fr
Sights
Sights
eeing St
Average block size: 100m x 70m
Shoreham St
Average block size 100m*70m
Green Spine
Driftwood St
Green Spine
Driftwood St
3
to Student Housing
nCept Street Pattern pt
to Student Housing
GeneRAL ConCept Street Pattern General Concept
Street Pattern
es
Street Pattern
Street Typologies
t on
Wa ter fr
t on
Wa ter fr
Sights
Sights
eeing St
eeing St
1
to Transit Station
Jane St
to Transit Station
Jane St
1
Shoreham St
Shoreham St
4 3
Green Spine
Driftwood St
2
to Student Housing
nCept Street Pattern pt
1
BOULEVARD
2
GREEN STREET
3
SMALL GREEN ACCESS
4
COMMERCIAL STREET
3
4 3
Green Spine
Driftwood St
2
to Student Housing
GeneRAL ConCept Street Pattern General Concept
Street Pattern
Street Pattern
Surveillability
t on
Wa ter fr
t on
Wa ter fr
Jane St
Jane St
SURVEILLED OPEN SPACE
North Promenade
Shoreham St
Central park
Driftwood St
Community Center
eeing St
SURVEILLED STREET
eeing St
SURVEILLED OPEN SPACE
Sights
Sights
SURVEILLED STREET
Pattern nCept StreetStreet Pattern pt
to Transit Station
Jane St
Jane St
eeing St
to Transit Station
Shoreham St
k size
section iv | 21st century garden suburb
k Size
North Promenade
Shoreham St
South Promenade
Central park
3
Pattern GeneRAL ConCept StreetStreet Pattern General Concept
Driftwood St
Community Center
South Promenade
20% of our developed units are affordable which will be incorporated into each development
phase
and
throughout
all the housing typologies, aiming at integrating a diverse social profile into the new neighborhood development.
Density Distribution Wa ter fr
Jane St Co
eeing St
Jane St Co
Sights
eeing St
mmercial Co rridor
t on
Sights
mmercial Co rridor
t on
Wa ter fr
Shoreham St
Shoreham St HIGH MEDIUM LOW
Driftwood St Driftwood St
3
density distribution GeneRAL ConCept Density Distribution General Concept Community Services rridor mmercial Co
rridor
Jane St Co
P
Jane St Co
P
eeing St
mmercial Co
P P
P
Sights
Sights
P
eeing St
section iv | 21st century garden suburb
Wa ter fr
t on
t on
Wa ter fr
49
density distribution nCept Density Distribution pt
Shoreham St
Shoreham St
Driftwood St
Driftwood St
3
Community services nCept Community Services pt
Community services GeneRAL ConCept Community Services General Concept
s
t on
Wa ter fr
Sights
Jane St
eeing St Shoreham St
Driftwood St
Integration nCept SocialSocial Integration pt
onfiguration
Wa ter fr
AFFORDABLE MARKET-RATE
Jane St
Jane St Shoreham St
eeing St
eeing St
Sights
Sights
t on
t on
Integration nCept SocialSocial Integration pt
Housing Unit
Housing Unit Configuration Configuration
Wa ter fr
Shoreham St
Driftwood St
Driftwood St
SECTION V
Framework for Sustainable Development
Master Plan
master plan
master plan | section v
54
Framework for Sustainable Development In the landscape framework, we can see how the concept is applied to the physical site. First, we are looking at the site to look at how our strategy is working with the existing, surrounding areas in the larger scale. Our core area has recommendations for new land-uses based on the existing conditions and the direction of future development. There are existing mixed use zones along Jane, Steels, and some in the York University. “revitalize The largest block of Jane by the new development is mainly for industry mixed use and residential strategy” mixed use located around the new station. Based on this, we are locating our mixed use buildings
A street view of intersecting Jane and Finch Streets.
along Jane and Shoreham roads. Jane is the main traffic road in this community and now it is very infamous for the most dangerous place in the city. “main connections Our goal is to and the three revitalize Jane neighborhood- by the mixed use scale greenways” strategy. Also, Shoreham is the main connection between our neighborhood, station, and York University. It is also main commercial corridor that brings the economic activity from the new development area. According to this strategy, main connections and the three neighborhood-scale greenways have been recommended. It is also derived from our landscape strategy through the integration of existing green infrastructure.
55
section v | master plan
Overall Master Plan of Black Creek Redevelopment.
Overall Plan
Based on the new connection framework, we suggest new bicycle path and bicycle share program. “new bicycle path The two main and bicycle share shelters in the station and the program� civic park will bring more tied connection between the neighborhood and the new metro station. Because the core area is mainly for the low-
income communities, we expect they will rely on the public transit a lot so that we propose to change some bus routes of the existing lines. The three existing bus lines - 35, 106, and 108 - now pass close to the core area to service to the downtown. We changed them to direct connections into the neighborhood and the new station.
Use/Public Realm STEELS
JANE
NEW SUBWAY STATION
56
SCHOOL COMMUNITY CENTER SHOREHAM
master plan | section v
MIXED USE NEW ROAD
Land Use/Public Realm INSTITUTION OPEN SPACE
NEW SUBWAY STATION
JANE
CIVIC OPEN SPACE
STEELS
Land Use: SCHOOL COMMUNITY CENTER SHOREHAM
MiXed use ZoninG AReA
MIXED USE NEW ROAD
INSTITUTION OPEN SPACE CIVIC OPEN SPACE
MiXed use ZoninG AReA
STER PLAN
4
Overall Plan
MASTER PLAN
ating with ng Green Infrastructure
Overall Plan
MAin GReenWAY CiViC GReenWAY subWAY stAtion
Integrating with Existing Green Infrastructure Connection System integrated with existing Green Infrastructure:
STER PLAN
MAin GReenWAY CiViC GReenWAY subWAY stAtion
Overall Plan
m
57
section v | master plan
Pedestrian/Bicycle System Pedestrian/Bicycle System: MAin GReenWAY CiViC GReenWAY biCYCLe pAtH biCYCLe sHARe sHeLteR
Overall Plan
[eXistinG biCYCLe pAtH]
4
tAnCe
MASTER PLAN
Overall Plan
min. 20min.
Proposed Transit Proposed Transit SystemSystem: Line 35 Line 106 WALkinG distAnCe
LINE 108 neW subWAY Line
Overall Plan
10min. 20min.
(station)
Green Infrastructure and Urban Agriculture
Landscape Plan
landscape plan
Green Infrastructure and Urban Agriculture
landscape plan | section v
60
The larger landscape framework is for much further future strategy. It may not be possible with the current funding options, but we hope this framework will help the community understand self-sustainability.
“multiple scale programs in realizing self-sustainability” It is based on three strategies. First, Black Creek conservation area is our main asset in terms of development and stormwater management. Second is improved mobility of the neighborhood through the main connections by using the surrounding infrastructure. Third, it is necessary to have multiple scale programs in realizing self-sustainability. There are main four green zones in both existing and new development areas -
Green connection on productive edge of Black Creek.
schools, parks, productive, and buffer area. The unique feature on the site is the Black Creek edge and the hydro corridor which is now empty green open spaces with electropower line. We developed these two areas turning into productive landscape. To develop the edge of Black Creek, we propose the buffer area to preserve the natural asset based on the Ravine boundary by the city research. To follow the conservation regulatory, we decided to develop the edge area rather than touching
“green infrastructure will bring job opportunities, livable environment, and increase the land value” the conservation area. And we connected all these green areas; we put energy clusters and multiple scale farming programs. This framework is to support the idea of “Self-
61
section v | landscape plan
Landscape Plan.
Landscape plan Green Area INSTITUTIONAL CIVIC PRODUCTIVE buFFeR RAVine bY-LAW eneRGY CLusteR GARden FARM LIVESTOCK
4
Framework that includes activities like community gardens will help the Black Creek residents better understand self-sustainability.
MASTER PLAN
Landscape plan
The buffer area dedicated to restore and preserve Black Creek’s ecology.
3. Urban Agriculture
ties
FieLd
FIGURE 64 - GREATE EMPLOY FOOD RELATED M GREATER TOR
section v | landscape plan
TION PURPOSES ONLY. S, PLEASE CONTACT NG & DEVELOPMENT
63
GARden
FARM LIVESTOCK
Urban Agriculture
March
LAKE SIMCOE
ar panel Proposed Model SMALL_ garden
MEDIUM_field
ss ent
THIS MAP IS FOR GENERAL ILLUSTRATION PURPOSES ONLY. FOR BOUNDARY INTERPRETATIONS, PLEASE CONTACT THE MUNICIPAL/REGIONAL PLANNING & DEVELOPMENT DEPARTMENTS.
LARGE_farm
Municip
Agricultu (Compile
Types of urban agriculture and the most suitable locations for it.
common gardens yard gardens roof gardens balcony gardens CALEDON
community gardens institution gardens park gardens farmer’s market community nursery livestocks compost water management KING
farmsteads greenhouses/solar panel orchards EAST GWILLIMBURY livestocks compost/biomass N E Wwater management MARK ET
GEORGINA
Other D
LAKE SIMCOE
Oak Rid Niagara
BROCK
3. Urban Agriculture UXBRIDGE
sustainable 21 century Garden Suburb”. Finally, by using existing programs such as Size of Company 5 Employees 6 to 20 Emplo SCUGOG For that, we needplan clear|programs for green garden training, farmer LAKE training, and York Landscape self-sustainable 21 Century Garden suburb 21 to 50 Emp GARden A R O R WHITCHURCHSCUGOG University’s 51 to 100 Em energy, stormwater management,AUand urban research STOUFFVILLE Over 100 Em RICHMOND “three HILL agriculture. groups,21we can Garden makesuburb Landscape plan | self-sustainable Century FieLd MASTER VAUGHAN PLAN different c onne c t i on s to our BRAMPTON MARKHAM According to our research, the city of Toronto FARM scales of own community center PICKERING HILLS has Green many urban agriculture programs that ood and Opportunities agriculture” to support our farmlands. LIVESTOCK encourage people to do multiple scales of OSHAWA Through this network, WHITBY UrbanAJAXAgriculture MISSISSAUGA farming. We suggest three different scales we hope green infrastructure will bring job of agriculture: gardens, crop fields LAKE in ONTARIO the oppor tunities, livable CLARINGTON environment, and productive edge, and farmland in the hydro increase the land value. Proposed Model CITY OF TORONTO corridor. Since Toronto already THIS MAP IS FOR GENERAL ILLUSTRATION PURPOSES ONLY. MEDIUM_field LARGE_farm FOR BOUNDARY INTERPRETATIONS, PLEASE CONTACT has many gardening networks SMALL_ garden THE MUNICIPAL/REGIONAL PLANNING & DEVELOPMENT DEPARTMENTS. and programs, our proposed model will work with the existing 0 5,000 10,000 infrastructure. Also, they will PLANS community gardens farmsteads common gardens institution gardens help the community to open cogreenhouses/solar panel yard gardens park gardens orchards roof gardens Base Mapping Source: op stores and a farmer’s market. farmer’s market Ministry of Municipal Affair balcony gardens livestocks Planning & Environmental S community nursery compost/biomass Manufacturing Information We can use this network to livestocks water management compost activate our own commercial water management corridor on Jane and Shoreham.
4
GEORGINA
UXBRIDGE
KING
NEWMARKE T
LAKE SCUGOG
RA AURO
Creek SNAP
BROCK
EAST GWILLIMBURY
CALEDON
RICHMOND HILL
WHITCHURCHSTOUFFVILLE
SCUGOG
VAUGHAN
BRAMPTON
MARKHAM
PICKERING
HALTON HILLS
AJAX
MILTON
WHITBY
OSHAWA
MISSISSAUGA
LAKE ONTARIO
CLARINGTON
CITY OF TORONTO
BURLINGTON
ª
CALEDON
Edgely Apartments
landscape plan | section v
64
BLACK CREEK EDGE _ Agriculture Plots
# Pro o
500’ Black Creek (Protected Area)
4
Irrigation Lines
Flood Protection
MASTER PLAN
Pedestrian Bridge
Landscape BLACK planCREEK | self-sustainable 21 C EDGE _ Existing
# Pro of
4
MASTER PLAN
100’
100’
500’
Nursey + Plots
Landscape Edge
Black Creek (Protected Area)
Landscape plan | self-sustainable 21 C
Nursery
Program Space
Urban Forestry
BLACK CREEK EDGE _ Phase 1
65
section v | landscape plan
# Productive Edge of Black Creek
4
Agricultural Plots
Harvest Space
MASTER PLAN
100’
100’
500’
Nursey + Plots
Landscape Edge
Black Creek (Protected Area)
Crop Expansion
Landscape plan | self-sustainable 21 Century Garden BLACK CREEK EDGE _Phase 2
# Productive Edge of Black Creek
4
MASTER PLAN
100’
100’
500’
Nursey + Plots
Landscape Edge
Black Creek (Protected Area)
Landscape plan | self-sustainable 21 Century Garden
District Energy Systems
Green Energy
green energy
green energy | section v
68
District Energy Systems Cold Canadian winters and hot summers leading to high heating and cooling energy consumption are major energy-related factors that are crucial for the social housing development. We learned in local case of Regent Park that energy usage can be reduced by 50% if the correct and effective district energy system is designed to provide heat and power for the entire neighborhood. Black Creek also has a potential to become self-sustainable city that has successfully integrated energyefficient technologies with local most cost effective renewable energy sources: solar water heating and power, geothermal, and biomass.
“energy usage can be reduced by 50%”
to store abundant solar energy underground during the summer months and distribute the energy to each home for space heating needs during winter months. Hydro corridor would become the core area for green energy development in Black Creek, where four “urban agriculture is different zones a key partner for the of existing biomass energy” i n d u s t r i a l , residential, open space, and institutional uses would be transformed into the energy fields, residential and civic zones, livestock and recreational, and R&D area overseen by York University. University would study, monitor and evaluate local energy production and flow. In addition to the social programming in the area, university
1. Green Energy
For future energy production, potential suppliers would be clustered in nodes and supply energy or treat waste locally Renewable Energy Potentialsof waste-tothrough the direct conversion energy where no landfill is needed. This is where urban agriculture is a key partner for the biomass energy use. Black Creek will develop a network of industrial processes which will use each other’s waste products and energy What which is most recapture suitable for surplus Black Creek community to become self-sustainable? outputs from one another’s processes in an integrated industrial ecosystem. The city will supply energy from a district system to all of the residents from this network. The community will be also heated by the district system designed BLACK CREEK| Energy Strategy Plan PennDesign CPLN702 Global Housing Studio // Spring 2014
eneRGY CLusteR
Biomass Solar Geothermal Wind Smart Grid Natural Gas Long-term Eco Disctrict
- Renewable Energy Potentials MARK KIESER | MISEON KIM | SIMONA UZAITE Prof. Nando Micale
- Green Job Employment/Training Opportun
69
TION PURPOSES ONLY. S, PLEASE CONTACT NG & DEVELOPMENT
section v | green energy
FIGURE 64 - GREATE EMPLOY FOOD RELATED M GREATER TOR
March
LAKE SIMCOE
unities ar panel
Municip
ss ent
Agricultu (Compile
GEORGINA
Energy Clusters marked in blue.
CALEDON
Oak Rid Niagara
BROCK
EAST GWILLIMBURY UXBRIDGE
NEWMARK ET
HILLS
Other D
Size of Company
5 Employees 6 to 20 Emplo 21 to 50 Emp 51 to 100 Em
KING SCUGOG would develop public campaigns well-being. By Garden leveragingLAKE these benefits a Landscape planawareness | self-sustainable 21 Century suburb A R O R WHITCHURCHAU SCUGOG and educate locals about the cost savings successful organizational structure will be STOUFFVILLE RICHMOND and new innovations in the energyHILL production created in the VAUGHAN “energy fields field. local energ y BRAMPTON MARKHAM would supply green industry which PICKERING Residential and civic zones would be more job opportunities would increase integrated to the community level. Black efficiency and OSHAWA WHITBY and training” AJAX MISSISSAUGA Creek area would be used for livestock p r o d u c t i v i t y. CLARINGTON which is huge potential industry in Toronto. Eventually, the existing hydro corridor would LAKE ONTARIO On the west side of the hydro corridor, energy be fully transformed into the local renewable CITY OF TORONTO fields would supply green job opportunities energy production and distribution to avoid and training for the locals in order to any currently lost electricity during long stimulate local economy and enhance social distance transmission.
Over 100 Em
ª 0
5,000 10,000
PLANS
Base Mapping Source: Ministry of Municipal Affair Planning & Environmental S Manufacturing Information
70
green energy | section v
INDUSTRIAL
RESIDENTIAL
ENERGY FIELDS
RESIDENTIAL + CIVIC ZONES
71
YORK STUDENT HOUSING
LIVESTOCK + BLACK CREEK
YORK UNIVERSITY
section v | green energy
BLACK CREEK
Water Quantity and Quality
Stormwater Management
stormwater management
stormwater management | section v
74
Water Quantity and Quality
Being on the outskirts of Toronto, Black Creek has an advantage to explore and replicate some of the successful water management models that have been used to great effect in Toronto area. One of the most successful stormwater management models, low impact development, will be
“a high use of existing and improved pervious surfaces” integrated with small scale hydrologic controls and water treatment mini-stations spread throughout the neighborhood and will be able to address both local water
ROAD
boundary road
ROAD
4
CROP PLOT
quantity and quality issues that Black Creek has been experiencing. Following the local conservation regulations, low impact development practice will be implemented within proposed redevelopment area focusing on a high use of existing and improved pervious surfaces that prevent from severe flooding. A large central park will connect the linear park to the existing stream, as well as four smaller parks that manage stormwater runoff and irrigation. In the core development area, newly installed green roofs, rain gardens and infiltration swales will BLACK CREEK EDGE _ Phase 2 also help to capture stormwater which later
CREEK EXTENSION
agriculture plot
creek extension
CROP PLOT
CROP PLOT
BLACK bLACkCREEK CReekEDGE _ Phase 2 (alt)
black creek
#P
bLACk CReek
Different types of extended green buffer will help to restore the Black Creek’s ecology and control stormwater runoff.
MASTER PLAN
boundary road
agriculture plot
Landscape plan | self-sustainable 21 black creek
agriculture plot
75
TION PURPOSES ONLY. S, PLEASE CONTACT NG & DEVELOPMENT
section v | stormwater management
FIGURE 64 - GREATE EMPLOY FOOD RELATED M GREATER TOR
March
LAKE SIMCOE
ar panel
Municip
ss ent
Agricultu (Compile
Stormwater corridors will be linked via improved streetscapes.
CALEDON
Other D
BROCK
EAST GWILLIMBURY UXBRIDGE
Oak Rid Niagara
By creating water quality monitoring and Size of Company 5 Employees 6 to 20 Emplo LAKE SCUGOG activities, organizing awareness 21cleanup Century Garden suburb 21 to 50 Emp SCUGOG 51 to 100 Em and educational workshops, participating Over 100 Em RICHMOND HILL in new water quality standard enforcement, OurBRAMPTON goal is toVAUGHAN mimic natural hydrologic a long term sustainable water management MARKHAM patterns by using existing natural site features PICKERING plan will be developed. together with distributed smaller scale stormwater controls in water control and Along with OSHAWA a mix of land uses such as WHITBY AJAX MISSISSAUGA energy clusters located along Black Creek high density residential and commercial, and within hydro corridor. All clusteredLAKEcontrol this development willCLARINGTON preserve natural ONTARIO points – stormwaterCITYcorridors will be linked habitats and reduce pressure for any OF TORONTO via improved streetscapes that will be turned future development near the ravine of into the greenways by populating them with Black Creek. By extending the green buffer, trees and serve as integrated stormwater runwe intend to restore the Black Creek’s off system. ecology. This productive edge will produce 0 5,000 10,000 food, jobs, and increase the land value. PLANS As the anchor institution, York University will Additionally, through the construction of Mapping Source: lead public stewardship and participation green roads, better connections can beBaseMinistry of Municipal Affair Planning & Environmental S Manufacturing Information programs which will help to maintain and forged and enhance livability. keep effective newly integrated systems. can be reused to grow food in the gardens of KING productive landscape the edge of Black Landscape planalong | self-sustainable RA WHITCHURCHAURO Creek ravine. STOUFFVILLE
scape Plan
HILLS
GEORGINA
NEWMARK ET
ª
Architectural Elements
Spatial Design
spatial design
spatial design | section v
78
Architectural Elements For the spatial and architectural design of the core area, we have focused on five major aspects of physical environment. By defining them, we intend to create a living environment that promotes communication between people of all cultural backgrounds, provides equal and easy access to facilities and open space, and integrates social elements. In this community, affordable housing is distributed among market-rate housing, though in different buildings. They look the same from “equal and the ex terior and easy access to have equal access facilities and to c ommuni t y open space” s er v i c e s , green s p ac e, s c ho o l s , and major roads. Social elements are designed into various spaces. For
LIVING
instance, community kitchens are located along the productive green edge to provide fresh and healthy foods as well as a place for people with different cultural backgrounds “reduce crime to share foods. Food in park space stands provide food for residents as well and streets” as the university. Trash can art provides children with the opportunity to learn and participate in painting. Mural art would be explored as a way to extend the existing culture of the community. International food festival provides annual celebration as a way to brand the community at the central park, where Community Watch programs would help reduce crime in park space and streets. Finally, the community center and new
Canadian Rambla
100’ Urban Scale
MIXED USE
4
MASTER PLAN
75’
Pedestian Scale
Typology | Building | Green Space
The tree-lined park - the Canadian Rambla - is designed to create an urban feeling.
WORKING
Newly defined green space is a core area for community gatherings
MASTER PLAN
79
4
Typology | Building | Green Space
Mixed Use development
section v | spatial design
HIGHRISE RESIDENTIAL TOWNHOUSE COMMERCIAL COMMUNITY SERVICE
4
MASTER PLAN
Typology | Building | Green Space
Public vs. Private
PUBLIC SEMI-PUBLIC SEMI-PRIVATE
4
MASTER PLAN
Typology | High-rise Shared Space
Townhouse variations
UNIT 1 UNIT 2 CIRCULATION PARKING
4
SHARED SPACE
MASTER PLAN
Typology | Townhouse
To better support these activities and achieve the goals, we focused on the five aspects of spatial design. First, it is important to note the relationship between buildings and open space. There are three major open space typologies. The central park serves all residents of this community and attracts residents of surrounding neighborhoods. It is a large civic space under the surveillance of surrounding mixed-use buildings. The annual food festival will happen here, as a way to brand this community. Children can have education opportunities and participate in the trash can art. The linear park runs through the whole community as a green spine. The tree-lined park, known as the Canadian Rambla, is designed to create an urban feeling. It is pedestrian and bicycling friendly. Sustainable elements, like green roofs, rain cisterns, and rain water gardens will be incorporated in its design. And thirdly, a smaller-scale community garden serving the adjacent residents. This productive garden provides parents with a place to teach their children how to grow vegetables. Immigrants from different places can also
Secondly, we design the relationship between buildings. The three typologies are mixed-use buildings with community services, residential high-rises with “The community ground floor Welcome Center c o m m e r c i a l , plaza is a place and high-rise residential with we want to townhouses. emphasize� The community Welcome Center plaza is a place we want to emphasize. It is between residential and the community service center. It holds events to welcome all new residents. Also, plaza would function as a place for people of different ages to get together. The townhouses provide surveillance and form a comfortable enclosure of the space.
Building -- Open Space
Building -- Building
Thirdly, it is important to increase the public realm for social activities through the design of single buildings, especially for high-rise buildings. We identified three kinds of shared space from public to all, to semi-public for residents of certain floors, to semi-private for close neighbors. People can access to the public intermediate roof space through stairs and elevators from the ground. This bridging space connects different parts of a building for people to get together. The semi-public
Space & Activity
Building
Unit
section v | spatial design
share their cooking recipes using the fresh and healthy food they harvest here.
85
school facilities would provide job training and education services.
4
MASTER PLAN
Typology |
Community Gardens.
| Building | Green Space
Community Garden
spatial design | section V
88
setback roof space is designed for residents of different floors to have a shared space close to them. Different activities can happen here, also with the potential to create jobs, such as managing the roof garden and recreational facilities. The semi-private space is more private for close neighbors to hold events like family parties as well as playground for kids. Then, we designed single buildings, mainly townhouses, to bring positive effect on its surrounding environment. The first is a stacked townhouse adjacent to the creek. The design creates great views for families. The second is facing the community roads, providing surveillance to keep it safe. The third takes
advantage of the elevation difference and creates smooth circulation. All of them are designed to benefit the residents who live in these townhouses as well as the surrounding environment. Finally, we focus on the design of flexible units to promote affordability, meeting the needs of immigrants. Immigrants who buy large units can rent some of the rooms to their relatives who immigrate later and share a common living space. They can also buy a smaller unit first, and when their relatives come, buy the adjacent unit, break down the walls and lease some rooms to the relatives.
Unit Configuration
4
MASTER PLAN
Typology | Unit
Unit Configuration - expanded
4
MASTER PLAN
Typology | Unit
89
Canadian Rambla
4
Sidewalk
Traffic /Bicycle
Pedestrian Plaza
15’
10’
30’
MASTER PLAN
LIVING
Traffic /Bicycle Sidewalk
10’
8’
Rain Cistern
Typology | Building | Green Space
Canadian Rambla
100’ Urban Scale
MIXED USE
4
MASTER PLAN
75’
Pedestian Scale
Typology | Building | Green Space
WORKING
section v | spatial design
Roof Garden
MASTER PLAN
Typology |
| High-rise Shared Space
MASTER PLAN
Typology |
| High-rise Shared Space
SECTION VI
Timeline of Strategy
Phasing
phasing
phasing | section vi
100
Timeline of Strategy To realize the plan, we propose a program of six phases, roughly three years per phase. The program mainly focuses on the land that is owned by TCHC and the City, and the public institutions such as conservation authority and school board. These pieces of land could be directly used, easily acquired or utilized by TCHC.
the residents to be relocated in each phase. Secondly, we identify strategic locations that could define the sub-area and leave the parcels that are potentially more valuable for later phases. Third, we lay out buildings with reference to the location of public amenities. Each phase and each sub-area has affordable units integrated.
There are also two surrounding areas for which we have physical plan and design. But since the private parties control them, we don’t consider phasing and financing for the development on these peripheral areas.
As mentioned earlier, in the traditional TCHC model, land is sold to private developers and money is acquired to replace affordable units. Based on this, we identified potential partnerships that enhance financial feasibility. In addition, social housing in prior phases could stage the residents to be relocated in the following phases. The phasing plan
The general strategy of phasing follows three principles. First, we ensure that the development capacity can accommodate
PERIPHERAL AREA PHASE1 AREA PERIPHERAL PHASE2 PHASE1 PHASE3 PHASE2 PHASE4 PHASE3 PHASE5 PHASE4 PHASE6 PHASE5
4
PHASE6
MASTER PLAN Core Area and Peripheral Area MASTER PLAN Core Area and Peripheral Area
Overall phasing based on zones and peripheral area.
2220
Overall Units
AffoRdAbLE
AffoRdAbLE
MARkET-RATE
MARkET-RATE
574
verall units
AffoRdAbLE
MARkET-RATE
MASTER PLAN
101
4
T-RATE
overall units
AffoRdAbLE
MARkET-RATE
MARkET-RATE
106
4
RATE
hase 1
AffoRdAbLE
MARkET-RATE
MASTER PLAN
Phase 1
Relocation Plan 1
AffoRdAbLE
AffoRdAbLE
106
4
RATE
elocation Plan 1
AffoRdAbLE
MARkET-RATE
MASTER PLAN
Relocation Plan 1
Phase 2
AffoRdAbLE
AffoRdAbLE
MARkET-RATE
MARkET-RATE
781
RATE
hase verall2units
781
108 106
4
AffoRdAbLE
MARkET-RATE
MASTER PLAN
overall2units Phase
section vi | phasing
Phase 1
AffoRdAbLE
$
$
$
5
Phasing Strategy
2
city developer
financing for phasing
$
3 $
city
$
city developer
$
4 $
1
v
v $
5 $
BanK
v
v
v
city developer
school board developer
conservation
conservation
$
6 $
102
phasing | section vi
consists of money and population flow within development on the south side could the site. further reinforce the value along the road. A community center will be built on this Overall, we propose to develop 574 affordable southern site as well. units, and 2,220 market-rate units in six phases. In Phase 4, we exchange the riverfront land to Conservation Authority for this parcel that In phase 1, a loan will be taken out to build they own on the north. By building two new 106 affordable units on TCHC owned land. schools and a community green, we hope to The lender of set the tone for the whole development. After “leveraging the the loan could the phase 4 is finished, two existing schools land value on be the bank or will be demolished and the land they currently the Jane Street� the government. occupy are freed for further phasing. The units could hold the residents relocated from the current In Phase 5, the central spine and the central senior housing and affordable family housing, park will be finished on the school board and free the land to be developed in the land. One more school will be built by private second phase. developers as a part of the land sale package. Additionally, TCHC will build a parking garage In Phase 2, we aim at leveraging the land on this parcel for the Conservation authority, value on the Jane Street, which is the North- and in return get the right to develop the land. South axis. Commercial properties will be built in the Jane-Driftwood corner to anchor the In the last phase, the land on the riverfront, retailers. The relocation follows the principles which we deem as the most valuable land, mentioned earlier. will be developed. We could seize the highest land value by putting it at the last phase. Traditional TcHc Model After residential units are built on the north area of Shoreham Street, comprehensive
school board developer
AffoRdAbLE
AffoRdAbLE
Relocation Plan 2
MARkET-RATE
MARkET-RATE
781
781
108 106
elocation Plan 2
AffoRdAbLE
MARkET-RATE
MASTER PLAN
103
4
-RATE
Relocation Plan 2
Phase 3
MARkET-RATE
MARkET-RATE
CoMMuNITy CENTER
CoMMuNITy CENTER
233
233
781
781 128 108 106
4
ATE
erall ase 3units
AffoRdAbLE
MARkET-RATE
MASTER PLAN
overall3units Phase
AffoRdAbLE
AffoRdAbLE
Relocation Plan 3
MARkET-RATE
MARkET-RATE
CoMMuNITy CENTER
CoMMuNITy CENTER
233
233
781
781 128 108 106
4
T-RATE
Relocation Plan 3
AffoRdAbLE
MARkET-RATE
MASTER PLAN
Relocation Plan 3
AffoRdAbLE
AffoRdAbLE
Phase 4
MARkET-RATE
MARkET-RATE
CoMMuNITy CENTER
CoMMuNITy CENTER SCHooL
SCHooL
130
130
233
233
781
RATE
hase verall4units
781
42 128 108 106
4
AffoRdAbLE
MARkET-RATE
MASTER PLAN
overall4units Phase
section vi | Phasing
AffoRdAbLE
AffoRdAbLE
phasing | section vi 104
Relocation Plan 4 AffoRdAbLE
AffoRdAbLE
MARkET-RATE
MARkET-RATE CoMMuNITy CENTER
CoMMuNITy CENTER
SCHooL
SCHooL
130
130
233
233
781
781
42 128 108 106
elocation Plan 4
AffoRdAbLE
MARkET-RATE
MASTER PLAN
105
4
T-RATE
Relocation Plan 4 AffoRdAbLE MARkET-RATE
MARkET-RATE
CoMMuNITy CENTER
CoMMuNITy CENTER
SCHooL
SCHooL 886
886
130
130
233
233
110 781
781
42 128 108 106
4
T-RATE
hase verall5units
AffoRdAbLE
MARkET-RATE
MASTER PLAN
overall5units Phase
Relocation Plan 5 AffoRdAbLE
AffoRdAbLE
MARkET-RATE
MARkET-RATE CoMMuNITy CENTER
CoMMuNITy CENTER
SCHooL
SCHooL
886
886
130
130
233
233
110 781
781
42 128 108 106
4
T-RATE
Relocation Plan 5 190
AffoRdAbLE
MARkET-RATE
MASTER PLAN
Relocation Plan 5 190
Phase 6
AffoRdAbLE
AffoRdAbLE
MARkET-RATE
MARkET-RATE
CoMMuNITy CENTER
CoMMuNITy CENTER
SCHooL
SCHooL
886
886
130
130
233
233
80 110
781
ET-RATE
overall6units Phase
781
42 128 108 106
4
AffoRdAbLE
MARkET-RATE
MASTER PLAN
overall6units Phase
section vi | phasing
Phase 5
AffoRdAbLE
SECTION VII
Project Funding and Realization
Financing
financing
Project Funding and Realization
financing | section Vii
110
In the traditional model, TCHC sells land to private developers to cover the replacement costs. We also intend to add partnership to the model.
Project-based Tool:
a. ppp b. tif c. tax credit City-wide Policy:
d. corporate tax e. sales tax
Right now the land price is around $20 per square foot. Under the traditional model, there is a 111-million-dollar gap. Only less than onefourth of our target number can be built.
“111-million-dollar gap� Take Lawrence Height as an example. Compared to the study area, it is half as far from downtown Toronto. The land value at Lawrence Height could sustain a 4-1 market to affordable ratio. However, in the study area, the land price is only one third that of Lawrence Height given its remote location and its low density characteristic. As a consequence, the traditional model only works here if the FAR in the area is up zoned to around 6, which does not agree with local market demand. Although our site is far from downtown, the new subway station and this revitalization plan will largely increase the land price. We came up with 3 price baselines for our financial plan. In the first, the land price remains the same as present with the financial gap of $111 millions. In the second baseline, the land price grows 50% to $30/sqft, and then the gap declines to about $99 millions. In the third, the land value increases aggressively 100% to $40/sqft, and the gap is reduced to $93 millions.
city developer
$
4
$
5
city developer
school board developer
conservation
conservation
$17,086,006
$12,873,553
$15,960,182
$25,238,064
$27,197,810
$25,758,000
$
$
3 $
city developer
$
$
6
school board developer
$
Traditional TCHC Model of Financial Strategy and Financial Gap.
financing financial gap
To fill the gap, we came up with our new model that incorporates multiple solutions. We devised five strategies in total. Three of them are specific to our project and the rest are citywide policies.
structure to replace the cash flow from the current ground parking space. Then TCHC could acquire the land, sell the land to the private sector, and build more affordable units.
The first strategy is to form partnerships with other parties in the “exchange the area. By trading the new school land they own with with currently the buildings they underutilized need, the TCHC can capitalize upon its campus� expertise in property development while getting appreciating land at a cheap price.
In Phase 5, the school board is our major partner. In this phase, TCHC could build a school for the school board, and propose to exchange the new school with currently underutilized campus. The school board acquires a new facility by giving out the strategic locations that are much more valuable to commercial development. The plan benefits both parties in the transaction, which is why we consider this scheme feasible.
One of the partners in the area is the conservation authority. Their mission is to preserve the natural treasure of the Black Creek area. We provide them the strip of land by the river and in return build a parking
One way to push this partnership one step further is to let TCHC play a more entrepreneurial role. In prior projects, TCHC does not contribute any cash equity towards the market project, thus having no
section vii | financing
5
2
$111,981,460 461 units
111
city
$
$
1
$
BanK
GAP
$
$20 /sqft
financing | section vii
112
obligation or risk of market project. However, in such an area where the land value could be elevated by the design and plan, TCHC could be more speculative. One possible attempt is to build affordable student housing with York University and sign a long-term lease with the university. The cash flow from the project could support more sustainable affordable housing development. These partnerships essentially trade fixed construction costs with land held by other parties in the “TIF has never been area. The practiced in Toronto� prerequisite for the approach to make money is that land value is high enough to exceed the construction cost. When the starting land value is below $30, the partnership, to the opposite, enlarges the gap. However, the approach transfers the liability of housing development to that of providing public
A.PPP $40
B. TiF
$12,485,413 $29,383,509
The second solution is to finance the public facilities and amenities through a site-wide TIF. TIF has never been practiced in Toronto. After looking at some of precedents in the US from different cities, we concluded the following. The fixed coupon rate was decided through the risk of projects and the size of the bond. The higher the coupon rate, the lower the proceeds from the TIF. In our TIF model, we calculated the expected revenues in different coupon rates through all three baselines with different coupon rates. And this is how much gap it could fill given different assumptions. The Low Income Housing Tax Credit has been one of the most common methods for social housing financing in the US. There are tax credits in Canada, but they cannot be traded,
C. Tax Credit $93,763,497 350 units
/sqft
$30
facilities, which could be covered by more financing tools.
$14,617,938
$99,854,992 372 units
/sqft
-$6,268,405
$20
$13,348,220
/sqft
-$12,132,155
financing Tax increment financing
$111,981,460 461 units
Black Creek
$20/sqft
Lawrence Heights
$65/sqft
113
Central Downtown
section vii | financing
Location and Price Comparison.
ncing Location and Price comparison and thus does not commit private money raise from $70 million to $91 million for the to public projects. The money is essentially proposed project. received from the federal government. The program is highly competitive in the US. If a Corporate surtax is a more direct financial source of affordable housing. Toronto is such “The Low Income Housing Tax a city where immigrants play an important Credit has been one of the most role in the labor force. Businesses in the city enjoy the cheap labor without paying for their common methods for social living expenses. This corporate surtax could housing financing in the US� establish the nexus that connects the low labor project is located in a HUD designated high cost in the city to the prosperity of commercial cost area, the eligible basis receives a 130% activities. There are currently around 60,000 adjustment. If similar tools in the US can units under TCHC’s management. Assuming be utilized, TCHC could sell the credits to the buildings need renovation or replacement investors to raise the capital; the gap can be every 30 years, adding 250 percentage points largely filled. Same rule applied, the tool could to the current corporate tax rate could help
B.TiF B.TiF
B.TiF
TiF ComPARABLeS in THe UniTeD STATeS YeAR
iTY
AnnUAL TAx inCRemenT
CoUPon RATe
114
TiF ComPARABLeS in THe UniTeD STATeS RABLeS in THe UniTeD STATeS iTTsBurgH, Pa 2001 $6,100,000 6.5%
AnnUAL TAx CiTY ew YeAR YorK ciTY, nY 2002 inCRemenT
financing chapter| |section Building vii
CoUPon YeAR $23,000,000 RATe PiTTsBurgH, Pa $8,250,000 2001 MinneaPoLis, Mn$6,100,000 2004 2001 6.5% new YorK ciTY, nY 2002 as 2005 Y Vegas, 2002 nV $23,000,000 5.0%$14,000,000 MinneaPoLis, Mn 2004 eaTTLe, 2005 $15,000,000 2004wa $8,250,000 11.0% Las Vegas, nV 2005 2005 iL $14,000,000 7.8%$12,000,000 Hicago, 2006 seaTTLe, wa 2005 2005 5.9% acKsonViLLe, fL$15,000,000 2007 $5,000,000 cHicago, iL 2006 2006 $12,000,000 6.0% KLaHoMa ciTY, oK JacKsonViLLe, 2007 fL $9,500,000 2007 2007 $5,000,000 9.5% oKLaHoMa 2007 ouisViLLe, KY 2011 ciTY, oK $6,000,000 oK 2007 $9,500,000 6.9% LouisViLLe, 2011 enVer, 2012 KY7.7%$7,000,000 2011co $6,000,000 DenVer, co 2012 wasHingTon, Dc$7,000,000 2013 $18,000,000 2012 12.0% wasHingTon, Dc 2013 2013 $18,000,000 4.9%$15,500,000 aLLas, TX 2014 DaLLas, TX 2014 2014 $15,500,000 5.9%
AnnUAL TAx inCRemenT 5.0%
CoUPon RATe
$23,000,000 7.8%
5.0% CoUPon RATe 11.0% 6% 7% 7.8% 8% 9% 5.9% 10% 6.0% 6% 9.5% 7% 8% 6.9% 9% 10% 7.7%
neT PRoCeeDS To in DiFFeRenT RATe CoUPon
neT PRoCeeDS
RATe Toin PRojeCT neT PRoCeeDS To DiFFeRenT RATe neT PRoCeeDS RATe $6,100,000 6.5% To in DiFFeRenT 6% $47,057,866 11.0% $8,250,000
5.9%
$14,000,000
6.0% $40
$15,000,000
9.5%
$12,000,000
6.9% $5,000,000
$30
$9,500,000 7.7% $6,000,000 12.0% $7,000,000
4.9%
$18,000,000
5.9% $20
$15,500,000
12.0% 6% 7% 4.9% 8% 5.9% 9% 10%
7%
$40
CoUPon RATe 6% 7% 8% 9% 10%
neT PRoCeeDS 8% To PRojeCT 9% $47,057,866 10% $36,003,842 $28,211,695 $21,990,454 6% $16,898,096 7%
$40
$30
8%
$44,575,116 9% $34,495,225 10% $27,115,612 $20,886,343 $16,225,914 6%
$20
$30
7%
$42,092,366 8% $32,909,202 9% $25,480,375 10% $19,782,232 $15,553,733
$20
6% 7% 8% 9% 10% 6% 7% 8% 9% 10%
neT PRoCeeDS $36,003,842 To PRojeCT $28,211,695 $21,990,454 $47,057,866 $36,003,842 $16,898,096 $28,211,695
$21,990,454 $44,575,116 $16,898,096 $34,495,225 $27,115,612 $44,575,116 $20,886,343 $34,495,225 $27,115,612 $16,225,914
$20,886,343 $16,225,914
$42,092,366 $32,909,202 $42,092,366 $25,480,375 $32,909,202 $19,782,232 $25,480,375 $19,782,232 $15,553,733 $15,553,733
5C.
Tax increment Tax Credit financing Tax increment financingfinancing financing Tax increment financing ng HCA multiple=100% PHASe
PHASe
PHASe
PHASe
PHASe
PHASe
AnnUAL CReDiT (THoUSAnD)
2,001
2,189
2,544
835
2,251
1,611
PV oF CReDiTS (THoUSAnD)
12,298
13,454
15,629
5,134
13,833
9,900
$70,000,000 HCA multiple=130% AnnUAL CReDiT (THoUSAnD)
PHASe 2,601
PHASe 2,846
PHASe 3,306
PHASe 1,086
PHASe 2,927
PHASe 2,095
PV oF CReDiTS (THoUSAnD)
15,987
17,490
20,318
6,675
17,984
12,870
$91,000,000
5
financing Tax credit
the city raise enough money to renovate and replace old stocks.
58,500 uniTs THrougHouT THe ciTY
Add-on Tax Rate
0.25%
1.00%
2.50%
Tax Revenue (mil)
53.1
212.3
530.8
Buildable Units
212
849
2123
Assumption: revenue distributed pro rAtA to populAtion
e. Corporate Tax Add-on Tax Rate
5
0.25%
0.50%
1.00%
Tax Revenue (mil)
82.6
165.1
330.3
Buildable Units
330
661
1321
financing corporate Tax
Assumption: revenue distributed pro rAtA to populAtion
section vii | financing
D. Corporate Tax
115
Another possible subsidy for public facilities is sales surtax. The tax revenue could be used to improve public transit, build schools and church or build garage. There i s a t r an si t improvement tax at the rate of 0.25% in s ever al c oun t i e s in Minne s o t a. Also in Texas, the rate ranges from .25% to 1%. The rationale is that public improvement helps enhance the local commercial opportunity. As mentioned earlier, the partnership could shift the liability of housing development to building public facilities. With the tax revenue, this shifted liability could be covered.
SECTION VIII
Vision in Mind
Conclusion
During Spring Break, prof. Nando Micale and students had the opportunity to travel to Toronto (Canada), where they visited Black Creek, Regent Park, and St. Lawrence neighborhoods. They also met
and exchanged ideas with local
planners.
conclusion Vision in Mind
section viii | conclusion
green-space focused one. We also proposed programs that could turn underutilized Black Creek to a productive landscape and a regional destination, and pair it up with various social programs. Finally, we devised a financial model that could sustain the revitalization in such a remote area. With this plan, we hope to realize our goal of building the 21st century Garden Suburb.
121
To conclude, Toronto is faced with a housing crisis characterized by a long waitlist for social housing and the deterioration of the current stock. The disinvestment of national and provincial money further aggravates the situation. We came up with a design that seizes the opportunities on the site, and changes the current street-oriented community pattern to a pedestrian friendly,
Design and Text: CPLN 702 Studio (PennDesign) Print: Replica Creative
University of Pennsylvania Department of City and Regional Planning Spring 2014
acknowledgments We would like to thank the following people for their support and guidance throughout this project: CPLN 702 Global Housing Studio Instructors: Nando Micale, Evan Rose, Stefan Al PennPlanning: John Landis (City of Regional Planning Department Chair), Kate Daniel Toronto Community Housing Corporation (TCHC): Kelly Skeith (Development Manager) Planning Alliance (Toronto, CA): John van Nostrand (Founding Principal) Toronto City Planning Division: Kyle Knoeck (Senior Planner) Wellesley Institute (Toronto, CA): Michael Shapcott (Director of Afford. Housing & Social Innovation)
pennplanning | cpln 702 studio | spring 2014