Primary school Design 2013

Page 1

EDUCATE TOGETHER PRIMARY SCHOOL

4TH YEAR

Dublin School of Architecture



4TH YEAR 2012-2013

Dublin School of Architecture

Dublin School of Architecture

1

4th Year, 2012 -2013


Contact: Paul Kelly + Patrick Flynn 4th year Module Coordinators Head of School Orna Hanly Dublin School of Architecture Dublin Institute of Technology Bolton Street Dublin 1, Ireland Tel: +353 1 4023690 www.dublinschoolofarchitecture.com www.dit.ie/architecture/urban-design/ Typeface: Gil Sans + Helvetica Design: Paul Kelly Š Dublin School of Architecture Press. All rights reserved. All information presented in this publication is deemed to be the copyright of the creator or the Dublin School of Architecture, unless stated otherwise. First Edition

Dublin School of Architecture

2

4th Year, 2012 -2013


CONTENTS

Dublin School of Architecture

3

Introduction Project Brief Site Laura Carroll Shane Phelan Cillian Wright Stephen Richardson

07 08 11 12 16 20 22

David Lally Fiona Canavan Ashling Cleary David McGowan OisĂ­n Jacob Dean Murphy James Hanlon Class List

26 28 30 34 38 40 42 46

4th Year, 2012 -2013


Dublin School of Architecture

4

4th Year, 2012 -2013


EDUCATE TOGETHER PRIMARY SCHOOL Peter Crowley Patrick Flynn Emma Geoghean Paul Kelly

Jim Roche

Dublin School of Architecture

5

4th Year, 2012 -2013


Dublin School of Architecture

6

4th Year, 2012 -2013


Introduction The introduction of a three plus two structure in the school has meant the Fourth and Fifth year programmes have shared a number of lectures series in the Advance Design Studio under the theme of “Schools of Thought�. A wide range of educational typologies will be investigated across the two years. In Fourth Year we have elected to investigate a new model for Department of Education and Skills schools, seeking to challenge the existing pedagogical norms with new ways of thinking about how and why we educate ourselves. Educate Together are our client body setting a context and ambition for the school within the scope of the Department of Education and Skills programme. For the purposes of this project a proposed site for an Educate Together School in Stepaside was selected. The projects was framed in the context of a Tectonic approach to site and programme, we posed the question given the immediate need for additional school places in Ireland at present what would become of these school buildings in the future? Might the building have the potential to adapt to a new community use, would the building touch lightly on the site and allow the land to return to a natural state in the future? Following their analysis of both the brief and the site each student adopted a personal approach to the constraints and opportunities presented. The projects in the following pages are a selection of this work.

Patrick Flynn Paul Kelly

Dublin School of Architecture

7

4th Year, 2012 -2013


Dublin Institute of Technology, Bolton Street. Dublin School of Architecture - Department of Architecture and Urban Design Degree Course in Architecture, Fourth Year 2012-2013 Stage 4 ADS VII Arch 4102 Project No. 2 Primary School - anticipating changing demographics Introduction Following through with the theme “Schools of Thought” the brief is to design a primary school. This project is intended to be derived from an idea focused on a construction method. There is a need for additional primary school places in the coming years, in time these buildings

could become obsolete, the task of his project is to examine the possibilities presented by develop an attitude to material and a construction method. The emphasis is on the Tectonic and how a building can adapt to changing circumstances.

Living & Learning and Assembly “Building art is a synthesis of life in materialised form. We should try to bring in under the same hat not a splintered way of thinking, but all in harmony together.” Alvar Alto “I don't divide architecture, landscape and gardening; to me they are one”. Luis Bargain “Proportions are what makes the old Greek temples classic in their beauty. They are like huge blocks, from which the air has been literally hewn out between the columns”. Arne Jacobson The relationship between decisions about material, structure and detail have significant impacts on the reading of a building and the confirmation or undermining do an architectural concept. This studio will examine the relationship between concept and the implemented

PK_2013_03_15

Dublin School of Architecture

ADS_VII

8

4th Year, 2012 -2013


architectural proposal. The means of this examination will be assembly drawings and sectional models supported by general arrangement plans and sections.

Brief Your brief is to design an primary school, the building should accommodate spaces described in the attached Department of Education and Science brief and respond to the Educate together ethos providing a school that is Multi-denominational, Co-educational, Child-centred and Democratically run. 0Stage 1 - Observation & Recording Information Tuesday 19.03.13 Site visit to the site. Presentation of site description and subsequent site analysis. Each student will examine the proposed site, gather detailed information on the following topics

PK_2013_03_15

Dublin School of Architecture

ADS_VII

9

4th Year, 2012 -2013


Dublin School of Architecture

10

4th Year, 2012 -2013


Aerial View of Site Dublin School of Architecture

11

4th Year, 2012 -2013


Laura Carroll Tectonics - Primary School

Dublin School of Architecture

12

4th Year, 2012 -2013


Dublin School of Architecture

13

4th Year, 2012 -2013


Laura Carroll Tectonics - Primary School

Dublin School of Architecture

14

4th Year, 2012 -2013


Dublin School of Architecture

15

4th Year, 2012 -2013


Tectonics - Primary School

Dublin School of Architecture

16

4th Year, 2012 -2013


Tectonics - Primary School

Dublin School of Architecture

17

4th Year, 2012 -2013


Shane Phelan Tectonics - Primary School

Dublin School of Architecture

18

4th Year, 2012 -2013


Shane Phelan Tectonics - Primary School

Dublin School of Architecture

19

4th Year, 2012 -2013


Cillian Wright Tectonics - Primary School

Dublin School of Architecture

20

4th Year, 2012 -2013


Cillian Wright Tectonics - Primary School

Dublin School of Architecture

21

4th Year, 2012 -2013


Stephen Richardson Tectonics - Primary School

F

t g s

1 f

E

Dublin School of Architecture

22

4th Year, 2012 -2013


Stephen Richardson Tectonics - Primary School

-30 Sedum Roof Matt on -Filter membrane on -50 Egg crate drainage layer filler with gravel on -Filter membrane on -150 EPS insulation -3 EPDM solvent welded membrane mechanically anchored through to roof deck on -100 Cross Laminated Timber Roof plates fixed to -100x400 Glulam Beams at 1300/2300 ctrs

-Zinc Standing Seam Roof fixed to Gal Steel Folded metal plates at 100ctrs fixed to CLT

-Zinc Standing Seam Roof fixed to Gal Steel Folded metal plates at 100ctrs fixed to CLT Internal Plywood storage units encased around the external wall.

-EX 100x25 SW Larch vertical T&G Cladding fixed with Austenitic S/S nails on -50x50 SW Horizontal Battens ate 400 ctrs on -Breather Membrane on -18 OSB on -200x44 SW Studs at 400 vertical ctrs with 200x44 SW sole and head plate fixed to sole plate. -With 200 cellulose insulation between -Vapour Check -50x25 vertical battens at 400ctrs -With internal Plywood storage units encased around the external wall.

-SW Painted Window Frame to RAL 1013 with top hung opening sections with 4-12-4 double glazed argon. High and low level opening sections to provide natural ventilation.

-15 Poured Resin floor finish on Notched Floor Panel -18 OSB on -150x44 SW Studs at 400 vertical ctrs -With 150 cellulose insulation between -Vapour Check -18 OSB on

15 Laminated Glass balustrade fixed with S/S fixings to 100x150 Glulam Columns

Ex 75x44 SW Decking boards at 85 ctrs

Gal Steel Shoe fixed to the Concrete Foundation Pad, supporting Inclined Glulam Column

400x400 Concrete Foundation Pad

Dublin School of Architecture

23

4th Year, 2012 -2013


Tectonics - Primary School

Dublin School of Architecture

24

4th Year, 2012 -2013


Tectonics - Primary School

Dublin School of Architecture

25

4th Year, 2012 -2013


David Lally Tectonics - Primary School

Dublin School of Architecture

26

4th Year, 2012 -2013


David Lally Tectonics - Primary School

Dublin School of Architecture

27

4th Year, 2012 -2013


Fiona Canavan Tectonics - Primary School

Dublin School of Architecture

28

4th Year, 2012 -2013


Detail Section 1:20

Dublin School of Architecture

29

4th Year, 2012 -2013


Ashling Cleary Tectonics - Primary School

Dublin School of Architecture

30

4th Year, 2012 -2013


Dublin School of Architecture

31

4th Year, 2012 -2013


Ashling Cleary Tectonics - Primary School

Dublin School of Architecture

32

4th Year, 2012 -2013


Dublin School of Architecture

33

4th Year, 2012 -2013


David McGowan Tectonics - Primary School

Dublin School of Architecture

34

4th Year, 2012 -2013


Dublin School of Architecture

35

4th Year, 2012 -2013


David McGowan Tectonics - Primary School

Dublin School of Architecture

1MBO

36

4th Year, 2012 -2013


Dublin School of Architecture

37

4th Year, 2012 -2013


OisĂ­n Jacob Tectonics - Primary School

Dublin School of Architecture

38

4th Year, 2012 -2013


Dublin School of Architecture

39

4th Year, 2012 -2013


Dean Murphy Tectonics - Primary School

Dublin School of Architecture

40

4th Year, 2012 -2013


Dublin School of Architecture

41

4th Year, 2012 -2013


James Hanlon Tectonics - Primary School

Dublin School of Architecture

42

4th Year, 2012 -2013


Dublin School of Architecture

43

4th Year, 2012 -2013


Dublin School of Architecture

44

4th Year, 2012 -2013


Dublin School of Architecture

45

4th Year, 2012 -2013


4TH YEAR Timothy Bergin Morgan Boland Kate Buck David Burke Fiona Canavan Laura Carroll Aisling Cleary Miriam Corcoran Mark Davy Sophie Dempsey Michael Drury Declan Duffy Paul Egan Caren Finnegan Jennifer Fisher Josephine Flahive James Hanlon John Hanrahan Cian Hughes Oisin Jacob David Keegan Nadine Kelly Anna Keogh David Lally Louis Lancon Niall Lennon Sophie Mc Cauley Aidan Mc Donnell Karen Mc Gillion David Mc Gowan Sinead Mc Loughlin Robert Mannion Pierre Marc Alba Martell John Meehan Ciaran Molumby Dean Murphy Matthew Murphy Daniel Nash Hugh Neary Louison Newlove Alison Noone Liam O Reilly Shane Phelan Mark Poland Egel Pruckte Stephen Richardson Ciara Ryan Natalie Scanlon Conor Sheehan Alan Sherlock James Slater Colum Smith Philip Tennyson Kenneth Tuite Georgina Vernon Cliodhna Walsh Cillian Wright Anne Young

GUEST CRITICS Dermot Boyd Ralph Bingham Jeffrey Bolhuis Noel Brady Brenda Carroll Johanna Cleary Michelle Fagan Niall Rowan

Dublin School of Architecture

46

4th Year, 2012 -2013


4TH YEAR Dublin School of Architecture 2012-2013

Dublin School of Architecture

47

4th Year, 2012 -2013


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.