Fdot unified work program ammendment 2 13 14

Page 1

Page 1 of 3 FLORIDA DEPARTMENT OF TRANSPORTATION

Unified Planning Work Program (UPWP) Revision Form MPO Requesting UPWP Revision:

Polk TPO

Type of UPWP Revision:

Amendment

UPWP Revision Occurring in:

FY 2013/14

UPWP Revision # 6

Reason for Polk TPO Board at their meeting held on 2/13/14 approved one (1) new consultant UPWP Revision: project that is proposed for FTA funding (5303/5305(d)) in FY 2013/14. • Update to the My Ride (Transit Development Plan) Financial Plan. A financial plan assessment will be completed to review & update as necessary. This review will accommodate potential changes in local funding & federal funding programs brought on by the federal MAP-21 legislation. The review's intent will be to ensure that the My Ride vision has a financial component that is reasonable & valid and that UPWP Task Information also validates the need for additional transit funding to achieve the desired vision over time. Additionally, the review of the costs and expenditures of the plan will be Fiscal Year 2012/13 documented to assist in determining the validity of assumptions and the full impact Task(s) Information - List Up to 8 If there are more than 8 changes, please use an additional form. of the investments in the capital and operating estimates of the plan. Task Amounts After Prior to Task(s) Number & Name Funding Source Revision Revision (1)

$

$

(2)

$

$

(3)

$

$

(4)

$

$

(5)

$

$

(6)

$

$

(7)

$

$

(8)

$

$

$

$

Total UPWP Balance for Fiscal Year 2012/13


Page 2 of 3

FLORIDA DEPARTMENT OF TRANSPORTATION

Unified Planning Work Program (UPWP) Revision Form Fiscal Year 2013/14 Task(s) Information - List Up to 8 If there are more than 8 changes, please use an additional form. Task(s) Number & Name (1) Task 3.2 Short Range Transportation Planning

Task Amounts After Prior to Revision Revision

Funding Source

$ 451,973

$ 451,973

(2)

$

$

(3)

$

$

(4)

$

$

(5)

$

$

(6)

$

$

(7)

$

$

(8)

$

$

$ 1,286,899

$ 1,286,899

FTA 5303 Funds

Total UPWP Balance for Fiscal Year 2013/14

This Section is Only Applicable to Amendments Amendment Due to: (Check all that apply) Change in FHWA Approved PL Budget Change in Scope of FHWA Funded Work Task(s) Addition or Deletion of Work Task(s) Amendment Part of De-Obligation: (mm/dd/yyyy)

Date UPWP Amendment Approved by MPO Board :

2/13/2014 (mm/dd/yyyy)

Date MPO Submitted UPWP Amendment for FDOT Review:

2/13/2014 (mm/dd/yyyy)

Date FDOT Submitted UPWP Amendment for FHWA/FTA Review:


Page 3 of 3

FLORIDA DEPARTMENT OF TRANSPORTATION

Unified Planning Work Program (UPWP) Revision Form Attachments to be Included with Form Submission: Revised UPWP Summary Budget Table(s) (Original & Proposed) Revised UPWP Task Sheet(s) (Original & Proposed) MPO Resolution and/or MPO Meeting Minutes Approving UPWP Amendment (Applicable only to Amendments)

Response to Request: FDOT Action on Request: (mm/dd/yyyy)

Signature Field

Date:

FDOT Comment:

FHWA Action on Request: (mm/dd/yyyy)

Signature Field

Date:

FHWA Comment:

FTA Action on Request: (mm/dd/yyyy)

Signature Field

Date:

FTA Comment:

Please Use this Field to Indicate Whether Additional Forms were Required for this UPWP Revision Submittal

Form

Of


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.