Ministry of Electricity & Water State of Kuwait
The International Water Summit - 17 January, 2016
Forecasting Water Requirements - 2030 New University & Bobyan Island - 50 MIGD.
Housing Projects – 200 MIGD Commercial & Industrial - 100 MIGD. Industrial Load & Oil Sectors - 75 MIGD +6% Annual increasing - Additional Amount of Water Required for Kuwait Projects up to 2030 450 MIGD
Water Demand & Available Capacity MIGD - 2030 year 2010 2016 2020 2025 2030
Available + Expected Capacity (MIGD) 400 480 718 950 1161
MAX Demand including Projects (MIGD) 360 451 569 693 843
1300 1161 MIGD
1100
900 843 MIGD
700 480 MIGD
500 451MIGD
300 100 2010
2016
MAX Demand including Projects (MIGD)
2020
2025 Available + Expected Capacity (MIGD)
2030
Future Desalination Projects
Power Station & Desalination Projects
Station
KAPP
KAPP
Power MW
Planned 1800 Combined cycle Al Zour North Phases II Proposed 2300
Al-Kheran Steam Turbines - Phases I
1500
Water MIGD
Tendering
107
Under evaluation
125
2017/2018
MEW
Al Nwaiseeb Steam Turbines - Phase I
3000
75
2017/2018 PQ will be out by 2nd quarter 2017
KAPP
Al Zour North Phase 3 & 4
1800
75
2018-2019
MEW
Doha Phase I (RO)
-
60
singed May31,2016
MEW
Doha Phase II (RO)
-
60
2024-2025
KAPP
Al - Kheran - Steam Turbines Phases II
1800
-
2023-2024
-
NEW Shuaiba South
1800
50
2021-2022
-
NEW Doha East
2400
100
2022-2023
Al Zour North Phase II - Combined cycle Total Water Production 107 MIGD. The Project will be Tendered by Kuwait Authority for Partnership Projects “ KAPP “
The 3 Consortia Submitted the Proposals ACWA / MITSUI /AL MULLA Group company KEPCO.
MARUBENI CORPORATION / FUAD ALGHANIM & SONS GROUP. SUMITOMO / OSAKA /NATIONAL INDUSTRIES.
Under Final Evaluation www.ptb.gov.kw
Al-Kheran Steam Turbines - Phases I Total water production 125 MIGD. The project is Tendered by Kuwait Authority for Partnership Projects “ KAPP “
To be Tendered after ZN Ph. II is awarded
Short list for Companies & consortia: Abengoa ACWA – AL MULLA Group holding company consortium. KEPCO. MARUBENI CORPORATION / FUAD ALGHANIM & SONS GROUP. MITSUBISHI. MITSUI. SUMITOMO / OSAKA /NATIONAL INDUSTRIES.
www.ptb.gov.kw
Al Nwaiseeb Steam Turbines - Phase I
Total water production 75 MIGD “ MSF “ To be Tendered by MEW. P Q. will be out by April 2017
Desalination Plants ( RO ) to be Tendered by MEW Doha Power Station Area Phase I 60 MIGD
Phase II 60 MIGD
Singed 30/5/2016
To be Tendered on 2024
Emergency RO Mobile Units – Ph I 30 units each 100,000 Gallon + Storage
Locations: Residential areas Water Tankers Stations Water Pumping Station Substations “Electrical”
Will be Tendered by April 2017
Water Net Works Map 8 x 1200 mm DIA F.W Contract Duration : 36 months (PROPOSED) Al Na’aim WDC 1200MIGD (Proposed)
MUTLA HIGH RES Existing 407MIGD Proposed 550MIGD Future 550MIGD (Under signing of contract) West Funaitees
1200mm Dia F.W ( Kabd Road) Start of Contract : February 2017Contract Duration : 30 month
4 x 1600 mm DIA F.W Contract Duration : 36 months
Khairan to Wafra 2X1600mm (PROPOSED)
WAFRA RES Contract Duration : 36 months
EX.WAFRA RES 185MIGD
Nuwaiseeb to Wafra 3X1600mm (PROPOSED)
Khairan 125MIGD Start of contract: 2022
Nuwaiseeb 75MIGD Issue of tender: 2020 start of contract 2025
Water Net Work Projects Water Pipe 1200 mm From Wafra to Sixth Ring Road (Sulaibyah Road-Kabd) Road( Ph.1) Water Pipe 1200 mm From Sixth Ring Road to Regional Road ( Ph.2) Water Pipe 2x1600 mm From Mina Abdullah water complex to the west Funaitees water complex with the necessary pumps Water Pipe of the brackish waters From Mina Abdullah water complex to ALZour complex water distribution Construction of 3 reinforced concrete fresh water ground reservoirs @ Mutla site No. 1 Construction of 9 Fresh Water Towers in Mutla site No. 2 Construction of 9 Fresh Water Towers in Mutla site No. 3 Construction Filling Station in South Mutla Construction of 2 reinforced concrete fresh water ground reservoirs with capacity of 85 million imperial gallons each and in West Funaitees (Ph.2) Development of New Doha Pumping complex & the main lines attached Development of Water pumping complex in Shuwaikh & Hawally Tender for In House Consultancy Consultancy for 4 Pumping complexes
Sulaibiya Waste Water Treatment
PRODUCTION 80 MIG D
40 MIGD Alwafra Farms
40 MIGD Abdely Farms
Law 48 /2005
A Kuwaiti Team from Ministry employees have been trained as judicial officers to issue violation warning tickets to the Citizens who waste water
Kuwait Alternative Energy Projects The Economy of Kuwait depends on OIL By 2030 about 900,000 Barrels / day will be use to cover the Demand for Electricity & Water Which will be 1/3 of Kuwait OIL Production
MEW & MPW Buildings
on 20 April 2014 started the operation of PV’s on the roofs of the Ministry of Electricity & Water and Public Works Buildings , The area of each building is 8400 m2.
2094 Polycrystalline panels for each ministry & each panel produce 245 watt . Total Power Production
1 MW
Kuwait Towers
Through the Offset program , PV’s has been
applied on the Parking Areas of Kuwait Towers.
Installed Capacity 117 KW
Ash- Shaqayah Alternative Energy Project
Phase I - 10 MW of Wind & 10 MW PV in operation since October 20, 2016
50 MW CSP which expected to be in operation April 2018. Phase II - 1 GW of PV will be Tendered by “ KNPC “ Kuwait National Petroleum Company July 2017 . The Land allocated can accommodate 3 GW of Alternative Energy.
PV @ Ground Water Reservoirs • 25 Locations • 300 MW Total Power Generation Ph1- 30 MW @ Subiya “ North East “ Budget 25 MKD
Preparing TOR For Consultancy Services – to be Tendered by March 2017
Abdaleyah Integrated Solar Combined Cycle “ISCC” Project Total 280 MW including 60 MW Solar. The project tendered by Kuwait Authority for Partnership Projects “ KAPP “ PQ List includes 8 Consortiums. Tendered on 8-NOV, 2015 & Closing date extended to February 4, 2017
Abdaleyah short list -ACWA / ACCIONA/ Al MULLA GROUP EDF / TOYOTA TSUSHO “ + TSK / AL SAGER ENGIE / ELECNOR JGC KEPCO Korea / KN /ARIRS INGENIERIA SISTEMAS RWE AG SOJITZ / ABENGOA/ FUAD ALGHANIM & SONS GROUP www.ptb.gov.kw
Generating Solar Electricity in 1500 Houses Integrating PV systems to rooftops on selected houses 2016 Ph1. 50 houses Completed by Life Energy Company "Germany “ - Average production of 5 KW/ house . Ph2. 100 houses & in the process
of finalizing the tender
http://shamsnakwt.com/
Other Solar Projects 1- MEW •Apply Solar PV on: a- Existing Car Parks. @ Power Stations & MEW Buildings. b- Stores. c- 6 Green buildings. d- Training Center. e- Laboratory Center. • Solar water heater.
2- Other Entities - All New Gov. Buildings “ Schools , University , Mosques “
Project Name Sidrah 500 Kuwait Oil Company “ KOC� Plant in West Om Gudair Oil Field
32,450 poly crystalline silicon panels & 12 inverters 10 MW capacity (DC under Standard Test Condition) 600m x 600m land savings equivalent to planting 500,000 Sidrah trees.
Project Commissioned 26 October, 2016
Kuwait National Petroleum Company
Applied the first roof top PV @ 2 Fuel Station with capacity of 50 Kwh which is enough to run the entire station @ peak time. Roof Top PV will be applied gradually for all Existing & Future Fuel Station
NEW Kuwait International Airport
16 MW Roof top PV solar with thin film technology.
It will be biggest roof top system in the world .
With special dry cleaning system ( electrostatic ).
Average cost 15 MKD.
The contract was signed 30.05.2016.
Expected date of project completion in 2022
Thank You For More Information , Please Contact Eng. Suhaila Marafi Director of Studies and Research Dept. Ministry of Electricity & Water Email :- samarafie@mew.gov.kw MEW Site : - http://www.mew.gov.kw Office No. +965 - 25371390 FAX No. +965 - 25371340