Parks & Sporting Grounds Asset Management Plan 2022-2032

The technical levels of services are outlined in Table 12.

Key Performance Measure Level of Service Performance Measure 2021 Performance

Advertisement

TECHNICAL LEVELS OF SERVICE

Accessibility Parks and play equipment comply with relevant minimum accessibility standards relative to open space function

Condition Regional - Condition assessment of Open space network every 3-4 years

Compliance of available parks and play equipment with current standards relative to open space function

Average network condition <= 2.5 out of 5 and with < 5% of stock in condition state 5.

Baseline audit yet to be undertaken

1.8 out of 5

1.8% in condition state 5

At present, the current asset register has not been assigned hierarchies. The results hence are at the entire asset portfolio level. The improvement plan addresses this.

District - Condition assessment of Open space network every 3-4 years

Local Level 1 - Condition assessment of Open space network every 3-4 years

Local Level 2 - Condition assessment of Open space network every 3-4 years

Pocket - Condition assessment of Open space network every 3-4 years

Average network condition <= 3 out of 5 and with < 5% of stock in condition state 5.

Average network condition <= 3 out of 5 and with < 10% of stock in condition state 5.

Average network condition <= 3.5 out of 5 and with < 5% of stock in condition state 5.

Average network condition <= 3.5 out of 5 and with < 10% of stock in condition state 5.

Table 13 - Technical Levels of Service