1 minute read
Riverbend Environmental Campus
Installation of a new 0.5 MGD Wastewater Treatment Plant including screening, sequencing batch reactors, clarification, filtration, UV disinfection, post aeration, sludge holding, thickening and dewatering, plant drain pump station, chemical feed systems, building rehabilitation, electrical power distribution - including standby generator, new SCADA system, and civil, structural, architectural, mechanical, electrical, and instrumentation. Airport No. 1 Lift Station and Force Main consisted of replacement of pumps, starters and other equipment at the existing pump station and installation of 17,000 LF of 12“ HDPE Force Main. Smithwick Creek Lift Station and Force Main included a new submersible wastewater pump station and installation of approximately 15,000 LF of 10” HDPE Force Main, 2,300 LF of 24” DIP sanitary sewer and 1,300 LF of 8” PVC sanitary sewer.
10-12”
24”
35,600 LF PIPE