Work Breakdown Structure Diagram

Page 1

Work Breakdown Structure

Source Material Supplies

Source Labour Supplies

Source Plant &Equipment Supplies

Source Facilities Supplies Project (WBS)

Concrete

Carpenters

PPE

Offices/Rest Facilities

Reinforceing Steel

Ground Workers

Signage

Portaloos

Timber

Drivers

Lighting

Office Equipment

Sand & Aggregates

Foreman/H&S Officer

Generator

Asphalt

Site Engineer

Site Fence

Kerbs

Fitters

Sykes Pump

Grass Seeds

Project Manager

Palisade Fencing

Plasterers

A. Planning Phase

Fuel

Pipes

Pumps

MH

MH Covers

Building Supplies

Heating Sytem

Sensing Equipment

Blocklayers

Mech &Elec Contractor

Quantity Surveyor

B. Specifics

D. Demolition Stage 1

Site Preparation

Storage Depot

E. Excavation Stage 1

F. Excavation Stage 2

G. Construction Stage 1 I. Excavation of Precast Sludge Collection Tank

H. Construction Stage 2

Ancillaries

Road Sweeper(Brush)

Dump Trucks

A1. Preliminary Inspection

A2. Site Investigation

A3. Feasibility

A5. Determine Construction Works

A4. Determine Contingencies

A6. Schedule

B1. Requirements

B2. Calculations

B3. Drawings

B4. Bill of Quantities

B5. Contracts C.1. Site Planning

C3. Site inspection and setting out

C2. Secure the site

C4. Site Infrastructure

C.5. Reroute Services

E.1. Excavation of Clarifier

D.1. Facilitate works

E.2. Excavation of Aeration Tank

E.3. Excavation of Primary Settlement

F.2. Excavation of Flume and Screening Station

F.1. Excavation of BalancingTank

E.4. Dewatering Provisions

F.3. Dewatering Provisions

G.1. Prepare the Base

G.2. Place floor formwork

G.3. Fix Steel

G.6. Construct Mass Concrete Walls

G.5. Shuttering

G.4. Pour Floor

G.7. Remove Shuttering

G.8. Backfill Excavation

H.1. Prepare the Base

H.2. Place floor formwork

H.4. Pour Floor

H.3. Fix Steel

H.6. Construct Mass Concrete Walls

H.5. Shuttering

H.7. Remove Shuttering

I.1. Prepare Sludge Collection Tank Base

H.8. Backfill Excavation

Small Excavator

Medium Excavator

Telescopic Loader

JCB

Cones

C.1.1. Organise Materials

C.1.2. Organise Labour

C.1.3. Investigate As-Built Drawings

C.1.4.Investigate Traffic Management Plan

C.1.5. Devise Traffic Management Measures

C.1.6. Instigate Traffic Management Procedures

C.1.7. Designate new Utilities Path

C.1.8. Delineate Area for Storage of Spoil

C.1.9. Designate Assembly Point

C.1.10. Designate Tradesmans Work Areas

C.1.11. Provisions for Sludge production before new plant completed

C.1.12. Allocate Building Rubble Tip Location

C.1.13. Order Materials

C.1.14. Cut and Bend Reinforcing Steel

C.1.15. Design & Manufacture Shuttering

C2.1. Open New Site Entrance

C2.2. Erect Fencing

Source Appropriate Machinery

Source Appropriate Fence and Entrance Barrier Setout Location of Fence & Construction Site Entrance

C3.2. Establish TBM (GPS Rover)

C3.3. Mark out Major Components (GPS Rover)

C3.4. Mark out Area outside site for Parking and Materials Storage

Acquire necessary Documentation

Ensure Current Drawing in use

Mark out Roads,Facilities Areas, Tank Alocations etc

Designate areas for Carparking

Assess for Hazards

Provide Settingout Tools &Equipment

Construct Health &Safety Plan

Designate areas for Materials Storage (Gravel, Spoil etc)

Provide PPE

Obtain evidence of Setout

C3.1. Walk over

(s)Tippers

Tractor & Trailer

Chemicals

H&S Equipment

Marker Tape

Goal Posts & Footings

Precast Sludge Tank

Mixers

C.4.1. Plant Operator Hut

C4.2. Offices

C4.3. Toilets/ Washroom

C4.4. Storage Depot/Test Equipment

C4.5. Canteen/Rest Facilities

C4.6. Site Roads

C4.7. Hardcore of Parking &Turning Area Infront of Site

C.4.8. Reset out again.

Locate Utilities

C.5.2. Isolate Services (Power Water etc)

C.5.3.Dig New Trench

C.5.4. Strip existing services

C.5.5. Extend & Relay services in new trenches

C.5.6. Note location of services

C.5.7. Re-fill trench

C.5.8. Compile AsBuilt Drawings

C.5.9. Produce As Built Drawing (Start)

C.5.10. Produce As Built Drawing (finish)

D.1.1. Remove Salvageable Materials

D.1. 2. Remove Sludge Drying Beds

D.1.3. Move plant controls to temporary location

D.1.4. Demolish Control Room Onsite

D.1.5. Haul Rubble to Stockpile

E.1.1. Excavate Tanks

Source Required Office Cabins

Source Required Toilet/Washroom Cabins

Source Required Storage Containers

Source Required Office Cabins

Source Suppliers of Quarry Materials

Source Necessary Plant

Organise Lifting Equiment is present on site

Organise Lifting Equiment is present on site

Organise Lifting Equiment is present on site

Organise Lifting Equiment is present on site

Source Necessary Plant

Source Suppliers of Quarry Materials

Install Necessary Test Equipment

Fit out to necessary standard

Source Necessary Drivers

Source Necessary Drivers

Fit out to necessary standard

E.1.2. Haul Spoil

E.1.3. Stockpile Spoil

E.1.4. Fence Excavation

Designate Suitable Location for Spoil Heap

Issue Appropriate Height for Spoil Heap

Comply with H&S Regulations

Source Necessary Plant

Source Necessary Drivers

E.2.1. Excavate

E.2.2. Haul Spoil

E.2.3. Stockpile Spoil

E.3.1. Excavate Tanks

Source Necessary Plant

Designate Suitable Location for Spoil Heap

Issue Appropriate Height for Spoil Heap

Source Necessary Plant

Source Suppliers of Quarry Materials

Source Necessary Drivers

Source Necessary Plant

Source Suppliers of Quarry Materials

Source Necessary Drivers

Source Necessary Drivers

E.3.2. Haul Spoil

E.3.3. Stockpile Spoil

E.3.4. Fence Excavation

E.4.1. Prescribe Dewatering Method

Designate Suitable Location for Spoil Heap

Issue Appropriate Height for Spoil Heap

Comply with H&S Regulations

Specify Method of Dewatering

Source Necessary Plant

Source Necessary Drivers

E.4.2. Hire Pump

Source Pump

E.4.3. Dig Sump Issue instructions re: size of sump and pumping requirements

E.4.4. Place Sykes Pump

E.4.5. Operate Pump

F.1.1. Excavate Tanks

F.1.2. Haul Spoil

F.1.3. Stockpile Spoil

F.1.4. Fence Excavation

Ensure fuel & Other Provisions for pump are allocated

Source Necessary Plant

Designate Suitable Location for Spoil Heap

Issue Appropriate Height for Spoil Heap

Comply with H&S Regulations

Source Suppliers of Quarry Materials

Source Necessary Drivers

Source Necessary Plant

Source Necessary Drivers

F.2.1. Excavate Tanks Source Necessary Plant

Source Suppliers of Quarry Materials

Source Necessary Drivers

F.2.2. Haul Spoil

F.2.3. Stockpile Spoil

Designate Suitable Location for Spoil Heap

Issue Appropriate Height for Spoil Heap

F.2.4. Fence Excavation

Comply with H&S Regulations

F.3.1. Prescribe Dewatering Method

Specify Method of Dewatering

F.3.2. Hire Pump

F.3.3. Dig Sump

Source Pump

Issue instructions re: size of sump and pumping requirements

F.3.4. Place Sykes Pump

F.3.5. Operate Pump Ensure fuel & Other Provisions for pump are allocated

G.1.1. Establish Levels Establish Recommended Elevations On-site

G.1.2. Place, CL 804

G.1.3. Level CL 804

G.1.4. Compact CL 804

Ensure base is firm enough

G.1.5. Verify Height Levels

G.2.1. Verify Height Levels

G.2.2. Oil Formwork

G.2.3. Place Formwork

Establish Recommended Elevations On-site

G.2.4. Blind Undulations and Compact Ensure base is firm enough

G.3.1. Set Reinforcing Steel

Order Required Reinforcing Steel

G.4.2. Pump Concrete (Y/N)

G.4.1. Order Concrete Specify Concrete Required

Source Conc Pump (If Required)

G.4.3. Screed Concrete

G.4.4. Finish Concrete

Ensure Required Conc Laying Procedures Adhered to

Ensure Required Conc Laying Procedures Adhered to

Inspect Steel Fixing is compliant

Source Necessary Plant

G.5.1. Oil Formwork

G.5.2. Setup Shuttering

Design Concrete Shuttering

Ensure safe working practices

Issue Design Drawings to Shuttering Carpenters

Oil Shuttering

G.5.3. Setup Scaffold

G.6.1. Order Concrete

Ensure safe working practices

Source Conc Pump (If Required)

G.6.2. Pump ConcreteY/N

G.6.3. Poker Vibrate Concrete

Ensure compliant working practice

G.6.4. Finish Concrete Ensure Required Conc Laying Procedures Adhered to

G.7.1. Remove Shuttering

Instruct as per curing time

G.8.1. Haul Backfilling from stockpile

Order Appropriate Machinery & Drivers

G.8.2. Backfill Tanks

G.8.3. Compact Backfill

Ensure necessary curing time adhered to

Ensure Backfill Material is properly compacted

H.1.1. Establish Levels

H.1.2. Place, CL 804

H.1.3. Level CL 804

Establish Recommended Elevations On-site

H.1.4. Compact CL 804

H.1.5. Verify Height Levels

H.2.1. Verify Height Levels

H.2.2. Oil Formwork

H.2.3. Place Formwork

Establish Recommended Elevations On-site

Ensure base is firm enough

H.2.4. Blind Undulations and Compact

Ensure base is firm enough

H.3.1. Set Reinforcing Steel

Order Required Reinforcing Steel

H.4.1. Order Concrete

H.4.2. Pump Concrete (Y/N)

H.4.3. Screed Concrete

H.4.4. Finish Concrete

H.5.1. Oil Formwork

H.5.2. Setup Shuttering

Specify Concrete Required

Source Conc Pump (If Required)

Ensure Required Conc Laying Procedures Adhered to

Ensure Required Conc Laying Procedures Adhered to

Design Concrete Shuttering

Ensure safe working practices

Issue Design Drawings to Shuttering Carpenters

Oil Shuttering

Inspect Steel Fixing is compliant

H.5.3. Setup Scaffold

Ensure safe working practices

H.6.1. Order Concrete

H.6.2. Pump ConcreteY/N

Source Conc Pump (If Required)

H.6.3. Poker Vibrate Concrete

H.6.4. Finish Concrete

H.7.1. Remove Shuttering

H.8.1. Haul Backfilling from stockpile

H.8.2. Backfill Tanks

H.8.3. Compact Backfill

Ensure compliant working practice

Ensure Required Conc Laying Procedures Adhered to

Instruct as per curing time

Order Appropriate Machinery & Drivers

Ensure necessary curing time adhered to

Ensure Backfill Material is properly compacted

I.1.1. Establish Levels

I.1.2. Place CL 804

I.1.3. Compact CL 804

I.1.4. Setup Formwork

Ensure Backfill Material is properly compacted

Specify Required Formwork

Source Necessary Drivers

Give Notification of Site Visit

High Vis Tape

Skip

Poker Vibrator

Test Equipment

Feasibility

Procurement

Investigate Requirements

April 16, 2014

Establish Requirements

Research Options

Appraise Options

Verify viability of Project

Design

Specifications

Prepare Drawings/ Documents

Secure Suppliers

Secure Labour

Document Control & Communication Plan

Risk & Value Management

Organise Bonds & Indemnities

Submit Tender

Initiate Bonds & Indemnities

Prepare Risk Register Sign Contract

Prepare Risk Matrix

Prepare Risk Management Plan (RAM)

Prepare Cost Management Plan

Prepare HR Management Plan

Monitoring & Control Measures

Contingency & Mitigation

Continuously Search for Efficient Work Prctices

Instigate Day to Day Financial Management

Quality Management

Contract Management

Implement ISO 9001 Establish Channels for Issueing Instructions

Establish Environment for Collaborative Working

Implement ISO 14001

Implement ISO 50001

Schedule Activities

Implement ISO 14064

Implement OHSAS 18001

Traffic Management Plan (Road Traffic)

Health &Safety

Comply with Safety Health & Welfare at Work Act 2013

Investigate Documents & Drawings

Devise Traffic Mangement Plan

Submit Proposal to Council

Notify Public of Changes

Implement Plan

I.1.5. Order Concrete

I.1.6. Pour Concrete

I.1.7. Vibrate & Finish Concrete

Order Required Concrete

Supervise Placing of Concrete

I.1.8. Place precast sludge collecton tank

I.1.9. Backfill Around Tank

J.1.1. Excavate for Flume

J.1.2. Establish Levels Establish Required Elevations for Flume