4. DM Offtake Nominations

Next Article
11 Not Used

11 Not Used

will by making an “NDM Offtake Renomination” revise on behalf of each User its NDM Offtake Nomination for the User's NDM Supply Meter Point Group for the Gas Flow Day.

3.2 The Nomination Quantity under a NDM Offtake Renomination will be the sum of the revised NDM Supply Meter Point Demand for each NDM Supply Meter Point in the User's NDM Supply Meter Point Group, determined in accordance with Section F paragraph 3.

4. DM Offtake Nominations

4.1 A User nominating quantities of gas for offtake in respect of each Gas Flow Day from the System at a Very Large DM Supply Meter Point or DM Supply Meter Point (as applicable) shall make an Offtake Nomination subject to and in accordance with this paragraph 4.

4.2 By not later than the Nomination Time a User shall submit a separate DM Offtake Nomination in respect of each Very Large DM Supply Meter Point or DM Supply Meter Point (as applicable).

4.3 Each DM Offtake Nomination shall specify:

(a) the Gas Flow Day;

(b) the identity of the User;

(c) the Supply Meter Point Reference Number; and

(d) the quantity of gas nominated for offtake.

4.4 A User shall not submit an Offtake Nomination in respect of a Very Large DM Supply Meter Point or DM Supply Meter Point (as applicable) which is a Maintenance Affected Point and in respect of which gas is not available for offtake on the Gas Flow Day or if the Implied Nomination Flow Rate exceeds any rate specified by the Operator pursuant to Section I paragraph 2.4.

4.5 The Operator may reject or (in its discretion) approve a DM Offtake Nomination:

(a) which is not submitted in accordance with, or does not comply with:

(i) the requirements in paragraph 1.7;

(ii) the requirements of paragraph 4.3;

(b) if the Implied Nomination Flow Rate exceeds 1/24 of the Supply Meter Point Capacity of the Supply Meter Point;

(c) if the quantity of gas nominated for offtake is expressed as being a negative quantity.

4.6 The Operator shall not be required to approve or reject a DM Offtake Nomination before the Nomination Time.

4.7 If in respect of any Very Large DM Supply Meter Point or DM Supply Meter Point (as applicable):

(a) a User has not submitted a DM Offtake Nomination by the Nomination Time; or

15