Willard Bridge Update February 26, 2015

Page 1

February 26, 2015


Completed Phases 1 & 2 of Design ◦ ◦ ◦ ◦

 

Held preliminary discussions with UPRR Held preliminary discussions with Westar

◦ 

In process of completing Phase 3 (Final) Completed Geological Investigation Completed Value Engineering Study (necessary for federal funding) Obtained 7 environmental clearances

Attaching to new bridge

Began R-O-W negotiations ◦ ◦ ◦

Agreed on price for SE quadrant Will be making contact for NE and NW quadrants Wabaunsee County to acquire for SW quadrant


SR (2006): 61.5 SR (2008): 61.2

• BCC Approved Commencement of Design (2009) • Position ourselves if any grant funding became available

SR SR SR SR

(2010): 61.2 (2012): 61.2 (2013): 50.7 (Current): 23.7


Met with Representatives of KDOT and Wabaunsee County to discuss funding assistance ◦ KDOT Advance

Met with Senator Moran to discuss funding assistance Met with Sheriff Staff RE: Increased enforcement and related issues Developed more stringent weight restrictions resolution to provide easier enforcement capabilities


Developed Cashflow Needs Projection

Developed Project Completion Schedules

Developed Potential Funding Strategies


Complete Final Design (Summer 2015)

Complete R-O-W acquisition (July 2015)

Obtain Permits (Nov 2015)

Finalize Funding Package

Bid/Construct

◦ ◦ ◦ ◦ ◦

UPRR* Corps of Engineers KDWR KDHE Notice of Intent KDOT Environmental Services Action Permit

*Critical Path Component


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01 TASK Jan

Feb Mar

2015 Apr May Jun Jul

Aug Sep

2016 Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Aug Sep

2017 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

2018 Mar Apr May

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge

Road Tie-In, Final Grading, Seeding


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01

TASK

2015 Jan

Feb Mar

Apr May Jun

Jul

2016 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul

2017 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul Aug Sep Oct Nov Dec

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge Const.

Road Tie-In, Final Grading, Seeding


REMAINING PROJECT COSTS 2015

2016

2017

Total

Design

$115,625*

$115,625*

R-O-W

$124,000*

$124,000*

$35,000*

$35,000*

UPRR Permit Utility Relocation Construction Const. Engineering

$100,000*

$100,000*

$8,014,000

$12,021,000

$20,035,000

$641,120

$961,680

$1,602,800

Contingencies

$100,000*

$641,190

$961,785

$1,702,975

TOTAL

$374,625*

$9,296,310

$14,044,465

$23,715,400

*Funding is Currently Available


YEAR

AMOUNT (est)

FUNDING SOURCE

2016

$7-$10M

KDOT Advance

STE* (2017-2026)

2016

$2-$3M

2016 Gen Fund

N/A

2017

$6M

CST** Excess

N/A

2017

$1M

Wabaunsee Co.

N/A

2017

$2-$3M

2017 Gen Fund

N/A

2017

$1M

STE/Exch. Funds/PW 391

N/A

2018 (if nec.)

$2-$3M

2018 Gen Fund

N/A

*Sales Tax Extension **Current Sales Tax

REPAYMENT SOURCE


KDOT Financial Advance

Sales Tax Extension County Bridge Allotment

Assistance in Expediting UPRR Agreement

Goal is a Dec 2015/Jan 2016 Bid

◦ Provides Construction Funding in 2016 ◦ Prior to Current Sales Tax Excess Funds Availability ◦ Significantly reduces bonding costs ◦ $32.5M (includes $10M allotted for Willard Bridge) ◦ Provides reimbursement funds for KDOT Advance ◦ KDOT/Sen. Moran

◦ Construction in Jan/Feb 2016

 Environmental Restrictions April 1st - August 31st

◦ Completion in Dec 2017


WILLARD BRIDGE

FINANCING

Greiner, Director of

PRESENTATION

Services

February 26, 2015

Let me begin by saying that we have been working on this issue for some me – both internally and with bond counsel. the County has sufficient funds set aside to cover all of the costs up to As Tom Vlach stated in his the construc phase. Therefore, we need to have the final details of our financing plan by the me constr begins which could be as soon as one year from now. I’d like to present some financing op O

that we are looking at and evalua ng.

n1

The County must look to statute for authority to bond. K.S.A. 68-1103 allows bonding for the replacement of a bridge. All the necessary paperwork could be completed in advance so that bonding could be secured prior to n. With the paperwork ready, this process could be completed and funded in 1-2 the start of constr months. The primary factor will be to determine the amount of financing needed. The following factors will affect this amount: 1. JEDO interlocal agreement - It is an ipated that $10 million from the sales tax extension will come to the County in annual allotments over the 15 year term beginning in 2017. 2. costs - Before construc begins, we will have accepted a bid for the project and will have the final constr cost. 3. Federal or state par cipa n in costs 4. Excess from the current sales tax – A more accurate es mate of this excess will be available when the the 2015 sales taxes receipts have been last road project costs have been determined and received. Interest and principal payments on the bonds will start immediately upon the sale of the bonds. Interest will be paid on the en re amount of the bond regardless of how much money has been spent. O

n2

to be issued for the replacement of the bridge, K.S.A. 10-123 Since K.S.A. 68-1103 permits general oblig authorizes the issuance of temporary notes as part of the financing for the replacement bridge. The County could issue a temporary note or series of notes with a local bank for the constr period of the bridge. The term of a temporary note could be six months, one year or one year with a call period. The benefits of the temporary notes are as follows: 1. Interest on the temporary note would only be on the principal amount of the note or series of notes total. rather than on the en re constr


WILLARD BRIDGE

FINANCING

PRESENTATION

progresses and funds are 2. The amount of the temporary notes could be increased as constr needed. 3. When received in 2017, the excess funds from the current sales tax could be used to pay co re all or a n of the temporary notes. costs or 4. When the 2017 sales tax allotment is received, those funds could be used for constr costs rather than issuing a temporary notes. costs paid from temporary notes would be When the bridge is completed, the amount of the co permanently financed with bonds and any temporary notes issued would be paid with bond proceeds. As an example, this method is similar to an individual building a home. They get a constr loan for the constr period. They borrow the money as it’s needed for the constr costs. When the home is completed, they obtain a mortgage and pay off the constr loan. They do not start making mortgage payments un l the house is completed. Since we would be paying interest only on the amounts needed, this op significantly. We will con nue to evaluate the ming and best financing

should cut interest costs

for this bridge.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.