Shawnee County Willard Bridge Update 04/23/2015

Page 1

April 23, 2015


Weekly Inspection Update

Design Update

Permitting Update

R O W Update R-O-W U d t

Utility Relocation Update

F di Update Funding U d t

Schedule Review

Oth Other It Items


y Finney y & Turnipseed p Conducted by ◦ Inspected Every Friday ◦ Conducted by Professional Structural Engineers ◦ Focusing on Areas of Higher Concern  Deteriorating Floor Beams

◦ No Change in Condition Since Last Status Update


Bridge Design Divided Into Three Units: ◦ ◦ ◦

Unit 1 (95% Complete) ◦ ◦

Superstructure design complete Substructure design in progress

Unit 3 (60% Complete) ◦

Superstructure design complete Substructure design in progress

Unit 2 (85% Complete) ◦ ◦

Unit 1: South end of bridge over UPRR Unit 2: Portion spanning Kansas River Unit 3: North end of bridge

Superstructure design in detailing phase

Estimated Completion date: July – August


UPRR

◦ Proposed plans (Unit 1) to be sent to UPRR week of April 27, 2015 ◦ Currently scheduling meeting with UPRR to review/discuss

Environmental

◦ Obtained 7 environmental clearances

Others ◦ ◦ ◦ ◦

Corps p of Engineers g KDWR KDHE Notice of Intent KDOT Environmental Services Action Permit


NE Quadrant ◦

NW Quadrant ◦

R-O-W documents still being finalized

SE Quadrant ◦ ◦

R-O-W documents still being finalized

Negotiations re-initiated with major property owner R-O-W documents being finalized for minor property owners

SW Quadrant ◦ ◦

R-O-W documents still being finalized Wabaunsee County will acquire


No Change

◦ Met with Westar in March ◦ Other utility involved is Rural Water ◦ Not a critical p path item at this point p


q KDOT Request

◦ No Change – Awaiting end of legislative session

City of Topeka (Sales Tax Extension Funds) ◦ No Change g - Interlocal Agreement g Negotiations g Upcoming p g

TIGER Grant

◦ USDOT now accepting applications g Projects j ($ ($10M+)) ◦ For Large ◦ Pre-application due May 4, 2015  SCDPW ready to submit pre-application, if authorized  Minimal Effort/No Obligation due June 5, 2015 ◦ Final Application pp J  Significant Effort  Insufficient staff/No grant writing experience  Will need to strategize how to complete


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No S 121015 00 SNCO Project No. S‐121015.00 KDOT Project No. 89C 0066‐01

TASK

2015 Jan

Feb Mar

Apr May Jun

Jul

2016 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul

Aug Sep

Oct Nov Dec Jan Feb Mar Apr May

Design Right‐of‐Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO BID Bridge Const.

SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding


Wabaunsee County Agreement ◦ Draft Copy Developed

Will be forwarding to County Counselor for final review

Will b be scheduling h d li meeting ti with ith Wabaunsee W b County C t

Next Update – May 21, 2015