MIDCO速 AQUATIC CENTER CONSTRUCTION UPDATE Fall2015Volume2

Dear Resident: Dear Resident, The Midco Aquatic Center at Spellerberg Park is taking shape as construction activities head into fall. The Midco Aquatic Center at Spellerberg Park is masonry taking shape construction activities head into Concrete foundation systems and exterior load-bearing wallsasare complete, while structural steelFall. and Concrete foundation systems and exterior load bearing masonry walls are complete, while structural steel roofing systems are well under way. In anticipation of a typical South Dakota winter, exterior envelope systems andscheduled roofing systems are well this under In anticipation a typical by South DakotaInterior Winter,building exteriorelements envelope are to be installed fallway. allowing for buildingofenclosure Christmas. systems are scheduled to be installed this Fall allowingare forinbuilding enclosure by Christmas. Interior building like the cast-in-place concrete observation mezzanine place. With a capacity of 500 spectators, the elements like the cast-in-place concrete observation mezzanine in place. With avisitor capacity of 500 spectamezzanine deck allows uninterrupted views to the 50-meter poolare below, enhancing experience. tors the mezzanine deck allows uninterrupted views to the 50 meter pool below enhancing visitor experi ence. Fifty-meter pool construction is proceeding on schedule. Numerous building trades are productively working50 together coordinating installation of mechanical piping,Numerous electrical conduit, reinforcing steel, meter pool construction is proceeding on schedule. buildingexcavation, trades are productively and concrete structures. Half the concrete pool floor has been poured and the project team expects the entire working together coordinating installation of mechanical piping, electrical conduit, excavation, reinforcing structure to be complete in December of this year. Remaining recreational pool construction will continue steel, and concrete structures. Half the concrete pool floor has been poured and the project team expects throughout the winter the entire structure tomonths. be complete in December this year. Remaining recreational pool construction will continue throughout the winter months. During During the thecourse courseof ofconstruction, construction Spellerberg Park amenities outside of the construction construction perimeter perimeter fence fence remain remainopen openand andavailable availablefor forpublic publicuse. use.These Theseareas, areasalong alongwith withaa24/7 24/7webcam, web camhelp helpprovide providefrontfront row observation to construction activities. As with any construction site, please use caution when approaching row observation to construction activities. As with any construction site, please use caution when approachconstruction areas and and actively supervise children. Our goal to send everyone homehome safelysafely everyevery day. day. ing construction areas actively supervise children. Our is goal is to send everyone We are grateful to announce that we have no lost time or recordable accidents on site to date. Thank you in advance We grateful to announce that we as have lost time or recordable accidents on siteaquatic to date.center Thankat forare your cooperation and patience weno continue construction of your new indoor you in advance for The yourMidco cooperation patience we continue construction of your new indoor Spellerberg Park. Aquaticand Center is on as schedule to open in Fall 2016. Additional projectaquatic inforcenter at Spellerberg Park. The Midco Aquatic Center is on schedule to open in fall 2016. Additional project mation including renderings, news releases, and sponsorship information is available at www.siouxfalls.org/ information including renderings, news releases, and sponsorship information is available at www.siouxfalls. indooraquaticcenter. org/indooraquaticcenter. Thanks again, Sioux Falls Construction

Thanks again, Sioux Falls Construction


Did You Know • • • •

YouMan Know  Currently overDid 20,000 Hours Currently Averageover of 45 Workers Per Day 20,000 man-hours 45 workers per day Average 1,700 of Yards of Concrete Poured to Date yards ofSeats concrete poured to dateArea 1,700 Nearly 500 on the Mezzanine Nearly 500 seats on the mezzanine area

General Project Timeline Project Timeline  Pools &General Interior Structures Fall 2015 • • • • •

& Interior Structures Pools Building Enclosed Enclosed Building Interior Finishes Interior Finishes SiteSite & Park Improvements & Park Improvements Project Project Completion Completion

FallWinter 2015 2015/2016 Winter 2015/2016 Spring 2016 Spring 2016 June 2016 June 2016 2016 FallFall 2016

Construction Contact Information for Aquatic Center ToryMiedema Miedema Tory

Tony Wiseman Tony Wiseman

Park Development Park DevelopmentSpecialist, Specialist City of Sioux Falls 605-367-8222, tmiedema@siouxfalls.org 605-367-8222 City of Sioux Falls tmiedema@siouxfalls.org

Project Manager, Sioux Falls Construction Project Manager 605-336-1640 605-336-1640 Sioux Falls Construction

Check out the Midco Indoor Aquatic Center at Check out the Midco Indoor Aquatic Center at http://www.siouxfalls.org/indooraquaticcenter www.siouxfalls.org/indooraquaticcenter for updated information. for updated construction information and clickconstruction on the webcam to Click on the webcam to in view work in at the construction site. view work progress atprogress the construction site.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.