Fair Park Update 7/30/18 What’s Happening on Site 7/30/18 North Fields - Continued monitoring of Bermuda sprigging (1st mow occurred 7/27) South Fields - Preparation for pervious concrete - Irrigation installation nearly completed - Bermuda sprigging completed at multi-use fields Restroom Building - Electrical rough-in and trim out nearly completed - Finishes and fixture installation completed - Concrete placement around restrooms underway Site Work -
Trailhead structure installation underway Picnic Pavilion installation underway Dog park sidewalks nearing completion Dog park irrigation installation underway Spring box installation completed Light poles installed and functioning Site concrete install in progress • East curbs and parking islands • Dog park sidewalk
Fair Park Update 7/30/18 Three Week Look Ahead North Fields - Monitor sprigging/mowing - Preparation for pervious paving - Complete remaining asphalt trails South Fields - Monitor sprigging - Continue preparation for pervious paving Restroom Building - Restroom building punch list - Continue concrete placement around building Site Work
- Complete dog park sidewalks - Continue work on south sidewalks (~20% remaining)
- Dog park retaining wall - Continue installation of trailhead structure - Continue installation of pavilions
Fair Park Update 7/30/18 Site Activity Photos Spring Box Installation
Spring Box Complete
Fair Park Update 7/30/18 Restroom Building Interior Finishes
Fair Park Update 7/30/18
Light Poles Installed
Fair Park Update 7/30/18 Trailhead Structure
North Field Bermuda
Fair Park Update 7/30/18 South Field Bermuda/Raingarden
Picnic Pavilion
Fair Park Update 7/30/18 Dog Park Sidewalks
East Road Preparation for Pervious Paving
Fair Park Update 7/30/18 Site Progression Photos July 2018 Aerial Photos
Fair Park Update 7/30/18 June 2018 Aerial Photos