Rural Development Eslarn The Eslarn wastwater projects. sanitizing the sewer system "schellenbachstrasse"

ISSUE 01.2016 | 03.07.2016

There comes a time when every community once must think about the future. Also the market town Eslarn now ­ after final judicial decision of the municipal council in May 2016 ­ starts with a first part of the necessary renovation. Most of the sewage system of the village dates back directly from the time after the Second World War. Over the past decades only new residential areas and there new sewers were created. In May 2016 it was decided to place the order for the renovation to a regional construction company. Some days later they started to work. The beginning in June 2016: creation of a waste water tank

The temporarily established place for construction and working materials.

Another temporarily established place for pipes and duct components.

The self-cast sewage tank / drain manifold.

Already back sealed part of the excavation. (mid of Juni 2016) page 01 of 4


Rural Development Eslarn The Eslarn wastwater projects. sanitizing the sewer system "schellenbachstrasse"

ISSUE 01.2016 | 03.07.2016

There comes a time when every community once must think about the future. Also the market town Eslarn now ­ after final judicial decision of the municipal council in May 2016 ­ starts with a first part of the necessary renovation. Most of the sewage system of the village dates back directly from the time after the Second World War. Over the past decades only new residential areas and there new sewers were created. In May 2016 it was decided to place the order for the renovation to a regional construction company. Some days later they started to work.

Another view on the self-cast sewage tank / drain manifold.

The second part of the excavations carried out in late June 2016th

Another small pit was opened.

Another view of the second excavation route.

page 02 of 4


Rural Development Eslarn The Eslarn wastwater projects. sanitizing the sewer system "schellenbachstrasse"

ISSUE 01.2016 | 03.07.2016

Locally limited excavations to affect traffic as little as possible.

They are woking hard (19 of June 1016).

They will continue here soon.

Re usable road part on July 3, 2016

This road part will be re usable until the 10 of July 2016.

Construction equipment you will need: Here a vibriting plate. page 03 of 4


Rural Development Eslarn The Eslarn wastwater projects. sanitizing the sewer system "schellenbachstrasse"

ISSUE 01.2016 | 03.07.2016

Locally limited excavations to affect traffic as little as possible.

They are woking hard (19 of June 1016).

They will continue here soon.

Re usable road part on July 3, 2016

IMPRINT DEEZ ­ Die Erste Eslarner Zeitung, Editorial: Theresia M. Zach, Ludwig­Müller­Str. 2, D­92693 Eslarn. Phone: 0049 (0)163 7093031, Fax: 0049 (0)9653 40 70 001, Email: oikos­ sms@office.eu.org. Responsible for the content (in German "V.i.S.d.P.:"): Michael W. Zach, Ludwig­Müller­Str. 2, D­ 92693 Eslarn. Phone: 0049 (0)163 7093031, Fax: 0049 (0)9653 40 70 001, Email: oikos­ sms@office.eu.org. Images are re usable under the Common Creatives License CC­BY­SA 3.0 non ported page 04 of 4


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.