LEAGUE CITY - EASTERN REGIONAL PARK
WE HAVE SUNSHINE, LET THE SITEWORK COMMENCE! Like many of Teal’s projects and all around Texas construction the site work has been halted due to the tremendous amount of rain delays. Eastern Regional Park is back rocking and rolling with completing the site work, and installing the landscaping. The project will be completed in mid-February. The project manager for the project is Jerry Stafford, superintendent is Barry Peel and Chantela Rowland as Project Coordinator.
TEAL January Newsletter 01.21.15
To Build Structures and Life-long Relationships through integrity, innovation, high-performance and an experienced professional team.
PROJECTS
SAFETY
ESTIMATING
MARKET TRENDS
INFORMATION TECHNOLOGY
TRAINING
TEALIANS
MARKETING
ESTIMATING & PROJECT LEADS We are continuing to bid and provide estimates for our current clients and starting new relationships. If you have any leads for estimating, please make sure to send them to Kelly Richardson. This is imperative to continue to keep the most up-to-date client and lead information. email: kellyrichardson@tealcon.com HOME 2 SUITES
PROJECT WINS PROJECT NAME Home 2 Suites Yes Prep Public Schools FTS International - Relocation Helfman Dealership - Parking Lot Expansion
PM Glenn Jarrett Michael Losoya Michael Losoya Michael Losoya
This project was negotiated by Dewayne Lucas and Glenn Jarrett. The current contractor was unable to complete the project, so Teal is coming in to save the day! It is a ground up construction of a hotel and is currently being bought out. Let’s all say CONGRATS to Dewayne and Glenn for their hard work at capturing this project!
BIDDING CALENDAR PROJECT NAME Houston Intercontinental - Eco Park II Kinsel Toyota New Building UH Clear Lake - Site Development COH - Grady Park Construction Brenham Pet Adoption and Care Center
BID DATE 01/22/15 01/22/15 02/10/15 02/12/15 02/12/15
LITHIA CJD - CORPUS
Lithia Chrysler Jeep & Dodge - Corpus Christi The buildings at Lithia are continued to be dried in. With the abundence of rain we have had for the last couple of months the projects site had been on hold until a dry week. Last week the crews were able to put a topping on the road base in the front parking lot and will be starting the placement of asphalt. The project’s substantial completion and owner move in will be the first week of February and final completion to follow in March. The project manager is Tom Gentry, superintendent Blue Vasquez and project coordinator, Morelva Gonzalez.
WELCOME TO TEAL Welcome to Teal, Alex Hotze! Alex Hotze is our new intern from Texas A&M University. He is currently working in our estimating department and will be moved around to learn all facets of construction management. Alex is signed up to graduate with a degree in Construction Science and a minor in Business in May or December 2016.
Last year, Teal joined the Texas A&M Construction Industry Advisory Council (CIAC). We have attended a career fair and is how we landed Alex. We are looking into the future to expand to other universities that teach architecture and construction.
Demontrond Toyota FINAL STAGES!
DEMONTROND TOYOTA
This is one of many projects Teal has completed for Demontrond Motors. The Toyota showroom will be turned over to the owner on January 31st. The renovation of the Toyota Dealership will be a four month project and will be added as another successful Demontrond. project. John LeBlanc and John Shead were the project management, Jim Jones as the superintendent, and Connie Enmon as project coordinator.
Lithia Subaru is OPEN!
LITHIA SUBARU
The new building’s Grand Opening was Monday, January 19, 2015. With major weather delays, the project team and subcontractors strapped down and worked 7 days a week for over 2 months to get the site work completed which was the final steps to turn it over to the client. John LeBlanc and John Shead were the project management, James Grant as the superintendent, and Connie Enmon as project coordinator.
THANK YOU, FAREWELL & GOOD LUCK Alexis Hinojosa is bidding farewell to Teal Construction and getting ready to welcome her new baby girl! Alexis has been with the company for 5 years and has successfully completed multiple careers moving quickly up. She was hired as a Project Coordinator, moving to Estimating and Marketing Coordinator, then rounded her career out as our Marketing Manager. With the help of Alexis, we have won numerous projects, joined new organizations and continued to build Teal Construction. Alexis has done an impeccable job and we are very sad to see her go, but know that she will conquer motherhood and congratulate her on the Hinojosa growing family. Alexis’s last day will be Friday, January 23rd (this Friday), so please make sure and go by to thank her on all of the hard work she has put into Teal Construction. Thank you Alexis!
HOLD ‘EM & HIT ‘EM COOKOFF The Houston Office held an appreciation event for our subcontractors, clients and designers on Friday, January 16th at the Hold ‘Em & Hit ‘Em Cookoff. Our Senior PM, Glenn Jarrett and his wife Diane, were the amazing cooks; serving us BBQ-ing pulled pork sliders, brisket, chicken, ribs, and jalapeño poppers. Everyone there could not get enough of the food and only sang praises. Many, many THANK YOU’s to the Jarrett’s for all of their hard work. We had a tremendous turn-out with over 100 subcontractors, clients, and designers and around 50 of our Teal family. Through this event we have built a stronger relationship with our subcontractors and have already been provided with more leads for 2015. Thank you to everyone that helped put this together, especially Mark Baumguard, Ernesto Castro, Alex Hotze, Marcelino Perez, and Bill Shultz for setting up and helping construct our area. AND Thank you to Jerry Stafford for being such and amazing sous chef.
“The Crymar Team and I had a great time at the cook off and Teal Appreciation event last Friday. Like we talked about, it was a first class party and you guys shows us and all your subs and customers what you guys are. I look forward to working with you and the Teal team for a long time.” -- Rick Wood Crymar Finishes
RAFFLE WINNERS Winner One: Taste of Texas Gift Card Rusty Slay, Baytex Glass Winner Two: Taste of Texas Gift Card Steve Hobbs, Dawson Van Orden Winner Three: Whiskey in the Water Jason Dawson, Dawson Van Orden Winner Four: Tequila Nights Allen Hensley, H4 Architects