CAPITAL PROJECTS FUNDS

FUND: Public Improvements Fund

2022 Accomplishments

Innovate with Collaborative Governance

• Executed an intergovernmental agreement (IGA) amendment with Douglas County to jointly fund the final design of the proposed Dransfeldt Road extension over Cherry Creek

• Executed an intergovernmental agreement (IGA) amendment with Douglas County to jointly fund the final design for the Lincoln Avenue widening project between Keystone Boulevard and Parker Road; design is underway

• Received preliminary approval from DRCOG/Colorado Department of Transportation (CDOT) for partial construction funding for the sidewalk/trail along the east side of Parker Road between the Pine Drive intersection, south to an existing sidewalk/trail north of Stroh Road

Develop a Visionary Community Through Balanced Growth

• Completed operational improvements to the southwest corner of Mainstreet and Parker Road

• Completed the Cottonwood Drive roadway widening over Cherry Creek with improvements between the Jordan Road intersection and Parker Road

• Completed the Parker Road multi-use trail/sidewalk project on the west side of Parker Road between the 20-Mile Road and Hess Road intersections

• Completed design of Town-wide responsive traffic signal system improvements

• Commenced preliminary design of the next Parker Road multi-use trail/sidewalk on the east side of Parker Road between the Sulphur Gulch Trail and south of Parker Square Drive

• Completed improvements to Motsenbocker Road at/near the Hess Road intersection

• Reconstructed Plaza Drive between Dransfeldt Road and Twenty Mile Road

• Completed the safety and circulation improvement project on/adjacent to Mainstreet (O’Brien Park to Victorian Drive (east) intersection)

• Installed Motsenbocker/French Creek traffic signal and extended communication infrastructure for traffic signals south to Stroh Road for improved coordination

• Completed the architect selection and the general contractor selection processes for the Town Hall expansion project

2023 Goals

Innovate with Collaborative Governance

• Execute an intergovernmental agreement (IGA) with Douglas County to jointly fund the construction of the proposed Dransfeldt Road extension over Cherry Creek

• Execute an intergovernmental agreement (IGA) with Colorado Department of Transportation (CDOT) for partial construction funding for the sidewalk/trail along the east side of Parker Road between the Pine Drive intersection and an existing sidewalk/trail north of Stroh Road

Develop a Visionary Community Through Balanced Growth

• Complete construction of the next phase of the Town of Parker’s responsive traffic signal system improvements

• Commence construction of the Dransfeldt Road extension project in the second half of 2023

Section Title

Capital Projects Funds

FUND: Public Improvements Fund

• Complete reconstruction of Keyser Creek Avenue pavement west of Motsenbocker Road

• Complete design and commence construction of the next Parker Road multi-use trail/sidewalk on the east side of Parker Road, south of the Sulphur Gulch Trail to south of Parker Square Drive

• Complete construction of the proposed Cottonwood Trailhead improvements

• Complete the next section of CORE power line conversion to an underground configuration in the Parker Road/Hess Road vicinity

• Complete the Canterberry Parkway redundant fiber optic interconnect project to improve traffic signal communications in the eastern portion of the Town

• Complete construction of the Crowfoot Valley/Bayou Gulch/Chambers traffic signal, in addition to traffic signals at Jordan Road/Parkerhouse Road and Chambers Road/Red Sky

• Complete construction of the Mainstreet/Twenty Mile Road intersection improvements

• Complete design and construction of the Hilltop Road/Canterberry Parkway area improvements

• Complete construction of the Pikes Peak Drive sidewalk improvements between Mainstreet and the Sulphur Gulch Trail

• Commence construction of the Dransfeldt Road widening between Mainstreet and Pony Express Drive

• Complete construction of the Mainstreet north side sidewalk improvements between Victorian Drive (east) and Discovery Park

• Competitively bid and construct the North Parker Road operational (Phase 1) improvements

• Commence the design process for the Town Hall expansion project