AR 518 & AR 718 – Integrated Architecture Design Project (Year 3- UNIT C) July – November 2022

5. MODELS

- 1:1500- Design in response to the urban context [Contextual Model] - 1: 500- Building Model - 1 : 500- Study Models / Building form / Design Mechanism / Materiality [Fun &

Experimental Models] - 1:250 / 1:100 / 1:50 - Partial model / Sectional Model / Facade Model [For Material

Explorations or Construction study]

6. TECHNICAL REPORT REQUIREMENTS [DETAILS IN APPENDIX 1]

- Working Drawing Compilation - Planning & Building Guidelines - Building Construction & Technology - Building Environmental Design & Sustainability Strategy

7. ALL WORKS FROM PROJECT 1 (INDIVIDUAL), SELECTED PROJECT 1 GROUP WORKS, PROJECT 2, AND PROJECT 3 MUST BE PINNED UP DURING THE INTERIM & FINAL CRIT.

APPENDIX 1 (PROJECT 3 TECHNICAL REPORT)

A3 Technical Report Requirements (AR 718)

1. PLANNING & BUILDING GUIDELINES a. Authority requirements – Planning & Building guidelines b. UBBL – site planning (turning radius / fire appliance & access / hydrant) c. Passive BOMBA Fire design 2. BUILDING CONSTRUCTION & TECHNOLOGY (AR 724)- Integration with

Working Drawing subject (follow subject requirements) 3. BUILDING SERVICES a. Lighting & Electricity (Natural & Artificial) b. Water & Sewerage c. Details- 1 page of Schematic Design Approach, 1 page of lighting study, 1 page of ventilation study, 1 page of water supply system, 1 page of sewerage system 4. BUILDING ENVIRONMENTAL DESIGN & SUSTAINABILITY STRATEGY-

Sustainable design / Indoor Space quality

SCHOOL of ARCHITECTURE and BUILT ENVIRONMENT

B. Sc. (HONS.) in ARCHITECTURE

AR 518 & AR 718 – Integrated Architecture Design Project (Year 3- UNIT C) July – November 2022

KEY TIMELINE

1. SCHEMATIC DESIGN a. Date : WEEK 11 (15/9) b. Requirement : Progressive GA drawings, 1 major section,1 major elevation, 1:500 mock up model and study models 2. OPEN JURY + INTERIM REVIEW 1 (10%) a. Dates : WEEK 13 (27/9 and 29/9) b. Requirement : Progressive GA drawings, 1 major section,1 major elevation, 1:500 mock up model and study models 3. INTERIM REVIEW 2 (10%) a. Date : WEEK 16 (20/10) b. Requirement : Progressive GA drawings (all floor plans, sections and elevations), axonometric drawings showing space and articulations of selected areas (1:50) and models (Study Models / Building form / Design Mechanism / Materiality) 4. FINAL REVIEW (30%) a. Date : WEEK 17 (25/10) & WEEK 18 (1/9) b. Requirement : Full blown presentation (to follow submission requirements)

Final Design Scheme by Sim Jian Kiang (UC 2022/01-05)