Tysons Update Photo credit: Photo courtesy of Dulles Corridor Metrorail Project.
Silver Line Phase 2 crew member welds a beam known as a purlin to complete column connections. There are 216 of these full penetration welds.
Facing east along the shuttle bus service lane between the Dulles Airport Station and Garage 1, Ironworkers use manlifts to complete the permanent welds of all connections.
Silver Line Phase 2 Windscreen Updates Progress at Dulles Airport Station By Marcia McAllister Structural steel erection work is complete on the north and south
W.M. Schlosser Co., completes welding work, crews will begin
sides of the Dulles Airport Station. The steel will support louvers
applying the steel coating system and install the glass screenwall
on the north side of the station and the glass windscreen on the
and louvers. Louver and glass deliveries are scheduled for June as
south side facing the main airport terminal. Once the contractor,
long as there are no COVID-19 manufacturing issues.v
Facing west along Saarinen Circle at the south side of the Dulles Airport Station. Structural steel erection work is complete and welding work is planned for the permanent connections.
60
T YSONS PREMIER v July // August 2020
Ironworkers weld a beam known as a purlin to complete column connections along the north side of the Dulles Airport Station. VIVARESTON.COM