One High School vs Two High Schools Cost Analysis

Page 1

Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013 COST ANALYSIS: FIRST COST (CONSTRUCTION) Budget Concepts: New High School is 36,000 SF larger than the High School addition for this comparison. Per MDE Guidelines a 900 student HS average is 205 SF/St. 1300 student HS average is 190 SF/ST (not including theatres). New building construction cost bid 2014 - $195/SF (assumption). Addition square footage cost is often a bit more expensive than new building (current assumption 22% more at $237.9/ SF ave) New buildings project costs are often higher than additions due to city development/infrastructure costs and fees (multiplier 1.3 vs. 1.25). Option A: High School Addition 900 Students x 165 SF/Student = 148,500 SF Building Construction

148,500 SF x $ 238/SF $ 35.343 mil x 1.25 $ 44.178 mil

(Bid 2014) Construction Cost Project Cost

Site development of 37 additional acres plus redevelopment of 17-22 existing acres (site changes: roads, fields) $ 6.45 mil $ 7.4 mil Additional site purchase: 37 acres Total project cost: $ 58.028 mil Option B1: A Second High School (900 Students) 900 Students x 205 SF/Student = 184,500 SF Building Construction

184,500 SF x $ 195 $ 35.977 mil x 1.3 $ 46.770 mil

(Bid 2014) Construction Cost Project Cost

Incl. New site development of 44-49 acres $ 10.0 mil New site purchase 44-49 acres (useable) Total project cost $ 56.77 mil Option B2: A Second High School (1,300 Students) 1,300 Student x 190 SF/Student = 247,000 SF $ 62.615 mil 247,000 Sqft. x $195 x 1.3 Incl. New site development 47-59 acres $ 10.7 mil New site purchase 47-52 acres (useable) Total project cost $ 73.315 mil Summary: Housing 900 students whether in an addition to your High School or a second High School, will be very similar in first cost. The actual proposed High School addition differs from “Option A” above as it includes some additional needs beyond only student capacity. (Examples: Community Gym Space, 2nd Auditorium, Gymnastics Gym etc.) total potential square footage = 192,226 SF, project cost with land $66.17 mil. KL/ISD_284/102131/community taskforce/cost_analysis

Page 1

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013

COST ANALYSIS ANNUAL OPERATING COSTS (UTILITIES, ETC.) Option A (148,500 SF) Addition to High School Natural Gas Electricity Water/Sewer Garbage Internet Telephone Copiers Insurance

Annual Cost $36,591 $118,617 $15,856 $0 Same $0 $3,660 $14,000

Option B (184,500 SF) Second High School Natural Gas Electricity Water/Sewer Garbage Internet Telephone Copiers Insurance

TOTALS $188,724

Annual Cost $45,461 $147,472 $19,700 $4,500 Same $294 $6,000 $17,500 $240,827

Cost Difference $8,870 $28,755 $3,844 $4,500 $294 $2,340 $3,500 $52,103

Summary: Opening a Second High School has some additional utility costs compared to a high school addition.

KL/ISD_284/102131/community taskforce/cost_analysis

Page 2

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013

COST ANALYSIS ANNUAL OPERATING COSTS (STAFFING COSTS) Option A Addition to High School Associate Principal Assoc. Prin. Secretary N/A N/A Additional .5 Para Food Svs. Employee Custodian N/A N/A Additional Salary N/A Activities Coordinator N/A N/A Additional Staff N/A N/A N/A N/A N/A

Cost $128,880 $40,409 $0 $0 $16,078 $18,452 $47,779 $0 $0

Option B Second High School Principal Head Secretary Office Para Front Door Greeter Health Para Food Svs. Manager Head Custodian Grounds (.5) Maintenance

Cost $151,441 $55,057 $26,451 $30,229 $32,155 $31,549 $54,496 $25,147 $50,294

Cost Difference $22,561 $14,648 $26,451 $30,229 $16,078 $13,097 $6,717 $25,147 $50,294

$2,000 $0 $98,709 $0 $30,970 $5,928 $0 $0 $0 $0 $0

Department Chairs Auditorium Coord. Activities Director Media Specialist Vision 21 - .5 Lunchroom Supervision Instrumental Director Vocal Director Orchestra Director Equipment Manager Website Editor

$14,000 $4,355 $113,533 $61,941 $30,970 $8,563 $6,700 $6,700 $4,700 $5,000 $3,000

$12,000 $4,355 $14,824 $61,941 $0 $2,635 $6,700 $6,700 $4,700 $5,000 $3,000

Athletics and Activities

$358,962 $1,075,243

$226,653 $553,729.50 Additional Annual Cost for Second High School

Athletics and Activities $132,309 TOTALS $521,514

Notes: No benefits were included in the costing this would typically run another 15-25%. Summary: Opening a Second High School has some additional salary costs compared to a high school addition. Teaching staff would be indirect proportion to students and therefore no difference in costs.

KL/ISD_284/102131/community taskforce/cost_analysis

Page 3

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013

COST ANALYSIS ANNUAL OPERATING COSTS (ACTIVITIES COSTS) Option A Addition to High School Additional Teams Non-Staff Costs

Additional Co-curricular Non-Staff Costs

Cost

Option B Second High School

Cost

Cost Difference

$TBD

All Teams Non-Staff Costs

$TBD

Assumed Negligible

$TBD

Additional Co-curricular Non-Staff Costs

$TBD

Assumed Negligible

KL/ISD_284/102131/community taskforce/cost_analysis

Page 4

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013

COST ANALYSIS ANNUAL OPERATING COSTS (TRANSPORTATION, ETC.) Option A Addition to High School - Additional Transportation 900 Students

Cost

Option B Second High School

Cost

Same

- Additional Transportation 900 Students

Same

- Shuttle between campuses

$10,000

$10,000

TOTALS $10,000

$10,000

TOTALS $0

KL/ISD_284/102131/community taskforce/cost_analysis

Page 5

Cost Difference

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013

COST ANALYSIS: SUMMARY

First Cost Summary: Building Land Site Development Furnishings Equipment Project Costs Totals

Option A High School Addition

Option B 900 Student High School

Cost Difference

$35.343 mil $7.4 mil $6.45 mil Included * Included * $8.835 mil $58.028 mil

$35.977 mil $10.0 mil Included Included * Included * $10.793 mil $56.77mil

$1,258,000

* Note: Both project cost multipliers include start-up cost for furnishings and equipment. This allowance is 10% of the building construction cost.

Option A High School Addition

Option B 900 Student High School

Cost Difference

Operating Cost (utilities)

$188,724

$240,827

$52,103

Staffing Cost

$521,514

$1,075,243

$553,729

Activities Cost

TBD

TBD

TBD

Transportation Cost

$0

$10,000

$10,000

Food Service Costs

Included above

Included above

Included above

Maintenance Costs

Included above

Included above

Included above

$1,326,070

$615,832

Annual Costs Summary:

Indentified Annual Cost Totals $710,238 Summary:

First Cost: The addition is likely somewhat more expensive. Estimate $1.258 mil. Annual Operating Costs: The 2nd High School is more expensive. Estimate $615,832 Annually Over 20 years: The additional operating costs could exceed $12 million (in today’s $). Operating Costs are often an important differentiator when looking long term.

KL/ISD_284/102131/community taskforce/cost_analysis

Page 6

Commission No. 102131


Independent School District #284 – Wayzata Public Schools Community Taskforce on Facilities Draft: May 1, 2013 COST ANALYSIS START UP COSTS (ACTIVITIES COSTS) Option A Addition to High School

Option B Second High School Football Track Basketball Tennis Golf Wrestling Volleyball Soccer La Crosse Baseball Softball Band Choir Hockey Swimming Drama SUBTOTALS Media Center Phy Ed Equipment Weight Room Marching Band Science Buildings and Grounds Culinary Computer Lab FACS SUBTOTALS TOTAL Less Allowance in First Cost Construction Unfunded Difference

Cost

KL/ISD_284/102131/community taskforce/cost_analysis

Page 7

Cost $103,830 $50,266 $12,260 $13,020 $3,400 $35,025 $15,675 $41,190 $15,670 $11,700 $4,050 $191,000 $60,500 $33,100 $51,850 $50,000 $692,536 $75,000 $46,000 $125,000 $181,000 $20,000 $150,000 $150,000 $30,000 $5,080 $782,080 $1,474,616 $1,439,000 $35,616

Cost Difference

Commission No. 102131