UK Power News - July/August 2024

Page 1


JULY-AUGUST 2024

The Drumcross Flexible Energy Plant is a 22.5MW site in Livingston, West Lothian. It has been built by Clarke Energy acting as the principal contractor.

Once operational Drumcross will supply electricity to SPEN and National Grid during periods of high demand on the electricity network.

The plant comprises 5 Jenbacher 4.5MW engines capable of ramping up to full capacity in just 5 minutes. The facility is scheduled for completion in late 2024.

Once it is up and running Drumcross will help SPEN and National Grid balance supply and demand by providing backup electricity during periods of high demand or low renewable generation, thereby ensuring a secure supply of electricity for local homes and businesses.

Forsa, the company behind the Drumcross project, has successfully developed, financed, and constructed 8 operational sites in GB, with a combined installed capacity of 196MW.

It currently has a further 103MW of plant under construction and scheduled to energise over the next 6 months, plus an additional 250MW development pipeline of contracted sites.

DON’T MISS POWEREX LIVE IN LONDON

Held at the prestigious Park Plaza, Westminster Bridge, London. Scheduled for Thursday, Dec 12th, 2024. 09:15 – 16:00

See page 2.

HVO IS THE ANSWER

Andy Towse, Product Quotes Manager at Dale, explains how using HVO could reduce CO2 emissions by up to 90%, with a reduction in NOx as well.

See page 12.

DRUMCROSS

FLEXIBLE ENERGY PLANT NEARS COMPLETION AT THE SITE NEAR WEST LOTHIAN

Forsa is well on its way to achieving its business target of 5-600MW of flexible energy generation capacity in the UK market. Drumcross will soon become the 12th operational site in the Forsa fleet, utilising fast start, high efficiency, H2ready generators. Once operational the site will export 20MW of electricity at short notice to the local distribution network during

times of high demand and low renewable output, efficiently supporting security of supply during the energy transition.

A spokesman comments: "Our business operates on a ‘cradle to grave’ principle, meaning that we develop our projects knowing we will be funding and constructing them. "We also construct our projects, knowing that we will be operating them."

DOWN THE PUB Target Power Generators won a contract to supply a large open-type generator to provide power for an iconic & highly-popular London barThe Castle Pub. See page 29.

Maximum Availability and Performance of MWM CHP and gas power plants: MWM gas engines and generator sets, including our original spare parts, are designed for top performance and efficiency. Governed by the same regulations as production parts, our spare parts ensure hassle-free operation, adhering to high-quality and availability standards.

www.mwm.net/spareparts

Publisher/Sales Director:

Neb Saric neb@wipmagazines.com

Publishing & Events Director:

Richard Teasdale richard@wipmagazines.com

Managing Editor: Aidan Turnbull aidan@wipmagazines.com

Accounts Manager: Alison Williams accounts@wipmagazines.com

Sales & Marketing Manager

Sarah Hallows sarah@wipmagazines.com

Far East Sales: Bob Liu

Room 926, No.1 Building, Phase II No.100 Jinyu Road, Pudong Shanghai, China

Mobile:+86-013817410089

Email: bob.liu@ronco.com.cn

Austria & Germany agent

Mario Dobresko power@wipmagazines.com

Contributors

MWM, Dale, Mecc Alte, Crestchic, Aprovis, UKGSA, Innio, Clarke Energy, CENTIEL, CENTRICA, THE SHENTON GROUP, Finning Energy &Transportation WB Power Services, Constant Power Solutions (CPS), PERKINS, Cummins Power Generation FPT Industrial/Iveco Group/ HiPower Systems, Siemens, X-Links, AFC, Genesal Energy, FW Power, Teksan, Green Power Systems, STAMFORD, Yellow Power, Rolls-Royce, MEMS, Eminox, EDINA, William Thompson & Sons, Yanmar Energy,Atlas Copco, Powersystems. ****************

UK POWER NEWS

Published by:

Power Media International Group Ltd, The Courtyard, 30 Worthing Road, Horsham, West Sussex, RH12 1SL, UK

Tel: +44 (0)1403 888019

Fax: +44 (0)1403 220751

powermediagroup.co.uk © Worldwide Independent Power (ISSN 1468-7100).

Subscription price £70 (UK), £140 (overseas) per year. Please send address changes to UK Power News, Power Media International Group Ltd 30 Worthing Road, Horsham, West Sussex RH12 1SL, UK.

SGT5-9000HL GAS TURBINE IS OFFICIALLY LISTED AS A GUINNESS WORLD RECORDS TITLE HOLDER

Siemens Energy’s SGT59000HL Gas Turbine at SSE Thermal’s Keadby 2 power station in North Lincolnshire, UK is now Guinness World Records title holder for the most powerful combined cycle power plant and the most efficient combined cycle power plant.

The two records were based on site specific test results corrected to ISO conditions and evaluated by external companies,

The efficiency record of 64.18% was verified in May 2024, in a plant powered by an SGT5-9000HL gas turbine. It is also the most high capacity combined cycle plant, at 849.45 MW. At such a power level, efficiency gains mean significant savings of resources.

In addition fast gas turbine ramping at the plant provides flexibility that allows it to complement renewable generation. It can also contribute to the UK’s net zero aims, with plans for decarbonising further, by introducing the potential to blend hydrogen into the plant fuel mix.

Construction of Keadby2 began in August 2018 and it was officially handed over in March 2023. It benefits from up-to-date power generation technology including the Siemens SGT5-9000HL 50Hz turbine which is considered the most efficient on the market and includes state-of-the-art 3D printed parts as part of its design.

SSE’s Keadby 2 is now in commercial operation. It is expected to be the cleanest and most efficient gas-fired power station in Europe, and is calculated to contribute over £1bn to the UK economy over its lifetime.

ANOTHER SUCCESSFUL POWEREX LIVE MIDLANDS

PowerwerEx Live Midlands 2024, held on Thursday, June 27th, 2024, proved highly popular with a genset and CHP sectors of industry. Conference Chairman Dave Andrews, of Claverton Energy, comments: “I fully believe this has been the most successful and best-attended PowerEx Midlands event ever.”

Hosting some of the foremost energy speakers in the country, this regional event - with an associated golf tournament held the day before the event (on June 26th, 2024) - offered all key sector players in the North of England a unique opportunity. They were all able to assess new trends, connect and develop all under one roof over the course of a single day. The event was sponsored & supported by UK Gen-Set and CHP Association (UKGSA) - see page 31 for more.

Just as in the previous year, the venue was the award-winning hotel and golf resort situated in the heart of the country - the Belfry Hotel and Resort in Royal Sutton Coldfield, West Midlands. The site offered 300+ luxurious bedrooms and suites. A major attraction was The Brabazon Gold Course, recognised as worldclass, having previously hosted The Ryder Cup more than any other venue in the world and home to the 2024 Betfred British Masters. One customer commented: " It takes real genius to make a success of combining a dedicated golf day on the Brabazon Course with a whole 2nd day looking at the best of the genset industry."

An event which has built upon success In 2023 the Mere Golf & Spa Club, Knutsford, Cheshire, was the setting for the first Power Media International Group’s PowerEx Live regional conference & exhibition.

The 2023 event was described by one attendee as “business, education and excellent golfing all rolled into one.”.

Adam Thomas, CTO, also commented on the PowerEx Live event in Cheshire: “Thanks for running the event, it was a good place to network with other people in the generator industry. The talks were informative and helped to give a good summary of the issues and opportunities in the market.”

If you enjoyed the PowerEx Live Midlands event - there is even more to come on Dec 12, 2024, London

Held at the prestigious Park Plaza, Westminster Bridge, London, 09:15 – 16:00 on Thursday, December 12th, this event aims to offer the perfect networking opportunities.

The GEN-SET, CHP & ENERGY LIVE Conferences are attended annually by a host of professionals across the Genset, CHP, Data Centre and Consultancy industry sectors. All the speakers were greatly appreciated by those present, with very well-attended lecture areas. Speakers featured were: Ian Bitterlin, Eric Lewis, Steve Peal, Mark Acton, Romain Mocaer from PowerGen Statistics, Venessa Moffat, Michaela Kendall and Dave Andrews of Claverton Energy. Other key speakers included Professor Pearson , Dr David Tok , Paul Woods, Josh Collins and Steve Hone from the Data Centre Alliance Conference Papers from PowerEx Midlands Live are available to download free online from the website.

Don’t miss PowerEx Live held on 12th December, 2024, London

PowerEx Live 2024 - THURSDAY 12th DECEMBER, Location: LONDON, UK

PowerEx Live 2024 at London’s Park Plaza Hotel, will be held on Thursday 12th December, 2024.

PowerEx Live 2024 aims to offer the perfect networking opportunities for international professionals across the Genset, CHP, Data Centre and Consultancy industry sectors.

With conference speakers at GEN-SET, CHP & ENERGY LIVE the top of their respective fields you can be sure to glean some valuable insights into the industry. The conferences are held alongside premier display space in a world class venue. This event has become a priority for all those in the power and energy markets. The conferences will run parallel with prime exhibitor space available in adjoining rooms. Do not miss this opportunity for networking with experts in all fields of CHP, Data Centres, Consultancy and Gensets.

The Power Hub Learning Zone

PowerEx Live 2024 will again feature a special Power Hub Learning Zone. The training experience will cover four subjects presented by different companies & speakers . The object is to teach, inspire and educate students, young people and fellow industry professionals about the importance of equipment familiarisation and other key aspects of the training experience within industry. This highlight of the UK’s Power & Energy calendar for 2024 is being held at . London’s iconic South Bank hotel, the Park Plaza, Westminster Bridge, London.

UK TO GET DESERT-DERIVED POWER BY 2034 THANKS TO US$14.1 MILLION

INVESTMENT - PROJECT COMPLETION BY 2034 LATEST

X

Xlinks First Ltd. has announced a $14.1 million investment from Africa Finance Corporation (AFC), the continent’s leading infrastructure solutions provider, to further the development of Xlinks’ UK - Morocco Power Project, which will provide affordable, reliable, clean energy from Morocco to Britain within a decade.

AFC’s support marks a significant milestone for the project, affirming Morocco’s role as a continental renewable energy leader, and demonstrating how Africa’s enormous renewable energy potential can provide solutions to benefit the global energy transition.

Once complete, the project’s wind and solar generation, combined with flexible battery storage, will supply 3.6GW of affordable, reliable, clean power to deliver 8% of the Britain’s current electricity needs – or the equivalent of 7 million homes. The new electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to Britain via 4,000km HVDC sub-sea cables.

The project will drive the creation of thousands of employment opportunities including a significant proportion of qualified jobs, supported by training and certification programs, which will help to consolidate the pioneering role of Morocco’s renewables expertise as a regional and continental energy hub. The project will also foster the establishment of an integrated renewable energy industrial ecosystem, including industrial production of renewable energy equipment, transformation, transport, storage, and reconversion, which combined will serve as a locomotive for growth and economic development.

Samaila Zubairu, AFC President & Chief Executive Officer, said: "Africa, with its immense renewable energy potential and vast natural resources, stands at the forefront of global net zero aspirations. Xlinks’ Morocco-UK Power Project exemplifies this pivotal role, showcasing Africa's capability to fuel Europe's shift to sustainable energy while simultaneously addressing urgent climate challenges.

"By harnessing the abundant wind and solar power of the Sahara and channeling it directly to one of Europe's largest energy markets, this project not only boosts the growth of Morocco's economy through significant export revenues but also catalyzes the development of local clean energy industries. As this transformative project advances, it will not only benefit Morocco and Africa but also significantly contribute to reducing greenhouse gas emissions, with the majority of investments set to drive this change occurring within the Global South."

James Humfrey, CEO of Xlinks First, said: “Securing AFC as an investor is a significant step forward in the development of the project. We are excited to be partnering with AFC, a leading financial institution created by African sovereign states, including the Kingdom of Morocco. They bring an unparalleled understanding of, and experience in, African infrastructure. Their mission - to foster economic growth and industrial development on the continent - aligns closely with the planned outcomes of the Morocco-UK Power Project."

TWO

GEN2250HC EMERGENCY POWER GENERATORS INSTALLED AT NHS

EASTBOURNE

HOSPITAL, EAST SUSSEX

The Eastbourne NHS Hospital needed to extend its emergency network with two new generating sets. It turned to GENESAL ENERGY to supply two GEN2250HC generators.

Features of the new units include: walls fitted with high-thickness acoustic panels and a synthetic foil for special soundproofing, guaranteeing also EI120 fire resistance.

The package includes outlet Air silencers fitted to the container and Inlet Air silencers integrated into the container.

Each of the generators is powered by a Mitsubishi S16R PTA engine fitted with a Mecc Alte ECO46 2S4A alternator on a base frame. Also supplied is a certified 1,000-litre double-walled (steel-steel) tank inside the container and exhaust gas silencers providing -40 dB

attenuation.

The gensets come with C5 paint surface treatment, according to ISO12944, an automatic fuel transfer system, special power outlet busbars for coupling to the busbar trunking system and motorised air inlet and outlet louvres and indoor space heaters.

GENERATOR SUPPLIED TO A TRANSPORTATION COMPANY BASED IN BURTON

A 330 kVA Doosan generator set was supplied to a well-known transportation company based in Burton by Teksan UK's North West Dealer, FW POWER.

The diesel generator set is used to provide a backup power for an office site. If the power goes out in the middle of a day, the generator kicks in and let people continue getting on with their jobs without interruption, says the company. This is a typical backup power equipment genset provided by Teksan UK.

For more than 25 years, thanks to its solid experience and engineering know-how, Teksan has been providing tailormade power solutions that can efficiently operate even under the most challenging conditions for major international projects such as constructions, telecommunications, data centres, shopping centres, hotels, residential buildings, supermarkets, sport

centres, mining facilities, hospitals, research centres, educational institutions and industrial plants all around the world.

Today, thanks to its high-quality generator sets approved with international quality certifications which are made of world’s top engine brands coupled to well know alternators to meet projects’ requirements of different output ranges, and fast and effective after-sales technical support and maintenance services in more than

Game-changing fuel efficiency

After a decade of engineering innovation, our next generation engine platform for industrial operations is here, ready for the challenges of today and tomorrow. More efficient, more powerful and more durable – all powered by cutting-edge technology. Scania has raised the bar.

Our new platform unlocks increased value from every drop. An up-to seven percent improvement in fuel consumption combined with an extended engine lifespan means you get more for longer. And reduced CO2 emissions across the range means you also get ready for sustainability regulation.

Step into the future of power solutions.

UNIQUE ALTERNATOR CHOSEN FOR RECENT NHS BACKUP GENERATOR

Green Power Systems Srl has been involved in the installation of standby power - based on a Cummins QSK78G9 - for an NHS hospital in England, ensuring the healthcare facilities had access to reliable back up power and playing a critical role in uninterrupted power supply, particularly during emergencies and grid failures. The standby power installed provides a reliable backup power source, enabling them to continue their critical operations, such as life-saving medical procedures and patient care, even during power outages.

Green Power collaborated with STAMFORD | AvK during the specification process of the project for their expertise in power solutions and their understanding of the healthcare sector which played a crucial role in ensuring that the systems met the stringent requirements of hospitals.

Green Power Systems Srl is a dynamic Italian company, leader in the design and manufacture of diesel generator sets. Green Power has achieved a primary position in both the Italian and international market thanks to its strength points: high quality products, reliable performances, worldwide after sales service and global dealers network.

The most relevant care of Green Power is the total customers’ satisfaction with the constant improvement of the products and services, with continuous innovation and technologies at the forefront and with a team of professionals that are always committed to establish professional as well as interpersonal consolidated relationships with collaborators and customers. Green Power is engaged in activities to support their local community and offer a broad product range for multiple kind of applications and with low emissions systems. Their systems are designed to meet the power requirements of various projects; with a capacity of 3000kVA, their solutions cater to a wide range of applications, from residential to industrial projects.

QSK78 G-Drive engine provides the optimal combination of productivity and performance. Its 4060-horsepower (3028 kWm) V18 configuration incorporates the best features of our QSK Series engines, including advanced combustion technology and robust base engine components. Featuring a high pressure (HPI-PT) full authority fuel system, the engine meets Tier 2 and 2gTA Luft emissions and has exceptional fuel efficiency. The CM2250 ECM provides the Power Generation Interface (PGI), the widely accepted SAE J1939 industry standard CAN based communication network and advanced engine protection, ensuring faster connectivity along with a superior fault-finding capability. Plus, the QSK78 comes with optional features like ELIMINATOR™, CENTINEL™, and Prelub™, which help to significantly reduce downtime for routine maintenance. Each QSK78 engine is covered by Cummins base warranty, one of the most comprehensive and simplest plans in the industry.

Features & Benefits are as follows:

- CTT (Cummins Turbo Technologies) HX82/HX83 turbo-charging – Utilizes exhaust energy with greater efficiency for improved emissions and fuel consumption.

- Ferrous Cast Ductile Iron (FCD) Pistons – The design and material used in these types of pistons ensure increased engine efficiency and durability. Reduces ‘piston slap’ and increases power efficiency.

- High Pressure Injection Fuel System – Provides a high-peak injection pressure for optimum combustion for low emissions and better fuel economy. HPI fuel injection provides a “soft” injection start for lower combustion noise.

- Low Temperature After-cooling – Enabled by a Two-Pump Two-Loop (2P2L) cooling system that utilizes 2 separate cooling circuit that allows for longer engine durability and fuel economy.

- G-Drive Integrated Design – Each component has been specifically developed and rigorously tested for G-Drive products, ensuring high performance, durability and reliability.

- Service and Support – G-Drive products are backed by an uncompromising level of technical support and after sales service, delivered through a world class service network.

The alternator installed in Green Power gensets - based on the Cummins QSK78G9 - is recognised as a crucial component in power generation systems, with the STAMFORD P80 HV at 2500kVA utilised in this particular healthcare project.

One of the key considerations in selecting the STAMFORD P80 HV alternator for this project was for its ability to withstand vibrations while maintaining optimal performance, in addition to its reliable and efficient reputation.

"STAMFORD alternators were specifically selected for their reliability and high level of quality - they now play a crucial role in supporting the healthcare sector," reports a spokesman.

31SG GAS ENGINES

ARE NOW SERVING A PEAKING POWER PLANT

Four 31SG gas engines are being supplied to CENTRICA as a key part of a 48 MW peaking power plant to support the growing use of renewables in the UK.

The plant, currently under construction in Brigg, Lincolnshire, is being delivered under an engineering, procurement and construction contract with British energy services and solutions provider CENTRICA. Once completed, the plant will provide essential grid balancing power generation alongside an existing 49 MW peaking plant in Brigg, Lincolnshire.

At the heart of this project are four highly-efficient gas engines: the new plant will operate with four 31SGs. These can reach full output within 2.5 minutes, present no minimum up or down time and are described as ideal for compensating the intermittent supply from wind and solar power.

“We are extremely pleased to support Centrica in their efforts to

decarbonise power production. This installation will help enable the use of clean renewable energy by providing the needed grid balancing. The Wärtsilä 31 engine platform is renowned for its high efficiency, and the engines are already able to run on a hydrogen blend. In the future our engines can be converted to run on sustainable fuels once they become widely available,” says Ken Engblom, Vice President Africa & Europe at Wärtsilä Energy.

Together, these assets will create nearly 100 MW of fast response capacity, ensuring reliable power supply. At the heart of this project are our highly efficient gas engines: the new plant will operate with four Wärtsilä 31SGs.

These can provide the following qualities:

-They can reach full output within 2.5 minutes

-No minimum up or down time -Ideal for compensating the intermittent supply from wind and solar power.

10MW UK FLEXIBLE POWER PROJECT WITH CARBON CAPTURE

Four Rolls Royce 16V engines were recently 'hot commissioned' by the National Grid at a flexible power project, RPL, with carbon capture and re-use 'CCR'.

The full testing and commissioning process took two weeks, during which time the units successfully generated power to the grid.

The first of the 16V engines was run up to speed and - after off-load testing - was synchronised to the grid and had power exported in March 2024.

The gas for the run - and the resultant electrical export - were both provided and received respectively under the commissioning arrangements, which form part of the Axpo PPA.

The 'hot commissioning' tests were carriued out successfully by Landmark Power Holdings, Yellow Power Ltd and Roll Royce mtu solutions under the supervision of

National Grid Energy Distribution (NGED). The operations of the power plant, comprising four Rolls Royce 16V engines, have now been transferred to LMPH.

The timeline for the testing and integration of the CCR element is on track to be completed during the remainder of 2024 with all key equipment, including the Asco CO2 scrubbing units and exhaust piping, now on-site and installed.

UK DATA CENTRE UPGRADE ALSO INVOLVED THE

CONSTRUCTION OF A BESPOKE ENERGY CENTRE

Whena major telecoms company sought to expand its data centre operation, it turned to Shenton Group to provide additional generators. These were installed alongside the company’s existing 19 generators and in conjunction with an Uninterruptible Power Supply system support, all within and around the construction of a new, bespoke Energy Centre.

The telecoms company had expanded its data centre operation, something which necessitated the building of a bespoke Energy Centre to house new generators. New servers needed to work in conjunction with an Uninterruptible Power Supply and backup generator support in order to ensure continuity of service in the increasingly likely event of power outages.

As the Energy Centre is situated in an urban environment, the telecoms company stipulated that the generators should have the necessary attenuation so as not to exceed sound levels of 65dBA at one metre.

Shenton Group’s Sales and Marketing Director, Curtis Meek explained the magnitude of the project and some of the factors that Shenton Group needed to consider in order to achieve a timely, problemfree delivery: “Considering the existing 19 generators, two new generators needed configuring in conjunction with an Uninterruptible Power Supply System. Therefore, the project needed to be orchestrated around the customer’s new Energy Centre building design work. Shenton Group’s installation work had to be undertaken out of hours and also whilst the building was still being constructed”.

Shenton Group successfully beat a number of competitors to win this major project. Working closely with the project’s Specifier, Shenton Group provided a complete turnkey operation including; design, supply, installation, testing and commissioning. With eight months in planning and implementation, and involving a team of 13, Shenton Group supplied two 3200kVA standby generators. Shenton Group’s Curtis Meek highlighted how Shenton Group’s planning phases consider all possible outcomes, including future expansion of clients’ businesses: “The generators have been installed on the ground floor of the Energy Centre and in separate rooms, designed so that a further two generators can be added at a future date if required.” Should the necessity arise, both generators are capable of providing prime power at 2920kVA with a 0.8 lagging power factor and with a 10% overload capability for a minimum of one hour. Shenton Group has also provided fuel tanks with sufficient capacity to enable the generators to run for eight hours at full load.

As the Energy Centre is situated in an urban environment, the telecoms company stipulated that the generators should have the necessary attenuation so that they do not exceed sound level of 65dBA at one metre. The generator rooms are therefore equipped with inlet and outlet attenuators with motorised louvers that have been sized to provide the appropriate combustion and air-cooling airflow requirements.

Remote Alfa Laval radiators had to be craned onto the roof of the new Energy Centre building to cool each generator. The radiators’ height is less than that of the surrounding louvres and they operate at noise levels of less than 65 dBA at one metre. These are connected to the generators by two cooling circuits per generator in 6 and 3 inch welded stainless steel pipework.

Further project work involved Shenton Group installing two 5000A Air Circuit Breaker Panels (ACBs). Both panels are adequately ventilated to allow continuous full load operation in the maximum ambient temperature likely to be present in the generator house during prolonged ‘on load’ runs. All internal connections within the panels are by means of 5000 Amp copper busbars, adequately spaced to allow for loadbank testing. Together, a total of 4850 metres of cable was used, equivalent to 3.2 miles. Load bank testing was carried out using 3500kVA Resistive/Reactive loadbank and all the necessary step loads and cold start tests were performed successfully.

PROVIDING STANDBY POWER TO A LEADING PRIVATE HOSPITAL IN THE UK

A backup failure at one of the UK’s leading independent healthcare providers required an immediate resolution.

A power outage in a hospital environment can be devastating. It may impact numerous services, including routine operations, complex surgeries, medical equipment and building infrastructure, all of which could compromise patient care.

In addition, the hospital also runs three specialised neurological rehabilitation residential centres, providing care for residents with complex neurological conditions. Hence the hospital needed a supplier to provide a rapid power supply to ensure they stayed online.

The client approached MEMS Power Generation to supply standby power whilst repairs were made to the hospital’s malfunctioning backup generator to reduce potential harm to the facility and its patients. MEMS has considerable experience delivering critical power to hospitals in short time frames –which was crucial to the continued running of the hospital.

The MEMS team determined that a 500kVA temporary generator would provide ample power to the London hospital should the need arise.

To ensure the temporary generator was connected, ready and waiting to deliver power when necessary, a fuel bulk tank and 125 metres of 240mm cable were all connected, installed and hooked up within 3 hours of

receiving instruction. The temporary standby generator installation was commissioned, and the hospital could continue providing its services uninterrupted.

MEMS helped the hospital stay up & running without the threat of a power outage.

The generator was in place and on standby for 14 days with 24/7 remote telemetry and fuel management support from MEMS if it had been required.

The job ran smoothly, with everything going to plan, reports the company. The hospital could run all its services, equipment, and residential centres continuouslyand safe in the knowledge that a tested temporary hire solution was in place.

The client was particularly impressed with the initial contact and quick response of the MEMS 24/7 staffed control room, as well as highlighting the company's skillset, knowledge and the exceptional work and helpfulness of the MEMS team on site.

MEMS Power Generation began in 1978 as an electrical engineering company. Since then it has grown to become one of the leading specialists in temporary power solutions, operating one of the country’s largest temporary generator rental fleets. A spokesman comments: "We are proud of our heritage as well as the fact that our customers value our commitment to high-quality service."

£1 MILLION + INVESTMENT AT NEW HEADQUARTERS IN THE UK

Continual investment is at the forefront of operations at Eminox, and the company reports its most recent programme has brought greater operational health and wellbeing benefits to the Eminox UK HQ.

The investment, of more than £1M, has seen significant operational improvements to the Eminox manufacturing areas to allow the installation of key equipment which both elevates production facilities and brings tangible benefits to all Eminox stakeholders.

The focal point of the installation is a Comas automated canning line which provides flexibility and consistent quality in volumes to suit

customer demand for the company's exhaust aftertreatment systems (EATS). This helps Eminox to support customers at its accredited facility, across many industry sectors requiring the latest in emission reduction technologies. including maritime, on road, power generation, agriculture AND non-road mobile machinery (NRMM).

The latest V-Type alternator has been developed in response to changing market needs and has been built for optimum performance and reliability in harsh marine environments. Having undergone rigorous testing, the V-Type is designed to deliver optimal uptime, so you can be sure of reliable power generation, regardless of the operational conditions and compliant with all marine classifications. With over 75 years in the power generation market we pride ourselves on being the Power from Within the systems and generator sets that our customers produce.

Choose wisely… Choose the V-Type.

The world’s largest independent producer of alternators 1-5,000kVA

UK BATTERY ENERGY STORAGE PIPELINE EXCEEDS 95 GIGAWATTS

EDINA reveals that the latest report from the trade association RenewableUK shows a significant surge in the total pipeline of battery energy storage projects, reaching a staggering 95.6GW, representing a remarkable 67.4% increase (38.5GW) from 57.1GW the previous year.

This substantial growth marks the second consecutive year the pipeline has experienced such significant expansion. The total includes a range of battery projects at various stages, from operational to those being planned.

The data underscores the increasing momentum and interest in battery storage within the energy sector, showcasing the industry's commitment to embracing innovative technologies and sustainable solutions. With such a promising outlook, the future of energy storage is bright and full of potential for further growth and development.

“It’s great to see that, for the second year running, the UK’s battery storage pipeline has grown by two-thirds within the space of twelve months. The appetite among investors to enter this rapidlygrowing market remains enormous,” explains Barnaby Wharton, Director of Future Electricity Systems, RenewableUK.

“Batteries have a key role to play in ensuring that electricity supply always meets demand. While there has been significant uptake in projects, we are far from delivering the 55GW of short-term flexibility by 2035 that the government says we need in its Review of Electricity Market Arrangements. We have the potential to move much faster by speeding up the process of consenting and connecting vital energy storage projects to the grid.”

PROVIDING ESSENTIAL EXTRA POWER CAPACITY FOR ONE OF THE UK'S LARGEST RECYCLING PLANTS

When William Thompson & Son decided to build a recycling facility in Scotland - one of the largest recycling plants in the country - it was quickly realised there was not enough spare utility power capacity on site. Extra power needed would have to be generated onsite.

The plant manufacturers and Thompson calculated an extra 500 kVA would be needed to run the plant. Westfield Generators became involved to provide a reliable power solution to power the industryleading technologically-advanced recycling plant.

The Recycling Centre is one of the largest of its kind in the UK and has the highest specification due to the latest patented technology. The plant will recycle all incoming and existing inert waste at Riggangower Landfill site into 5 different aggregate sizes and 2 grades of sand. It has a throughput of 120 tonnes per hour and Silts will be handled via a filter press thereby avoiding the need for settlement ponds.

Also, graded topsoil and subsoils will be created as part of the waste selection process of the plant. A Cat C15 500 Kva generator was supplied and installed alongside a 10,000 litre Bulk Fuel Tank which is connected to the generator with

The operational capacity of battery storage has surged to 4.4GW, with projects under construction now totalling 4.3GW. The average project size seeking planning permission has increased by 53MW or an impressive 196%, climbing from 27MW in 2019 to 80MW today.

According to RenewableUK, an additional 30.4GW has received approval, while 26GW is currently in the planning stages.

It has been reported that another 30.4GW is in the early stages of development but this has not yet been submitted so far.

a fully compliant double skinned fuel pipe system. The tank is also fitted with a fuel dispensing system used to fill the fuel tanks of mobile machinery used in the operation of the plant.

The generator is fitted with battery charging and engine heaters to ensure prompt starting and reduce engine wear. The machine is remotely controlled from the Plant Control Room.

About the 320 - 500 ekW diesel generator set: the C15 diesel generator sets have been developed for mission critical, standby and prime applications.

They produce reliable power from 320 to 500 ekW at 60 Hz, meeting ISO 8528-5 transient response requirements and are built to accept 100 % rated load in one step.

The engines are certified Low Fuel Consumption, U.S. EPA Certified for Stationary Emergency Use Only (Tier 2 or Tier 3 Nonroad Equivalent Emission Standards), EU Stage IIIA Nonroad Emission Standards, China Nonroad III Emission Standards. Features of the genset include: - Integrated Cat® Product Link™ Control System -Track Genset Health and Operation Parameters - Genset Utilization and Performance Tracking - Remote Connectivity Optimised.

NEW 35 KVA HYDROGEN-BASED FUEL CELL POWERPACK AVAILABLE

The HP35FA1Z is a compact and multi-unit controllable hydrogen fuel cell power generation system produced by Yanmar Energy Systems Co., Ltd.

The HP35FA1Z uses a proton exchange membrane (PEM) fuel cell and has a power output of 35 kW during grid connection and 35 kVA during standalone operation.

The compact unit weighs 1,650 kg and measures 2,340 mm wide and 900 mm deep with has a height of 2,290 mm.

The system does not emit greenhouse gases like carbondioxide (CO2) or air pollutants such nitrogen oxides (NOx) during operation, reports the company.

The unit's compact design includes all necessary operating equipment, simplifying installation and achieving one of the smallest footprints in its power output class. The HP35FA1Z supports the integrated control of up to 16 units, allowing for adjustment of operating units and output control based on power demand and available hydrogen supply.

THE UKPN DIARY - EXHIBITIONS, SEMINARS & OTHER EVENTS

22 Aug 2024

York Races – Ebor Festival - UKGSA Hospitality Event, UK

5 Sept 2024

Green Gas day National Motorcycle Museum, Birmingham

11 - 12 Sept 2024

Resource & Waste Management Expo 2024 NEC, Birmingham,

18 Sept 2024

CABLES 2024 Conference Bristol

19 Sept 2024

Cricket at Trent Bridge UKGSA Hospitality Event, UK

24-26 Sept 2024

SOLAR & STORAGE LIVE NEC Birmingham

24 - 27 Sept 2024

WindEnergy Hamburg Hamburg, Germany

8-9 Oct 2024

IHEEM/HEALTHCARE ESTATES

The UK’s Largest Event for Healthcare Engineering and Estates Management Professionals Manchester Ventral

9 - 10 Oct 2024

Floating Offshore Wind 2024 P&J Live, Aberdeen

12 Oct 2024

INSIGHTS 2024 CONFERENCES & GRAND GALA sponsored by EUROPGEN Naples, Italy

16-17 Oct

HIGHWAYS UK - HIGHWAYS EQUIPMENT SHOW NEC Birmingham

23 – 24 Oct 2024

The Showman Show, Newbury Showground, Berkshire, UK

23 - 24 Oct 2024

Renewable Energy Scotland Event 2024 Scottish Event Campus, Glasgow, UK

24 Oct 2024

Smart Energy Conference & Exhibition 2024 ICC Belfast, Belfast, Northern Ireland, UK

28-30 Oct

Power Conference Eat Midlands (I PowerE) Hilton East Midlands

6 -7 Nov 2024

Offshore Wind North East Conference & Exhibition Sunderland

6 - 7 Nov 2024

NIBS Battery Conference Telford, Shropshire. UK

12 - 13 Nov 2024

Future Energy Wales 2024

International Convention Centre Wales,

13 - 14 Nov 2024

Future of Utilities: Smart Energy 2024 St Pauls, London, UK

13 - 14 Nov 2024

Energy Transition Summit 2024 London, UK

19 Nov 2024

European Utilities 2024 London

20-21 Nov 2024

DATA CENTRES IRELAND RDS Dublin, Ireland

20-21 Nov 2024 EMEX

UK Net Zero & Energy Management Expo ExCel London

12 Dec 2024

PowerEx Live London

Park Plaza Westminster Hotel, London SE1 7UT, UK

25-27 Feb 2025

INTERNATIONAL ENERGY WEEK QEII Centre, London, UK

5 - 6 Mar 2025

Low Carbon Agriculture Coventry

5 - 6 Mar 2025

ENERGY NOW EXPO Coventry

12-13 March 2025

DATA CENTRE WORLD ExCel London, UK

12-13 March 2025

Distributed Energy Show - NEC, Birmingham, UK

12- 13 Mar 2025

The Energy Storage Show Birmingham

13 March 2025

SMMT Electrified 2025, QEII Centre, London, UK

2-3 April 2025

SOLAR & STORAGE LIVE ExCel London, UK

7-9 April 2025

MIDDLE EAST ENERGY 2025 Dubai, UAE

8 - 10 Apr 2025

Ocean Business [Gensets, Wind & Water)]

National Oceanography Centre, Southampton, UK

May 14-15 2025

All Energy & Decarbonise 2025

The meeting place for the renewable and low carbon energy community SEC Glasgow, Glasgow

20-21 May 2025

UTILITY WEEK LIVE

Flexible Energy/Sustainable Infrastructure Show NEC Brimingham

24 - 26 June 2025

InstallerSHOW [Heat, Water, Air & Energy] Birmingham

July 2025 -date & venue to be confirmed Golf Day PowerEx Live Midlands 2025

9 -10 July 2025

Battery Cells and Systems Expo (BCS) Birmingham

12-13 Feb 2025

EXECUTIVE HIRE SHOW Coventry UK

17-19 Feb 2025

ELECTRICITY STORAGE SUMMIT 2025 InterContinental Hote, O2, London, UK

Dec 2025 [exact date TBC]

PowerEx Live London 2025 Conference

Park Plaza Westminster Hotel, London SE1 7UT, UK

GREEN HYDROGEN IS AT THE HEART OF TODAY'S SUSTAINABLE DISTILLING PRACTICES

WHICH ALSO REDUCE CARBON EMISSIONS

Powersystems has played a pivotal role in a groundbreaking project at Arbikie Highland Estate Distillery, which aims to become the world’s first distillery powered entirely by green hydrogen. This innovative initiative marks a significant milestone in Arbikie’s mission to revolutionise sustainable distilling practices and reduce carbon emissions.

Located amidst the picturesque Angus Hills, Arbikie Highland Estate Distillery has installed a new 1 MW wind turbine as part of its commitment to sustainable energy solutions. The wind turbine provides renewable electricity that will power an electrolyser, producing green hydrogen through water electrolysis. This green hydrogen will then be utilised in a hydrogen-compatible boiler, significantly reducing the distillery’s carbon footprint and advancing its environmental goals.

Powersystems has collaborated with renewable energy specialists Locogen and Logan Energy on this transformative project. Its team has been entrusted with the Electrical Balance of Plant (EBoP) works, including system design, engineering studies, and the integration of electrical infrastructure necessary to support the wind turbine and hydrogen electrolyser.

Powersystems has the task of executing the Electrical Balance of Plant (EBoP) works for Arbikie’s groundbreaking project. Its responsibilities encompass the complete system design and engineering studies necessary for the project. Powersystems' engineering team has worked closely with civil engineering contractors to design, construct, and outfit the substation buildings with small power and lighting systems. Additionally, the company handles the installation of comprehensive earthing systems across the entire project.

A spokesman comments: "We are also in charge of procuring essential components such as transformers, switchgear, and LV distribution systems, as well as the 11,000V and 400V cabling required for effective communication between the wind turbine, hydrogen electrolyser, and distillery.

"Our work includes the installation, connection, testing, and commissioning of the G99 and G100 protection systems. Throughout the project, Powersystems ensures compliance with all Health, Safety, and Environmental (HSE) and Construction (Design and Management) (CDM) regulations while providing robust project management and SAP duties."

The success of this ambitious project depends on seamless collaboration between diverse stakeholders, including civil engineering teams, wind turbine specialists, hydrogen electrolyser technicians, and Scottish Power Energy Networks (SPEN). Powersystems has played a key role in facilitating these collaborations to deliver a fully-integrated and efficient system.

Despite the complexities of co-ordinating such a multifaceted project, the timeline for Arbikie’s hydrogen-powered distillery remains ambitious yet achievable. The design and procurement phase spanned from December 2022 to May 2023, with site installation, commissioning, and testing scheduled from June to August 2024.

Powersystems’ involvement extends to the design and construction of substation buildings, installation of earthing systems, and procurement of key components such as transformers, switchgear, and LV distribution systems.

The spokesman continues: "Our expertise will ensure seamless connectivity and communication between the wind turbine, hydrogen electrolyser, and distillery, creating a fully integrated and efficient system.

"This project exemplifies Powersystems’ commitment to delivering innovative and sustainable solutions that align with our clients’ environmental objectives. By ensuring strict compliance with all HSE regulations, we provide comprehensive project management to support Arbikie’s pioneering efforts in green hydrogen technology. Arbikie’s ambitious project is part of the Green Distilleries competition, an initiative by the Department for Business, Energy & Industrial Strategy (BEIS) that supports distilleries in cutting CO2 emissions. Having received substantial funding, Arbikie is leading the charge in sustainable distilling by implementing cuttingedge renewable energy solutions."

Iain Stirling, Director of Arbikie Highland Estate, said: “We are delighted to pioneer the use of green hydrogen in the distilling industry. As the latest custodians of our family farms and distillery, it’s very important to our family to be as sustainable as possible.”

CHP: ENERGY-EFFICIENT SUSTAINABLE SOLUTIONS FOUND FOR UK RAILWAY PROJECT

Catalyst Digital Energy is an award-winning business energy consultant operating in the industrial and commercial sectors.

Building on more than 20 years of experience, it has a reputation for excellence in the UK, Irish and International energy markets. Catalyst is recognised by clients globally as a trusted source for integrated energy solutions, reliability, and innovation across a full spectrum of energy disciplines. A spokesman explains: "We offer private and public sector client’s access to our strong consulting capabilities across all major energy services, including risk managed flexible and fixed energy procurement, our EaaSi™ digital energy bureau solutions, and energy service consulting."

Catalyst Digital Energy was involved in a CHP project to provide an affordable, energy-efficient and sustainable solution to a mixed use development site around a large railway station. This had to be

achieved without compromising the quality of living, or the availability of energy supply.

The goal was made even more ambitious to cut carbon emissions by at least 50%

"Providing the ideal, tailored solution for the circumstances is something which we pride ourselves on and because the development was delivered in phases it was essential that we delivered an energy infrastructure which would evolve along with the construction work," explains a spokesman.

Today, the main T1 energy centre at the site houses two 2MWe Combined Heat and Power (CHP) engines and three 10MWt boilers. An additional 2MWe CHP engine will be added in the future to meet the increased energy demand.

The energy centre, which was built underneath a car park and had an irregular shape which presented several challenges.

The energy centre is now at the heart of the development, providing 95 per cent of the heating and hot water and 79% of the electricity.

The success of the energy centre has meant that they can confidently state that all homes will meet the Code for Sustainable Homes Level 4 or above and that each office featured in the development will be deemed BREEAM “Excellent” or

MWM 25H2-Kit

Operation with hydrogen.

New variants of the TCG 3016, TCG 3020 and TCG 2032 series enable natural gas operation with hydrogen admixture of up to 25 vol.%. Retrofit solutions for existing plants are also available.

www.mwm.net/25H2-Kits

HVO: THE ANSWER TO GENERATOR EMISSIONS REDUCTION PROBLEM

With the new Labour government determined to meet the 2050 net zero target, pledging to ‘make Britain a clean energy superpower’, the drive to adopt renewable fuel and energy sources is stronger than ever for UK businesses. Hydrotreated Vegetable Oil (HVO) as a fuel source has enjoyed a recent swell in popularity, with large organisations like DHL, Royal Mail, rail freight companies, and councils across the UK all adopting it as a fuel source.

London Gatwick has become the latest establishment to join the ranks, switching its 300 ground fleet vehicles from diesel to HVO, slashing carbon emissions by 90%.

But it’s not just businesses with vehicle fleets that could benefit from switching to HVO. Those who rely on diesel generators as a backup energy source could also see their CO2 emissions reduced by up to 90%, and a significant reduction in nitrogen oxide (NOx), particulate matter (PM) and carbon monoxide (CO) emissions.

Dale Power Solutions, one of the UK’s largest suppliers of uninterruptible power supplies (UPS) and emergency backup generators, has developed its range with HVO use specifically in mind.

Andy Towse, Product Quotes Manager at Dale, said:

“You can use HVO in most generators in just the same way as you would use mineral diesel. You can use HVO in all our new generator ranges, but if you want to use it in your existing equipment, you just need to seek advice about fully cleaning your fuel system, pumps and engine first.

Once everything is properly prepared, there’s no difference in the experience of using this fuel,

compared with diesel. And its outstanding green credentials will help businesses get to net zero much faster.”

HVO as a greener alternative for diesel generators

Many organisations have standby generators onsite ready to make sure their critical operations continue in the case of a power cut. Those companies need a fuel source onsite to power those generators. Traditionally, this has been mineral diesel. But in recent years there’s been a gradual but steady move towards HVO.

Hailed as one of the cleanest fuels available, HVO is a renewable alternative to diesel.

Made from vegetable oils and animal fats, it’s produced through a hydrotreatment process to remove impurities.

Meeting EN15940 standards and Fuel Quality Directive 2009/30/EC Annex II, HVO represents an exciting opportunity for those businesses looking to reduce their carbon footprint.

Even though HVO is a far greener choice than sticking with fossil diesel as a fuel source, its adoption has been relatively sluggish.

The upfront cost of the fuel is higher than it is for diesel, so this might have delayed some companies in taking the leap.

But as we move to the country-wide 2050 target for net zero - not to mention the new government’s enthusiasm for environmental issues - regulations are only going to get tighter.

Plus, with HVO there is an intrinsic efficiency. Which means lower long-term maintenance and repair cost burdens. It’s likely that as demand for renewable and greener fuels continues to ramp up, HVO will become more widely available. So, it follows that the price will also start to drop.

How HVO can boost businesses’ ESG strategies

“You can use HVO in most generators in just the same way as you would use mineral diesel. You can use HVO in all our new generator ranges, but if you want to use it in your existing equipment, you just need to seek advice about fully cleaning your fuel system, pumps and engine first."

In a competitive market, businesses looking to stand out are focusing a lot of attention on refining their ESG (Environmental, Social and Governance) strategies.

A strong ESG strategy helps attract more customers, investment opportunities and higher calibre employees. It can enhance a company’s reputation and lead to lower long-term running costs.

A good way for organisations to fulfil the environmental aspect of their ESG strategy would be to look for ways to minimise any negative impacts their operations might have on the planet. With the drive towards drastically reducing carbon emissions, businesses are seeking to use more renewable energy sources in a bid to reduce their carbon footprint.

As a renewable fuel source, HVO use is clearly preferable to relying on fossil fuels, especially given the net zero emissions target of 2050.

Switching from diesel to HVO for backup generators can translate to a CO2 emission reduction of up to 90%, not to mention the lower levels of NOx, particulate matter and carbon monoxide released into the atmosphere.

For more information on HVO compatible generators, visit: www.dalepowersolutions.com

DATA CENTER POWER SOLUTIONS

Secure and efficient

Improve your sustainability and support your local grid operator with Jenbacher backup data center solutions.

When it comes to backup power, reliability is your top concern. With INNIO Group’s Jenbacher engines, you gain startup and performance comparable to traditional diesel generators – all while achieving your decarbonization goals with 90% less NOx emissions! Plus, our gas generators are rated for continuous operation, so they can support your local utility by allowing participation in grid balancing and capacity markets. Jenbacher systems run on a wide range of gases, with the option to convert to CO2-free H2** operation once it is more readily available.

Let us support your transition journey. jenbacher.com

* & indicates a trademark.

** In general, “Ready for H2” Jenbacher units can be converted to operate on up to 100% hydrogen in the future. Details on the cost and timeline for a future conversion may vary and need to be clarified individually.

Jenbacher is part of the INNIO Group

WHY YOU SHOULDN'T GET EXCITED ABOUT YOUR UPS

be spotted before they become significant problems.

If we are honest, when it comes to technology, most people like to “fit and forget”. A decade ago, standalone mono-block uninterruptible power supplies (UPS) were installed and pretty much, if they did their job, they sat in the corner and were largely forgotten about until

they reached their end of design life or there was a component failure, explains Aaron

Oddy, Sales Manager, Centiel.

The whole point was that nobody got excited about their UPS providing it continued to work and was efficient as possible. The UPS provider might have performed a preventive maintenance visit and checked its operation from time to time but essentially, it was viewed as a true fit and forget system. However, technology has moved on, and times have changed. While we still don’t want our customers to get excited (or worried) about their UPS, it can be beneficial for them to interact with the equipment a little bit more and here’s why.

Monolithic Versus Modular

Monolithic standalone UPS can be inefficient when compared with correctly configured true modular systems and they also contain multiple potential single points of failure. When they do go wrong, it can take a significant amount of time to repair them and get them back online, resulting in the critical load being on raw mains for an extended period if spare parts are not readily available.

The general trend and move to modular UPS (compared to standalone/monolithic) has

introduced far greater levels of availability and uptime, due to the removal of single points of failure and faster Mean Time To Repair (MTTR), which is great news for data centres and facilities needing to protect critical loads.

Modular UPS systems, like all essential equipment, also need regular preventative maintenance to ensure they continue to run optimally. This might include regular impedance testing of batteries or a six-monthly discharge test to ensure the UPS switches from inverter to batteries smoothly. Think of this a bit like checking oil, water and tyre pressures in your car.

The UPS will also need remedials during its life span. This is the need to change specific components before they reach their end of life which poses a risk to the critical load. Just like changing a Cam Belt in a vehicle before it hits a certain milage, the Capacitors in a UPS generally need to be replaced every 5-6 years to minimize the risk of failure.

It is also important to note that if servicing does not occur at the right time, the UPS’ warranty could be invalidated, but more importantly, any other minor issues can

“The good news is that UPS technology is more userfriendly than ever before. An easy to use and understand user interface, the intelligence built into the system and the electronic controls put in place all help to ensure that the load remains protected during any system interrogation or maintenance."

A preventative maintenance plan for your UPS will ensure these essential regular checks and repairs are completed and the system continues to run as optimally as possible.

Increased flexibility and optimal system function require interaction and engagement with the technology.

For example: Centiel’s modular UPS with safe-true-hot-swap functionality offers the option to swap modules safely within a running load, meaning such systems are far more flexible. Modules are easily changed, added or removed onsite in minutes by a trained engineer. If it is necessary to replace a module and send it for repair, no downtime is experienced, ensuring maximum availability.

Any data centre or facility with a trained first level response team will therefore have more availability and resilience across their UPS systems than those without trained personnel.

Here, education is key. First level response training for a UPS system can take just a day, or sometimes we invite clients to our factory in Switzerland so they can learn a little more about how their UPS works.

Our customers who have been trained can now complete basic monitoring and diagnostics of the UPS.

On the rare occasion a fault does occur, UPS modules can be safely swapped in less than three minutes, and the faulty module shipped back to Centiel for testing and repair.

This is much faster than waiting for an emergency engineer on a typical six-hour response time as part of a contract.

Although we still don’t want customers to get excited/worried about their UPS, we don’t want them to be afraid of it either.

First level training can increase site resilience significantly, particularly for facilities with multiple systems in addition to potentially reducing preventative maintenance contract costs too. For more information about Centiel please see www.centiel.com

GENERATORS

400KVA INDUSTRIAL DIESEL

GENERATOR FOR LONDON'S

POPULAR CASTLE PUB

Target Power Generators was contacted by an existing M&E contractor, Red Electric Designs Ltd, to help the company procure a large open-type generator which could achieve 400 kVA in prime power. The generator was an open type and needed a residential exhaust to help reduce noise levels. The customer also wanted to monitor the generator remotely, so Target Power Generators modified the system to suit client needs.

At the Castle Pub in London, the management wanted to monitor its new generator remotely so Target Power Generators fitted an 8-relay extension for the client. A 630A automatic transfer switch was also installed - like the genset itself this was manufactured to UK standards, ensuring top quality performance.

The original specification included the following: AV440 400 kVA open-type diesel generator, three-phase 415 V; 630A automatic transfer switch; Residential exhaust; 8-relay extension; DSE7320 control module; ABB 4-pole circuit breaker

This emergency standby diesel generator was designed for industrial use and its role was to power the new build pub premises should the power go off for any reason.

A company spokesman commented: "Our client chose Target Power because we offer customisable diesel generator solutions. This was the second time they used us, having previously procured a Super Silent diesel

generator for a residential application. The customer was also working within a budget and knew Target Power Generators could deliver a high-quality industrial diesel generator at the right price for them. They wanted Target Power to supply the generator and provide a FAT (factory acceptance test) and price commissioning for them as well."

The generator was being used for standby purposes, so it was of critical importance that Target Power sourced one of the most reliable engines for the project.

It chose the Volvo Penta TAD1344GE engine for the genset. The generator had to start within 10 seconds and also reach 50% step load. The Volvo engine was able to achieve this.

The spokesman added: "We had to produce an 8-hour internal tank to support the Volvo diesel generator for continuous running for 8 hours at 100% load. The tank was fully bunded, and we used high-quality anti-vibration mounts to help reduce noise levels."

He continued: "We understand that different markets require different generator builds. In the EU, our sets come with a standby kit as standard, which includes automatic mains failure (AMF) and a water jacket heater.

"Therefore, this open-type generator for The Castle Pub was manufactured to UK and EU specifications, including a 4-pole breaker, earthed neutral link, bunded base, high-grade sound insulation, and more."

“Our client chose Target Power because we offer customisable diesel generator solutions. This was the second time they used us, having previously procured a super silent diesel generator for a residential application. The customer was also working within a budget and knew Target Power Generators could deliver a high-quality industrial diesel generator."

The generator needed to be loaded onto a flatbed truck because a crane was being used to offload the generator. Target Power manufactured the base with lifting eyes capable of lifting the whole generator set.

The client allowed eight weeks to produce the set. This timeframe provided Target Power with enough time to design and manufacture the open-type diesel generator to the client's specifications. Furthermore, because the client wanted an 8-relay extension, Target Power also designed the control box to accommodate it.

With over 25 years of power generation experience, Target Power Generators Ltd has dedicated itself to providing customers with high-quality diesel generators, reliable petrol generators and exceptional service.

It is widely-regarded as a 'go-to wholesale supplier and manufacturer of power generation solutions in the UK. 'Power that hits the mark' is the company slogan.

target-generators.com

BIODIESEL GENSET WITH N+1 CONFIGURATION FOR PROCESSING PLANT

One of JS POWER's customers required a generator to run on B100 Biodiesel to make its processing plant 100% self-sufficient, using their own biodiesel to power the process. The customer also wanted an N+1 configuration to make sure there was no loss of power, reports UKPN.

One of JS POWER's customers required a generator to run on B100 Biodiesel to make its processing plant 100% self-sufficient, using their own biodiesel to power the process.

The customer also wanted an N+1 configuration to make sure there was no loss of power and to have the capability of adding more sets in the future.

A company spokesman comments: "Our team supplied 2X JSPBD 500, these generators are warranted for B100 Biodiesel which conforms to the EN14214 standard. The sets were fitted with DSE 8610 synchronising panels and configured as an N+1 system. This configuration provides a backup for the prime-running generator."

The system provided by JS POWER can also cope with extra loads in the future as any load demand greater than the continuous rating of the prime running set starts the standby generator and shares the load.

The addition of more sets in the future is also made easy with DSE 8610, so this system is ready for whatever the future may hold. These sets were also connected to a DSE 891 Gateway, so their activity can be monitored 24/7

in real-time.

Provided for the site was the following:

- 2 x JSPBD500; Scania DC13 72A HighPerformance Fuel Optimised, Electronic Engine; Mecc Alte Prime Rated 400/230v Alternator; Electronic Governor; Lube Oil Drain / Valve Coolant Drain / Valve; 230V Engine Coolant Heater; Coolant Drain / Valve; DEFRA-compliant fully extended bunded base fuel tank (UK Legal Requirement); DEFRA-compliant bund leakage alarm (UK Legal Requirement); Powder-coated, galvanised steel sound-attenuated canopy; 230/24V Static Battery Charger; DSE 8610 Auto Synchronisation Control Panel; Motorised MCCB; Fire valve and Wire; and a DSE 891 Gateway.

JS POWER offers customers an advanced bio-diesel generator manufacturing and in early 2024 announced the availability of build slots, exclusively for businesses seeking a green fuel alternative. The company's biodiesel generators are designed to significantly reduce greenhouse gas emissions, showcasing company commitment to a cleaner, greener planet. This offers some significant advantages:

“Our

team supplied 2X JSPBD 500, these generators are warranted for B100 Biodiesel which conforms to the EN14214 standard. The sets were fitted with DSE 8610 synchronising panels and configured as an N+1 system. This configuration provides a backup for the prime-running generator. The system can also cope with extra loads in the future."

* Renewable Fuel Source: Bio-diesel is derived from renewable resources, aligning with your corporate sustainability goals and reducing reliance on finite fossil fuels.

* Efficiency and Reliability: Ensure a stable and uninterrupted power supply for businesses with highly-efficient and reliable bio-diesel generators.

* Custom Solutions: every company’s energy needs are unique. The JS POWER team of experts will collaborate closely with clients to create a customised generator which perfectly fits operational requirements.

* Comprehensive Support: From installation to ongoing maintenance, JS POWER has a dedicated support team available to assist customers every step of the way, allowing them to focus on what matters most – their business.

JS POWER offers UK built, outstanding quality, CE-approved diesel and biodiesel generators. The company installs, supplies and service many types of diesel generators across the globe.

A spokesman comments: "With over 60 years of experience, you can be sure our team is efficient and knowledgeable in every aspect of generator maintenance and servicing. We supply a large range of generators, all using only genuine components from leading brands.

Portable and standby diesel generators are available from 6.6kVA to 2500kVA.

"Our engineers cover the length and breadth of the country and we provide 24/7 response together with yearly maintenance contracts for your generators."

jspower.co.uk

GENSETS

TIER IV DATA CENTRE INSTALLS

NINE GENERATORS IN WORCESTERSHIRE

As part of its expansion into the UK market, IONOS has built its first UK tier IV data centre, located at the new Worcestershire Six Business Park. To ensure that the data centre met tier IV standards, IONOS required huge levels of redundancy on site, meaning the management team required an extensive critical power set up onsite. Vital Power won the tender for the project.

The data centre built for IONOS contains of four server rooms and one main office. Each server room consists of four strings, each requiring its own generator, UPS, Tx and cooling system.

Vital Power was selected to supply, install, and commission nine industrial diesel generators on server rooms 1 & 2 and the office.

The Scope Of Works involved the following:

-8 x 550kVA prime/ 605kVA standby diesel generators each with a Scania IIIA engine, Stamford alternator & DSE 8620 control panel

-Each generator feeds from its own 8000L external bulk fuel tank

-Bespoke exhaust system – a twin walled exhaust stack that has been designed to divert fumes away from the building and ground level -1 x 350kVA/ 385kVA standby diesel generators each with a Scania IIIA engine, Mecc Alte alternator & DSE 7320 control panel

-Expansion module fitted onto each panel which feeds in IONOS’ bespoke Building Management Systems (BMS), allowing site to monitor their critical power systems alongside other elements of the facility.

The DSE8620 is an Auto Mains (Utility) Failure Control Module suitable for paralleling single gensets (diesel or gas) with the mains (utility) supply.

The module will automatically start the generator on detection of a mains failure and will control the switchover from and back to the mains (utility) supply, offering an uninterrupted return. The modules synchronising functions include automatic synchronising with built-in synchroscope and closing onto dead bus. Direct and flexible outputs from the module are provided to allow connection to the most commonly-used speed governors and automatic voltage regulators (AVRs).

“Vital Power was invited to tender for the IONOS project, and subsequently installed generators to provide critical power suppliers. The data centre contains of four server rooms and one main office. Each server room consists of four strings, each requiring their own generator, UPS, Tx and cooling system."

A sophisticated module monitoring an extensive number of engine parameters, the DSE8620 will annunciate warnings, shutdown and engine status information on the back-lit LCD screen, illuminated LED, remote PC, audible alarm and via SMS text alerts.

The module includes RS232 and RS485 ports as well as dedicated terminals for system expansion.

The DSE8620 is compatible with electronic (CAN) and non-electronic (magnetic pick-up/alternator sensing) engines and offers a comprehensive number of flexible inputs, outputs and extensive engine protections so the system can be easily adapted to meet the most demanding industry paralleling requirements.

The modules can be easily configured using the DSE Configuration Suite Software. Selected front panel editing is also available

Founded in 2016, Vital Power has grown exponentially, becoming one of the UK’s leading critical power solutions providers. Its foundations have been built upon providing industry leading, customer-focussed critical power solutions, with a modern twist on a mature industry, reports the company.

IONOS was established in 1988 and is the largest hosting company in Europe, managing more than eight million customer contracts and hosting more than 12 million domains in its regional data centres around the globe.

The IONOS group operates in fifteen countries around the world and employs 3,500 people worldwide.

vitalpower.co.uk

SUSTAINABILITY INNOVATION FEATURES AT ROYAL ASCOT 2024

At Royal Ascot 2024, a commitment to sustainability was showcased through the utilisation of innovative, sustainable initiatives. UKPN outlines a number of key solutions deployed at this significant event

Royal Ascot 2024 featured a number of significant sustainable initiatives. These included the Greener Battery 422 for energy storage, the Solar Street LED Light for lighting, the CombiMax SMARTSolar waste compactor, Smartflower solar power and even EV waste vehicles.

A spokesman from ROCKVOLT commented: "These initiatives significantly enhanced the event's green credentials, aligning with environmental goals and demonstrating a proactive approach to sustainable event management. The Smartflower, a continuous feature since its launch in 2022, is the world’s only solar solution using an all-in-one, sculptural design. It offers a nominal output of 2.5kWp and annual production between 4,000 to 6,500kWh. It operates in temperatures from -20°C to 55°C, and includes safety features for high winds. Weighing about 700kg, it requires four fastening points and 16ft³ of clear space. The system has a 25-year performance warranty and a 2-year system warranty, ensuring long-term reliability. It provides clean, sustainable energy for businesses, homes or stadiums, and looks great."

Making its second Royal Ascot appearance, the Greener Battery 422 model is an all-in-one solution housed in a 10-foot container, offering high-capacity and robust energy storage. It has

a storage capacity of 422 kWh and delivers power up to 318 kVA. The unit weighs 8700kg, making it substantial yet highly functional for a variety of applications.

This model operates on a three-phase 230/400 Vac grid connection and is equipped with PowerSyntax (power lock) connectors for efficient energy transfer.

Designed for a wide range of temperatures from -20°C to 40°C, it ensures performance under diverse conditions.

The battery system is liquid-cooled and meets several safety and operational standards, including IP55 and EMC Directive 2014/30/ EU, ensuring reliability and safety in various environments. It powered the Village Enclosure. Installed permanently in The Windsor Enclosure, the Solar Street LED Light 10W from Stratuslight features a polycrystalline solar panel with a 50W maximum power and dimensions of 700x540x30 mm. It includes a 10W LED luminaire with asymmetric optics, delivering 1200 lumens, ideal for street lighting.

The system is controlled by an intelligent solar controller that supports up to 10A, ensuring efficient battery management and protection. It's equipped with an 18Ah gel battery and can illuminate for up to 12 hours.

Recommended for mounting heights between 3 to 7 metres, this solar system is designed

for poles with a 60 mm diameter. The concept is said to be ideal for walkways, to aid crowd access and egress.

venue.
“At Royal Ascot 2024, sustainability innovation took the best learnings from the great work completed in 2022 and 2023 and raised the bar again."
- Peter Watts Rockvolt Managing Director

Making its Royal Ascot debut, the Europress CombiMax SMARTSolar is a solar-powered waste compactor designed for handling cardboard, plastic, and mixed waste. It can accommodate several standard container sizes, including 14 m³, 17 m³, and 20 m³. This device is equipped with four 300W solar panels and can operate independently of mains power, making it ideal for remote or electricity-scarce locations.

It offers significant operational flexibility, running for over 2.5 hours on solar energy alone on sunny days, with the option to use mains power for additional running time. The CombiMax SMARTSolar is robust, efficient, and tailored with feed hoppers according to specific needs, ensuring it meets diverse waste management requirements.

Peter Watts Rockvolt MD, concludes:"At Royal Ascot 2024, sustainability innovation took the best learnings from the great work completed in 2022 and 2023 and raised the bar again. These initiatives significantly enhanced the event's environmental impact, showcasing a commitment to greener practices through cutting-edge technologies. My question to all events and sports venues would be ‘why wouldn’t you seek to implement these technologies?’ They’re so efficient, easy to install and operate, and have tangible environmental benefits" www.rockvolt.co.uk

Peter Watts

HYDROGEN

CAPABLE OF 25% HYDROGEN BLENDS: THE TCG 3016 SERIES GENERATOR SETS

MWM has introduced gas gensets of the TCG 3016 series in the range from 400 kW to 1 MW - these can be operated on natural gas blended with up to 25% hydrogen, reports UKPN

MWM currently offers generator sets configured to enable operation on natural gas blended with up to 25% hydrogen for continuous, prime, and load management applications.

Additionally, the company offers retrofit kits that provide hydrogen blending capabilities of up to 25% hydrogen for existing plants.

Reducing greenhouse gas emissions

Powerful hydrogen-based energy solutions

Renewable hydrogen fuel can help to reduce greenhouse gas emissions.

“We offer our customers hydrogenbased highperformance energy solutions that can help them reduce greenhouse gas emissions and use more sustainable energy sources,” explains Rene Ludvik, MWM Director.

MWM gas generator sets can already be operated with up to 10 percent hydrogen blends and are characterized by their high efficiency in decentralized energy generation.

MWM generators are traditionally at the

forefront when using alternative types of gas for power generation.

The generator sets can be configured to operate on a wide range of biogas fuels, including digestor biogas, landfill gas, and wastewater biogas.

The development and launch of hydrogen blended solutions address growing customer demand as the hydrogen supply infrastructure matures.

MWM is committed to helping customers meet their climate-related goals by providing products that facilitate the fuel transition, increase operational efficiency and reduce emissions.

The TCG 3016 gas genset from MWM introduces a new generation of gas genset technology to combine reliability, robustness, and maximum efficiency within the 400kWe – 1MW range.

The TCG 3016 gas genset is MWM’s smallest model offering greatly reduced installation and operating costs and includes the Total Plant and Energy Management (TPEM) control. This has been designed to ensure maximum reliability and availability.

“The TCG 3016 gas genset is MWM’s smallest version but features a TPEM (Total Plant & Energy Management) which eliminates the need for additional control systems. All power plant data for the genset, backup genset, and plant control are combined in one system, resulting in high efficiency through optimum control of the power plant.”

The TCG 3016’s improved oil management and optimised cylinder and turbo chargers set new standards in terms of durability and reliability.

The gas genset has the highest efficiency in its output class through unique combination of long maintenance intervals (80,000 operating hours for Natural Gas) and high efficiency (electrical efficiency up to 43.5 percent).

The TCG 3016 has a smaller setup area than comparable gensets due to its compact design and integrated tanks for daily refilling.

Due to the flanged genset concept, the vibration decoupling takes place directly between the gas engine and the base frame, helping to further reduce setup costs.

With a greatly reduced oil consumption of less than 0.1 g/ kWhe – the TCG 3016 gas engine boasts the lowest lubricant consumption in its class.

MWM, a part of Caterpillar Inc., stands for highly-efficient and more sustainable solutions for distributed power generation and manufactures gas gensets and power plants, as well as combined heat and power (CHP) plants.

Today, MWM tcommands a strong market position in the field of highly efficient, advanced distributed energy solutions. The company serves customers around the globe as a reliable partner for proven and sustained added value in the implementation of power plant projects.

MWM’s products are the result of more than 150 years of experience in the development and optimization of gas engines and generator sets for natural gas, biogas and other special gases. For more information, please visit: mwm.net and caterpillar.com

GENSETS

MINSTER COURT, LONDONGENERATOR INSTALLATION

The M&E Contractor selected Regency Power Generation Ltd to design and deliver a power solution for one of the most iconic buildings in London, The Minster Building. This is an unusual neo-Gothic office building which deviated significantly from the standard rectilinear office building formula well-established in the City. Minster Court is a complex of three office buildings, completed between 1991 and 1992 ,reports UKPN.

Situated in No. 3 Minster Court, the London Underwriting Centre (LUC) is intended to run in parallel with the Underwriting Room at Lloyd’s of London, providing a facility for insurance underwriters to meet brokers at a single venue (the Lloyd’s building itself being only open to Lloyd’s syndicate underwriters).

Minster Court is a complex of three office buildings, completed between 1991 and 1992 and designed by architects GMW Partnership. The style has been described by some architectural experts as being “postmoderngothic”.

Regency Power Generation Ltd. - supplier of the site's genset - Is a key company in the UK's generator sector, delivering state-of-the-art power solutions.

The company specialises in providing robust control gear, high-performance generators, expert consulting, and comprehensive service

and support for a diverse array of projects across the residential and commercial spectrum. It has a number of clients in the capital.

A spokesman comments: "Our commitment to excellence ensures that each client receives tailored solutions designed to meet their unique power needs."

Regency was under contract to deliver and lift into position a bespoke diesel generator set at one of the apex openings on the roof, with the final position being on the rail which accommodates the window cleaning cradle. This operation was achieved in a 6-hour time window, reports Regency Power, as it was impossible to close the main road due to the location of the London underground (District Line).

Regency planned and arranged all permits, closures and crane hire in Central London as a key part of the contract.

“Regency Power Generation was contracted to deliver and lift into position a bespoke diesel generator set at one of the apex openings on the roof, with the final position being on the rail which accommodates the window cleaning cradle. This operation was achieved in a 6-hour time window."

Acoustic canopies for smaller diesel generators offer a cost-effective solution for clients, says Regency Power. Most standard products come in a canopy. Various custom options can be purchased or special custom designs can be made to order.

Regency Power offers a range of diesel generators suitable for a vast array of applications. The company is typically able to offer clients both standard specfication units and custom-built equipment which can suit almost any application or location.

In a previous contract, Regency Power was able to provide a suitable power solution for another high-profile Lonodn location.

20 Finsbury Circus is a listed building which posed many challenges for the company . Originally being positioned on the roof, the genset design had changed due to structural issues and the generator was relocated onto the basement of the building.

This move presented further challenges for the company's engineering team. Ultimately, a plant room solution was designed and provided by Regency Power. This incorporated an exhaust system solution, including an inbuilt catalytic convertor in the silencers enabling the equipment to discharge exhaust fumes safely.

www.regency-generators.co.uk

£250 MILLION 100MW GREEN HYDROGEN PRODUCTION FACILITY

WILL BE BUILT IN HULL

Green hydrogen developer Meld Energy has received approval from the East Riding of Yorkshire Council in the UK to construct a £250 million, 100 MW green hydrogen production facility in Hull. The project will position the Humber area as a centre of excellence for hydrogen.

Meld Energy is now preparing to build the green hydrogen production facility at Saltend Chemicals Park, a move that will create the capacity to meet up to 30% of the park’s existing hydrogen demand.

This increase in green hydrogen production will lead to a reduction in carbon-dioxide emissions of 125 000 tonnes annually, a substantial step towards a more sustainable future.

Saltend Chemicals Park is a hub for major chemical businesses such as BP Petrochemicals, Mitsubishi Chemicals UK and Ineos.

Hydrogen can be used as a replacement for natural gas, as a fuel for various modes of transport such as buses, heavy goods vehicles, and cars or as an ingredient for clean hydrogen derived fuels.

When burned, it does not produce carbon, which makes it compatible with legislation aimed at addressing climate change. Meld’s green hydrogen will be produced through electrolysis, a process that involves using electricity from fully renewable sources to split water into hydrogen

and oxygen. Hydrogen is crucial for the chemical industry’s transition to net zero, as it offers a viable path to decarbonisation, especially considering the industry’s significant use of gas.

Meld Energy submitted a bid to access funding from round two of the government’s Hydrogen Production Business Model in April of this year. Successful schemes are expected to be announced later this year, with the government aiming to support up to 875 MW of hydrogen production in total.

The Humber region is a large industrial centre and the biggest industrial emitter of CO2 in the UK – with over 5% of the UK’s overall emissions and 50% more than the next largest region, which makes it an ideal location for hydrogen production.

Earlier this year the government announced the first round of successful projects under the electrolytic Hydrogen Allocation Round (HAR1) generating 125 MW, in addition to the 34 MW through round 1 of strand 2 of the Net Zero Hydrogen Fund (NZHF).

The second Hydrogen Allocation Round (HAR2), which is over 3 times the size of HAR1,

is now underway, and the contracts from round 2 of the NZHF strands 1 and 2 will be announced.

This progress has been possible due to the UK’s strong policy framework for growing hydrogen production – including the Hydrogen Production Business Model, Low Carbon Hydrogen Agreement and the Uk Government's Low Carbon Hydrogen Standard.

Together this has proved an investable model which has leveraged private investment to kick start the UK’s hydrogen economy.

“Meld’s green hydrogen will be produced through electrolysis, a process that involves using electricity from fully renewable sources to split water into hydrogen and oxygen. Hydrogen is crucial for the chemical industry’s transition to net zero, as it offers a viable path to decarbonisation, especially considering the industry’s

significant use of gas."

There is a target for the UK to reach of 10 GW of low carbon hydrogen production capacity by 2030, subject to affordability and value for money, with at least half of this coming from electrolytic hydrogen.

In addition to this, the government aim was to have up to 1 GW of electrolytic hydrogen and up to 1 GW of carbon capture, usage, and storage (CCUS) enabled hydrogen in construction or operation by 2025.

As the hydrogen production landscape develops, the Uk can expect to see CCUS enabled hydrogen supporting decarbonisation in the industrial clusters, and increasingly large electrolytic projects sited in locations which allows industry to take advantage of the deployment of renewable electricity generation.

Transport and storage (T&S) infrastructure will be needed to connect and balance this production with demand.

A Hydrogen T&S Networks Pathway has been formally identified, supporting emerging regional networks centred on the availability of storage and credible regional production and demand as the priority for early T&S infrastructure.

About the company

Meld Energy serves as a developer specialising in green hydrogen production within the renewable energy sector. The company focuses on creating hydrogen powered by renewable energy sources to supply low and zero carbon fuels for various industries, including road transport, shipping, and aviation. meld.energy

MIDLANDS HOSPITAL IN THE UK RECEIVES

TWO KD1100 GENSETS

A

Midlands hospital in the UK needed a standby power solution - two 2 x KD1100 gensets - to provide vital back-up power for the facility in case of a power failure. WB Power Services Ltd (WBPS) won the contract to specify, design, and install two key substations, reports UKPN.

As part of the contract with a Midlands Hospital

WB Power Services Ltd (WBPS) undertook the full design and project management of the site and associated works.

The main challenge was to meld all the different elements the hospital authorities requested into a seamless single solution.

Additionally, the generators had to be configured so that either generator could feed power to the other package and, ultimately, the hospital building.

It was also important to create minimal disruption within the busy hospital which continued to function while the power equipment installation was carried out.

WBPS project managers liaised closely with the hospital staff to gather specific onsite knowledge. The company was also responsible for control and management of the site area, Health and Safety, staff inductions, welfare facilities, site security, and all temporary services.

WBPS specified Kohler’s KD1100 generator alongside the KohlerKH03860T alternator.

Kohler’s compact, fuel-efficient, power-dense, and highly reliable 12-cylinder, 2-litre KD27V125DES engine could comfortably deliver the full power and flexibility required to meet the hospital’s current and future needs - this was the assessment of WBPS.

The sets were provided with a dual battery, dual battery charger, and dual starter motor arrangement to enhance starting reliability and a 200-hour lube oil make-up tank to ensure safe long-term continuous running of the sets.

The two generating sets were housed in their own custom-made acoustic containers rated to achieve a noise level of 65dBA @1m FFC (both sets running) and came complete with fire detection, fuel shutoff valve, and all internal lighting and ventilation.

To minimise the footprint of the entire package, the container housing the generator was

“WBPS specified Kohler’s KD1100 generator alongside the KohlerKH03860T alternator.

Kohler’s compact, fuel-efficient, power-dense, and highly reliable 12-cylinder, 2-litre KD27V12-5DES engine could comfortably deliver the full power and flexibility required to meet the hospital’s current and future needs. The sets were also provided with a dual battery and dual battery charger."

designed to accommodate a penthousestyle inlet and horizontal discharge arrangement.

The dual roof-mounted exhaust gas silencers were arranged for high-level vertical discharge.

WBPS successfully provided an innovative “one-stop shop” package, including project design, optimized transformer and switchgear solutions, customised Kohler generating sets and associated control systems, and all electrical installation and civil works.

Modular packaged solutions meant that much of the required testing was completed before delivery to cut down site installation and commissioning time.

The Midlands Hospital NHS Foundation Trust provides a full range of acute services (including 24-hour accident and emergency care) to the whole population and specialist services for children.

As the area's only acute district general hospital, with 24-hour Emergency Department services, the authorities are responsible for providing care and treatment to more than 400,000 people.

The NHS Hospital Foundation Trust works with NHS Professionals (NHSP) who manage the staff and locum bank. Working through NHSP helps the Trust reduce its reliance on recruitment agencies enabling cost savings to be reinvested into where it matters most, patient care and safety.

Thanks to the hard work and expertise of the WBPS technical team the Midlands Hospital can now continue giving thousands of patients a year the professional care they need safe in the knowledge that emergency power is ready to kick in if ever needed. www.wbpsltd.co.uk

LIGHTING TOWERS

FIRST HYBRID LIGHT TOWER

OFFERS EXCELLENT

PERFORMANCE & EFFICIENCY

At the beginning of the year Atlas Copco launched its first hybrid light tower - and now in the season of music festivals and construction development - the HiLight BI+ 4 is set to transform industry. The innovative light tower incorporates state-of-the-art surface mount device (SMD) LED lighting technology and lithium-ion batteries to provide excellent performance and efficiency.

Lighting towers like these are essential for operators at construction sites, events, mines, emergency applications and rental companies will be able to reduce their carbon footprint and operating costs while improving sustainability levels – both environmentally and in business, reports Atlas Copco.

Combining the use of lithium-ion batteries with a low-consumption Stage V diesel engine, the new HiLight BI+ 4 light tower offers users maximum flexibility as it has four operating modes: it can be powered directly from mains electricity, from its lithium-ion batteries, from its diesel engine, or from a hybrid setting to make the most of the energy available.

The light towers have a battery autonomy of seven hours when operating at their full potential.

When using their dimming function, they can provide over 20 hours of silent and emission-free operation with a single charge.

With a battery recharging time of just four hours, the HiLight BI+ 4 can also feature an external power plug as an option.

When operating in hybrid mode, relying on both the batteries and the engine, the light tower’s fuel consumption is an average of 0,29l/h, which is the lowest average fuel consumption in its class of light towers.

Thanks to the incorporation of a battery, operators can reduce up to seven tonnes of CO2 per unit, per year, compared to traditional diesel-powered light towers. By optimising their energy consumption, users can reduce their environmental impact and improve their

“The flexible temporary lighting solution is also the first of Atlas Copco’s light towers to feature highly efficient SMD LED lights, which are 20% more efficient than alternative Chipon-Board (COB) LED lights found in alternative light towers and competitive solutions."

profitability considerably.

The 5kW lithium-ion battery technology delivers a higher performance than comparative light towers powered by absorbent glass mat (AGM) lead acid batteries. The lifespan of a lithium-ion battery is superior in comparison and is expected to last approximately 36,500 hours, compared to just 1,500 hours for AGM lead acid batteries.

Introducing the ability to use batteries reduces the use of the engine, which extends the unit’s lifetime and results in a temporary lighting solution with a low Total Cost of Ownership (TCO). With a 60% reduction in engine runtime, service intervals are three times longer than light towers that run solely on diesel.

The HiLight BI+ 4 requires minimal maintenance every 1,500 hours of lighting, so users can save on costs associated with servicing.

The flexible temporary lighting solution is also the first of Atlas Copco’s light towers to feature highly efficient SMD LED lights, which are 20% more efficient than alternative Chip-on-Board (COB) LED lights found in alternative light towers and competitive solutions. Each light tower has four floodlights providing 150W power to reliably cover 4,000m2, extending the working days and contributing towards a safe working environment. The HiLight BI+ 4 is ergonomic, with fully hydraulic mast lifting and electric mast rotation, which is easily controlled on the system’s control panel.

The box-type light tower is 15% lighter than any hybrid light tower available on the market. Operators can fit up to 22 units on a standard 13-metre Eurotruck, which positively impacts transportability and improves operational efficiency.

Eric Tomin , Product Marketing Manager Lighting Towers and Portable Generators, Atlas Copco Power and Flow division, explains: "Sustainability is increasingly important for our customers as they look to improve their environmental credentials, and so we have made it front of mind when designing new equipment.

"This new hybrid light tower is the first of a kind, combining the very latest SMD lighting technology with lithiumion batteries to deliver the very best performance and efficiency."

www.atlascopco.com

SAVETHEDATE

RDS, Dublin: 20-21 Nov 2024

Infrastructure • Services • Solutions

DataCentres Ireland combines a dedicated exhibition and multi-streamed conference to address every aspect of planning, designing and operating your Datacentre, Server/ Comms room and Digital storage solution – Whether internally, outsourced or in the Cloud.

DataCentres Ireland is the largest and most complete event in the country. It is where you will meet the key decision makers as well as those directly involved in the day to day operations.

Entry to ALL aspects of DataCentres Ireland is FREE

• Market Overview

• Power Sessions

• Connectivity

• Regional Developments

• Open Compute Project

• Heat Networks and the Data Centre

• Renewable Energy

• Standby Generation

• Updating Legacy Data Centres

60+ Speakers & Panellists

100+ Exhibitors

Networking Reception

OLIVE SQUARE, ST

JOHNS

WOOD, CENTRAL

LONDON - SILENT

GENERATOR DEPLOYED

FOR NIGHTTIME USE FOR FIVE MONTHS

One of the clients of Power Saving Solutions (PSS) - Olive Square, St Johns Wood, a property maintenance & refurbishment company, requested the deployment of a Hussh Pod 30/45.

The Hussh Pod 30/45, with a 60kVA diesel generator, was delivered to a client at a site in Central London. The Hussh Pod 30/45 itself is a powerful and silent battery power unit with a 30kw three-phase inverter and 45kwh of stored power, reducing emissions and noise pollution while providing reliable, clean energy.

The Hussh Pod's role in this contract was to supply power for property flood repairs, including pumps with silent battery power during the nighttime between 3pm to 9am, and a diesel generator to supply the site with power during the day whilst also recharging the Hussh Pod’s batteries.

The setup had to be as sustainable as possible during the day so site power was provided from the diesel generator, due to this being the highest load points.

The Hussh Pod's role was to supply power during the nighttime hours to equipment such as

pumps and heaters. This setup achieved a 71% reduction in the amount of fuel being used by the generator and in CO2 emissions reduction, reports the company.

The equipment was on hire for five months and operated on Hussh Pod battery for 71% of the timeframe, with the generator running for the remaining 29%.

This resulted in an approximately 13,249 litres of fuel being saved at a value of £19,874 and a reduction of nearly (39,094kg of CO2 compared to when running solely on a diesel generator, explains Power Saving Solutions (PSS).

These figures are based on the generator being a 60kVA with a fuel consumption of 5-litres per hour at a cost of £1.50 per litre), reports the company.

Power Saving Solutions (PSS) was initially established as an electrical contractor and

“The Hussh Pod's role in this contract was to supply power for property flood repairs, including pumps with silent battery power during the nighttime between 3pm to 9am, and a diesel generator to supply the site with power during the day whilst also recharging the Hussh Pod’s batteries. The setup had to be as sustainable as possible during the day so site power was provided from the diesel generator."

July13th,2021: Londoners suffering flooding

an offgrid power specialist. However, as the company saw more and more customers asking for advice on energy generator solutions, it developed its off-grid power solutions into hybrid power generators.

Today Power Saving Solutions designs and manufactures a unique range of affordable, state-of-the-art Hussh Pods built for industry.

The Hussh Pod Hybrid Generators assist customers in significantly reducing carbon emissions, cutting fuel costs and lessen noise pollution.

The company's engineers are all CSCS and 18th Edition-accredited and regularly upskilled in the latest technologies, methodologies and techniques at a purpose-built training area in Meden Vale. This gives PSS access to the most highly-skilled personnel in the industry, and, as a result, the company is able to create the best hybrid solutions with advanced functionality to meet the needs of every sector and niche.

A spokesman concludes: "We also work closely with our suppliers to ensure that the components we source are of the highest quality, the most up-to-date and cost-effective in the market.

"This has enabled us to produce the most efficient generators on the market, both in terms of lower emissions and higher performance. Coupled with our efforts to help companies reduce their carbon outputs and meet targets, we now pledge to have our own company carbon neutral and net zero by 2025." powersavingsolutions.co.uk

4,500+ visitors from energy, environment, sustainability and climate action space

81% of visitors are budget holders or influencers

+£1m average spend of 1/3 of our visitors in the next 5 years

83% of exhibitors rated the quality of visitors as excellent SPONSORED BY

IPowerE - 12th International Power Conference

East Midlands 29-30 October 2024

2-day Conference & Afternoon Workshop

The IPowerE afternoon Workshop and two-day conference will be held at the Hilton East Midlands.

Following on from the IPowerE’s successful 2022 Power Technologies conference this next conference continues to offer a broad selection of genres and topics, offering a unique opportunity to listen to industry experts describe the latest developments in power generation, storage and grid stability. It will consider the engineering, technology and application of these key elements of the Future Energy Mix.

Globally, the power generation sector is addressing the challenges of the climate emergency, integration of large scale renewables and energy storage, and continued energy security.

The transition to increased renewable power generation sources will require current established technologies and energy sources to work alongside innovative solutions in future years and allow energy supply to be delivered in a flexible way.

The conference programme will include a Keynote speech from Darren Davison, Siemens Energy UK & Ireland and presentations from Ansaldo, Carlton Power, Delta Xero, GE, Moove, SSS Gears, Strathclyde University, Torishima Pumps, Siemens, MHI, UK Atomic Energy, Ethical Power, Cranfield University DESNZ, and Rolls-Royce SMR.

CPD – Attending will not only give you access to industry leaders, it will also make a notable addition to your CPD

Workshop (Monday afternoon)

Monday afternoon’s workshop will be an interactive session led by industry professionals. Exhibition tables and space for pop-up banners is available. Please contact the office for more information.

The conference will include a range of industry professionals presenting on power technology design and supply, project development, and energy policy relevant to the future energy sector. An opportunity to question these experts is included in the conference programme.

Conference Dinner (Tuesday evening)

This gives the perfect opportunity to network. The 3-course meal will be held at the Hilton Hotel, providing a more informal setting to continue those all-important contacts and starting discussions with other attendees.

TICKET PRICE: Early Bird Price (valid until 30th September)

Delegate: £550 + VAT/Member: £470 + VAT

Delegate: £600 + VAT

IPowerE Member Delegate: £520 + VAT

Young Engineer (<35): £300 + VAT

Student: £160 + VAT

Please note that the conference dinner on Tuesday evening is included in the conference ticket price.

BOOKING

For more information e:mail enquiries@ipowere.org or call the office on +44 (0)1234 214340.

LOCATION

Hilton Hotel East Midlands Airport, 24 Derby Road, Derby DE74 2YZ.

Event sponsored by SPECTRO JET-CARE

Britain's newest association - UKGSA has a vision of serving its members and the industry by encouraging the sharing of knowledge in the field of Gen-Sets and CHP throughout the entire independent standby power and energy sectors

It has a greater aim to promote the interests of the Generating Set industry for UK Manufacturers, Suppliers & Distributors, Service Providers, Rental Companies and Power related providers. and beyond.”

So far 50+ key companies have joined UK GEN-SET & CHP ASSOCIATION and the association very much looks forward to expanding both its membership base and its many activities during the course of 2024-25.

The latest company to join UKGS is APROVIS.

In a very short space of time, APROVIS has established itself as an innovative energy company on both the national and the international market. Its expertise lies in exhaust gas and gas treatment technology. The company is regarded globally as being a qualified specialist in its field – whether customers are looking for specific individual components or compact system solutions.

For more information about UKGSA and company Membership please visit: www.ukgsa.uk

HEATING IS ONE OF THE BIGGEST SOURCES OF UK EMISSIONS, SAYS

ADE

The Association for Decentralised Energy (ADE) congratulates the new Government on their win and commits to supporting the Labour Party in their delivery of key policies that will shape how the UK decarbonises.

The ADE’s Chief Executive, Caroline Bragg, said: “We congratulate the Labour Party on their success.

"The new Government’s commitment to a massive acceleration of renewables will protect us from another energy crisis and our members have the answer to making this work in practice – by creating a smarter system that puts money in the pockets of

households and businesses.

“As we know, heating is one of the biggest sources of UK emissions. With the mandate now given to the new Labour Government, now is the time to move decisively towards a low cost, just path for decarbonising heat.

Billions of pounds of investment are waiting to invest in zero carbon heat infrastructure across the UK’s cities and towns - all we need is certainty.

With decisive action and ambitious targets, we can create hundreds of thousand jobs, drive economic growth and save the UK billions.”

Email: external.affairs@theade.co.uk.

On behalf of the members of the Association for Consultancy and Engineering and the Environmental Industries Commission, Chief Executive Officer Kate Jennings said, “We would like to congratulate Sir Kier Starmer and the Labour Party on winning the UK General Election.

"In June we shared a 100 day plan for this new chapter of UK government.

"The plan contains practical steps including the need for an infrastructure and industrial strategy, investment pipeline and effective risk management, to accelerate the development of much needed infrastructure, while placing nature and biodiversity at the heart of all designs."

She continued: "The depletion of nature and the escalating need for climate resilient facilities, buildings and spaces, to sustain our planet and growth, means that this is the

time to change how decisions and choices are made.

"We look forward to working in partnership with our members and national, devolved and local government stakeholders to advocate and where possible help to take our plan forward.

"Our members have many of the answers to the big infrastructure, nature and climate resilience questions; by partnering with government, we aim to help cut through the myriads of demands and focus on the most important measures that will shape thriving and safe communities and deliver sustainable growth and prosperity for the future.”

Kate concluded: “We have a robust stakeholder engagement programme in place and will be monitoring and reporting on progress at key government milestones during the first 100 days and beyond.”

PRODUCTS & SERVICES

NEW RANGE OF STATIONARY GENSETS

HIMOINSA has extended its range of stationary generator sets to 220 kVA, with new models designed specifically for stationary applications.

The new HSF 150, HSF 170, HSF 175, HSF 195 and HSF 220 extend up to 220 kVA. (Photo: Himoinsa)

The HSF 150, HSF 170, HSF 175, HSF 195 and HSF 220 models incorporate the features of the HSF range and have been integrated into a new version of the HS60 canopy, adapted to the needs of gen-sets with higher power ratings. Available in 50and 60-Hz three-phase versions, the HS60 canopy comes with a standard liquid retention tray for liquids to prevent spillage. It provides anti-correction and anti-rust protection and comes with large side doors to allow full access to the interior. www.himoinsa.com

WHAT IF YOUR STORAGE BATTERY COULD 'TALK BACK' TO YOU?

A new system-on-chip, the result of an ongoing collaboration between battery management experts Eatron Technologies and edge AI leader Syntiant, offers an unprecedented turnkey solution to the challenges of battery performance and safety forpower generation and BESS systems.

The integrationfriendly AI-BMSon-chip can unlock 10% additional capacity and enhance battery lifespan by up to 25%, while substantially reducing time-to-market. The optimised solution delivers exceptional performance and efficiency in a costeffective package,

combining Eatron’s Intelligent Software Layer with Syntiant’s ultra-low power Neural Decision Processor.

Eatron’s pre-trained models deliver state-of-health, state-ofcharge, and remaining useful life assessments with exceptional accuracy out of the box, thereby maximising available power. Predictive diagnostics, meanwhile, can detect potential battery issues long before they occur, enhancing safety, says the company.

Thanks to the efficient processing power of Syntiant’s NDP120, the AI-BMS-on-chip can operate on the edge, where it can deliver real-time analysis and decision-making directly on the device without needing to rely on complex cloud infrastructure that might otherwise introduce cost, latency and power consumption issues. eatron.com

NEW DATA CENTRE POWER BATTERIES OFFER GREATER EFFICIENCY & RELIABILITY

ABB is promoting a new development - nickel-zinc (NiZn) batteries - as part of its MegaFlex range, to provide guaranteed high power density and sustainable UPS solutions for data centres and other critical power applications.

According to ABB the new batteries could address the sustainability challenges associated with the increasing digitalization trend. Provided by ZincFive - a company which develops proprietary nickel-zinc battery storage technology to provide electricity specifically for data centres and other applications - these batteries are said to offer a 'sustainable alternative to conventional chemistries while meeting the needs of high-power, high-density UPS'.

The NiZn batteries use abundant, recyclable materials, nickel and zinc, which are non-toxic and non-flammable. Research indicates the batteries’ greenhouse gas emissions are four times less than lead-acid and six times less than lithium-ion batteries. The energy footprint with NiZn batteries is also said to be 23-33% smaller than lithium-ion and lead-acid batteries. NiZn batteries provide enhanced safety compared to conventional lithiumion batteries which makes their transportation and installation easier, particularly in mission-critical applications, reports ABB. For these reasons, introducing NiZn battery technology benefits ABB’s MegaFlex, already known for its high system efficiency of up to 97.4% and power availability of up to 1.6 MW UL and 2.0 MW IEC. ABB reports that testing has confirmed ZincFive's NiZn battery technology as a dependable and safe substitute for traditional lead-acid and lithium-ion batteries. With over 150 megawatts of these integrated systems already implemented, ABB is well on the way toward a net-zero future. new.abb.com

WHAT IF THE ACTUAL MATERIAL OF YOUR GENSET CANOPY COULD MAKE UP YOUR BATTERY STORAGE SYSTEM?

Swedish startup Sinonus offers an innovative energy storage solution which could turn giant turbine blades into batteries one day. This involves not just turbine blades but anything made using carbon fibre could be turned into an energy storage unit thanks to Sinonus’ pioneering tech developed at the Chalmers University of Technology in Gothenburg, Sweden.

The company's work with carbon fibre could lead to “massless” batteries where the material itself serves as energy storage and as part of the device’s outside case. According to ther company it's a matter of developing carbon fibre which offers both the stiffness required for structural integrity and the electrochemical performance needed to store energy.

Sinonus has already developed a proof of concept, replacing AAA batteries in the lab with its carbon-electrode batteries. Its prototype at Chalmers University offers just 24 Watt-hours per kilogram (Wh/kg). By comparison, existing lithium-ion batteries typically have an energy density between 80 and 120 Wh/kg.

Markus Zetterström, CEO at Sinonus, has explained that the material doubling as a structural integrity component helps justify the loss of electrical storage efficiency. He says: “Storing electrical energy in carbon fibre may perhaps not become as efficient as traditional batteries, but since our carbon fibre solution also has a structural load-bearing capability, very large gains can be made at a system level.”

Sinonus argues that - by using “the mass that is already there” to store energy - this could serve to reduce the weight and volume of equipment while still improving overall system performance. The end result might not be as efficient as a LiON battery pack at the moment but it is still smaller and lighter while still providing the same battery life. sinonus.com

INNIO is headquartered in Jenbach (Austria), with

ENGINE MANUFACTURERS GUIDE

INNIO Jenbacher gas engines

Headquarters: A-6200 Jenbach (Austria) T +43 5244 600-0 F +43 5244 600-527 jenbacher.info@ge.com www.gejenbacher.com

Manufacturer of gas driven generator sets and cogeneration systems in a power range from 0.25 to 3 MW. Model Fuel

m3N. Dry exhaust gas; based on 5% O2. For engines with 1,200 rpm please contact GE Energy’s Jenbacher product team.

TAD1242GE 352 409

TAD1640GE 393 462

TAD1641GE 433

TAD1642GE 485 570

INNIO Jenbacher gas engines

network in more than 80 countries.

Jenbacher* product portfolio 2022

NOTES

operations in Waukesha (Wisconsin, U.S.) and Welland (Ontario,

A team of more than 3,500 experts provides life-cycle support to the more than 54,000 delivered engines globally through a

Power Generation

INNIO Jenbacher gas engines

Headquarters: A-6200 Jenbach (Austria) T +43 5244 600-0 F +43 5244 600-527 jenbacher.info@ge.com www.gejenbacher.com

R Schmitt Enertec GmbH

56743 Mendig, Germany T +49 2652 9351810 F +49 2652 9351822 info@rschmitt-enertec.com www.rschmitt-enertec.com

Manufacturer of gas driven engines,generator sets and cogeneration systems in the range from 100 - 500 kW.

RSE Engines for natural gas and biogas

Model fuel Freq. Electric output

M06-G/B T0D41 g 50 140 kW

M06-G/B TID41 g 50 200 kW

M06-G/B T2D41 g 50 250 kW

M08-G/B TID41 g 50 260 kW

M08-G/B T2D41 g 50 333 kW

M12-G/B TID41 g 50 400 kW

M12-G/B T2D41 g 50 500 kW

M06-G/B T0D41 g 60 150 kW

M06-G/B TID41 g 60 210 kW

M06-G/B T2D41 g 60 250 kW

M08-G/B TID41 g 60 280 kW

M08-G/B T2D41 g 60 333 kW

M12-G/B TID41 g 60 420 kW

M12-G/B T2D41 g 60 500 kW

RSE engines for LPG

M06-PT0D41 g 50 115 kW

M06-PTID41 g 50 173 kW

M06-PT2D41 g 50 205 kW

ENGINE MANUFACTURERS GUIDE

M08-PTID41 g 50 233 kW

M08-PT2D41 g 50 260 kW

M12-PTID41 g 50 350 kW

M12-PT2D41 g 50 450 kW

M06-PT0D41 g 60 130 kW

M06-PTID41 g 60 173 kW

M06-PT2D41 g 60 205 kW

M08-PTID41 g 60 233 kW

M08-PT2D41 g 60 260 kW

M12-PTID41 g 60 350kW

M12-PT2D41 g 60 450 kW

Manufacturer of gas driven generator sets and cogeneration systems in a power range from 0.25 to 3 MW.

m3N. Dry

NOTES

485 570

Perkins Engines Company Limited

Peterborough PE1 5FQ

Contact name:- Simon Gray

Tel: +44 (0) 1733 583000

M06-PT0D41

M06-PTID41

M06-PT2D41

M08-PTID41

M08-PT2D41

M12-PTID41

M12-PT2D41

M06-PT0D41

M06-PTID41

M06-PT2D41

M08-PTID41

M08-PT2D41

M12-PTID41

M12-PT2D41 RSE engines

M06-HT2D41

M08-HT2D41

M12-HT2D41

M06-HT2D41

M08-HT2D41

Perkins Engines Company Limited

Headquarters: A-6200 Jenbach (Austria)

Peterborough PE1 5FQ

Contact name:- Simon Gray

Tel: +44 (0) 1733 583000

T +43 5244 600-0 F +43 5244 600-527 jenbacher.info@ge.com www.gejenbacher.com

Email: gray_simon_j@perkins.com

Perkins is one of the world’s leading suppliers

Manufacturer of gas driven generator sets and cogeneration systems in a power range from 0.25 to 3 MW.

in dieselor 1000 kWE prime in gas.

SCANIA ENGINES

SE-151 87 Sodertalje Sweden

Tel +468553 81000

Fax +468553 898 12

E-mail engines@scania.com

Web www.scania.com

UK Contact – Mark Swindell

Scania GB Ltd

Tel +44 1908 329386

E-mail mark.swindell@scania.com

Diesel & Gas engines for power generation

m3N. Dry exhaust gas; based on 5% O2. For engines with 1,200 rpm please contact GE Energy’s Jenbacher product team.

Prime power 250kVA to 700kVA Stand by power 250kVA to 770kVA

TAD1242GE 352 409

TAD1640GE 393 462

Engine range prime power 50hz & 60hz at (70% mean load factor)

TAD1641GE 433 509

TAD1642GE 485 570

Scania produce diesel and gas powered engines for various Industrial and Marine applications,tionally low fuel consumption.

Perkins Engines Company Limited

Peterborough PE1 5FQ

All models are available to meet current emissions requirements, Scania engines are now available to meet both Tier 4F and EU Stage V. Alternative fuels

Contact name:- Simon Gray

Tel: +44 (0) 1733 583000

Email: gray_simon_j@perkins.com

Perkins is one of the world’s leading suppliers

Many of our engines can also operate on Bio-diesel conforming to EN14214 and HVO conforming to EN159540

RSE engines for Woodgas

R Schmitt Enertec GmbH

M06-HT2D41 g 50 122 kW

M08-HT2D41 g 50 166 kW

M12-HT2D41 g 50 250 kW

Email: gray_simon_j@perkins.com

M12-HT2D41

M06-HT2D41 g 60 140 kW

56743 Mendig, Germany T +49 2652 9351810 F +49 2652 9351822 info@rschmitt-enertec.com www.rschmitt-enertec.com

M08-HT2D41 g 60 180 kW

M12-HT2D41 g 60 275 kW

Manufacturer of gas driven engines,generator sets and cogeneration systems in the range from 100 - 500 kW. RSE Engines for natural gas and biogas

Perkins is one of the world’s leading suppliers

in dieselor 1000 kWE prime in gas.

Model fuel Freq. Electric output

M06-G/B T0D41 g 50 140 kW

Volvo Penta

M06-G/B TID41 g 50 200 kW

SCANIA ENGINES

SE-151 87 Sodertalje Sweden

Tel +468553 81000

405 08 Gothenburg, Sweden

M06-G/B T2D41 g 50 250 kW

Fax +468553 898 12

Tel +46 31 235460

M08-G/B TID41 g 50 260 kW

M08-G/B T2D41 g 50 333 kW

E-mail engines@scania.com

Web www.scania.com

Model Spec RPM kWm kVA

M12-G/B TID41 g 50 400 kW

M12-G/B T2D41 g 50 500 kW

TAD530GE Diesel 15002) 75 85

UK Contact – Mark Swindell

M06-G/B T0D41 g 60 150 kW

TAD531GE Diesel 15002) 88 100

TAD532GE Diesel 15002) 113 130

M06-G/B TID41 g 60 210 kW

TAD550GE1) Diesel 15002) 76 86

M06-G/B T2D41 g 60 250 kW

Scania GB Ltd

Tel +44 1908 329386

E-mail mark.swindell@scania.com

TAD551GE1) Diesel 15002) 89 101

M08-G/B TID41 g 60 280 kW

TAD730GE Diesel 15002) 113 130

M08-G/B T2D41 g 60 333 kW

TAD731GE Diesel 15002) 132 152

M12-G/B TID41 g 60 420 kW

TAD732GE Diesel 15002) 162 186

M12-G/B T2D41 g 60 500 kW

Diesel & Gas engines for power generation

Prime power 250kVA to 700kVA Stand by power 250kVA to 770kVA

RSE engines for LPG

TAD733GE Diesel 15002) 175 201

TAD734GE Diesel 15002) 213 245

M06-PT0D41 g 50 115 kW

TAD750GE1) Diesel 15002) 114 131

M06-PTID41 g 50 173 kW

Engine range prime power 50hz & 60hz at (70% mean load factor)

TAD751GE1) Diesel 15002) 13 152

M06-PT2D41 g 50 205 kW

TAD752GE1) Diesel 15002) 158 182

M08-PTID41 g 50 233 kW

TAD753GE1) Diesel 15002) 173 199

M08-PT2D41 g 50 260 kW

TAD754GE1) Diesel 15002) 217 250

M12-PTID41

TAD940GE Diesel 15002) 241 277

M12-PT2D41

TAD941GE Diesel 15002) 280 326

M06-PT0D41

TAD1341GE Diesel 15002) 271 315

M06-PTID41

TAD1342GE Diesel 15002) 303 352

M06-PT2D41 g

TAD1343GE Diesel 15002) 325 378

M08-PTID41 g

TAD1344GE Diesel 15002) 354 412

M08-PT2D41

TAD1345GE Diesel 15002) 388 451

M12-PTID41 g

Scania produce diesel and gas powered engines for various Industrial and Marine applications,tionally low fuel consumption. All models are available to meet current emissions requirements, Scania engines are now available to meet both Tier 4F and EU Stage V.

Alternative fuels

TAD530GE TAD531GE TAD532GE TAD550GE TAD551GE TAD730GE TAD731GE TAD732GE TAD733GE TAD734GE TAD750GE TAD751GE TAD752GE TAD753GE TAD754GE TAD940GE TAD941GE TAD1341GE TAD1342GE TAD1343GE TAD1344GE TAD1345GE TAD1351GE TAD1352GE TAD1354GE TAD1355GE

TAD1351GE1) Diesel 15002) 279 324

M12-PT2D41 g

TAD1352GE1) Diesel 15002) 314 365

RSE engines for Woodgas

TAD1354GE1) Diesel 15002) 328 381

M06-HT2D41

TAD1355GE1) Diesel 15002) 355 413

M08-HT2D41

TAD1640GE Diesel 15002) 392 461

TAD1641GE Diesel 15002) 430 505

TAD1642GE Diesel 15002) 503 591

TWD1643GE Diesel 15002) 536 630

TAD1650GE1) Diesel 15002) 393 462

TAD1651GE1) Diesel 15002) 430 505 Engines are also available for1800rpm/60Hz

Many of our engines can also operate on Bio-diesel conforming to EN14214 and HVO conforming to EN159540

Volvo Penta
08 Gothenburg,
+46 31

Membership Benefits

• Training Days

• Exhibiting at 15+ Shows

• Member Networking Events

• 62,000+ Digital Association

Magazine Distribution

• Founder Member Badge

• Association Magazine x2

Free Adverts

• Annual Statistics

• Quarterly Newsletter

• Hospitality Days

• Access link to White Papers

+ lots more...

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.