Construction Analysis Assignment 1. Flipbook Section ‘as-built’

Page 1

ABPL20033 - Construction Analysis, Semester 2 - 2019 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Anastasia Sklavakis, Tutor Ziyang Yuan, 1025198, 10 August 2019 Lake Wendouree house, Tutorial no.5 ASSIGNMENT 1

FLIPBOOK SECTION AS-BUILT: assigned section and construction sequence


10

WALL SYSTEM EXTERNAL WALL

SERVICES AND FINISHES

The kitchen equipments are transported to the houes and installed after the completion of internal partitions and ceilings.

4

A P3

STRUCTURAL SYSTEM

A P3

The steel structure inside the kitchen bench which support the whole structure is installed at the same time with the primary steel columns and beams.

DINING ST-01

SERVICES AND FINISHES

10

Paint the internal walls as the painting colour selected refers to the material lists. Floorboard installation should commence after wall painting finishes since it can prevent floorboard from being stained on by paint.

FFL 453.20

4

VOID OVER DINING

ENSUITE ST-01

STRUCTURAL SYSTEM

After the concrete slabs are completely cured, the installation of the structural systems commence. Steel columns are placed in position by crane. SERVICES AND FINISHES

10

Towel rack is installed to position on the wall after the treatment of the wall completed.

9

ENTRY ST-01

STONE SETOUT POINT

INTERNAL PARTITIONS

Internal partitions are constructed as stud walls to divided the space inside the house which according to the architectural drawings. Partition walls are covered by plasterboard (13mm thickness) to achieve water resistant to wet are in the house.

RECESS IN FLOOR

GLASS FLOOR GL-10

BH-05

SITTING TF-01

STUDY

POWDER Rm ST-01

7 7 01

GROUND FLOOR PLAN SCALE 1:50 @A3

7

Insulations are installed into the stud wall inside the house to improve the temperature controling. Scaffolding are used for installing the external wall and cladding to keep workers safe.

WALL SYSTEM EXTERNAL WALL

Brick walls are constructed both internal (Both sides of the stairs) and external (around living and east wall) of the house. Insulations are installed between stud wall and internal brick wall.

02

FIRST FLOOR PLAN SCALE 1:50 @A3

ABPL20033 - 2019, Ziyang Yuan | 1025198 |Tutorial 05 | Anastasia Sklavakis | p. 2

WALL SYSTEM CLADDINGS

The installation of cladding will be commenced after the confirmation of windows locations since builders need to cut the cladding in accordance the dimension of the windows and doors. VM Zinc cladding are applied to the external wall of three bedrooms on upfloor for a life span.

8

WINDOW SYSTEM

Windows with 30 x 1.6mm anodised aluminium angle sill are nailed onto the internal stud wall by bullet nails and some of them are sealed to prevent heat from running off the house.


6

SERVICES AND FINISHES

ROOF SYSTEM ROOF STRUCTURE AND COVER

5

Timber roof structures are shaped first to form the supporting elements for roofing system. Timber beams and joists are nailed together. Breathable roof sarking is installed above the timber roof battens. Bulk thermal insulation are installed between roof rafters and roof joists to keep heat flow from running off the house which is 210mm in thickness.

INTERNAL PARTITIONS

Partition walls are covered by plasterboard in 13mm thickness to achieve water resistant to wet are in the house. M10 bolt to joist located directly below braced walll or M10 anchor to slab on ground floor.

FLOOR SYSTEMS GROUND FLOOR STRUCTURE

9

5

INTERMEDIATE FLOOR STRUCTURE

Timber trusses are fixed on steel beams by bolts and there is a 10mm gap between ceiling and underside of steel work. Joist hanger to suit fully nailed on the timber blocks which are bolted onto the steel beams.

4

INTERMEDIATE FLOOR STRUCTURE

Floor substrate is installed on the first floor by nails for further construction. The spacing and span of the joists and beams are applied refers to the structural drawings.

6

Services including heating and cooling equipments are installed. Furnitures are installed into or moved into the house from the factory.

10

STRUCTURAL SYSTEMS PREPARATION AND COMPLETION OF BUILDING STRUCTURE

Crane is hired for placing and installing the structural beams and columns on the ground floor. Trusses and beams are basically bolted onto the steel columns sometimes with cope required to support the whole main structure.Structural bracings are installed to support the main floor structural systems.

ROOF STRUCTURE

Box gutters are installed between roof sheets to collect the stormwater and carry it to ground by external downpipes.

3

There are 50mm thick sand lays over the compacted fills before installing the 0.2mm polyethylene waterproof mambrance. Reinforced meshes are fixed onto the waffle slab by bar chairs.

SITTING AREA

STUDY

ENSUITE VOID OVER DINING

WINDOWS SYSTEMS

Crane is required for placing the large size glazing windows on the correct position on site and cooperated by workers to install. Windows are nailed onto the internal stud wall by bullet nails and some of them are sealed to prevent heat from running off the house.

8

9

W17

CEILING STRUCTURE

Thermal insulation are installed in the roof and ceiling of the house which is 210mm in thickness. Ceiling sheet are using 13mm plasterboard to achieve water resistant to wet.

7 ENTRY HALL

KITCHEN

DINING

POWDER Rm

Foam plastic are installed between stud wall and internal brick wall. Insulations are installed into the stud wall inside the house to improve the temperature controling. 2-brick rebate (172mm typical) is installed at the bottom of the brick wall.

Kitchen Bench supported by steel structure

03

SECTION A SCALE 1:50 @A3

1

FOUNDATION SYSTEMS EXCAVATION, DEMOLITION AND FOOTINGS

The excavation starts after demolition complete, trenches are dug for footings and excavates the site to the required level on the construction plan. The footings are poured as the foundation.

3

2

FLOOR SYSTEMS GROUND FLOOR STRUCTURE

15MPa blinding concretes are required here which founded min 200mm into the stiff clay refers to the soil report. Several layers of compacted engineer fills are installed above the blinding concrete. Waffle slabs (ploythylene void )are installed to save the usage of concrete.

WALL SYSTEMS EXTERNAL WALLS

FOUNDATION SYSTEMS RETAINMENT AND SERVICES PIPES LAYOUT

The plumber digs trenches for the layout of water and gas pipes for the kitchen above it.

3

FLOOR SYSTEMS GROUND FLOOR STRUCTURE

Engineer visits the site to check the position of the waffle slabs and reinforcement meshes. Then concrete paving slabs are poured into the correct loaction on site.

ABPL20033 - 2019, Ziyang Yuan | 1025198 |Tutorial 05 | Anastasia Sklavakis | p. 3

2

FOUNDATION SYSTEMS RETAINMENT AND SERVICES PIPES LAYOUT

The plumber digs trenches for the layout of the services pipes which according to the details on the construction drawings. Services pipes for water, gas, electricity and drainage lays out into the trenches for toilet and kitchen.


1. FOUNDATION SYSTEMS: EXCAVATION, DEMOLITION AND FOOTINGS 1.1 The builder need to get the relevant permissions first which includes building permit and demolition permit. 1.2 The demolition contractor inspects the site to observe site condition including the existing buildings or materials from the previous property. 1.3 Contact the supplier and disconnect the water, gas and electricity services before the demolition. 1.4 The demolition commences after a confirmation of the demolition plan, it removes old building including its footings. 1.5 Then a land surveyor measures the site by using theodolite on tripod according to the Australian standard height datum to ensure the building will be constructed properly later. 1.6 The movable site office is placed beside the construction area and the toilet as well for the workers. 1.7 The excavation starts after demolition complete, trenches are dug for footings and excavates the site to the required level on the construction plan. 1.8 The footings are poured as the foundation.

2. FOUNDATION SYSTEMS: RETAINMENT AND SERVICES PIPES LAYOUT 2.1 Before layout the services pipes, make sure the gas and electricity services are disconnected from the suppliers and get the permission from the local water authority to start working. 2.2 The plumber digs trenches for the layout of the services pipes which according to the details on the construction drawings. 2.3 Remove the sand and soil on site to be ready for the construction of the foundation systems. 2.4 Services pipes for water, gas, electricity and drainage lays out into the trenches dug before. 2.5 The 15MPa blinding concretes are required in this construction project which founded min 200mm into the stiff clay refers to the soil report.

3. FLOOR SYSTEMS: BASEMENT AND GROUND FLOOR STRUCTURE (BASEMENT/SLABS/ SUSPENDED FLOOR) 3.1 Several layers of compacted engineer fills are installed above the blinding concrete. 3.2 There are 50mm thick sand lays over the compacted fills before installing the 0.2mm polyethylene waterproof mambrance refers to the structural drawings 3.3 Timber formed retainment structures are installed for later concrete pouring supports. The area for bathroom are reserved with a gap under normal ground level. 3.4 Waffle slabs (ploythylene void )are installed above the waterproof mambrance refer to the structural drawings. 3.5 Reinforced meshes are fixed onto the waffle slab by bar chairs. 3.6 Engineer visits the site to check the location of the waffle slabs and reinforcement meshes. 3.7 Concrete paving slabs are poured into the correct loaction on site.

4. STRUCTURAL SYSTEMS: PREPARATION AND COMPLETION OF BUILDING FRAME/STRUCTURE 4.1 After the concrete slabs are completely cured, the installation of the structural systems commence. 4.2 First find the correct positions for the base of the steel columns and beams for further installation which refers to the structural drawings. 4.3 Crane is hired for placing and installing the structural beams and columns on the ground floor. 4.4 Trusses and beams are basically bolted onto the steel columns sometimes with cope required to support the whole main structure. 4.5 Scaffolds are installed on site upto first floor for workers to construct the further timber structures easily and safely. 4.6 The external wall are built during the structure installation. 4.7 Structural bracings are installed to support the main floor structural systems.

Construction stages 1-5, summary ABPL20033 - 2019, Ziyang Yuan | 1025198 |Tutorial 05 | Anastasia Sklavakis | p. 4

5. INTERMEDIATE FLOOR STRUCTURE 5.1 After the build of the external wall and internal wall, the intermediate floor structure installation commence. 5.2 The spacing and span of the joists and beams are applied refers to the structural drawings. 5.3 The connections between the timber structure and steel columns and beams are normally bolted or nailed to position. 5.4 Floor substrate is installed on the first floor by nails for further construction. 5.5 Timber trusses are fixed on steel beams by bolts and there is a 10mm gap between ceiling and underside of steel work. 5.6 Joist hanger to suit fully nailed on the timber blocks which are bolted onto the steel beams.


6. ROOF SYSTEM: ROOF STRUCTURE AND COVER 6.1 The scaffolding and safety barriers are installed upto the roof level to enable workers to install roof structures and protections and for the safety purpose as well. 6.2 Timber roof structures are shaped first to form the supporting elements for roofing system. 6.3 Timber beams and joists are nailed together to form the primary roof structure. 6.4 Breathable roof sarking is installed above the timber roof battens to protect it from mould growing and also improve thermal performance by reducing flow through the roof structure. 6.5 Bulk thermal insulation are installed between roof rafters and roof joists to keep heat flow from running off the house which is 210mm in thickness. 6.6 Metal roofings are applied for all house roof top using zinc or aluminium sheets. 6.7 Box gutters are installed between roof sheets to collect the stormwater and carry it to ground by external downpipes.

8. WINDOWS SYSTEMS 7. WALL SYSTEMS: EXTERNAL WALLS AND CLADDINGS 7.1 Brick walls are constructed both internal (Both sides of the stairs) and external (around living and east wall) of the house. 7.2 Foam plastic are installed between stud wall and internal brick wall. 7.3 Insulations are installed into the stud wall inside the house to improve the temperature controling. 7.4 The installation of cladding will be commenced after the confirmation of windows locations since builders need to cut the cladding in accordance the dimension of the windows and doors. 7.5 VM Zinc cladding are applied to the external wall of three bedrooms on upfloor for a life span. 7.6 Scaffolding are used for installing the external wall and cladding to keep workers safe.

8.1 Large windows are all transport to site by small tracks carefully to ensure its safety. 8.2 Crane is required for placing the large size glazing windows on the correct position on site and cooperated by workers to install. 8.3 Windows are nailed onto the internal stud wall by bullet nails and some of them are sealed to prevent heat from running off the house. 8.4 The detailed connections between windows and external claddings must refer to the drawings to construct correctly. (such as waterproof) 8.5 Conservatory of the house installs single glazed louvres to keep this room warm or cool by controllabe ventilation. 8.6 External wall windows are all using double glazed type to minimise noises.

9. INTERNAL PARTITIONS AND CEILING STRUCTURE 9.1 Internal partitions are constructed as stud walls to divided the space inside the house which according to the architectural drawings. 9.2 Partition walls are covered by plasterboard (13mm thickness) to achieve water resistant to wet are in the house. 9.3 Thermal insulation are installed in the roof and ceiling of the house which is 210mm in thickness. 9.4 Service wires running across inside the stud walls and ceilings which refers to the architectural and mechanical drawings. 9.5 Ceiling sheet are all using 13mm plasterboard to achieve water resistant to wet. Except the timber (ship lapped) ceilings in dining room and villaboard using in plant room and conversatory.

Construction stages 6-10, summary ABPL20033 - 2019, Ziyang Yuan | 1025198 |Tutorial 05 | Anastasia Sklavakis | p. 5

10. SERVICES AND FINISHING TRADES 10.1 Service wires are well organised from one start point to the using end. 10.2 Services including heating and cooling equipments are installed properly inside the house such as the underfloor heating system. 10.3 Start painting the internal walls as the painting colour is selected refers to the material lists. 10.4 Floorboard installation should commence after wall painting finishes since it can prevent floorboard from being stained on by paint, 10.5 Furnitures are installed into or moved into the house from the factory carefully normally with the protection mambrance. 10.6 Reconnect gas and electricity services to make it ready to use. 10.7 Clean the whole house including carpets and floors and hand over the property to the owner.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.