Mumbai Metro - Overview

Page 1

PROJECT TRAINING FINAL JURY

MUMBAI METRO LINE3–UGC02 NATM FOR ADITS ANDCENTRAL CAVERN .

3D MODEL

EXERCISE ON PROJECT DELAY SUBMITTED BY :BHUMIKA RAJ UC5316

GUIDED BY PROF. RESHMA SHAH.


INTRODUCTION TO ACTIVITY           

Construction of adit and central cavern by NATM methodology Element: Adit 3 and central cavern connecting two boxes at kalbadev station. ( station box1 and station box ) Location:It is situated between gridline 5 & 7 and central cavern, upline tunnel at Kalbadevi station Clear width: 6 m Length of entire adit :23.5M Width of cavern:9.5m Grade of Concrete for shot crete: M35 Grade of Steel for wire mesh: Fe500D : 150*150*6 mm Diameter of rebars for rock bolts: 32mm dia Blasting : explosive name – ideal power 90 Electronic detonators Soil strata: grade 2 rock

Quantum of work observed for Adit  Total excavation:167 m3  Total shotcrete:37.5m3  Total explosives :35.36kg Quantum of work observed for central cavern  Total explosives :86 kg

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

2


OBSERVED ACTIVITY LOCATION

ACTIVITY LOCATION This shows the activity location which is situated between two station box.

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

3


ACTIVITY LOCATION

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

4


tunnel works

PRELIMINARY ACTIVITIES

FEASABILITY SRUDY

PLANNING

SELECTION OF AGENCIES

DESIGN

LAUNCHING OF TBM

QUALITY INSPECTION

EXECUTION

INTIAL DRIVE

MAIN DRIVE

CROSS PASSAGES

MISCALLAN EOUS

NATM

LAYING OF TRACKS / VENTILATIO N ETC

SUMP PASSAGE

ADITS

CENTRAL CAVERN DRILLING AND BLASTING WORKS

ADIT 1

SUBMITTED BY : BHUMIKA RAJ (UC5316)

ADIT 2

ADIT 3

ADIT 4

SHOTCRETE

WIREMESH

ROCK BOLT

ADIT 5

ADIT 6

WORK BREAKDOWN STRUCTURE

ADIT 7

Your Logo or Name Here

5


STRATIGRAPHY OF SOIL CONDITION. STRATIGRAPHY OF SOIL CONDITION AT KALBADEVI STATION ACCORDING TO THE GEOLOGICAL INVESTIGATION REPORT

Conclusion:After a critical review of data and site observation and monitoring it has been found that GWL is 2 m to 5.0 m BGL. However, for calculations, as per the tender recommendations, the water level will be taken at ground level.

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

6


FACE MAPPING AND PROBE HOLE .

During the TBM excavation frequent probing & face mapping was carried out for Kalbadevi station.The geological profile shown below is based on mapping & probing data, RMR at the tunnel face varies here from 64 to 71 thus good quality basalt (grade II) is considered at the excavation face of NATM tunnels as well.

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

7


DESIGN METHODOLOGY

METHODOLOGY

•Analytical methods are based on RMR system. The RMR‐system a) Uniaxial compressive strength b) RQD c) Spacing of discontinuities d) Condition of discontinuities e) Ground water conditions f) Orientation of discontinuities The RMR of the rock is worked out as per the above properties and the support is designed .

ANALYTICAL

The RMR‐system based on few parameters

FEM

For this design, PLAXIS 2D is used for analysis of the ADIT in FEM based models.

GUIDELINES FOE EXCAVATION AND SUPPORT SPANNING 10 M IN TUNNEL ACCORDING TO RMR METHOD ROCK MASS 1 VERY GOOD RMR 81-100

EXCAVATION Full face 3 m advance

ROCK BOLTS Generally no support required except rock bolting

SHOTCRETE

STEEL RODS

II GOOD ROCK RMR 61-80

Full face 1-1.5 m advance Complete support 20m from face

3-2m long bolts spaced 2.5 mm with ocassional wire mesh

50m crown where required

none

III FAIR ROCK RMR 41-60

Top heading and benching 1.5-3 m advance in top heading

Systematic bolts 4m long spaced 1.5-2 m in crown with wire mesh

100-150mm in crown

Light to medium ribs spaced 1.5 m where required

Note-Yellow highlight shows the grade of rock observed at kalbadevi

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Note :2d model generated by plaxis model Your Logo or Name Here

8


INSTRUMENTATION AND MONITORING • 3D Targets • Strain gauges The 3D Targets –FUNCTION For 3D Targets, the total station used for the monitoring should measure up to the required precision level. To obtain accurate results both high quality 3D targets and a high precision total station are required. For typical details monitoring instruments and procedures reference shall be taken to design manual and NATM specification. The 3D Targets –LOCATION

DIFFICULTIES FACED There is always a risk of heavy groundwater inflow in tunnels. Hence, dewatering pumps shall beinstalled while near unsupported face. A detailed calculation for the same would be included in

The crown is always at a higher risk then rest of the tunnel while excavation. Hence, excavation shall begin form crown and then going towards invert.

definitive design.

Figure 12: INSTRUMENTATION AND MONITORING

Your Logo or Name Here

9


ADIT DRAWINGS

Your Logo or Name Here

10


ROCKBOLTING DETAILS

50

32

Your Logo or Name Here

11


CONSTRUCTION METHODOLOGY NATM AT KALBADEVI AT A GLANCE . ENTERING INSDIE

DRILLING AND BLASTING EXACACVTION USING SPLITTER

ROCK BOLTING MAIN TUNNEL

PROFILE MARKING PROFILE MARKING

STEEL SUPPORT

FACE DRILLING FACE DRILLING

CORE CUTTING

INTIAL CUT TO START SPLITTING

CONTROLLED CHARGING PLAN VIEW OF JUNCTTION AT ADIT AND TBM

SEGMENT REMOVAL

CONTROLLED BLASTING SCALING

GROUT REMOVAL

MUCKING

FACE READY FOR EXACVATION

DEFUMING

MIS FIRE CHECKING GOING FOR NEXT ROUND TO COMPLETE BLASTING ACTIVITY

SCALING AND MUCKING

PRELIMANRY SUPPORT

MARKING OF SEGMENTS

NEXT CYCLE

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

12


CONSTRUCTION METHODOLOGY

U JACKS AND WALERS

TUNNEL INVERT

MARKING OF POINTS ON SEGMENT

REMOVAL OF SEGMENT

SUBMITTED BY : BHUMIKA RAJ (UC5316)

3d picture for the drilling by jumo driller produced in sketch up.

3d picture after removal of segment produced in sketch up. Your Logo or Name Here

13


CONSTRUCTION METHODOLOGY

EXCAVATION IN TRANSITION ZEON

3d picture for primary support procedure produced in sketch up.

HEADING IS CARRIED OUT ALONG THE ENTIRE LENGTH OF ADIT BY EXCAVATOR AFTER THAT WITHIN INTERVAL OF SOME LENGTH BLASTING CAN BE CARRIED OUT

EXCAVATION UPTO PLATFORM LEVEL HEADING IS CARRIED OUT ALONG THE ENTIRE LENGTH OF ADIT BY EXCAVATOR AFTER THAT WITHIN INTERVAL OF SOME LENGTH BLASTING CAN BE CARRIED OUT

NO,

DESCRIPTION

8

PULL CONSIDERED IN ADIT IS 1.15 SO AEXCAVATING 1.15 M ON THE FACE IS DONE FIRST

9

WIREMESH OF SIZE 150*150*6 IS PLACES ON THEINNER FACE

10

SHOTCRETE IS DONE THROUGH PNEMARIC SHOYCRETE MACHINE WITH REBOUOND LIMITED TO 10%. PNEUMATIC SHOTCRETE MACHINE IS USED ON SIT E.

11

ROCK BOLTING IS DONE AT THE END BY USING RODS OF 32 MM DIA BEFORE THAT RESIN CAPUSLES ARE ATTACHED SO THE ROD IS EMBEDDED IN THE SOIL AND FACE PLATE IS ADDED FOR SUPPORT

Your Logo or Name Here

14


PROCEDURE SKETCH

AFTER THE SEGMENT ID REMOVED DRILLING BY EXACAVTION MEAN IS STARTED JUMBO DRILLER IS USED TO DRILL INTO THE SEGMENTS

BY THE MEANS OF EXCAVATOR THE EXCAVATION IS CARRIED OUT FURTHER

DETAILS CAPSULE

RESIN

shelf life: 6 months,gel time: 30 seconds,setting time:120 seconds,dia 33 mm,length300mm,storage 25 degree .They are provided so they can gel the rod inisde the drilled holes

ROCKBOLTING IS CARRIED OUT

AT EVERY 1 M ADVANCE WIREMESH IS FIXED 150*150*6 MM IN SIZE

OF

SHOTCRETE IS CARRIED OUT IN ADIT BY PNEUMATIC SHOTCRETE MACHINE

NOTE : Drilling and blasting cannot be carried out initially on the face as it can damage the allignment of other adjacent rings to it so firstly excavation is done through excavator and after some distance geologist intervenes in the process and approves that when it is safe to carry out blasting At adit 3, excavation was carried out till 5.3 m after that distance blasting was carried out till next 18.63m through out the adit length

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

15


BLAST DESIGN PATTERN SKIN TO SKIN HOLES ARE PROVIDED ON THE PERIPHERY THEY HAVE 102 DIA AND THEIR FUNCTION IS TO TANSFER THE VIBRATION TO THE ADJACENT MASS SO THEY HAVE LARGER DIA

REAMER HOLES ARE PRESENT ON THE FACE O IN THE MIDDLE THEIR PURPOSE IS TO PROVIDE CLEAR FACE FOR NEXT CYCLE

SUBMITTED BY : BHUMIKA RAJ (UC5316)

PRODUCTIVE HOLES ARE PROVIDED IN THE CENTRE BETWEEN PHERIPHERY AND REAMER HOLES

Your Logo or Name Here

16


BLAST DESIGN PATTERN

PRODUCTIVE HOLES

PERIPHERY HOLES

REAMER HOLES

PERIPHERY HOLES

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

17


PROCEDURE FOR DRILLING AND BLASTING

1 DRILLING OF HOLES 1.2 M DEPTH 1) 2) 3)

PERIPHERY REAMER PRODUCTIVE

3

2

INSERTING EXPLOSIVE INSIDE THE HOLES AND ADDING SPACER AS REQUIRED WITH THAT ATTACHING THE ELECTRONIC DETONATOR

Skin to skin holes are provided on the periphery they have 102 dia and their function is to tansfer the vibration to the adjacent mass SUBMITTED BY : BHUMIKA RAJ (UC5316)

STEMMING IS DONEWHICH IS FILLING THE HOLE WITH SAND FSO DURING BLAST THERE IS NO REBOUND OF EARTH MATERIIALS

Reamer holes are present on the face o in the middle their purpose is to provide clear face for next cycle

4

BLASTING IS CARRIED OUT WHICH IS FOLLOWED BY DEFUMING

Productive holes are provided in the centre between pheriphery and reamer holes

Your Logo or Name Here

18


QUANTITY FOR BLASTING

Chainage :Sr.N o.

Description

1

Round 1

2

Round 2

3 4 5 6 7 8 9

Round 3 Round 4 Round 5 Round 6 Round 7 Round 8 Round 9 Total

FOR ADIT 3

Adit 3D/L. From To Pull Qty (m) (m) (m) (Cum) 5.3 6.45 1.15 21.51 No Of Charg Blast Date Holes e Timing 06-11- 2.14pm 6 2.25 2019 . 3.39pm 11 3.68 . 07-11- 11.55a 10 3.5 2019 m. 12.42p 12 2.875 m. 4.312 2.44pm 17 5 . 5.56pm 19 4.375 . 08-11- 4.06pm 28 6.187 2019 . 5.52pm 18 4.25 . 09-11- 12.50p 18 3.93 2019 m. 139 35.36

EXPLOSVES(kg EXPLOSIVES( ) no) 35.36 kg 282

29.44 28 23 34.5 35 49.496 34 31.44 282.876

EDS

Fro m (m)

PF.

18

Cavern

Cavern

Chainage :-

0.2 CATRIDGE USED(NO)

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE :UC5316 MUMBAI METRO LINE3 UGC-02 MEASUREMENT SHEET

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE :UC5316 MUMBAI METRO LINE3 UGC-02 MEASUREMENT SHEET

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE:UC5316 PROJECT TRAINING 2019-2020 ( MUMBAI METRO UGC-02) Measurement Sheet

Eds

Sr.N o.

1

1 1

1

2

1 1 1 1 1

3 4 5 6

1 9

7

Description Bottom tightness

Round 1 mmct Bottom tightness Round 2 mmct Round 03 mmct Round 04mmct Round 5 mmct Round 6 mmct+bott om tightness Total

1.2 No Of Hole s 37

To (m) 2.4 Charg e

Pull (m) 1.2 Date

Qty (Cum)

9.25

2.25

11

2.937 5

14

3.5

23.04 Blast Timing

23.01.20 20

1.45pm

5.59pm 24.01.20 20

12.40p m 1.38pm

15

4.062 5

02.55p m

18

4.5

4.08pm

20

5

137

CHARGE /0.125

Chainag e :Sr.N o.

12.25 34.5

5.20pm

25.01.20 20

1.49pm

Descripti on

Remark. 1

6

53

PF.

NO OF CATRID GE

no. Of stld:01 NO. Of ED01 NO. Of ED01 NO. Of ED01 NO. Of ED01 NO. Of ED01 NO. Of ED01 NO. Of ED01

2

74

3 4

18 23.5

5

28 6

32.5

7

Bottom tightness Round 1 mmct Round 2 mmct Round 3 mmct Round 4 mmct+ bottom tightness Round 5 mmct Round 6 mmct

Fro m (m)

To (m)

Pull (m)

Qty (Cum)

0

1.2

1.1

21.12

No Of Hole s

Charg e

Date

Blast Timing

24

5

21.01.202 0

5

0.875

7

2.625

3.31pm

10

2.5

5.36pm

14

7.125

22.01.202 0

12.05p m 01.40p m

12.01p m

NO. Of ED02

8

9

98 350

19

4.75

24

6

2.51pm

Round 7 mmct

24

6

4.06pm

Round 8 mmct

7

Total

Remark.

NO OF CATRIDGE

CHARGE/0.1 25

No. Of ED:01 No. Of ED:01 No. Of ED:01 No. Of ED:01

40 7 21 20

No. Of ED:01 57

1.01pm

36 40

PF.

103

2.187 5 29.87 5

5.51pm

No. Of ED:01 No. Of ED:01 no. Of stld:01 NO. Of ED01 no. Of stld:01 NO. Of ED02

38 48

48

17.5 296.5

9

Your Logo or Name Here

19


QUANTITY FOR DRILLING AND BLASTING SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJ CODE :UC5316 MUMBAI METRO LINE3 UGC-02 MEASUREMENT SHEET

UNITS .

Adit 3D/L.CAVERN From (m)

Chainage :Sr.No.

Description 1

2.4 No Of Holes

To (m) 3.8

Pull (m) 1.4

Charge

Qty (Cum)

PF.

Date

Remark.

12.51pm

NO. Of ED-01

9

3

1.42pm

NO. Of ED-01

3 Round 3 cst

16

5

2.54pm

NO. Of ED-01

4

34

8.5

4.38pm

NO. Of ED-01

23

3.875

5.52pm

NO. Of ED-01

89

23

Round 2 cst

Round 4+5 cst

5 Round 7 mmct Total

27.01.2020

Blast Timing

2.625

2

TOTAL QUANTITY FOR ALL THREE ROUNDS OBSERVED TOTAL EXCAVATION 71..04Cu.m. AVERAGE 1.2 M PULL CATRIDGES

ED(adit) 1%

26.88

7

Round 1 cst

NO OF CATRIDGE

catridges/ explosives(adit) 25%

CHARGE /0.125 21

ED(caven) 2%

24 40

catridges (Cavern) 72%

68 31 184

ED(adit)

catridges/ explosives(adit)

ED(caven)

catridges (Cavern)

830 NO.

Table 7:QUANTITY FOR BLASTING AT CENTRAL CAVERN ROUND 3 NOTE – ROUND 1 CTS, it refers to the blasting started from chattrapati shivaji station side and same for Mumbai central station mmct. *Blasting pattern remains same refer blasting pattern drawing , some improvisations are done on site as site conditions vary,( no of holes may differentiate and no of rounds may reduce or increase ) *The variation is based on the experience of blasting head and engineer

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

20


TIMECYCLE ANALYSIS sr. no

FOR ADIT

TIME CYCLE FOR ADIT 3 ( CLASS 2 ROCK) UNIT DETAILS

Time cycle for central cavern from( 0.00m adit 3 towards adit 13.8m chainage ) DESCRIPTION

1 2 3

area peripheral length effective pull

m2 m m

89.25 12.5 1.12

4

excavation

hours

88

65

total 2 shifts of 11 hours with 1 hour break each , pull of 1.15 at adit is observed

5

survey and mapping

hours

2

0.5

surveyor comes in shifts one in morning and then in evening.

6

mucking

hours

6

6

1 hours taken to remove muck everyday for 6 pulls

7

wire mesh

hours

18

18

two layers of wiresmesh is laid after every excavation round which consumes 1.5 hours so for 6 pulls

8

rockbolting

hours

12

12

for rock bolting in one pull 2 hours are consumed so for 6 pulls

9 10 11 12 13 14 15

shotcrete total time for activity conigency total time for activity working hours working days advance per days

hours hours hours hours hours wd/month m/day

48 174 17.4 191.4 22 25 1.75

16

monthly progress excavation

m/month

43.75

in 2 rounds it is done and is carried out simultaneously with excavation at every 1.15 m its done which consumes 4 hours for 60 one pull so for 6 pulls 161.5 total time taken for adit l=7.140 16.15 contingency @10% 177.65 22 22 working hours ( break of 2 hours) 25 deducting sundays and holidays 2.36 Daily excavation Monthly excavation=working days * 59 advance each day

Exacavation quantity

cu.m

71

No of holes

no

329

penetration rate

10m/hr

drilling for 32 mm holes

blasting and charging

hours

hours

defuming

6

for one face approximately 2 hours are consumed for drilling and pull is 1.2m on average so for 3 rounds

10

2.5 hours for entire blasting includes inserting exolosives and attaching electronic detonators for one pull so for 3 rounds

3

defuming for 1 hour is done after every round so for 3 rounds

total time for activity

hours

16.5

conigency

hours

1.65

total time for activity

hours

18.15

working hours

hours

22

working days

wd/month

25

for one day progress

cu.m/day

86

monthly progress drilling and blasting

cu.m./month

2150

hours

m2

m(1.12*7) 88 89.25 7 22 22.3125 1.75 65

SUBMITTED BY : BHUMIKA RAJ (UC5316)

89.25 7 30.2076 2.36923 22 9 1

Your Logo or Name Here

21


TIME CYCLE ANALYSIS Time cycle comparison 100 90 80 70 60 50 40 30 20 10 0

DELAY TIME COMPARIOSN

ACTIVITY TIME CYCLE COMAPRISON 12 10 8 6

0.5 excavation survey and mapping Series1 ACTUAL

4 mucking

wire mesh rockbolting shotcrete

Series2 PLANNED

Linear (Series1)

INFERENCE: • The deviation is observed when compared with the planned time cycle..There is peak observed in exacavation due to the unexpected excavating condition. • it was about 23 hours delayed, another difference is observed in shotcrete it would take 60 hours according to the planned timecycle but due to easy availability of equipments and labours it was completed earlier. • From the above graph is is conducive to say that actual time cycle is consuming more time then planned so the contractor will have to mitigate the delay and cope up.

2 0 drilling for 32 mm holes blasting and charging

Series1 ACTUAL

Series2 PLANNED

defuming

Linear (Series1)

32.5 32 31.5 31 30.5 30 29.5 29 28.5 28 1

OBSERVED

INFERENCE :The peak observed in drilling and blasting with comparison to planned time cycle is due to the unavailability of detonators on site , so it took 10 hours instead of 7.5 to completed the task.this timecyle analysis for entire drilling and blasting activity for 13.8 m chainage as observed on site for central cavern

2

3

PLANNED

4

5

6

Linear (OBSERVED )

INFERENCE :This graph shows the comparison between planned and observed delay time with time on y axis and rounds on x axis. The peak observed in round 1 and 5 of adit was due to unavailability of shotcrete pump on site For round 3 the delay was due to unavailability of excavator on site. The delay time(contingency) set by the contractor isYour 10% Logoofor the Nametotal Here activity timecyle. 22


LABOUR PRODUCTIVITY

ACTIVITY

SUB ACTIVITY

LABOURS

TIME TAKEN

FOREMAN SKILLED UNSKILLED TOTAL HR

QUANTU UNIT M

LABOUR PRODUCTIVITY

167 Cu.m

41.75

MAN DAY

PREMINARY

EXACVATION

1

2

2

5

88

4

PRELIMANRY SUPPORT

SHOT CRETE(PULL 1.2)

2

2

2

6

48

2.181818

37.5 M3

17.1875

WIRE MESH

1

2

3

6

18

0.818182

101 kg

123.4444

ROCK BOLTS

1

3

2

6

12

0.545455

63 kg

115.5

DRILLING AND BLASTING

2

5

2

9

13.5

0.613636

329 cu.m

total

7

14

11

SUBMITTED BY : BHUMIKA RAJ (UC5316)

536.1481

10 9 8 7 6 5 4 3 2 1 0

LABOURS INVOLVED IN ACTIVITY

EXACVATION

SHOT CRETE(PULL 1.2)

WIRE MESH

ROCK BOLTS DRILLING AND BLASTING

INFERENCE :maximum no of labour force is observed in drilling and blasting as it’s a tedious activity involving more work force while in excavation one operator operating excavator is enough for carrying out the activity

32 179.5

Your Logo or Name Here

23


RATE ANALYSIS

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY NAME:-

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY NAME:BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 Measurement Sheet Item Item Description Unit Qty Rate Amount No

Item No

material Labour

skilled unskilled C

0 man/da y man/da y man/da y

B

Rate

Amount

1

1200

1200

2

600

1200

2

500

1000 3400 0

C

hours

70

934

water and electricity cost(4% of A+B) Contingeny(2% of A+B+C+D)

136 1378.32

E

miscallaneous(15% of A+B+C+D)

10544.148

total

80838.468 rs/m3

37.5

7000

0 man/day

2

1200

484.06

material

B

150 *150* 6 wire mesh Labour

man/day

2

660

1320

unskilled

man/day

2

540

1080 31050

operator

skilled

D E

Contingeny(2% of A+B+C+D)

E

hours

48

4000

unskilled

192000

1242

miscallaneous(15% of A+B+C+D)

4485.84 34316.67 6

total

289344.5 16

cost per m3

Amount

10 1

52

1

120 0

1200

2

660

1320

3

540

1620 4140 0

5252 0

0 C

water and electricity cost(4% of A+B)

kg man/d ay man/d ay man/d ay

2400

skilled

Machines and equipments

A. 26250

65380

D E

Item No

kg

Labour

shot crete machine

cost per m3

Qty

BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 Measurement Sheet Qt Rat Item Description Unit y e Providing for and fixing of wire mesh of size 150*150*6 after layer of shotcrete on the rock surface for 6m wide adit including drilling,, fixing transportation complete. under the supervision of engineer in charge

material m35

operator

Machines and equipments exacavtor hitachi

Unit

kg A. m3

operator

Item Description

NAME:-

Providing for and carrying out shotcreting for 6m wide adit as per specification using M35 grade of concrete including batching, transportation, spraying etc. . under the supervision of engineer in charge

Providing for and excavating for 6m wide adit using NATM tunnelling method, as per detailed drawing and specification including lead and lift . under the supervision of engineer in charge

A. B

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 Measurement Sheet

7715.86

D E E

Machines and equipments water and electricity cost(4% of A+B) Contingeny(2% of A+B+C+D) miscallaneous(15% of A+B+C+D)

165.6 86.112 658.7568 10302.468 8

total Cost/kg

102.0

Your Logo or Name Here

24


RATE ANALYSIS SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY NAME:-

BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 Measurement Sheet Item Description Unit

Item No

A.

B

C

D E E

Carrying out rock bolting for 6m wide adit using 32mm dia rebar with face plate of thickness 12 mm and resin capsules of required specifications including fixing transportation, drilling etc. as per the enginner in charge . material

Qty

Rate

Amount

A.

kg

63.3

52

3291.6

face flate 150*150*12 resin capsules(constect 28 mm) Labour

kg no

21.15 20

40 60

846 1200 0

operator

man/day

1

1200

1200

skilled

man/day

3

660

1980

unskilled

man/day

2

540

1080 4260

Machines and equipments DRLLING MACHINE

HOURS

12

900

10800

total cost/kg

Item No

kg

rock bolts 32mm

water and electricity cost(4% of A+B) Contingeny(2% of A+B+C+D) miscallaneous(15% of A+B+C+D)

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 Measurement Sheet

NAME:-

170.4 304.608 710.2512 21582.8592 213.65

Item Description Providing blasting for central cavern at kalbadevi station including inserting explosives and detonators , transportation,fixing etc under supervision of general consultants(for 71.01 cu.m.) BLASTING MATERIAL IDEA POWER 90 ELECTRONIC DETONATOR

B

C

Labour operator skilled unskilled foreman Machines and equipments

D E E

water and electricity cost(4% of A+B) Contingeny(2% of A+B+C+D) miscallaneous(15% of A+B+C+D) total cost per m3

Unit

Qty

Rate

Amount

m3

KG NO

man/day man/day man/day man/day

97.25 30

1 5 2 1

140 8

13615 240

1200 660 540 1000

0 1200 3300 1080 5820 0 232.8 121.056 926.0784 26534.9344 279.31

Your Logo or Name Here

25


ABSTRACT SHEET NAME:-

Item No

1

2

3

4

5

SCHOOL OF BUILDING SCIENCE AND TECHNOLOGY BHUMIKA RAJCODE NO:-UC5316 PROJECT TRAINING 2019-2020 ABSTRACT SHEET Item Description Unit

Providing for and excavating for 6m wide adit using NATM tunnelling method, as per detailed drawing and specification including lead and lift up to 1.5m M3 Providing for and carrying shotcreting for 6m wide adit as per specification using M35 grade of concrete including batching, transportation, spraying etc. M3 Providing for and fixing of wire mesh after1st and 2nd layer of shotcrete for 6m wide adit including drilling, transportation etc complete, transportation, spraying etc. Kg Carrying out rock bolting for 6m wide adit using 32mm dia rebar with face plate of thickness 12 mm and resin capsules including transportation, drilling etc. kg Providing blasting for central cavern at kalbadevi station including inserting explosives and detonators , transportation,fixing etc under supervision of general consultants m3

SUBMITTED BY : BHUMIKA RAJ (UC5316)

ACTIVITY WISE COST BREAK UP

Qty

Rate

Amount

167

555.65

921794

wiremesh 3% rockbolting 2%

blasting 2%

excavation 52%

shotcrete 41% 37.5

7872

295200

101

102

10302

63.3

213

13483

71.04

279

19820

excavation

shotcrete

rockbolting

blasting

wiremesh

INFERENCE : Maximum cost is obtained for excavation as it requires more time and equipment compared to other activities also shotcrete cost is more because rebound factor comes into play which happens on site which is 10-20%. Your Logo or Name Here

26


PARADIGM SHIFT MEASURES

ACTIVITY ANALYSIS

LEADING INIDCATORS

•In NATM works excavation , drilling , blasting and charging play a very important role,.So care should be taken to carry out the blasting and charging activity safely so there is no fatality on site. Environmental monitoring •At kalbadevi there are many old buildings and it’s quite dense also so vibration limit isto maintained which is 3.5Hz which requires continuous monitoring. •When explosives are blasted ammonium nitrate is produced which is harmful to the environment So continuous monitoring is carried out to maintain the air quality for air.

SHOTCRETE STRENGTH

SHOTCRETE: It forms a major part of the activity so extra care should be taken .Before shotcrete is done its trial is carried out where trials are done and compressive strength of shotcrete is measured, and the graph plotted from the data should obtained J2 curve ,below J1 curve the shotcrete should be rejected

SUBMITTED BY : BHUMIKA RAJ (UC5316)

LAGGING INDICATORS

• Flexible – Support provide as required by the ground conditions . One of the advantage at kalbadevi was that the strata was hard compared to other stations so it was faster to carry out the preliminary works like shotcrete , installing wiremesh and rock bolting • Economical – Support provided as required by the encountered ground conditions, in contrast to TBM segments, which are designed for worst load case – if needed or not, therefore overdesigned. • Adaptable – Optimizing equipment and crews, allowing multiple heading operations concurrent

Shotcrete rebound :So if highly skilled operator will apply 81% of the correctly, with only 19% used inadequately (including 8% rebound rate, 10% over-spraying and 1% potential fallout).

Your Logo or Name Here

27


MODEL LEVELS ( KALABDEVI STATION) SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE AND ACCESS LEVEL AT KALBADEVI STATION

SKETCH UP MODEL FOR PLATFORM AND CONCOURSE/ MEZZANINE LEVEL AT KALBADEVI STATION

OBSERVED PORTION

ULPINE TUNNEL

GIRGAON STATION START

SKETCH UP MODEL FOR PLATFORM AND UNDERCROFT LEVEL AT KALBADEVI STATION

CST STATION END

DOWNLINE TUNNEL

KALBADEVI STATION

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

28


3D MODEL VIDEO

SUBMITTED BY : BHUMIKA RAJ (UC5316)

Your Logo or Name Here

29


PROJECT DELAY India, there are currently more than 26 metro rail projects at various levels of planning, construction and operation. A number of new phases of metro rails are being planned and will be launched soon. Various studies have documented delays in planning and execution of metro rail projects in India as well as the world. In this report, an attempt has been made to understand various issues or impediments which are faced by the metro rail corporation in executing the metro rail projects. There are numerous factors which may cause hindrance to the project execution such as funding capacity of governments, finance arrangements, competing technologies, feasible operational model, stakeholder issues etc

So if we take into consideration Mumbai metro line 3 project, over all there have been many issues related to this magnum project which bears the responsibility of giving mumbaikars a new transport system. In specifically package 2, is taken into consideration there have been many issues

CHRONOLOGY OF DELAYS

2/3/17 utility diversion issues at grant road station

6/7/201 7 Nosecan t piling work carried out during night time

SUBMITTED BY : BHUMIKA RAJ (UC5316)

12/8/20 17 delay at girgaon sttaion due to ganesh mahotsa v

7/01/20 18

21/05/2 018

3/2/18

7/8/18

3/12/18

4/3/19

feb 2019

global procuremen t issue of

TBM#2 was on halt due to Parsi fire temple issue

main drive transfer issue

Land accquisitio n issues

Sewer Line diversion Works:

NATM WORKS KALBADE VI STATION

mining and segment productivity decrease

lifting pin

Figure 19: CHRONOLOGY OF DELAYS

grant road

24 jan 20 pour 4, no concrete pump was vaialable so work was halted so 11 hours

Your Logo or Name Here

22 marc h 20 covid 19

30


TIME LINE OF DELAYS AT MML3-UC02 delay due to ganesh mahotsavat at girgaon station

Utility diversion issue at Grant Road station 2/3/17

6/7/17

12.8.17

no secant piling work carried out at night time(10pm6am)

127 days

uncerta in

7.1.18

22.3.20

21.5.18

23 days

1 day

5/9/17

no secant piling work carried out at night time(10pm6am)

17 days

global procurement issue

10.12.20 18

3/12/1 8

20.2.18

main drive transfer issue

feb 2019

365 days

14 days

july 2018

22 march 20 24.3.20

covid 19

Non availability of concrete pump

tbm mode chnaged

171 days

2 days

28 days

mining and segment productivity decrease

land accquisition issue

TBM hault due to parsi temple 8.1.18

july 2017

main drive transfer issue

135 days

mining and segment productivity decrease

land accquisition issue 3/2/18

global procurement issue

delay due to ganesh mahotsavat at girgaon station

Utility diversion issue at Grant Road station 5/7/17

TBM hault due to parsi temple issue

2 weeks

tbm mode change

march 2019

till 22 march

20 april 20 27.03.20

covid 19

non availablility of concrete pump at CST

Figure 20: TIMELINE OF DELAYS

Your Logo or Name Here SUBMITTED BY : BHUMIKA RAJ (UC5316)

31


DELAY

Start /finish

Base line Start/finish

difference

10/12/18 July 2018 4.3.19

21/5/18 July 2017 3.10.19

-135 -360 -171

Form commencement

14.01.18

106

Tree plantation and cutting issue

Form commencement

20.02.17

157

Traffic diversion issue Utility diversion issue Limited hours of working GIRGAON STATION Tree plantation and cutting issue Traffic diversion issue Utility diversion issue Delay in productivity of secant piling due to noise issue. Delay due to ganesh mahotsav so excavation work was effected Non availability of strut and waler CST STATION Tree plantation issue No availability of concrete pump for pour no 6 Main drive transfer issue

24.10.16 2.3.17 6.7.2017

17.7.17 5.7.17 Till future

266 127

9/2/17 14.12.16 2.3.17 6.02.17

83 132 107

12.8.17

17/05.17 17.5.17 5.7.17 Uncertain-tilll furture 3.09.17

29 feb 20

24 feb 20

5

19.01.17 27 jan 2020 20 deb 2019

26.08.16 24 jan 2020 3 feb 19

189 2 -17 208

Project key dates and delays COMENCEMENT DATE : 8 JULY 2016 KALBADEVI STATION Tbm hault due to parsi temple issue Land accuiqusition issue Natm works at kalbadevi station GRANT ROAD STATION Delay In handing over land

PROJECT KEY DATES OF DELAYS

23

Your Logo or Name Here SUBMITTED BY : BHUMIKA RAJ (UC5316)

32


REWORK DEFCETS OVERRUNS AND TIME LOSS LATE APPROVALS BY AUTHORITIES

VISIBLE PARAMETERS FOR PROJECT DELAY

IDENTIFYING THE BLIND SPOTS THROUGH ICE BERG

POOR PLANNING , POOR FEASABILITY STUDY AND LACK IN REAL TIME COORDINATION LABOUR STRIKES / NATURAL DISASTR(COVID 19) AND OTHERS BUILDING INFORMATION PROJECT IS LESS PROMINENT WHICH IS LESS INNOVATIVE TECHNIQUES USED . POOR QUALITY / UNAVAILABILITY OF MACHINERY

LESS VISIBLE PARAMETERS FOR PROJECT DELAY

POOR TARINING PROGRAMS CONDUCTED

Your Logo or Name Here


OUTCOMES

0.5

TARGET VALUE DESIGN MARKET VALUE

0.4 SAVINGS

0.3 0.2

TARGET VALUE

0.1 0

SETTING A TARGET VALUE DESIGN This is to set the target value less than market value so if the contractor keeps the track of the graph and observes the cash flow seems to go above the market value they can work out possibilities and lower the graph So contractor can save the money and use it for other capital investments

BIM

By doing the real time coordinaton with building information model the contractor can reduce rework which can save resources to an extent.

TRADING TIME WITH COST If new methodologies which are a bit costlier but inclined to give faster results are adopted the on the principle of trading time with cost should be adopted, so cash outflow can also be recovered.. Your Logo or Name Here

34


ANALYSIS STUDY OF DELAY DURING VARIOUS PHASES OF CONTRUCTION

PRE CONSTRUCTION PHASE

Planning/scoping phase: Delay can be significant when litigation is initiated. • Development phase: Permitting (environmental, fish and wildlife, railroad, etc.), right-ofway acquisition, and utility agreements can be significant causes of delay. • Contracting phase: Generally, this phase has less incidence of delay but can still have issues. • Construction phase: This phase has numerous opportunities for delay and is often the delay most visible to the public

400

PRE CONSTRUCTION DELAY

•INCREASE IN SCOPE OF WORK OF… 20 2 •NON AVALIBILITY OF STRUT AND WALER 10 30 •TBM HAULT DUE TO PARSI TEMPLE ISSUE.

100 0 tility diversion issues at grant road station

28 •LATE RESPONSE FROM MGL AT GIRGAON…

200

rehabilitation •procurement issue at of tunnel kalbadevi and boring girgaon machine DAY Column1 Column2

CONSTRUCTION PHASE

CONSTRUCTION PHASE DELAYS •COVID 19

300

•GLOBAL PROCUREMENT ISSUE

1

•DELAY AT GIRGAON STATION DUE TO… 14 Description of delay

157 201

• utility diversion issues at grant road station • rehabilitation issue at kalbadevi and girgaon land accquisition issue for kalbadevi station box • less awareness lead to protests to oppose the project • procurement of tunnel boring machine

266

•delay at girgaon sttaion due to ganesh mahotsav •delay for natm works at kalbadevi •global procurement issue of lifting pinz •Sewer line diversion at grant road •tbm hault due to parsi temple issue. •slow piling due to noise issue •revision in girgaon station pile plan •non avalibility of strut and waler •(pour 4 )concrete pump unavailability •increase in scope of work of bcs(building condition survey) •traffic diversion issue at grant road •Late response from MGL at girgaon for div. scheme 201 •tree plantation issue at grant road 157 •covid 19

365 146 14 171 1 127 135 30 10 2 20 266

28

135 127 171 DAYS

Your Logo or Name Here SUBMITTED BY : BHUMIKA RAJ (UC5316)

60

35


CONCLUSION

Total duration of the project in contract was 1638 days, but the setback is that the delay is about 93% of the total time duration which is 1526 days.So the project is delayed majorly due to delays in construction phase which is 883 days and in pre construction phase also delay of about 643 days is observed. As delays till 22 march are curated the project lags behind substantially and it will take almost twice times the time taken for completion and handing over which is tentative 6 nov 2023 instead of 10 jan 2012. SUBMITTED BY : BHUMIKA RAJ (UC5316)

In a city like Mumbai which is densely populated and carrying out mega construction in congested and century old areas like kalbadevi and girgaon it’s a task it self. So geography and city’s development also plays an important role in identifying the delays or assuming the delays • When comparing with the research paper and from my study and observation of delays, majority caused are due to external factors in Mumbai metro line 3 – UGC02, also client related administrative factors have cause delay. Contractor related issues are still prevelant but not at large scale, as they are linked with the client tasks. • So if client related tasks get delayed (eg tbm hault at kalbadevi)i) Entire project time line is disturbed if each project is linked as they have a start to start type relationship.( all tbm related activities hindered) Start to finish relationship are not that much affected as they are not linked with any other task..

Your Logo or Name Here

36


THANKYOU

Your Logo or Name Here

37


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.