4 minute read

Figure 54: Softwares Used

Construction Reference Drawings shall fully detail the construction of the elements covered by the Definitive Design and shall show in full the Works to be constructed. The Contractor's design outputs shall also be delivered in a 3D model in BIM (Building Information Modelling) of all components of the Works desigred by the Contractor as part of the contract. ' The 3D Model based design, required to be submitted by the Contractor as part of his Design Submissions, should be dynamic to the design modifications occurrirg during the Design & Construction phases and will reflect the quantities with the feature of quick estimation using Navisworks or its equivalent that has software capability to deliver the outputs like,construction sequencing, structural and utilities/services clash detections etc.

2 9 R E QU I R E M E NT S D U R I N G C O NS T R U C T I O N P H A S E

Advertisement

The principal requirements relating to design during the Construction Phase are  the production of Working Drawings,  the preparation of technical submissions as required under the Contract  the compilation of the Final Design and the production of the As-Built Drawings.

 Working Drawings shall be prepared as required under the Contract. They shall be endorsed by the Contractor as being in accordance with the Construction Reference Drawings. The Contractor shall endorse the submissions required under the Contract that “all effects of the design comprising the submission on the design of adjacent or other parts of the Works have been fully taken into account in the design of these parts." At least 3 months but not more than 6 months prior to the anticipated date of substantia- completion of the Works, the Contractor shall submit the Final Design to the Engineer. The Final Design is the design of the Permanent Works embodied in: a)the latest revisions of the documents comprised in the Definitive Design Upon completion of the Works or at such time as agreed to or required by the Engineer, the Contractor shall prepare drawings which, subject to the Engineer's Notice, shall become the As-Built Drawings. All such drawings shall be endorsed by the Contractor as true records of the construction of the Permanent Works and of all temporary works that are to remain on the site. The Contractor shall also show the locations of utilities exposed, relocated, diverted, new or retained. The Contractor shall note that a Master Interface Matrix and Interface Coordination Sheets refer Appendix 19, have been developed for the Mumbai Metro Line-3. The matrix identifies the lead Interfacing Contractor who shall coordinate the interfaces for all Interfacing Contractors, and the Interface Coordination Sheets describe the details of the interfaces. Appendix 19 contains the requirements of the Interface Management Plan (IMP) to be prepared and implemented by the Contractor. The IMP will identify the mechanism by which the Contractor and the Interfacing Contractors will work together to coordinate the design, and construction, of the various elements of the Project works. The Contractor shall review and update the IMP on a monthly basis. The Employer and Engineer will hold Project Quarterly Review Meetings (QRM), at three monthly intervals. The Contractor shall attend these QRM and shall report the progress of his works and the state of his interface with otherInterfacing Contractors and shall provide the Engineer with the

SUBMITTED BY: BHUMIKA RAJ UC5316 128

necessary assistance and information for conducting the QRM. Refer to Clause A18 of Subdivision Subdivision-A of this Part 2, Section VI Employer's Requirements.54

DESIGN SUBMISSIONS OF DRAWINGS

2 9 . 1 P R E L I M I NA R Y D E S I G N SU B M I S S I O N

Description

 the quality assurance plan for design  a review of the outline design criteria  the submission of design manuals  the submission of proposed software  the prelininary equipment layouts and details  the preliminary maintenance analysis  the preliminary off site testing recommendation  the submission of specifications proposed for the Work  the identification of design codes and standards  the CAD procedures  preliminary station layout and sizing  preliminary bored tunnel sizing  an alignment review  the preliminary construction methodology  the design submission programme (update)  the preliminary traffic management plan  the utility diversion plan  proposed site surveys, existing building surveys and otherfield surveys  a preliminary review of permanent land requiremen  preliminary ground treatment proposal  preliminary building and structure protection proposal  preliminary water well monitoring, protection and replacement proposal  preliminary monitoring plan  preliminary geological model  add'tional ground investigation proposal  reinstatement drawings.

2 9 . 2 D E F I NI T I V E D E S I G N D RA W I NG S

The Definitive Design Submission shall include drawings that shall illustrate the proposed Definitive Design and in particular shall include, but not be limited to, the following;  general arrangements of all required rooms and facilities of the stations  (including subways leading into stations) , including a Finishes Schedule  for all rooms and spaces for doors, windows, etc.. and details of all

54 Part 2. Employer's Requirements Section VI. Sub-Division -— A. General

SUBMITTED BY: BHUMIKA RAJ UC5316 129

This article is from: