Project Cycle Report: Infrastructure Project

Page 133

MUMBAI METRO LINE 3

.

Construction Reference Drawings shall fully detail the construction of the elements covered by the Definitive Design and shall show in full the Works to be constructed. The Contractor's design outputs shall also be delivered in a 3D model in BIM (Building Information Modelling) of all components of the Works desigred by the Contractor as part of the contract. ' The 3D Model based design, required to be submitted by the Contractor as part of his Design Submissions, should be dynamic to the design modifications occurrirg during the Design & Construction phases and will reflect the quantities with the feature of quick estimation using Navisworks or its equivalent that has software capability to deliver the outputs like,construction sequencing, structural and utilities/services clash detections etc. 29 REQUIREMENTS DURING CONSTRUCTION PHASE

The principal requirements relating to design during the Construction Phase are   

the production of Working Drawings, the preparation of technical submissions as required under the Contract the compilation of the Final Design and the production of the As-Built Drawings.

Working Drawings shall be prepared as required under the Contract. They shall be endorsed by the Contractor as being in accordance with the Construction Reference Drawings.

The Contractor shall endorse the submissions required under the Contract that “all effects of the design comprising the submission on the design of adjacent or other parts of the Works have been fully taken into account in the design of these parts." At least 3 months but not more than 6 months prior to the anticipated date of substantia- completion of the Works, the Contractor shall submit the Final Design to the Engineer. The Final Design is the design of the Permanent Works embodied in: a)the latest revisions of the documents comprised in the Definitive Design Upon completion of the Works or at such time as agreed to or required by the Engineer, the Contractor shall prepare drawings which, subject to the Engineer's Notice, shall become the As-Built Drawings. All such drawings shall be endorsed by the Contractor as true records of the construction of the Permanent Works and of all temporary works that are to remain on the site. The Contractor shall also show the locations of utilities exposed, relocated, diverted, new or retained. The Contractor shall note that a Master Interface Matrix and Interface Coordination Sheets refer Appendix 19, have been developed for the Mumbai Metro Line-3. The matrix identifies the lead Interfacing Contractor who shall coordinate the interfaces for all Interfacing Contractors, and the Interface Coordination Sheets describe the details of the interfaces. Appendix 19 contains the requirements of the Interface Management Plan (IMP) to be prepared and implemented by the Contractor. The IMP will identify the mechanism by which the Contractor and the Interfacing Contractors will work together to coordinate the design, and construction, of the various elements of the Project works. The Contractor shall review and update the IMP on a monthly basis. The Employer and Engineer will hold Project Quarterly Review Meetings (QRM), at three monthly intervals. The Contractor shall attend these QRM and shall report the progress of his works and the state of his interface with otherInterfacing Contractors and shall provide the Engineer with the

SUBMITTED BY: BHUMIKA RAJ UC5316

128


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Figure 83: Closure Of Project Flowchart

1min
page 194

Figure 81: Manpower Status0

0
page 190

Figure 72: Contents Of Mpr

5min
pages 183-185

Figure 71: Weekly Details

2min
page 182

Table 40: Characteristics Detail

1min
page 155

Figure 70: Billing Flowcart

1min
pages 180-181

Table 45: Format Of Snag List

1min
pages 178-179

Figure 62: Segments Location

1min
page 152

Figure 61: Tmt Bars Location

2min
pages 148-149

Figure 55: Codification Example

1min
page 135

Figure 40: Project Package Details

1min
page 74

Figure 31: Flow Chart For Labour License

4min
pages 86-87

Table 30: Cash Outflow

1min
page 78

Table 24: Cost Estimate

2min
page 71

Figure 54: Softwares Used

4min
pages 133-134

Table 32: Cash Outflow For Year 2016-2017

0
page 120

Figure 37: Work Schedule Format

2min
page 64

Table 14: International Protocols

1min
page 62

Figure 11:Mumbai Metro Network

1min
page 36

Table 2: List Of Projects

1min
page 21

Table 11: Funding Pattern Break Up

4min
pages 46-49

Figure 5: Alignment Of Passengers In Suburban Rail

3min
pages 28-29

Figure 13: Funding Breakup

1min
page 43

Figure 14:Flowchart Showing The Formation Of Insititutional Framework By Goi For Carrying Out Approvals

3min
pages 52-53

Figure 33: Bid Document Details

3min
pages 50-51
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.