Figure 55: Codification Example
architectural parts necessary to describe design condition and methods of application and construction. elevations and perspectives and landscaping; layouts and details of structural elements; associated fittings; slopes and earthworks; structural and surface drainage; access roads and temporary road works; pumping systems electrical plant rooms such as UPS, DG set etc.; provisions for railway works, electrical and mechanical services and equipment; existing and proposed utilities; road works and works related to traffic management including decking.
2 9 . 3 D E S I G N S U B M I S S I O NS - C O NS T RU C T I O N P H A S E
Advertisement
On the issue of a Notice in respect of the Construction Reference Draw'ngs the Contractor shall produce the proposed Working Drawings. The ‘Working Drawings shall include the Construction Reference Drawings, which may be supplernented by further drawings developed in accordance w'th the Construction Reference Drawings such as site sketches, bar bending scfedules, bar reference drawings, fabrication and shop drawings, construction erection sequences, finishes material list with accompanying specification, and the like. All such drawings shall comply with the requirements of the Contract.
Prior to submission of the proposed Working Drawings, the Contractor shall endorse the appropriate original paper drawings as "Good for Construction". If the Engineer so requires, the endorsed original shall be submitted to the Engineer who shall, if he has no objection to the contents of the submission, further endorse the original by stating that he has no.
Equipment on the Permanent ‘Works. This analysis shall be in sufficient detail to demonstrate that the Contractor's proposals are safe and have no adverse-Built Drawings, endorsed by the Contractor, shall be Submitted to Engineer for a Notice of No Objection in accordance with GCC and in electronic format using a commercially