Bim portfolio

Page 1

FANTASTIC INTEGRATIVE BUILDING MODELING | FINAL PROJECT ABRAHAM GUTIERREZ | FALL 2013


CODE + SITE ANALYSIS n

TEMPERATURE DIAGRAM

00 05

business group:

B

zoning category:

CB - 2

Jan

10

v

15

No

20

parking:

avg. body temperature

25 30

OFFICE : 1 space per 350 sq. ft. COMMERCIAL : 1 space per 400 sq. ft. up to 30,000 sq. ft. If over, an additional 1 per 800 sq. ft. Each parking spot must be at minimum of 250 sq. ft. Handicap accessible spots should be a minimum of 500 sq. ft.

high - low temperature range

35 40

Oct

50 55

avg. ground temperature

e

0

avg. temperature

EXITS: If 1 - 500 occupants, a minimum of 2 exits per story. If 500 - 1000 occupants, a minimum of 3 exits per story. If more than 1000 occupants, a minimum of 4 exits per story.

rear yard requirements:

None

side yard requirements:

None

projections into required yards: The following can project 2 ft. into the setback: less than or equal to 12 ft. The following can project 4 ft. into the setback:

45 0%

average humidity

If there is a patio, the front setback can be less than 25 ft. If there is a garage, the front setback is 20 ft.

s

B

ay

exceptions:

avg. room temperature 50

M

minimum wind speed

On corner lots, the front setback is right at the edge of the property line, but can’t be further than the setback established by adjacent lots.

55

g

average wind speed

No less than the average setback established by developement on the adjacent lots.

July

front yard setback:

Au

maximum wind speed

Any lot line along a dedicated street (not an alley) is a front yard.

April

Sept

w

June

The means of egress shall have a ceiling height of nothing less than 7 ft. 6 in. Door width should not be less than 32 inches. Walking surfaces shall be slip-resistant and securely attached. The path of egress should not be interrupted by any building element. Exit stairways should have a clear width of 48 inches between handrails. Stairways with occupancy less than 50 shall not be less than 36 inches. Each area of refuge should have a wheelchair space of 30 x 48 in. for each 200 occupants.

Mar

45

means of egress:

front yard:

Dec

b Fe

100%

Project Site Commercial Facilities Green Space Parking Lots Public Transportation

Awnings, canopies, chimneys, sills, eaves, belt courses, comices, bay windows with a gross floor area of Stairways, unenclosed fire escapes, porch overhangs and/or balconies (covered or uncovered).

MAIN STREET

lot requirements: LOT AREA = no requirements LOT COVERAGE = no requirements LOT WIDTH = no requirements

height limits:

None

floor area requirements:

None

vision clearance: FRONT YARDS: In a front yard, there is a limit to the height of walls, fences, and other structures. No structure should be higher than a line extending from a point 2.5 ft. above natural ground level at the front lot line to a point 4.5 ft. high at a depth of 25 ft. from the front lot line.

landscape requirements: At least 90% of required front yard (not including driveways and paved curb returns) up to a minimum of 10% of the total developed lot area should be landscaped and permanently maintained. INTERIOR COURTYARDS: Not included in required landscaping. Buildings with zero front and side setbacks are not required to have on-site landscaping. EXCEPTION: When a structure with zero setback has adjacent parking. 10% of the parking area must be landscaped. The parkway areas of adjacent rights-of-way (not including driveways and paved curb returns) should be landscaped and permanently maintained. Off-street parking that is immediately next to any street should be screened from the street by a 2.5 ft. solid fence. The fencing should be set back no more than 6 ft. The area between the fence and the property line (if any) must be landscaped and permanently maintained. All required landscaping must be visible from the public right-of-way and placed for maximum enhancement of the property and the Broadway Corridor. Hard surface materials can only be brick, stone, and modular pavers. Landscaping cannot include the use of concrete or asphalt (whether smooth, pattern, colored, or containing large aggregate). Landscaping that is within the visibility triangle of a corner lot should be in compliance with the vision clearance standards. CORNER LOTS: On a corner lot, the max height is 2 ft. for trees, shrubs, plants, signs, or any other structure that obstructs view. The 2 ft. height is measured from top of the curb of the adjacent street that is within the intersection visibility triangle. INTERSECTION VISABILITY TRIANGLE: A triangle sight area at all intersections. Includes the portion of public right-of-way and any corner lot within a triangle formed by a diagonal line extending through points on the 2 property lines 25 ft. from the street corner intersection of the property lines (or the point of intersection of the property lines extended) and intersecting the curb lines. PARKWAYS: In a parkway there is a 3 ft. limit to the height of shrubs, plants (excluding trees), signs or any such structure that obstructs view. The 3 ft. is measured from the top of the curb of the adjacent street in the parkway area. EXCEPTION: Trees may be in parkway area. If a tree’s trunk diameter is greater than 2 ft. measured at 3 ft. above ground level, the tree should be trimmed. The trimming should be done so that no foliage is less than 6 ft. above the top of the curb of the adjacent street. EXCEPTION: No evergreen or coniferous species of tree shall be allowed in the parkway.

B

BROADWAY B

B

B

B

TEXAS AVENUE

SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

WIND SPEED AND HUMIDITY


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

MASS MODEL STUDIES commercial space

commercial space

commercial space

commercial space

lobby, loading, mail space

lobby, loading, mail space

lobby, loading, mail space

lobby, loading, mail space

office space

office space

office space

office space

PLAN VIEW

PLAN VIEW

PLAN VIEW

PLAN VIEW

PERSPECTIVE

PERSPECTIVE

PERSPECTIVE

PERSPECTIVE

Sarah Armanovs

Abraham Gutierrez

Sergio Cabello

Carlos Pantoja

The mass model has crevices on all sides to allow for natural ventilation of the building. These crevices also let in natural light throughout the building. Courtyards are formed on all sides of the building. However, no courtyards exist on the south side to avoid direct sun.

Parking is located on the lower South side of the building with offices and living spaces being located above the parking on the South side and extending alond the West side. Commercial spaces are located on the ground level, opposite the parking area and a green space/roof garden is located above the commercail space. The lobby faces North and is an open space from the ground floor to the top of the building for uninterrupted view to the high rise across the street. This open area also provides natural daylighting for the entire building.

The shape of the building allows for more natural lighting during the day and natural ventilation. Most of the wind in Lubbock, during the summer, usually comes from the SouthEast which will go through the building. During winter, the wind is more frequent from the west side which the building blocks off. The open space on the ground floor will allow for vehicular circulation as well as pedestrian. This will help the commercial spaces that are also located on the ground floor.

The mass model is oriented to face north, allowing the maximum amount of natural daylight on that side. A courtyard is created on the north side that blocks strong winds from the south while allowing for air to move naturally throughout the space. The resulting courtyard responds to the climate while inviting pedestrians to visit.


DPROFILER MASSES + ENERGY ANALYSIS Model 2

Model 3

Model 4

SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

Model 1

The core of the building is located towards the middle so that vertical circulation is easily accessible between the different levels and different program spaces. The building is clad in glass and brick, depending on where views outside are desired.

The cladding was placed to utilized the maximum amount of natural sunlight throughout the day. The service core is placed at the entrance to guide pedestrian traffic the the proper location up entering.

The building is placed along the north and west boundaries of the site and steps down to the ground floor by floor resulting in exterior roof terraces for people to access. There is also a seperation of mass of the first few floors. This is to provide a physical buffer from Office Space to Retail Space while also providing a light tunnel from the southeast corner of the sight to the northwest corner. The cladding placed on the southeast side of the building is mostly precast and glazing to provide the most daylight. Along the North side are more ribbon windows and along the west side the cladding is a random assortment of glazing and metal panels.

The building is designed to maximize the amount of natural light while taking into consideration the excessive amount of light entering through the East and West faรงade. Its shape is able to create a pocket of air that allows for the building to cool off naturally at the core. There are two cores which are the most suitable for the circulation regarding ADA regulations.


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

CHOSEN DPROFILER MODEL

Northwest View

Southeast View

Northeast View

Plan View

We chose this buidling design because of the asthetic design and the exterior spaces created by the terracing of the building. The cost analysis also showed that the building was an economical choice as it was not the most expensive of the group. The orientation of the building design takes advantage of the major circulation occuring on the adjecent streets. The building itself is a pathway as it allows circulation to go through it into an exterior courtyard.

Net Present Value Over 15 Years Initial Mechanical System Cost: First Year's Electricity Cost: First Year's Natural Gas Cost: Net Present Value:

$550,772.05 $15,183.00 $5,433.00 $860,012.05

Analysis Summary Peak Building Load: Peak Electrical Load: Electricity Use: Natural Gas Use:

132 Tons 268KW 11.43kWh / SF 16.71 kBtu / SF

265.34 SF / Ton 7.65W / SF $0.0379 / Unit $0.9283 / Unit

Monthly Utility Consumption by End Use

Annual Utility Consumption by End Use


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

BASEMENT PLAN


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

1st FLOOR PLAN


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

FLOOR PLANS

2nd STORY 3rd STORY

4th STORY 5th STORY


CORE DETAIL PLAN 17'-4" 1'

5'-10"

2' 3'-1/4"

9 1/2"10"

2'-11 1/2"

8'

6'-3 1/2"

vertical ventilation shaft electrical closet

8'

44'-1 1/4"

8'-3"

2'-8"

6 1/2"

26'-3 1/4"

male restroom

janitor closet

female restroom

3'-2 1/2"

2'-7"

4 1/4" 8"

8'-6"

stairwell

6"

9'-4"

7'-9 3/4"

SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

6"

10'-8 1/4"

elevator


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

STRUCTURAL SYSTEM OCCUPANCY GROUP: b-business

12" x 12" cast in place columns

CONSTRUCTION TYPE: II

reinforced precast concrete panels

3 hour non combustible sprinkled

STRUCTURAL SYSTEM AND CONSTRUCTION TYPE

The design is made of a concrete column and slab system. The module is roughly 15 feet by 15 feet, but is slightly irregular as it follows the angled footprint of the building. The longest span of the concrete slab is 21 feet. The glass curtain walls span from slab to slab, and are placed in front of the structural columns.

15'-4"

reinforced concrete elevator shaft 1'

14'

ESTIMATED SIZE OF MEMBERS

The estimated sizes of the components used are 12” x 12” columns and a slab of 12.”

1'

14'

FIRE RESITANCE STRATEGY

The building is 3-hour fire rated. The concrete column and slab system helps to achieve this. On each floor of the building has two fire egress stairs. Each stair is located as far apart from the other in opposite corners of the building. The walls of the stairs are fire rated for 3 hours and built with 5 inch precast concrete panels. The doors to the stairwells are metal exterior doors with a small glass window. The entire assembly of the door is rated for 3 hours. Though the elevator would not be used in the event of a fire, the elevator walls are made of 3 hour fire rated glass. Each floor is designed to have fire sprinklers.

hole in floor slab for plumbing wall shaft

1' 14'

hole in floor slab for vertical MEP shaft

1'

14'

12" cast in place concrete flat slab 1' structural concrete walls in basement

15' 10' 8' 14' 14' 14' 15'-4"

1'

1'

1'

10'

1' 80'-4"

site


MECHANICAL SYSTEM

SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

MECHANICAL ZONES

SIZE OF MEMBERS Cooling Tower: 15’ x 7‘ Supply duct, branch: 2’ x 1‘ Supply diffuser: 2’ x 2‘ Supply duct, main: 3’ x 3’ Return duct: 3’ x 3’ Return branch duct: 2’ x 1‘ Return grille: 2’ x 2‘ Exhaust louvre: 3’ x 8‘ Heating coil: 5’ x 1’ Cooling coil: 5‘ x 1’ Fan: 5‘ x 5’ Boiler: 5’ diameter, 7’ height pipes to coil: 3” diameter chimney: 2’ x 2‘ combustion air vent: 3’ x 2’ Chiller: 6’-3“ x 11’-6” pipes to coil: 5” diameter water pipes to cooling tower: 8.5” diameter Fresh air louvre: 3’ x 8’

The building is divided into three different zones for seperate heating and cooling needs. The office and retail spaces require similar heating and cooling needs. However, the two spaces have been split into two different mechanical zones because of the different hours of the day they are occupied. The retail space is located on the bottom two floors of the left wing of the building. This zone has to potential to be occupied roughly 14 hours a day. The office spaces are located on the 3nd and 4rd floor. They are occupied about 9 hours a day. The studio living spaces are located on the 5th floor. Their mechanical zone has been established to accomodate 24-hour occupancy.

HEATING/COOLING SYSTEM

A variable air volume (VAV) system was chosen to provide comfort for the occuopants of the mixed-use building. Such a system allows for a high degree of local temperature control, which can meet the needs of both residents and workers in the buildng. Furthermore, a VAV system is economical to install and to use. The VAV system in the building is divided into two seperate parts. This allows for a more efficient distribution of air, thus decreasing operating costs.

MAJOR MECHANICAL SPACES

The basement and roof of the building are where the major mechanical spaces for the VAV system are located. A mechanical shaft connects the basement to the roof. In the basement, there are three major spaces: the fan room, the boiler room, and the chilled water plant. There are no walls to divide the “rooms” in order to allow for the space in the basement to be used most efficiently. A fan pulls fresh air into the supply duct. The supply duct then runs through a heating (winter) and cooling (summer) coil. The heating coil is connected to the hot water boiler, while the cooling coil is connected to the centrifugal chiller. The centrifugal chiller has condenser and chilled water pipes that connect to the cooling tower on the roof. The overall system has been sized for 40,00 s.f. of conditioned space. This number is generous and decreases the operating load on the system.


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

ELECTRICAL SYSTEM

utility switchboard transformer switchboard circuit breaker switchboard metering switchboard horizontal cable ladder vertical cable ladder pad mounted transformer

Veritcal electrical closets are the core of the elctrical system. The closets hold the switchboards, and from the closets cable trays run out and throughout each floor. The electricity is supplied from the city, and the voltage decreased with pad mounted transformer on the exterior of the building. The design of the electrical and telecommunication systems supports the data-intensive requirements for the offices.


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

PLUMBING SYSTEM Vertical Storage Tank Ventilation, Toilet

8� Standpipe

Ventilation, Sink

Vertical Piping

Sprinkler Heads

-The sprinkler system and the plumbing are both supplied with muninicipal water. The sprinkler system pumps city water up into a storage tank on the roof. The plumbing system directly uses the water for toilets and sinks. A hot water heater heats up water for the sinks. The waste from the toilets goes down a direct vertical pipe and is pumped out to the city sewage disposal system.

Sewage Pipe Hot Water Hot Water Heater Cold Water Sewage Pump


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

ENERGY ANALYSIS

Energy Performance Evaluation

Energy Performance Evaluation

[Project Number] [Project Name]

[Project Number] [Project Name]

Key Values General Project Data Project Name: City Location: Climate Data Source: Evaluation Date: Building Geometry Data Gross Floor Area: Treated Floor Area: External Envelope Area: Ventilated Volume: Glazing Ratio:

Heat Transfer Coefficients Building Shell Average: Floors: USA_TX_Fo...6_TMY2.epw External: 11/26/2013 1:45:31 AM Underground: Openings: F4 [archbim-armanovs]

365.95 330.80 677.26 4631.18 0

sq ft sq ft sq ft cu ft %

Building Shell Performance Data Infiltration at 50Pa: 1.90 Outer Heat Capacity: 65.16*10^-4

ACH Btu/sq ft,F

Specific Annual Demands Net Heating Energy: Net Cooling Energy: Total Net Energy: Energy Consumption: Fuel Consumption: Primary Energy: Fuel Cost: CO2 Emission:

U value 0.32 0.59 - 0.59 0.06 - 0.73 ---

[Btu/sq ft,F,hr]

8.00 395.37 403.37 604.08 604.08 1774.17 72.07 132.16

kBtu/sq fta kBtu/sq fta kBtu/sq fta kBtu/sq fta kBtu/sq fta kBtu/sq fta USD/sq fta lb/sq fta

Energy Cost 3

[%]

[%] 94

95

95

97

Energy Consumption by Targets Energy

Energy

Fossil Secondary

Source Name Oil Electricity

Total: Energy Quantity 3

Heating Service Hot-Water Heating Cooling Ventilation Fans Lighting Equipment

2

Energy Consumption by Sources Source Type

Energy Targets

CO2 Emission 5

CO2 Emission Quantity

Primary

Cost

kBtu/a

kBtu/a

USD/a

6628 193200

7290 579600

192 6794

1284 26963

199828

586891

6986

28247*

CO2

Target Name

Quantity

Primary

Cost

Emission

kBtu/a

kBtu/a

USD/a

lb/a

Heating Cooling Service Hot-Water Ventilation Fans Lighting & Appliances

lb/a

Total:

2645 189566 4066 79 3470

2909 568699 4631 238 10412

76 6666 118 2 122

512 26455 783 11 484

199828

586891

6986

28247

Primary Energy

Energy Quantity 22

Primary Energy 2

2 [%]

[%]

95

97

97

2 [%]

95

97

95

97

99

Quantity by Source: Primary by Source: [kBtu/a]0

[%]

199828

586891

Quantity by Target: Primary by Target: [kBtu/a]0

199828

586891


SARAH ARMANOVS / SERGIO CABELLO / ABRAHAM GUTIERREZ

ENERGY ANALYSIS

Energy Performance Evaluation [Project Number] [Project Name] Energy Cost 22

Energy Sources

CO2 Emission 3 22

Fossil Oil Secondary Electricity

32 [%]

[%]

95

94

95

93

Project Energy Balance Lighting and Equipment

Supplied Energy per Month

3470.8 kBtu/a

2109.0

Human Heat Gain 3951.4 kBtu/a

1500

Service Hot-Water Heating 4066.3 kBtu/a

1000

Heating

2645.3 kBtu/a

500 Jan

Feb

Mar

Apr

May

Jun

Jul

Aug Sep

Oct

Nov Dec

Transmission

3821.4 kBtu/a

0 [kBtu] 0

Transmission

4621.7 MBtu/a

Infiltration

1086.6 MBtu/a

Ventilation

895.6 MBtu/a

Sewage

3982.7 MBtu/a

Cooling

Emitted Energy per Month

130789.2 MBtu/a

Thermal Blocks Zones Assigned 1 2

Thermal Block 003 uncondi 004 cond

3

Total:

Operation Profile Unconditioned Library (open stac...

Gross Floor Area sq ft 67.87 298.08

Volume cu ft 759.32 3871.86

365.95

4631.18

Environmental Impact Source Type Fossil Secondary

Source Name Oil Electricity

Total:

Primary Energy kBtu/a 7290 579600

CO2 emission lb/a 582 12230

586891

12812


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.