SoA PVdm

Page 1

Photovoltaic Demonstration Module Sponsored by the Charlotte Green Initiative University of North Carolina Charlotte

School of Architecture

Professor Dale Brentrup Professor David Thaddeus Antonio Martinez Todd Chappell Jason Chappell Brandt Hewitt Omar Villa Cevallos Ryan Miller

UNCC Staff + CGI

Megan Smith David Jones John Boal Larry Lane


Photovoltaic Demonstration Module Sponsored by the Charlotte Green Initiative University of North Carolina Charlotte _Site Analysis _Design Process _Structural Details _Drawings + Renderings _Schedule + Budget


Storrs Building Mechanical Wing UNCC School of Architecture

Solar Potential Site Diagram

Future : Solar Grid

CGI PVdm

N PV Project - Storrs Bldg. Grid Future projects


Site Analysis - Solometric Suneye Sponsored by the Charlotte Green Initiative University of North Carolina Charlotte

1

Hemispherical Snapshot The Solometric Suneye is a tool that photographs and analyzes the sky for potential direct solar radiation. By performing 4 sessions (2 positions on the wall during winter and summer), we were able to determine the optimum angle, azimuth, and placement of the photovoltaic array.

2 Monthly Solar Access


1 2


Design Process Initial Concepts Sketches and Justification


Rotation

Optimal for Time of Year

Optimal for Time of Day

N



Photoltaic = Electricity We intend to offset the energy consumption of the Storrs building by feeding 120V/208V AC intoa lighting distribution panel. The power produced will be on metered and the information shared with the University and local community via internet. This module will serve the public as a demonstration of the potential and feasibility of Solar Energy.


Storrs Electrical

4.8 Kw of DC electricity will travel be piped along the wall and into the Storrs Mechanical Wing. It will be converted and monitored by equipment mounted to the space on the wall adjacent to the lighting panel, approximately 90’ from the panels themselves.


Photons to Electrons UTILITY METER

AC DISCONNECT

L1 L2

L1

L1

PHOTOVOLTAIC ARRAY

INVERTER

DC DISCONNECT

MANUAL DISCONNECT

L2

L2

L2

N

N

N

+

+

+

Riser Diagram

Equipment

Monitoring

-

-

+

+

-

-

+

-

+

+

-

-

+

+

-

+

-

-

+

+

-

-

+

+

-

-

+

+

-

-

+

+

-

N

+ G

+

L1

+

G

Junction Box

+

+

+

G

G

+


Structural Details

4x3x1/4” and 3x3x3/16” Structural Steel Angle fabricated by Steel Fab, Charlotte. 1/4” Rod System by Hayn Architectural Systems, Connecticut.


Structural Details - Tension Cables

Tension cables provide rigidity by both immobilizing the various pin connections and tying the columns together into a single unit.


Cable Terminal Nodes Hayn Architectural Systems : SS 306 Terminals + Cable Steel Fab, Charlotte : Miled Steel Structural Angle and Plate Fabrication Connection A

Discs cut from 1/4� steel plate will be welded into the primary structural angles. They wil serve as terminal points for the cable system while holding the two Angles together.

Connection A

Connection A


Connection B

Connection B

Primary to Secondary 1/4� Steel Plate composes the interface between the 4x3x1/4 primary structure and the 3x3x3/16 secondary. It will be fabricated into tabs that negotiate the camber resulting from rotation in design.


Structural Interface These modified tabs are designed to be efficient at fabrication. Both interface tabs come from the same 1/4� steel plate.


Connection C

Achoring + Footings The elevated footings display the simple pin connection that flows from the gradually slendering columns as they delicately provide adequate structural support for the photovoltaic panels.

Connection C Connection C


Concrete

The footings will be of concrete left over from construction on campus. They are placed 14’ O.C. , this is done to match the concrete reinforcement in the wall, which runs vertically every 24� O.C.


Renderings + Drawings


10.1.09


1.21.10


South Elevation

North Elevation


Plan

West Elevation


Plan + Elevations


Structural Plan + Elevations Cable/Rod Assembly in

Red


Project Schedule Fall 2009 Flowchart

September 1 2 3 4 5 6 7 8 9 10 11 12

October

13 14 15 16 17 18 19 20

November

December


ARCH 4890 Research Schedule SoA Photovoltaic Array Construction In order to fulfill the Independent Study as an architectural learning medium, the students involved in the project will meet every Tuesday and Thursday from 14:00 to 15:15 in the Daylighting Lab (Storrs 122). Also, there will be a midterm presentation as well as a final presentation and critique. August 2009

October 2009 (continued)

8.25_First Meeting between students and professor Dale Brentrup (Daylighting Lab) 8.27_Finalization of process, purpose, and schedule (Daylighting Lab) 8.28_Meeting with Facilities Management and Campus Sustainability Manager 8.29_Design Charette, group discussion

10.20_Meet with prospective Engineering Students / outline efficiency model 10.22_Begin Construction Process / Site Preparation 10.24_Primary Structure / Concrete Form 10.25_Primary Structure / Concrete Pour 10.27_Primary Structure 10.29_Primary Structure 10.31_Primary Structure

September 2009 9.1_Site analysis / Allocate work associated with final Design Drawings 9.3_Inventory and Efficiency Check 9.4_Meeting with Erik Lensch, David Jones, John Boal 9.5_Finalize Design Drawings/ Details 9.6_Present Drawings to Mac Fake / UNCC D.O.I. 9.8_Meeting with Bigwoods Engineering / Craig Gammarino (Daylighting Lab) 9.10_Meet with Electrical and Structural Engineering students v 9.15_Executive Documentation Production: Initiation 9.17_Executive Documentation Production: editing and presentation to Professor Brentrup 9.19_Executive Documentation Production: Finalize/Print 9.22_Develop Budget Sheet (including inventory) 9.24_Meeting with Facilities Management and Charlotte Green Initiative (Daylighting Lab) 9.29_Acquire Budgeted Funds, organize purchase of primary materials October 2009 10.1_Pick up steel / primary materials / Hardware 10.6_Fabrication 10.8_Fabrication 10.10_Fabrication 10.13_Fabrication (student holiday) 10.15_Fabrication 10.19_CAMPUS SUSTAINABILITY WEEK BEGINS

November 2009 11.3_Primary Structure 11.5_ Primary Structure 11.7_ Primary Structure 11.8_ Primary Structure 11.10_ Primary Structure 11.12_ Primary Structure 11.14_ Primary Structure (if needed) 11.15_ Primary Structure (if needed) 11.17_Primary Structure Finished 11.19_Midterm Presentation 11.24_Final Material Acquisition 11.26_THANKSGIVING HOLIDAY December 2009 12.1_Electrical / Mechanical Construction Begins 12.3_Electrical / Mechanical Construction 12.5_Construction 12.6_Construction 12.8_Construction 12.9_Construction 12.10_Construction (reading day) 12.17_Final Presentation


Budget solar power 300 watt Photovoltaic Panels AC/DC Disconnects

16

0.00

(Donated by Dale Brentrup, UNCC SoA)

1

0.00

(Included by Dale Brentrup, UNCC SoA)

3,230.00

Sunny Boy© 5000US Power Inverter

1

(Sun Electronics, Miami)

Professional Installation

per W

1

560.00

(SMA Solar Technologies)

.75 yds

90.00

(UNCC CoE, Lowes)

62‘

60.00

(FOILS, Harrisburg)

16

29.00

(Grainger, Charlotte)

4

590.00

(A 1 Fasteners, Charlotte)

Site Preparation/Approval

4

structure 1/2” Plate A36 steel (joints, footing)

4’x4’

230.00

1/4” Plate A36 steel (joints, wall mount)

4’x8’

180.00

5,000.00

(Argand Energy Solutions, Charlotte)

Manual Override Disconnect Metering anchoring Concrete (fly ash, portland cement, recycled aggregate) #2 Rebar

3

Anchoring Bolt Assembly (1/2” x 12” with fasteners) Wall Mount Assembly + Installation (core drilling, bolts, epoxy)

Joint Fabrication

(Facilities Management, NC 1 Call)

(FOILS, Harrisburg) (FOILS, Harrisburg)

(UNCC SoA, Metromont, C + M Steel)

3x4x1/4 A36 Structural Steel Angle

14x20’

1070.00

(C+M Steel or Howard Steel, Charlotte)

2x2x3/16 A36 Structural Steel Angle

15x20’

450.00

(C+M Steel or Howard Steel, Charlotte)

Structural Member Fabrication

20

3030.00

16

400.00

Primary to Tab Assemblies (1/4 “ dia Arch. Bolt, SS316)

23

160.00

(Grainger, Charlotte)

Tab to Secondary Assemblies (1/2 “ dia Arch Bolt, SS316)

15

220.00

(Grainger, Charlotte)

Cable Assembly ( pin to pin, pre-swaged adjustable terminals SS316) hardware Pin Assemblies (1” dia Arch. Bolt , SS316)

Total / Kit of Parts

15,300.00

(Metromont, C + M Steel) (Hayn™Terminals, Connecticut)

(Engineering Deptartment UNCC)

Charlotte Green Initiative


Intellectual + Financial Contributors

Friends + Advisors Dale Brentrup David Thaddeus Greg Snyder Ryan Buyssens John Boal David Jones Megan Smith Michael Baer Phil Meacham Keith Pehl Brian Dutterer Erik Lensch Rich Priess Drew Skau



Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.