Week 7 Journal Off Campus
The exteriors on a part of the building have already been completed. Hence, all the structural members are already in place, but interiors and other neccessities such as utilities and services remain to be installed. The site observed was an apartment complex under construction. The foundations and the frame of the superstructure have been completed. Scaffolding around the building remain to help the construction process by supporting the structure temporarily.
Constructing Environments Brian Siu (635900)