Michael Mina Restaurant Proposal

Page 1

BUILD GROUP INC. RESTAURANT PROPOSAL

457 MINNA STREET, SUITE 100 SAN FRANCISCO, 94103 T: 415.367. 9399 WWW.BUILDGC.COM


September 17, 2013 Mr. Alex Ertis 100 Montgomery Street Suite 715 San Francisco, CA 94104 Mr. Ertis: We are pleased to submit our qualifications, pricing, and schedule for the Pabu and Ramen Restaurant project at 101 California Street. We believe Build Group is bestqualified to build your project for the following reasons: Preconstruction Expertise We have provided an extensive Preconstruction phase to ensure every aspect of your project has been thoroughly planned before we set foot on-site. We looked at two different’ means and methods’ of executing your project. The first option is to proceed in a single phase with a single building permit (see enclosed schedule). In single phase we would wait for issuance of the Building Permit, which we estimate to be January 7th. We would proceed with construction immediately and expect Final Inspections to be around April 14th. The other option is break the construction phase into two phases and apply for two permits, demolition and construction (see enclosed phased schedule). By applying for demolition permit early in the Schematic Design Stage, we estimate, we can start ‘roughin’ construction on November 25th and expect Final Inspections around March 13th. Seamless Transition One of Build Group's biggest strengths is providing a seamless transition from Preconstruction through Construction. We do this by providing an open-book approach to all of our projects confirming every step of the process with the entire project team. The Perfect Team We have hand-selected our most qualified team of interior and restaurant experts. Our team has completed over 20 Signature Restaurants in San Francisco alone of a quality level expected in the Pabu and Ramen Restaurants. This team's unmatched experience will ensure they will hit the ground running. We are excited to submit our package for your review. Please don't hesitate to contact me if you have any questions or need additional information. Thank you, John Santori, Principal The Build Group


Table of Contents 1 About Build Group 2

2 Similar Projects

3

3 Resumes

4

4 Schedules

5

5 Pre-Construction,

6

General Conditions

7

and Fee’s

8

6 Insurance Documents


1. About Build Group


INC Build Group is a boutique general contractor focused on providing a high level of service to exclusive clientele. High selective about deploying their top-tier staff, the owners have a deep understanding of their client’s business and are committed to providing Principal involvement on all projects. To them, client relationships are everything and are driven by trust and integrity. Consequently, Build Group clients depend on the company to act as an extension of their own organizations. While most general contractors are simply pricing plans, Build Group’s staff sources new real estate opportunities and figures out creative ways to make deals pencil. In 2007, Ross Edwards Jr. and Eric horn founded the company after spending nearly 25 years in the construction industry. Although they were extremely proud of their many accomplishments, they realized that their previous company had grown into a large corporate organization and they had become fairly far removed from the trenches. They felt inspired to do something more entrepreneurial, which would allow them to work more closely with their clients. In the beginning of 2010, Build Group acquired Fine Line Group, a high-end retail and seismic upgrade company with over 30 years of construction experience. The company is known for evolving creative building methodologies and project delivery strategies that successfully manage and support the client’s design and business goals. The acquisition brought personnel with experience in high-end restaurant, hotel, and flagship retail experience. Fine Line Group has a wide-ranging repertoire of high-end signature restaurant projects including Kokkari, Postrio and Redwood Park in San Francisco. The company has also completed interior projects that include luxury brands such as Gucci, Christian Dior, John Varavatos, and Anne Fontaine. Build Group has grown consistently since its inception. Employee owned, the company now has a total of over 200 staff members. In August 2011, the company was included on the prestigious “Inc. 500” list, which profiled the nation’s fastest growing companies.


2. Similar Projects and References

457 MINNA STREET, SUITE 10


INC

MC2 DESCRIPTION 14,000 sf signature restaurant ARCHITECT Mark Cavagnero Associates PROJECT DURATION 6 Months

SAN FRANCISCO, CA

Elegance and refined beauty are captured in this historical building restoration. The project entailed seismic upgrade of the building and build out of the high−end interior. The raw brick and exposed steel beam construction of the interior walls are softened by the airy stretched fabric screen at the maple ventwood ceiling and light maple millwork throughout. Selected walls were finished with integral colored Italian plaster then polished to a high sheen. The flooring consists of beautifully finished limestone slabs.


INC

KOKKARI RESTAURANT @ JACKSON SQUARE SAN FRANCISCO, CA DESCRIPTION 8,000 sf signature restaurant ARCHITECT Backen & Gillam PROJECT DURATION 7 months

Designed by the award-­­winning architect Howard Backen of Backen & Gillam Architects, the design captures the feel of the European o l d -­­world. The commitment to excellence embodied in this signature restaurant places it instantly at the forefront of Hellenic Mediterranean venues nationally. Major features include specially distressed hardwood floors, exposed ceiling beams, lintels, shutters, and operable windows, which provide the feel of a Mediterranean open air café.


INC

LOONGBAR @ GHIRARDELLI SQUARE SAN FRANCISCO, CA DESCRIPTION 12,000 sf signature restaurant ARCHITECT Studio Arquitectura PROJECT DURATION 6 Months

This historic building at Ghirardelli Square was an existing two level theater. The project entailed converting it into an unusual dining theater with Pan−Asian flavor and ambiance. The design skillfully fused elements of a Buddhist temple with those of a contemporary California restaurant, which brought an upscale Asian dining experience to San Francisco.


INC

DESCRIPTION 18,000 sf signature restaurant ARCHITECT Kuleto’s ConsulNng and Design PROJECT DURATION 6 months

MCCORMICK & KULETO’S @ GHIRARDELLI SQUARE, SAN FRANCISCO, CA This spectacular bay view restaurant was built using a full complement of specialty finishes, including the use of natural dark wood, all custom built lighting, rich colors and original glass work to create a traditional ambience. The project included constructing new public stairway to Ghirardelli Square, landscaping the adjacent park, and re−lighting the Municipal Pier.


INC

SPLENDIDO @ EMBRACADERO CENTER SAN FRANCISCO, CA DESCRIPTION 8,000 sf signature restaurant ARCHITECT Kuleto ConsulNng & Design PROJECT DURATION 6 Months

This project, one of Pat Kuleto’s most beautiful designs, utilized an impressive range of fine artisans and unique materials in its creation. Finishes included a pewter top bar, Mexican wormwood walls, French slate flooring, hand−hewn wood ceiling beams, limestone columns, hand−blown glass light fixtures and blacksmith wrought ironwork.


INC

VERTIGO @ THE TRANSAMERICA PYRAMID SAN FRANCISCO, CA DESCRIPTION 9,000 sf signature restaurant ARCHITECT Engstrom Design Group PROJECT DURATION 5 Months

Located at the base of the Transamerica Pyramid, this signature restaurant incorporated a myriad of materials such as handcrafted wire railing, copper bar fronts, custom light fixtures and multicolored wood flooring. The impressive ceiling finishes ranged from walnut to canvas to shimmering copper screens. The project entailed the build out of four floors. It also involved a major exterior entry change to the Pyramid: a 200 feet structural ramp over the Redwood Park area.


INC

ONE MARKET

DESCRIPTION 11,000 sf signature restaurant ARCHITECT Architects II PROJECTED DURATION 6 Months

SAN FRANCISCO, CA

This signature restaurant was constructed in the Historic Southern Pacific Building in downtown San Francisco for Michael Dellar and Chef Bradley Ogden. Design features include custom sandcast glass panels at the pilasters, a terrazzo bar top, with Amarillo marble, and multicolored slate floors. Other finishes include row steel detail accents throughout custom hand−blown Italian crystal light fixtures. The state of the art 4,000 sf kitchen includes a popular “Chefs” table surrounded by the bakery, ice cream room, butchery and assorted cook lines.


INC

CAPPELINI DESCRIPTION 7,500 sf restaurant ARCHITECT Kuleto Consulting & Design PROJECT DURATION 6 Months

SAN MATEO, CA

This restaurant construction involved not only a full seismic upgrade but also included creating a mezzanine with a new elevator to service 3 levels. The finishes were Honduras Mahogany for the bar and bar back, a three marble weave pattern floor, and several hand-painted oil Frescoes.


INC

BRIX RESTAURANT DESCRIPTION 5,000 sf restaurant ARCHITECT Huntsman Carrell Design PROJECT DURATION 6 Months

YOUNTVILLE, CA

This restaurant is set in the Napa Valley surrounded by an olive grove and walking garden. The interior is reminiscent of and elegant country lodge. The Cherry wood beams and ceilings are set against warm plaster walls, slate floors and marble counters. A real stone fireplace in the lounge makes this space very inviting.


INC

POSTRIO RESTAURANT @ UNION SQUARE SAN FRANCISCO, CA DESCRIPTION 8,500 sf signature restaurant ARCHITECT Engstrom Design Group PROJECT DURATION 3 months (fast track)

The elegant remodel of this signature restaurant included a bentwood curved ceiling, custom lighting, and bird’s eye maple columns, and was accented with Gilhooly glass wall sculptures. The bar and pizza oven were remodeled in a classic style with exposed brick and custom copper ribbons. All work was completed while the restaurant remained fully operational.


References Bill Upson/Owner of Real Restaurants (415) 331-­­9101 x13 (415) 302-­­0685 mobile Owner of Bisteca, Fog City Diner and Loongbar @ Ghirardelli Square Sal Masoto/VP for Westfield (415) 512-­­6776 (909) 549-­­0446 mobile Operations Manager for San Francisco Centre: Build Group built over 15 food services John Dern/Owner of Dern Greinetz Inc (415) 986-­­6888 (510) 207-­­6846 mobile Owner of Postrio & Kuleto Restaurants on Union Square, Vertigo @ Transamerica Pyramid Peter Back/Senior VP of Boston Properties (415) 772-­­0781 (415) 760-­­6552 mobile Director of Operations at Embarcadero Center: Build Group constructed over 15 restaurants at Embarcadero Center including several signature restaurants including Splendido’s. Diane Knoll/Senior VP of Northwestern Investments (415) 956-­­3100 (415) 710-­­4158 mobile Owner of Ghirardelli Square over saw the construction of 3# signature restaurants including McCormick Kuleto’s and Loongbar. Michael Dellar/Owner of Lark Creek Restaurant Group (415) 655-­­7630 x30 (415) 265-­­6200 mobile Owner of Larkcreek Inn in Larkspur and One Market Restaurant


180 Harbor drive. suite 100 sausalito, ca 94965 tel: 415/331-9101 Fax: 415/331-9022

December 8, 2011

real restaurants mustards grill napa valley fog city diner san francisco osaka tra vigne & cantinetta napa valley bix san francisco roti san francisco buckeye roadhouse marin county pan-o-rama baking co. san francisco cafe museo in sf moma modern catering san francisco , bump s aspen ajax tavern aspen beetlenut san francisco

real american restaurants

To Whom It May Concern: I have been working with John Santori of Build Group for over 18 years on a multitude of restaurant projects. John and his team at Fine Line Group (which later became Build Group) have completed three signature restaurants for me, including Fog City Diner and Bistecca on the Riverwalk, both in Scottsdale, Arizona, and Loongbar at Ghirardelli Square in San Francisco. My first introduction to the team that is now Build Group was on our two restaurants on the Riverwalk, Bisteca and Fog City Diner. I was very impressed with the proactive way they approached both projects, especially Bisteca. Bisteca was the signature restaurant for Riverwalk. The finish was primarily custom millwork -- ceiling, walls and booths. I was also very impressed with their attention to details. They brought both projects in on time and in budget. Because of the success of both these projects, I hired John and his team to build our most challenging signature restaurant, Loongbar at Ghirardelli Square. Loongbar was a very unique project with a challenging complex Asian--inspired design and full seismic upgrade of the building. The work entailed converting an existing two level theater in this historical building into a 12,000 square foot one of a kind Asian dining theater.

fog city diner chicago tomatina napa valley walnUt creek santa clara

I especially liked working with John and his people because of their proactive customized approach to every project. Their preconstruction support to my architects and consultants was invaluable to the success of each of my restaurants

loongbar san francisco postino lafayette

Given my long history of success working with John and his team, I am confident in my recommendation of Build Group.

Sincerely,

Bill Upson


Dern Greinetz Inc. Telephone 415 986 6888 Facsimile 415 536 3843 email DernGrein@aol.com

December 6, 2011 To Whom this May Concern: My company has worked with the people of Build Group (formerly Fine Line Group) many times over the past 15 years. Our first project together was the development of Vertigo restaurant and bar located in the Transamerica building in San Francisco. I found their work to be professional and their integrity to be substantial. Their millwork in particular was of a very high quality. Tom Harty was the superintendent for the Vertigo. The restaurant was spread over four floors and was custom designed with intricate and elaborate finishes. Tom paid close attention to the design details and installation of the one of a kind finishes. The design was successfully implemented because of his close oversight. Thanks to Tom’s hard work the restaurant won many awards for design. In addition to his quality of work, the thing I liked most about Tom was his proactive attitude throughout the entire project. He not only took on his own scope but also scheduled and managed all of my consultants. In addition, our firm hired the people of Build Group for the renovation of Postrio restaurant and bar, and the seismic strengthening of Villa Florence Hotel and Kuleto's Italian Restaurant. We were pleased with their ability to complete the job on time and with a minimum of disruption. I would be delighted to work with the Build Group Team on any of my future projects. Sincerely,

John B. Dern

650 Delancey Street Suite 219 San Francisco California 94107


EMBARCADERO CENTER

Mr. Raymond E. Terwilliger The Olympic Club 524 Post Street San Francisco, CA 94102 Four Embarcadero Center Suite 2600

Dear Raymond:

San Francisco, California 94111-5994

I have worked very closely with Fine Line Group consistently over the past five years on many projects located in the Embarcadero Center. They have remodeled over 27 retail spaces for us, including several high-end restaurants.

Telephone 415 772 0500 Fax 415 982 1780

Fine Line Group has been extremely concise and timely on all of the work they have done for us. They have continued to handle things professionally, and have completed all projects with notable success. We rely on Fine Line Group on a monthly basis for anything from preliminary budgets to construction repairs, and they have never let us down. I can without a doubt recommend Fine Line Group for your club house renovation project. I can assure you they would meet even your highest expectations. Sincerely,

Russ Campbell Director, Retail Properties cc

John Santori

Managing Agent: Pacific Property Services, L.P.


Ghirardell Square wo rd l y fl a v or. local fl air. 900 NORTH POINT STREET SAN FRANCISCO CA 94104 TELEPHONE

415.775.5500

.

FAX.415.775.0912

h t t p : / / w w w . G h i r a r d e l l i S q . c o m

Mr. Yuji Tsunoda Eugene & Associates, Inc. Chaya Brasserie 8741 Alden Drive Los Angeles, CA 90048 Dear Mr. Tsunoda, I am writing this as a testament to the workmanship and quality of service of the Fine Line Group Inc. as a general contractor. As the General Manager of Ghirardelli Square in San Francisco, I have had the opportunity to work with Mr. Santori and the Fine Line Group Inc. as the principal contractor during the construction of two major restaurants that are currently part of the Ghirardelli Square scene. The restaurants include McCormick & Kuleto’s 18,334 square feet and Oritalia (now La Pasta) 2,103 square feet. The Fine Line Group was recently contracted and is currently involved in the construction of a third major restaurant for Ghirardelli Square. Fine Line is currently building a restaurant for Mark Miller and work includes the seismic up-grading of the Power House Building, the location for this new restaurant. Our experience with the Fine Line Group has been nothing short of outstanding. They continually meet their deadlines and have been consistently productive in determining solutions for the many problems that develop in projects of the magnitude of the above restaurants. I would wholeheartedly recommend the services of the Fine Line Group Inc. to any entity seeking a dependable construction company for projects of any size. I am available to discuss the merits of the Fine Line Group Inc. at any time. Please feel free to call me if you have any questions. Sincerely

Louis Ligouri General Manager


Wolfgang Puck 1114 Horn Avenue Los Angeles, CA 940069 Dear Wolf: Long time no talk to. I understand things are going great for you. Thought I'd let you know about Fine Line Group, who I've enjoyed working with. I've had the pleasure of designing and constructing several restaurants including McKormick & Kuleto's, Splendido's and Ristorante Capellini in collaboration with Fine Line Group. Their attention to detail, their overall workmanship, professionalism and team spirit contributed greatly to the success of these projects. Despite many design changes during the construction of these projects, Fine Line Group was able to react quickly to implement these changes and still complete the projects either on time or ahead of schedule. Their skill in the field and ability to respond quickly, to anticipate problems, develop value engineering, suggest creative alternatives, coordinate, manage and ultimately complete a project in a professional manner is a rarity in today's marketplace. I highly recommend Fine Line Group as a Contractor in the construction of any restaurant facility. Give me a call next time you're in town -- I'd love to say hello. Sincerely,

Pat

30

LIBERTYSHIP WAY #207

SAUSALITO, CALIFORNIA 94965

415.331.0880

FAX 415.331.2954


Mr. Wolfgang Puck Spago's 1114 Horn Avenue Los Angeles, CA 90069 Dear Wolfgang: I am writing this letter in response to a recent inquiry from John Santori at the Fine Line Group, general contracting firm. I understand that you are considering Fine Line proposed restaurant you are planning in California.

Group

for

a

If you have not already made your decision, I'd like to suggest that your project would benefit greatly from the attention and expertise that Fine Line brings to the table. Michael Dellar and I have recently completed two projects with Fine Line, our new One Market Restaurant in San Francisco and an around-the-clock five day "fast track" gut and remodel of our Lark Creek Inn restaurant kitchen in Larkspur. Although both projects were very different, they were similar in the professional manner in which they were planned and executed. From a chef's perspective, I especially appreciate Fine Line Group's extensive experience with restaurant construction and their consequent attention to design, function and suitability of detail. Their innovative "team approach" to construction is refreshing and positive and made the experience almost enjoyable! Good luck with your new venture. I hope to see you at your next grand opening. Regards,

Bradley M. Ogden cc: John Santori

1 Market Street, San Francisco, California 94 10 5 - 1 57 2 Restaurant (415) 777 - 5577 t Of fice 777 - 55 88 t Fax 777 - 44 11


San Francisco Chronicle What will Brad Ogden’s spectacular new San Francisco restaurant, One Market, and the new Coach leather goods store at Post and Grant have in common with 20 Talbot’s apparel stores in three states, Brobeck’s justcompleted Palo Alto law office and three Alders Duty Free shops in Las Vegas? They’re all projects of Fine Line Group, a San Francisco general contracting firm that’s not at all general.

Upscale Contractor On The Fast Track By Lloyd Watson

“We’ve been increasing revenues 30 percent to 35 percent a year for the past three years. This year we’ll double to somewhere between $15 million and $20 million in new business. We’ve got 12 projects under way and another 12 in negotiation.” Santori, 46, has all the usual answers as to why his company is “so hot” – quality workmanship, fast-track performance, good follow-up and maintenance. “Ninety percent of our business is repeat.” But Fine Line also offers something that is unique. “Despite the computers in the office, construction is one of the most backward of businesses.” Santori said. “There’s always been an adversarial relationship between the contractor and the architect/owner. We’ve tossed that old negative way of doing business out the window. We take the team approach and share some of the risk that normally falls entirely on the owner.” Fine Line works up its budget from the architect’s schematic drawings rather than the much more expensive working drawings. “Only the subcontractors know the real cost of building,” Santori said. “So we bring all the potential subcontractors to the job site and walk them through the project. Then we can commit to a price that the developer

can take to his investors as a firm number.” By so doing, Santori says he can save an owner 10 percent or more of a project’s overall cost. That can be especially significant when construction runs from $250 to $300 a square foot – as it did for the Splendido’s and McCormick & Kuleto restaurants, both recent Fine Line jobs. A fourth-generation San Franciscan who worked his way through Lowell, USF and Cal as a carpenter, Santori began by specializing in interiors for major exhibits at the Legion and DeYoung museums and the California Academy of Sciences. When Prop 13 killed off much museum funding, he switched to retail and restaurant interiors. His Fine Line partner is Bob Helmers, 46. Their pet project of the moment is the $2.5 million-plus One Market restaurant being built for acclaimed chef Ogden, 38 and his Lark Creek Inn partner, Mike Deller, 46. It’s scheduled to open by Thanksgiving in the old SP Building at the corner of Market and Steuart.

The restaurant will be one of the city’s largest, with floor-to-ceiling windows looking on to the Embarcadero and the Ferry Building. It will employ 150 people and seat more than 300 – 10 of them at a chef’s table in the kitchen, which will take up more than 40 percent of the 10,300-square-foot space.

Copyright © by the San Francisco Chronicle. Raprintad by parmission.


San Francisco Business Times

In the last 20 years, contractor John Santori has rebuilt himself, his company and the construction industry at least a half a dozen times.

Convincing Others to Try Something New By Susan Smith Hendrickson

Changing the course of his own life wasn't difficult. If Santori had followed his original career path to attend Columbia University Medical School, he would still be his same innovative self, and no doubt gone on to become something like a reconstructive surgeon. Instead, Santori has reinvented the way seismic work and high-end retail and restaurants projects are done. Changing the ways of the construction industry proved more difficult. Said Santori, "The construction business isn't very innovative." Santori chose a career in construction, in 1974, after spending his summers framing houses for his uncle. Building seemed like it would be a lot more fun than the years of studying that medical school required. Soon he learned that it would also be more challenging. Santori's first company, Santori Construction, started out with small projects and was soon called on to renovate San Francisco's California Academy of Sciences and the Legion of Honor. "We were cheap," said Santori, who loved the opening parties that went with doing museum work. In 1979, Proposition 13 wiped out all the funding for library and museum construction and almost demolished Santori's company. To stay alive, Santori turned to high-end retail construction, signing on four partners who each put in $500 for a total of $2,000 in startup funds. They spent the money on stationery for their new company, the Fine Line Group, photocopied the American Institute of

Architect's San Francisco directory and went door-to-door looking for projects. Lacking retail experience, work was difficult to get, so Fine Line took what other construction firms wouldn't. In 1980, their largest job was for the department store Liberty House. Their fee: $5,000. At a Christmas party, Santori announced that Fine Line was going out of business in March. After that announcement, they received $4 million in letters of intent from Liberty House and Bullock's. Fine Line decided to give the construction industry another try. Wanting to be like the big players in the industry, it moved from its original home in Marin to San Francisco. Soon, Liberty House pulled out of California, and so did Bullock's. "We learned a new word -- diversification," Santori said. IBM was Fine Line's next big client, but the 1980s were also a time of downsizing for the technology giant. During this series of disasters, Santori picked up on a way of doing construction that would save his business -- and the budgets of others. While working with a Los Angeles architecture firm, Santori was introduced to the Japanese fast-track method of building. Santori was astounded by the method's short construction period. He studied it for 10 years before finding a client that would allow him to test his new-found approach to building. Rizzoli's bookstore decided to give the method a try. Santori had already >>


Continued

San Francisco Business Times

remodeled two of the chain's stores, and the owner was anxious to try anything that would prevent him from closing a third store and losing business during the long remodeling process. "With Japanese fast track, you can advertise that you are closing on a Friday, `come see our new store on Monday,' " said Santori. Because of the months spent planning, measuring and doing most of the building off-site (which is cheaper), construction of a store happens almost overnight. Fine Line's first Japanese fast track project was a success and the company realized it had found a niche: meeting next to impossible deadlines. The company reinforced its theory by completing the renovation of the French Lycee School in San Francisco in fiveand-a-half months, four months ahead of its set schedule. Santori next applied Japanese fast-track construction to the seismic renovation of Rizzoli's San Francisco store. The project had a 14- month deadline. Fine Line completed it in five-and-a-half months. Now Santori wants to completely change the way seismic work is done in the Bay Area. After all, a lot of buildings still have to get up to code before the 2002 deadline. To help them, Fine Line has joined with two universities and started a new division, Composite Structures, to test a new building material made out of carbon fiber, which is 10 times stronger than steel. "In every other industry, you have to deal with the Steve Jobs-types, working away in their garages, trying to innovate," said Santori, a biochemist by degree. "I named my company the Fine Line Group, not Fine Line Construction, because I don't know where we will be in 10 years." Copyright 1999 Amarican City Businass Journals Inc.


Hospitality Design

On time and on budget are words clients like to hear – but often don’t – from their contractors. With the Fine Line Group, a San Francisco-based commercial interior construction firm headed by CEO John S. Santori, clients can anticipate a construction experience that is designed to save time, money, and energy often spent on unforeseen problems.

On Time & On Budget By Suzanne Dorn

According to Santori, Fine Line does this by following a methodology of teamwork based on Japanese management principals. Specializing in high-end West Coast restaurant projects, Santori’s 40-person firm is responsible for building some of San Francisco’s most successful venues, such as the $2.5 – million One Market restaurant and McCormick & Kuleto’s, created by award-winning restaurant designer Paul Kuleto. What sets his firm apart from the competition, Santori says, is the amount of pre-construction planning that goes into each of its projects. “Pre-planning allows us to make scheduling and budgetary commitments that are invariably met,” he adds.

item-by-item budget review is performed that actual work begins – with fewer hitches than might be the case without such meticulous preplanning. Though he earned a biochemistry degree from the University of California, Berkeley in 1970, Santori has always had a taste for the construction business. He worked for an uncle framing house during his college days, “and it progressed from there,” he says. In 1974, he started his own construction firm, which worked mainly on museum projects. That firm, eventually renamed the Fine Line Group, expanded its market to include retail and restaurant projects, as well as some hotel projects for Hyatt. With annual billings of $20 million, Santori and his Fine Line Group are at work currently on the California Culinary Academy, Chalkers Billiard Club, and Silks restaurant, all located in San Francisco.

On all Fine Line projects, a team composed of the client, architect, contractor, and subcontractors is organized at the outset of a project. In the earliest stages of planning, each team member participates in several inspections to become totally familiar with the project so that there are no surprises down the road. “Each team member will be expected to perform as specified and for the price agreed to,” Santori explains. Team members each have an equal voice in the numerous plan reviews and revisions that take place during the planning period. It is only after final revised schematics are approved by everyone on the team and an

Reprinted with the permission of HOSPITALITY DESIGN Magazina.


Visual Merchandising + Store Design

versatility has insulated us to some degree … and our willingness to offer additional services that other builders don’t offer has worked in our favor.”

Problem Solving – Fine Line Group’s Competitive Edge By Bob Jordan

How does a construction company enjoy 20- to 30-percent growth in the depths of a recession when its principal clients are retailers going through the worst down market in a decade? By accepting smaller profit margins, by being more versatile and budgetconscious than competitors and by helping clients solve time constraint and design problems. At least that’s the formula used by San Francisco-based contractor Fine Line Group. Fine Line’s President and COO, Bruce Clymer, says it’s worked so well that the company expects 30- to 40-percent growth throughout the rest of the year. Since its inception in 1979, Fine Line’s 40 employees, under the direction of CEO John Santori, have gathered clients such as Coach, Talbots, Liberty House, Confetti candy stores, Duty Free Shops, Sharper Image and Hyatt Regency Hotels. While the group’s work is primarily confined to the Southwest – California, New Mexico, Nevada and Arizona – future plans include venturing to the Northwest and Hawaii. “The recession has given us a lot of good customer,” Clymer says. “Our

One of those services includes site surveys. For example, the firm reviewed four possible locations for Talbot’s flagship store in San Francisco’s Union Square. Before leases closed, Fine Line found asbestos problems in one and structural problems in another. They also advised Talbots of city building codes and restrictions that might adversely affect their project. “After site selection, we quickly got involved with the construction teams, helping to develop cost estimates,” Clymer explains. “There were some plaster ceilings in the existing space. The architects contacted us to see what we could do to salvage and determine whether we could repeat those original details throughout the space. That’s the kind of challenge we love to rise to.” Say you’re a store designer who has just been given a rehab assignment with a limited budget, a ridiculously short completion date of eight weeks and very upscale expectations for the result. Is this mission impossible? Maybe not. You fall into the classic profile of clients that sought the services of Fine Line Group this past year. Satisfied clients include such retail icons as I. Magnin, Bullock’s, Gumps and Coach. “We were able to do a renovation for Coach in eight weeks, Talbots took about ten weeks… and that was in the middle of the earthquake.” Clymer says. The Coach renovation, at Post and Grand Streets in San Francisco, involved a new façade, plus internal remodeling. “We knew an eight-week schedule was very ambitious,” admits Michael Fernbacher, Coach’s project manager. The renovation budget was

incomplete and some of the finishing detail had yet to be determined. These challenges left Fine Line undaunted – they assigned Steve Fairclough to the project as field superintendent. “Steve has a millwork background,” Fernbacher explains. “This makes him sensitive to the larger architectural issues – and ability to see further ahead. Also, we are very much problem-solvers. Where many builders are always complaining about design problems, Fine Line becomes part of the design team – they think like designers.” Fairclough sweated out every detail, according to Fernbacher. Fine Line located subcontractors to accommodate special metalworking requirements. Innovative construction methods, that involved removing, restructuring and reusing existing metal design elements, economically solved design problems on the façade. Unique scaffolding allowed ceiling and floor work to progress simultaneously. Tasmanian oak cabinetry and trim gave the Coach store the look of rich mahogany at a fraction of the price. “They kept moving, taking it all in as we went,” says Fernbacher. “We had considerable changes – both in design and price – and they were able to accommodate it all.” Gene Messina, Coach’s manager of store construction, was so pleased with the final result that he’s decided to replicate many of the Fine Line’s ideas in the firm’s other stores. The secret of Fine Line’s success lies in the company’s philosophy of selecting clients with whom they hope to build long-term relationships. Clymer says Fine Line works to develop a team concept between client, architects and other contractors. >>


Continued

Visual Merchandising + Store Design

Another of our services is our ability to provide subcontractors who provide quality work at competitive prices,” says Clymer. “We try to target clients who are growing. We repeat a lot of work with different architects. This enables us to negotiate attractive prices. It also makes it easier to devise alternative ways of constructing thing within structural limitations. “Systemization is the key,” insists Clymer. “We are highly organized, with highly developed computer systems. This permits us to organize our subcontractors more efficiently. We’re able to be more creative on the financial end, allowing projects to move forward before the design is complete.” As an example, in the Coach project Fine Line separated the façade from the prime contract. This permitted the firm to set a ballpark figure and begin construction while the final design problems and costs were worked out for the rest of the project. Leadership is another key. “We often teach our subcontractors how to bid,” Clymer says. “We teach them to develop detailed proposals. We keep them trim. We’re really strong on realistic bids. Then we protect our subs – we make sure we keep our promises.” Trust is extended through the client- architect-builder team. It makes for long-term, stable relationships where work can be done on a handshake if need be.


3. Resumes


Organizational Chart Michael Mina Ellen Owner

Designer

MEPS Engineer

Structural Engineer

Architect (TBD)

(TBD)

(TBD)

Kitchen Designer

Plumbing Contractor

Lighting Designer

HVAC Contractor

Proforma

Kitchen Designer

Eric PM

E r i c

David Const Mgr

John Sponsor

O w n e r

Julio Project Manager

Frank Estimator

Bob Superintendent

Fire Protection Contractor

Ross Project Engineer

Eric Precon


INC

Julio Guerrero Project Manager Experience Julio Guerrero is a versatile design and construction professional with over 11 years’ experience, and significant restaurant expertise. Educated in architectural design, his unique background before joining Build Group includes working for major restaurant companies and architecture firms. He brings a proven track record for successfully executing a client’s vision while keeping strict adherence to the project budget, schedule, and brand identity. In his role has Preconstruction Project Manager, Julio collaborates with owners, construction managers and architects. He provides affective value engineering while maintaining design intent, helps develop quality construction documents and identifies possible owner-design conflicts. Clients benefit from Julio’s passion for architecture and past construction experiences. He has a deep understanding of the restaurant business and the design profession.

Relevant Projects 

Peet’s Coffee and Tea 10 locations within San Francisco Nationwide Mixt Greens 3 full service restaurants within San Francisco 2 full service restaurants within Los Angeles 3 full service restaurants within Washington D.C. HMS Host Nationwide Over 20 design concepts including California Pizza Kitchen, Starbucks and Roadhouse 66 Café Workshop San Francisco, CA

Build Group Projects:  Westfield, San Francisco Center  Panda Express-San Francisco 

Mrs. Field’s- San Francisco

Education and Credentials Kansas State University B.A. Architecture Planning and Design, 2001

457 Minna Street, Suite 100 San Francisco, CA 94103 T: 415.367.9399

www.buildgc.com


INC

Frank Coppolillo Chief Estimator Experience Frank Coppolillo brings over 22 years’ experience in the construction industry ranging from Project Management to Lead Estimator and then to Chief Estimator. His knowledge of projects from every perspective has led him to be extremely effective as Chief Estimator for Build Group. He is very detailed orientated and offers a wide range of services from Conceptual to Pre-Construction to negotiated / hard bids for every new project. Prior to joining Build Group Inc., Frank gained experience at PWI Construction, McHugh Construction and Walsh Construction.

Relevant Projects • • • • • • • • •

$22.5MIL – Tiffany & Co -HI/CA/OH/IL $9.3MIL- Bvlgari – CA/AZ/TX/GA/FLA $2.2MIL – Emporio Armani – CA/FLA/IL $3.4MIL – Tory Burch – CA/FLA/IL $5.9MIL – Michael Kors – NY/MA/CA/NV/GA/AZ/PA/WA $330MIL – Aqua Building – Chicago, IL $120MIL – Blackstone Hotel – Chicago, IL $220MIL – Telluride Ski Resort – CO $64MIL – Riverside HS – Brookfield, IL

Education and Credentials Masters of Architecture – IIT Chicago, ILL BFA – Iowa State University

457 Minna Street, Suite 100 San Francisco, CA 94103 T: 415.367.9399

www.buildgc.com

• • • •

$500K – N-Counter restaurant – Tempe AZ $1.7MIL – Naperville performing arts center $55MIL – Plainfield IL School district package $32.5MIL – Gallery 400 Condominiums – Chicago, IL


INC

Eric Owen Project Manager Experience Eric Owen brings over 20 years’ experience in construction ranging from Project Engineer to Project Manager to Chief Estimator to Business Development. His strong skills in Preconstruction and client relations, leads him to successfully identify and bring value to projects. Eric has strong talents for working with both clients and contractors to get the team going in the right direction. His overall quality, performance, and customer satisfaction are fully realized. Prior to joining Build Group, Mr. Owen gained experience at DJK Construction, Donnelly Kerley Builders and his own company, DHS Construction Services.

Relevant Projects Build Group Projects: Lupicia Tea, Westfield Centre, San Francisco Tenant improvement Cafe Central, Westfield Centre, San Francisco Tenant improvement Previous experience while at another firm: • • • • • • • • • •

Club Nokia at L.A. Live, Los Angeles Park Place Restaurant, Cupertino Regal Cinemas at L.A. Live, Los Angeles H5, San Francisco Intuit, San Francisco Lontree Center, Brentwood Metroplex Office Centre, Concord Cypress Hotel, Cupertino, Kimpton Group 400 Castro Street, Mountain View Emery Station 3 Parking Garage, Emeryville

Education and Credentials California State University, Chico B.S. Construction Management, 1995

457 Minna Street, Suite 100 San Francisco, CA 94103 T: 415.367.9399

www.buildgc.com

• • •

Residence Inn by Marriott, Pleasanton San Francisco Towers, San Francisco U.S. Geological Survey, Menlo Park


INC

Ross DeLoria Project Engineer Experience Ross brings exuberance to the projects he’s assigned through his various experiences in different sectors of the industry. Working mainly as a support assistant to the chief estimator and the head of operations, Ross never says no to any challenge or task. Technologically adept, energetic, and always willing to go the extra mile.

Relevant Projects Build Group Projects:  

Hotel Renoir, San Francisco, CA – Structural retrofit and historical renovation, tenant improvement T.I. Estimating – Walgreens, Equinox Gym, Suitsupply, Hog Island Oyster Company, and other high end retail and dining

Previous experience while at other firms:    

Project Manager/Estimator for drywall and paint at Russell Hinton Company Project Engineer at PG&E M.A.O.P. pipeline project Engineering Technician at the Marin County Department of Public Works: Land Development IST Intern at Field Paoli Architects

Education and Credentials   

B.S. Civil Engineering, Environmental Studies – Chico State University NCEES Fundamentals of Engineering Exam – E.I.T. USGBC – LEED G.A.

457 Minna Street, Suite 100 San Francisco, CA 94103 T: 415.367.9399 www.buildgc.com


4. Schedules


Pabu & Ramen Restaurants @ 101 California St I

Mina Group

INC

Build Group Subject to Change Sep 8, '13 Sep 15, '1 Sep 22, '1 Sep 29, '1 Oct 6, '13 Oct 13, '1 Oct 20, '1 Oct 27, '1 Nov 3, '1 Nov 10, ' Nov 17, '1Nov 24, ' Dec 1, '13 Dec 8, '13 Dec 15, '1 Dec 22, '1 Dec 29, '1 Jan 5, '14 Jan 12, '1 Jan 19, '1 Jan 26, '1 Feb 2, '14 Feb 9, '14 Feb 16, '1 Feb 23, '1 Mar 2, '1 Mar 9, '1 Mar 16, ' Mar 23, ' Mar 30, ' Apr 6, '14 Apr 13, '1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23 3/2 3/9 3/16 3/23 3/30 4/6 4/13

ID 1 2 3

Task Name

Duration

Start

Finish

Predecessors

112 days? Tue 9/10/13Wed 2/12/14

PRECONSTRUCTION Preselection of Consultants by Ownership

16 days Tue 9/10/13 Tue 10/1/13 12 daysMon 9/16/13 Tue 10/1/13

Contractor

4

RFP for Contractors

6 daysMon 9/16/13Mon 9/23/13

5

Contractors submit Proposals

5 days Tue 9/24/13Mon 9/30/13 4

6

Ownership selects Contractor

1 day Tue 10/1/13 Tue 10/1/13 5

7

Architect

16 days Tue 9/10/13 Tue 10/1/13

11

Structural Engineer

16 days Tue 9/10/13 Tue 10/1/13

9/16

6 days 9/24

RFP for Contractors 5 days 10/1

Contractors submit Proposals 1O dw aynership selects Contractor

15 16

Concept Drawing Stage

24 daysWed 10/2/13Mon 11/4/13

CONTRACT

38 daysWed 10/2/13 Fri 11/22/13

Schematic Drawing Stage

27 days Fri 10/11/13 on 11/18/13

Discovery

11 daysMon 10/7/13 on 10/21/13

23 24 30 31 39 40 45 46

Demolition Permit

7 days? Fri 10/11/13 on 10/21/13

47

Architect does Demolition Drawings

5 days Fri 10/11/13 hu 10/17/13 32FS-10 days

48

Submit for Demolition Permit (Over the Counter)

2 days Fri 10/18/13 on 10/21/13 47

10/11

5 days 10/18

Architect does Demolition Drawings 2 daysSubmit for Demolition Permit (Over the Counter)

49 50

MEPS Engineer by Architect (Design Build Option)

12 days Fri 10/11/13 on 10/28/13

Kitchen Drawings (Final)

24 daysWed 11/6/13Mon 12/9/13

MEPS Engineering Stage (Design Build Option)

14 days ue 10/29/13 Fri 11/15/13

55 56 64 65 72 73

Prebid MEPS & Drywall (Option)

12 days? Tue 11/5/13 ed 11/20/13

74

MEPS Contractors Agree to match their Original Bid

1 day on 11/18/13 on 11/18/13 68,69,70,71

75

Bid Drywall (Minimum of 3# bidders per trade)

10 days Tue 11/5/13 on 11/18/13 74FS-10 days

76

Confirm Budget for MEPS & Drywall with Schematic Budget

77

If confirmed then Build Group moves forward with Contract

11/18

1 dMaEyPS Contractors Agree to match their Original Bid

1 dayTue 11/19/13Tue 11/19/13 74,75 1 day? ed 11/20/13 ed 11/20/13 76

78 79

Design Development Stage

108 daysMon 9/16/13Wed 2/12/14 10/25

15 days

Architect does DD Drawings

80

Architect does DD Drawings

81

Architect Incorporate Discovery into DD Drawings

2 days Tue 10/8/13Wed 10/9/13 40FS-10 days

82

Architect incorporate MEPS Engineering Dwgs into DD Drawings

2 days on 11/18/13Tue 11/19/13 68,69,70,71

83

Architect Incorporate Kitchen Drawings into DD Drawings

2 days ed 11/13/13 hu 11/14/13 57

84

Build Group Revises Schedule for DD Drawings

2 days Fri 11/8/13 on 11/11/13 80FS-5 days

85

Ownership approves Final DD Drawings & Schedule

86

Build Group bids Final DD Drawings w/approved Schedule (Minimum of 3# bidders/t

87

Owner approves Final Budget

1 day Fri 12/6/13 Fri 12/6/13 86

88

Owner & BG meet & agree to a reduction of Construction Contingency

1 dayMon 12/9/13Mon 12/9/13 87

12/9

89

Final Contract Amount is incorporated into Approved Contract

1 dayTue 12/10/13Tue 12/10/13 88

12/10

90

Build Group issues Subcontracts to Subcontractors

1 day ed 12/11/13 ed 12/11/13 89

15 days Fri 10/25/13 hu 11/14/13 32 10/8

2 daAyrschitect Incorporate Discovery into DD Drawings 11/18 11/13 11/8

1 day Fri 11/15/13 Fri 11/15/13 84,80 15 days Fri 11/15/13 Thu 12/5/13 80

2 dAarycshitect incorporate MEPS Engineering Dwgs into DD Drawings

2 dAarycshitect Incorporate Kitchen Drawings into DD Drawings

2 daysBuild Group Revises Schedule for DD Drawings 11/15

1 dOawynership approves Final DD Drawings & Schedule

11/15

15 days

Build Group bids Final DD Drawings w/approved Schedule (Minimum of 3# bidders/trade) 12/6

1 dOawyner approves Final Budget 1 dOawyner & BG meet & agree to a reduction of Construction Contingency

12/11

1 dFianyal Contract Amount is incorporated into Approved Contract 1 dBauyild Group issues Subcontracts to Subcontractors

91 92

Permit Drawings Stage

45 days Fri 10/25/13 hu 12/26/13

95 96 97

108 daysMon 9/16/13Wed 2/12/14

Submittals

24 days ue 11/19/13 Fri 12/20/13

HVAC (Assuming Original Designer meets Budget)

98

HVAC Ductwork & Linear Diffusers

22 days ue 11/19/13 ed 12/18/13

102

HVAC Equipment

24 days ue 11/19/13 Fri 12/20/13

106

24 days ue 11/19/13 Fri 12/20/13

Electrical

107

Lighting

112

Dimmer System

116 117

5 days ue 11/19/13 on 11/25/13 24 days ue 11/19/13 Fri 12/20/13

Plumbing (Assuming Original Designer meets Budget)

Project: Mina Restaurant @ 101 C Date: Tue 9/17/13

24 days ue 11/19/13 Fri 12/20/13 24 days ue 11/19/13 Fri 12/20/13

Fixtures Task

Milestone

Project Summary

External Milestone

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

Deadline

Split

Summary

External Tasks

Inactive Task

Inactive Summary

Duration-only

Manual Summary

Finish-only

Progress

12 Tue 9/17/13


Pabu & Ramen Restaurants @ 101 California St I

Mina Group

INC

Build Group Subject to Change Sep 8, '13 Sep 15, '1 Sep 22, '1 Sep 29, '1 Oct 6, '13 Oct 13, '1 Oct 20, '1 Oct 27, '1 Nov 3, '1 Nov 10, ' Nov 17, '1Nov 24, ' Dec 1, '13 Dec 8, '13 Dec 15, '1 Dec 22, '1 Dec 29, '1 Jan 5, '14 Jan 12, '1 Jan 19, '1 Jan 26, '1 Feb 2, '14 Feb 9, '14 Feb 16, '1 Feb 23, '1 Mar 2, '1 Mar 9, '1 Mar 16, ' Mar 23, ' Mar 30, ' Apr 6, '14 Apr 13, '1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23 3/2 3/9 3/16 3/23 3/30 4/6 4/13

ID

Task Name

Duration

Start

Finish

121

Fire Protection (Assuming Original Designer meets Budget)

19 days ue 11/19/13 Fri 12/13/13

125

Millwork

45 days hu 12/12/13Wed 2/12/14

130

Storefront

33 days hu 12/12/13Mon 1/27/14

135

Kitchen & Bar (By Owner)

30 days Tue 12/10/13 Mon 1/20/14

139

Stone & Tile

Predecessors

101 daysMon 9/16/13 Mon 2/3/14

140

Quarry Tile

17 days hu 12/12/13

144

Ceramic Tile

28 days hu 12/12/13Mon 1/20/14 90

148

Stone Tops

38 days hu 12/12/13 Mon 2/3/14

152

Wood Flooring

27 daysMon 9/16/13 ue 10/22/13

156

Carpet

27 days hu 12/12/13 Fri 1/17/14

Fri 1/3/14

160 161 162

98 days? on 11/25/13 Wed 4/9/14

CONSTRUCTION

38 days on 11/25/13Wed 1/15/14

ROUGH CONSTRUCTION

11/25

163

MOBILIZATION

5 days on 11/25/13 Fri 11/29/13 29

164

Soft Demolition

6 days ue 11/26/13 Tue 12/3/13

167

Layout

5 days ue 11/26/13Mon 12/2/13

179

Install Walls

6 days ed 11/27/13Wed 12/4/13 168

180

Install Bar Dies

3 days Tue 12/3/13 Thu 12/5/13 174

181

Millworker Confirms Layout

182

Install Door Jambs

183

Install HVAC Ductwork

184

Install Exhaust Duct

8 days Fri 11/29/13Tue 12/10/13 171

185

Install Exhaust Hoods

3 days

186

Install HVAC Equipment

3 days on 12/23/13 ed 12/25/13 183,102

187

Rough In Electrical

188

Rough In Plumbing through Slab

6 days Tue 12/3/13Tue 12/10/13 174

189

Rough In Plumbing into walls & Ceiling

6 days Thu 12/5/13 hu 12/12/13 179

190

Relocate Sprinklers

6 days ed 12/11/13 ed 12/18/13 183

191

Install all Backing

4 days hu 12/12/13Tue 12/17/13 179FS+5 days

192

Install Steel Supports for Countertop

193

Frame in Ceilings & Soffits

10 days ed 12/11/13Tue 12/24/13 184,179,183

194

Install Lighting

10 days ed 12/18/13Tue 12/31/13 193FS-5 days,10

195

Install Dimmer Panel

196

Rough In Emergency Lighting

2 days ed 12/25/13 hu 12/26/13 193

197

Rough In Low Voltage

4 days Fri 12/27/13 Wed 1/1/14

204

Rough In Inspections

2 days Tue 1/14/14Wed 1/15/14 194,189,187,185

5 days MOBILIZATION

11/27

6days

Install Walls

12/3

3 dayIsnstall Bar Dies

11/29

1 day Fri 11/29/13 Fri 11/29/13 177

1 dMaiyllworker Confirms Layout 12/10

3 daysTue 12/10/13 hu 12/12/13 179FS+3 days 11/27

10 days ed 11/27/13Tue 12/10/13 168

3 dayIsnstall Door Jambs

10 days

11/29

Install HVAC Ductwork

8 days

Install Exhaust Duct 1/9

Thu 1/9/14 Mon 1/13/14 179,184,138FS12/23 12/5

20 days Thu 12/5/13 Wed 1/1/14 179

12/3

20 days

6 days

12/5

6 days 12/11 12/12

2 days ed 12/18/13 hu 12/19/13 191 12/11

Rough In Electrical Rough In Plumbing through Slab Rough In Plumbing into walls & Ceiling 6 days

Relocate Sprinklers

4 days

Install all Backing

12/18

2 daInystall Steel Supports for Countertop

10 days 12/18

Frame in Ceilings & Soffits 10 days 12/23

2 days on 12/23/13Tue 12/24/13 179,112

3 days Install Exhaust Hoods

3 dayIn s stall HVAC Equipment

Install Lighting

2 daInystall Dimmer Panel

12/25

2 daRyosugh In Emergency Lighting

1/14

2 daRyosugh In Inspections

205 206

FINISH CONSTRUCTION

207

Install Sheetrock @ Walls & Ceilings

3 days Thu 1/16/14Mon 1/20/14 204

208

Taping

7 days Tue 1/21/14Wed 1/29/14 207

209

Finish Electrical

15 days Thu 1/30/14Wed 2/19/14 208

1/30

15 days

210

Finish Painting & Wallcovering

25 days Thu 1/30/14 Wed 3/5/14 208

1/30

25 days

211

Finish HVAC

212

Finish Lighting & Dimmer System

213

Back of the House

242

Storefront

245

Kitchen & Bars

60 days? Thu 1/16/14 Wed 4/9/14

Taping Finish Electrical Finish Painting & Wallcovering 2/13 2/6

8 days Thu 2/6/14Mon 2/17/14 208FS+5 days,11

5 days

8 days

Finish HVAC Finish Lighting & Dimmer System

3 days Tue 1/28/14 Thu 1/30/14 48 days Mon 2/3/14 Wed 4/9/14

Install Stone @ Entry & Around Bars

4 days Thu 2/27/14

Install Wood Floor @ Dining

6 days Wed 3/5/14Wed 3/12/14 261,152

263

Install Carpet @ Dining

2 days Thu 3/13/14 Fri 3/14/14 262,156

2/27

Tue 3/4/14 252,144

4 days Install Stone @ Entry & Around Bars 3/5

6 days

Install Wood Floor @ Dining

3/13

2 dIanysstall Carpet @ Dining

3/13

1 dFianyal Inspections

4 daysMon 2/10/14 Thu 2/13/14

Finish All Low Voltage Wiring

271

Final Inspections

272

Punchlist

10 days

273

Install all FFE

10 days

274

Employee Training

10 days

1 day Thu 3/13/14 Thu 3/13/14 257,262,261

1 day

GRAND OPENING

Project: Mina Restaurant @ 101 C Date: Tue 9/17/13

7 days

25 days? Thu 1/30/14 Wed 3/5/14

262

275

3 days Install Sheetrock @ Walls & Ceilings 1/21

5 days Thu 2/13/14Wed 2/19/14 208FS+10 days

261

264

1/16

Fri 3/7/14 Thu 3/20/14 271FS-5 days Fri 3/7/14 Thu 3/20/14 271FS-5 days

Fri 3/7/14 Thu 3/20/14 271FS-5 days Fri 3/21/14

3/7

10 days

3/7

10 days

Punchlist Install all FFE

3/7

10 days

Employee Training 3/21

Fri 3/21/14 273,274

Task

Milestone

Project Summary

External Milestone

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

Deadline

Split

Summary

External Tasks

Inactive Task

Inactive Summary

Duration-only

Manual Summary

Finish-only

Progress

22 Tue 9/17/13

1G dRayAND OPENING


Pabu & Ramen Restaurants @ 101 California St

Schedule #2

Mina Group Build Group

I

INC

Subject to Change Sep 8, '13 Sep 15, '1 Sep 22, '1 Sep 29, '1 Oct 6, '13 Oct 13, '1 Oct 20, '1 Oct 27, '1 Nov 3, '1 Nov 10, ' Nov 17, '1Nov 24, ' Dec 1, '13 Dec 8, '13 Dec 15, '1 Dec 22, '1 Dec 29, '1 Jan 5, '14 Jan 12, '1 Jan 19, '1 Jan 26, '1 Feb 2, '14 Feb 9, '14 Feb 16, '1 Feb 23, '1 Mar 2, '1 Mar 9, '1 Mar 16, ' Mar 23, ' Mar 30, ' Apr 6, '14 Apr 13, '1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23 3/2 3/9 3/16 3/23 3/30 4/6 4/13

ID 1 2 3

Task Name

Duration

Start

Finish

Predecessors

112 days? Tue 9/10/13Wed 2/12/14

PRECONSTRUCTION Preselection of Consultants by Ownership

16 days Tue 9/10/13 Tue 10/1/13 12 daysMon 9/16/13 Tue 10/1/13

Contractor

4

RFP for Contractors

6 daysMon 9/16/13Mon 9/23/13

5

Contractors submit Proposals

5 days Tue 9/24/13Mon 9/30/13 4

6

Ownership selects Contractor

1 day Tue 10/1/13 Tue 10/1/13 5

7

Architect

16 days Tue 9/10/13 Tue 10/1/13

11

Structural Engineer

16 days Tue 9/10/13 Tue 10/1/13

9/16

6 days 9/24

RFP for Contractors 5 days 10/1

Contractors submit Proposals 1O dw aynership selects Contractor

15 16

Concept Drawing Stage

24 daysWed 10/2/13Mon 11/4/13

CONTRACT

38 daysWed 10/2/13 Fri 11/22/13

Schematic Drawing Stage

27 days Fri 10/11/13 on 11/18/13

Discovery

11 daysMon 10/7/13 on 10/21/13

23 24 30 31 39 40 45 46

Demolition Permit

7 days? Fri 10/11/13 on 10/21/13

47

Architect does Demolition Drawings

5 days Fri 10/11/13 hu 10/17/13 32FS-10 days

48

Submit for Demolition Permit (Over the Counter)

2 days Fri 10/18/13 on 10/21/13 47

10/11

5 days 10/18

Architect does Demolition Drawings 2 daysSubmit for Demolition Permit (Over the Counter)

49 50

MEPS Engineer by Architect (Design Build Option)

12 days Fri 10/11/13 on 10/28/13

Kitchen Drawings (Final)

24 daysWed 11/6/13Mon 12/9/13

MEPS Engineering Stage (Design Build Option)

14 days ue 10/29/13 Fri 11/15/13

55 56 64 65 72 73

Prebid MEPS & Drywall (Option)

12 days? Tue 11/5/13 ed 11/20/13

74

MEPS Contractors Agree to match their Original Bid

1 day on 11/18/13 on 11/18/13 68,69,70,71

75

Bid Drywall (Minimum of 3# bidders per trade)

10 days Tue 11/5/13 on 11/18/13 74FS-10 days

76

Confirm Budget for MEPS & Drywall with Schematic Budget

77

If confirmed then Build Group moves forward with Contract

11/18

1 dMaEyPS Contractors Agree to match their Original Bid

1 dayTue 11/19/13Tue 11/19/13 74,75 1 day? ed 11/20/13 ed 11/20/13 76

78 79

Design Development Stage

108 daysMon 9/16/13Wed 2/12/14 10/25

15 days

Architect does DD Drawings

80

Architect does DD Drawings

81

Architect Incorporate Discovery into DD Drawings

2 days Tue 10/8/13Wed 10/9/13 40FS-10 days

82

Architect incorporate MEPS Engineering Dwgs into DD Drawings

2 days on 11/18/13Tue 11/19/13 68,69,70,71

83

Architect Incorporate Kitchen Drawings into DD Drawings

2 days ed 11/13/13 hu 11/14/13 57

84

Build Group Revises Schedule for DD Drawings

2 days Fri 11/8/13 on 11/11/13 80FS-5 days

85

Ownership approves Final DD Drawings & Schedule

86

Build Group bids Final DD Drawings w/approved Schedule (Minimum of 3# bidders/t

87

Owner approves Final Budget

1 day Fri 12/6/13 Fri 12/6/13 86

88

Owner & BG meet & agree to a reduction of Construction Contingency

1 dayMon 12/9/13Mon 12/9/13 87

12/9

89

Final Contract Amount is incorporated into Approved Contract

1 dayTue 12/10/13Tue 12/10/13 88

12/10

90

Build Group issues Subcontracts to Subcontractors

1 day ed 12/11/13 ed 12/11/13 89

15 days Fri 10/25/13 hu 11/14/13 32 10/8

2 daAyrschitect Incorporate Discovery into DD Drawings 11/18 11/13 11/8

1 day Fri 11/15/13 Fri 11/15/13 84,80 15 days Fri 11/15/13 Thu 12/5/13 80

2 dAarycshitect incorporate MEPS Engineering Dwgs into DD Drawings

2 dAarycshitect Incorporate Kitchen Drawings into DD Drawings

2 daysBuild Group Revises Schedule for DD Drawings 11/15

1 dOawynership approves Final DD Drawings & Schedule

11/15

15 days

Build Group bids Final DD Drawings w/approved Schedule (Minimum of 3# bidders/trade) 12/6

1 dOawyner approves Final Budget 1 dOawyner & BG meet & agree to a reduction of Construction Contingency

12/11

1 dFianyal Contract Amount is incorporated into Approved Contract 1 dBauyild Group issues Subcontracts to Subcontractors

91 92

Permit Drawings Stage

45 days Fri 10/25/13 hu 12/26/13

95 96 97

108 daysMon 9/16/13Wed 2/12/14

Submittals

24 days ue 11/19/13 Fri 12/20/13

HVAC (Assuming Original Designer meets Budget)

98

HVAC Ductwork & Linear Diffusers

22 days ue 11/19/13 ed 12/18/13

102

HVAC Equipment

24 days ue 11/19/13 Fri 12/20/13

106

24 days ue 11/19/13 Fri 12/20/13

Electrical

107

Lighting

112

Dimmer System

116 117

5 days ue 11/19/13 on 11/25/13 24 days ue 11/19/13 Fri 12/20/13

Plumbing (Assuming Original Designer meets Budget)

Project: Mina Restaurant @ 101 C Date: Tue 9/17/13

24 days ue 11/19/13 Fri 12/20/13 24 days ue 11/19/13 Fri 12/20/13

Fixtures Task

Milestone

Project Summary

External Milestone

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

Deadline

Split

Summary

External Tasks

Inactive Task

Inactive Summary

Duration-only

Manual Summary

Finish-only

Progress

12 Tue 9/17/13


Pabu & Ramen Restaurants @ 101 California St

Schedule #2

Mina Group Build Group

I

INC

Subject to Change Sep 8, '13 Sep 15, '1 Sep 22, '1 Sep 29, '1 Oct 6, '13 Oct 13, '1 Oct 20, '1 Oct 27, '1 Nov 3, '1 Nov 10, ' Nov 17, '1Nov 24, ' Dec 1, '13 Dec 8, '13 Dec 15, '1 Dec 22, '1 Dec 29, '1 Jan 5, '14 Jan 12, '1 Jan 19, '1 Jan 26, '1 Feb 2, '14 Feb 9, '14 Feb 16, '1 Feb 23, '1 Mar 2, '1 Mar 9, '1 Mar 16, ' Mar 23, ' Mar 30, ' Apr 6, '14 Apr 13, '1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23 3/2 3/9 3/16 3/23 3/30 4/6 4/13

ID

Task Name

Duration

Start

Finish

121

Fire Protection (Assuming Original Designer meets Budget)

19 days ue 11/19/13 Fri 12/13/13

125

Millwork

45 days hu 12/12/13Wed 2/12/14

130

Storefront

33 days hu 12/12/13Mon 1/27/14

135

Kitchen & Bar (By Owner)

30 days Tue 12/10/13 Mon 1/20/14

139

Stone & Tile

Predecessors

101 daysMon 9/16/13 Mon 2/3/14

140

Quarry Tile

17 days hu 12/12/13

144

Ceramic Tile

28 days hu 12/12/13Mon 1/20/14 90

148

Stone Tops

38 days hu 12/12/13 Mon 2/3/14

152

Wood Flooring

27 daysMon 9/16/13 ue 10/22/13

156

Carpet

27 days hu 12/12/13 Fri 1/17/14

Fri 1/3/14

160 161 162

98 days? on 11/25/13 Wed 4/9/14

CONSTRUCTION

38 days on 11/25/13Wed 1/15/14

ROUGH CONSTRUCTION

11/25

163

MOBILIZATION

5 days on 11/25/13 Fri 11/29/13 29

164

Soft Demolition

6 days ue 11/26/13 Tue 12/3/13

167

Layout

5 days ue 11/26/13Mon 12/2/13

179

Install Walls

6 days ed 11/27/13Wed 12/4/13 168

180

Install Bar Dies

3 days Tue 12/3/13 Thu 12/5/13 174

181

Millworker Confirms Layout

182

Install Door Jambs

183

Install HVAC Ductwork

184

Install Exhaust Duct

8 days Fri 11/29/13Tue 12/10/13 171

185

Install Exhaust Hoods

3 days

186

Install HVAC Equipment

3 days on 12/23/13 ed 12/25/13 183,102

187

Rough In Electrical

188

Rough In Plumbing through Slab

6 days Tue 12/3/13Tue 12/10/13 174

189

Rough In Plumbing into walls & Ceiling

6 days Thu 12/5/13 hu 12/12/13 179

190

Relocate Sprinklers

6 days ed 12/11/13 ed 12/18/13 183

191

Install all Backing

4 days hu 12/12/13Tue 12/17/13 179FS+5 days

192

Install Steel Supports for Countertop

193

Frame in Ceilings & Soffits

10 days ed 12/11/13Tue 12/24/13 184,179,183

194

Install Lighting

10 days ed 12/18/13Tue 12/31/13 193FS-5 days,10

195

Install Dimmer Panel

196

Rough In Emergency Lighting

2 days ed 12/25/13 hu 12/26/13 193

197

Rough In Low Voltage

4 days Fri 12/27/13 Wed 1/1/14

204

Rough In Inspections

2 days Tue 1/14/14Wed 1/15/14 194,189,187,185

5 days MOBILIZATION

11/27

6days

Install Walls

12/3

3 dayIsnstall Bar Dies

11/29

1 day Fri 11/29/13 Fri 11/29/13 177

1 dMaiyllworker Confirms Layout 12/10

3 daysTue 12/10/13 hu 12/12/13 179FS+3 days 11/27

10 days ed 11/27/13Tue 12/10/13 168

3 dayIsnstall Door Jambs Install HVAC Ductwork

10 days

11/29

8 days

Install Exhaust Duct 1/9

Thu 1/9/14 Mon 1/13/14 179,184,138FS12/23 12/5

20 days Thu 12/5/13 Wed 1/1/14 179

12/3

20 days

6 days

12/5

6 days 12/11 12/12

2 days ed 12/18/13 hu 12/19/13 191 12/11

Rough In Electrical Rough In Plumbing through Slab Rough In Plumbing into walls & Ceiling 6 days

Relocate Sprinklers

4 days

Install all Backing

12/18

2 daInystall Steel Supports for Countertop

10 days 12/18

Frame in Ceilings & Soffits 10 days 12/23

2 days on 12/23/13Tue 12/24/13 179,112

3 days Install Exhaust Hoods

3 dayIn s stall HVAC Equipment

Install Lighting

2 daInystall Dimmer Panel

12/25

2 daRyosugh In Emergency Lighting

1/14

2 daRyosugh In Inspections

205 206

FINISH CONSTRUCTION

207

Install Sheetrock @ Walls & Ceilings

3 days Thu 1/16/14Mon 1/20/14 204

208

Taping

7 days Tue 1/21/14Wed 1/29/14 207

209

Finish Electrical

15 days Thu 1/30/14Wed 2/19/14 208

1/30

15 days

210

Finish Painting & Wallcovering

25 days Thu 1/30/14 Wed 3/5/14 208

1/30

25 days

211

Finish HVAC

212

Finish Lighting & Dimmer System

213

Back of the House

242

Storefront

245

Kitchen & Bars

60 days? Thu 1/16/14 Wed 4/9/14

Taping Finish Electrical Finish Painting & Wallcovering 2/13 2/6

8 days Thu 2/6/14Mon 2/17/14 208FS+5 days,11

5 days

8 days

Finish HVAC Finish Lighting & Dimmer System

3 days Tue 1/28/14 Thu 1/30/14 48 days Mon 2/3/14 Wed 4/9/14

Install Stone @ Entry & Around Bars

4 days Thu 2/27/14

Install Wood Floor @ Dining

6 days Wed 3/5/14Wed 3/12/14 261,152

263

Install Carpet @ Dining

2 days Thu 3/13/14 Fri 3/14/14 262,156

2/27

Tue 3/4/14 252,144

4 days Install Stone @ Entry & Around Bars 3/5

6 days

Install Wood Floor @ Dining

3/13

2 dIanysstall Carpet @ Dining

3/13

1 dFianyal Inspections

4 daysMon 2/10/14 Thu 2/13/14

Finish All Low Voltage Wiring

271

Final Inspections

272

Punchlist

10 days

273

Install all FFE

10 days

274

Employee Training

10 days

1 day Thu 3/13/14 Thu 3/13/14 257,262,261

1 day

GRAND OPENING

Project: Mina Restaurant @ 101 C Date: Tue 9/17/13

7 days

25 days? Thu 1/30/14 Wed 3/5/14

262

275

3 days Install Sheetrock @ Walls & Ceilings 1/21

5 days Thu 2/13/14Wed 2/19/14 208FS+10 days

261

264

1/16

Fri 3/7/14 Thu 3/20/14 271FS-5 days Fri 3/7/14 Thu 3/20/14 271FS-5 days

Fri 3/7/14 Thu 3/20/14 271FS-5 days Fri 3/21/14

3/7

10 days

3/7

10 days

Punchlist Install all FFE

3/7

10 days

Employee Training 3/21

Fri 3/21/14 273,274

Task

Milestone

Project Summary

External Milestone

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

Deadline

Split

Summary

External Tasks

Inactive Task

Inactive Summary

Duration-only

Manual Summary

Finish-only

Progress

22 Tue 9/17/13

1G dRayAND OPENING


5. Pre-Construction, General Condition and Fee’s


INC

Pre- Construction, General Conditions and Fee’s Pre-Construction Services (See Schedules for Details) - Weekly meetings w/Architect, Engineer’s, Suppliers - Detailed progress budgets on Schematics / DD’s / Progress to CD Permit - Value Engineering / Identifying “long-lead’ items - Pre-Construction scheduling / detailing the schedule w/Milestone objectives - Soliciting /budgeting w/sub-contractors / reviewing scope of work - Development of MEPS scope of work - Identifying and budgeting hard and soft costs in schematic drawings to permit set General Conditions - $8,000 per week - Project Executive - Project Manager - Project Coordinator - Full-time on site project superintendent - Debris boxes - Clean up - Plans and printing - Field office (Inside the space) includes supplies and phones - Small tools - Equipment rentals as needed - Temporary toilet and eye wash stations - Scaffolding and shoring if applicable - Safety Engineer - Coordination and permit pick up (Cost of permit is reimbursable) - Photographing job progress - Postage and Messenger - Coordination of Sample submittals - Weekly sub-contractor meetings on site - Project signage (State of CA.) mandatory / safety manuals on site / hazard materials information - Temporary lighting and spider boxes - Schedules - Three week look ahead schedule - Weekly Owner meetings on site Fee -

4.5% of total contract amount

Lump Sum- Builders Risk -

$5,000 Lump Sum Add $12,000 if Earthquake Insurance is Required


6. Insurance Documents


DATE (MM/DD/YYYY)

CERTIFICATE OF LIABILITY INSURANCE

09/13/2013

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). CONTACT 1-415-391-1500 PRODUCER LIC #0726293 NAME: FAX PHONE Arthur J. Gallagher & Co. Insurance Brokers of CA Inc. (A/C, No, Ext): 415-391-1500 (A/C, No): 415-391-1882 E-MAIL 1255 Battery Street #450 gcssfcerts@ajg.com ADDRESS: INSURER(S) AFFORDING COVERAGE

San Francisco, CA 94111 INSURER A : INSURED

INSURER B :

Build Group, Inc

NAIC #

OLD REPUBLIC GEN INS CORP NATIONAL UNION FIRE INS CO OF PITTS

24139 19445

INSURER C :

457 Minna Street

INSURER D :

San Francisco, CA 94103

INSURER E : INSURER F :

CERTIFICATE NUMBER: 35699876

COVERAGES

REVISION NUMBER:

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR LTR

A

ADDL SUBR INSR WVD

TYPE OF INSURANCE GENERAL LIABILITY

X

X

POLICY NUMBER

A1CG98751201

POLICY EFF (MM/DD/YYYY)

POLICY EXP (MM/DD/YYYY)

12/31/12 12/31/13

DAMAGE TO RENTED PREMISES (Ea occurrence)

X

COMMERCIAL GENERAL LIABILITY CLAIMSMADE

A

LED AUTOS X HIRED AUTOS X

UMBRELLA LIAB

1,000,000 100,000

GENERAL AGGREGATE

$

5,000 1,000,000 2,000,000

PRODUCTS - COMP/OP AGG

$

2,000,000

MED EXP (Any one person)

$

PERSONAL & ADV INJURY

$

$ X

AUTOMOBILE LIABILITY

ANY AUTO ALL OWNED

$

$ OCCUR

GEN'L AGGREGATE LIMIT APPLIES PER: PR POLICY LOC OX JE CT

X

B

X

LIMITS EACH OCCURRENCE

X

A1CA98751202

12/31/12 12/31/13 COMBINED SINGLE LIMIT (Ea accident) BODILY INJURY (Per person)

$

1,000,000 $

SCHEDU

BODILY INJURY (Per accident) $

AUTOS NONOWNED AUTOS

PROPERTY DAMAGE (Per accident)

$

COMP/COLL Ded :

$

1,000

EACH OCCURRENCE

$

AGGREGATE

$

5,000,000 5,000,000

X

EXCESS LIAB

BE060468834

OCCUR

12/31/12 12/31/13

CLAIMSMADE

DED X A

RETENTION $

10,000

WORKERS COMPENSATION AND EMPLOYERS' LIABILITY ANY PROPRIETOR/PARTNER/EXECUTIVE OFFICER/MEMBER EXCLUDED?

$

X

X

A1CW98751203

12/31/12 12/31/13

Y/N N/A

(Mandatory in NH)

If yes, describe under DESCRIPTION OF OPERATIONS below DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (Attach ACORD 101, Additional Remarks Schedule, if more space is required)

RE: Evidence of Insurance for RFP

WC STATUTORY LIMITS E.L. EACH ACCIDENT

OT HER $

1,000,000

E.L. DISEASE - EA EMPLOYEE $

1,000,000

$

1,000,000

E.L. DISEASE POLICY LIMIT


CERTIFICATE HOLDER RE: Evidence of Insurance for RFP Evidence of Insurance

CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE

, © ACORD 25 (2010/05) ranshargcs 35699876

1988-2010 ACORD CORPORATION. All rights reserved. The ACORD name and logo are registered marks of ACORD


buildgc.com 457 Minna Street, Suite 100 San Francisco, CA 94103 415-367-9399 info@buildgc.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.