PORTAFOLIO INSTALACIONES I

Page 1

PORTAFOLIO 2021-0

INST ALACIONES I

521

Jose Luis Reyes Ñique

MARIA CAMILA HEREDIA 2 0 1 8 2 1 3 9

Facultad de Ingenieria y Arquitectura Carrera de Arquitectura - Área de Construcción Ciclo 2021-0



CONTENIDO

G

GLOSARIO

4

EV1

DOTACIÓN DIARIA, VOLUMEN DE CISTERNA Y TANQUE ELEVADO

6

EV2

MEMORIA DESCRIPTIVA

10

EV3 EV4 EV5 EV6 EV7 EV8

CG 10

CG 7 / CG 11

LABORATORIO 1

RED DE AGUA FRÍA Y CALIENTE VIVIENDA UNIFAMILIAR

26

CG 1 / CG 5 / CG 8 / CG 9 / CG 10

PRÁCTICA DE AULA

RED DE AGUA FRÍA Y CALIENTE VIVIENDA UNIFAMILIAR

38

RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

42

CG 1 / CG 5 / CG 8 / CG 9 / CG 10

CG 1 / CG 5 / CG 6 / CG 8 / CG 9 / CG 10 / CG 11

LABORATORIO 2

RED DE DESAGÜE VIVIENDA UNIFAMILIAR CG 1 / CG 5 / CG 8 / CG 9 / CG 10

PRÁCTICA DE AULA

60

RED DE DESAGÜE VIVIENDA UNIFAMILIAR

78

RED DE DESAGÜE EDIFICIO EDIFICIO MULTIFAMILIAR

82

CG 1 / CG 5 / CG 8 / CG 9 / CG 10

CG 1 / CG 5 / CG 6 / CG 8 / CG 9 / CG 10 / CG 11


G

GLOSARIO

INSTALACIONES SANITARIAS Conjunto de tuberías de agua fría, caliente, desagües, pluviales, potabilización, accesorios,etc. que sirven para abastecer de agua potable y eliminarla a través de los desagües.

AGUAS SERVIDAS Aguas residuales domésticas que son el resultado de las actividades cotidianas de las personas, necesitan tratamiento que consiste en una serie de procesos para eliminar los contaminantes y hacerla apta para riego, entrega de ríos, mares y lagos.

TANQUE ELEVADO Estructura hidraulica de almacenamiento instalado en la parte superior de la edificación para reservar una cantidad de agua con la capacidad de satisfacer las necesidades del tipo de edificio.

CISTERNA Depósito subterraneo que tiene como función recoger el agua de la red publica y conservarla para luego succionarla mediante un bombeo e impulsarla hacia el tanque elevado para su proxima distribución.

4


TRAMPA P Conocida como una trampa de lavabo que se encuentra en la mayoría de los sumideros. Esta crea un sello de agua que evita que el olor de las alcantarillas pase a través de las tuberías del desagüe y la plomería hacia la casa.

MONTANTE DE DESAGÜE Tubería vertical de un sistema de desagüe que recibe la descarga de los ramales, comprendida entre el colector y la salida a los servicios para destinarlos a la caja de registro.

SISTEMA SÉPTICO Sistema de tratamiento primario que transforma los sólidos orgánicos en líquidos, gases y sólidos sedimentables, dentro de una cámara cerrada conocida como FOSA SÉPTICA para un tratamiento y luego llevarlo al destino final, la tierra.

DESAGÜE PLUVIAL Agua de lluvia proveniente de los techos, patios, azoteas y áreas expuestas que podrá ser conectada a la red pública del alcantarillado si es que la red lo permite. Cuando no exista un sistema de alcantarillado pluvial y la red pública haya sido diseñada para recibir aguas servidas únicamente, no se permitirá descargar a ellas las aguas de lluvia. Estas se dispondrán al sistema de drenaje o áreas verdes existentes.

5


EV1

DOTACIÓN DIARIA VOLUMEN DE CISTERNA Y TANQUE ELEVADO

6


OBJETIVO Comprobar y practicar los temas teóricos referidos a sistemas de alimentación en una vivienda o edificios de diferentes usos. Calcular la dotación diaria, el número de aparatos sanitarios, el volumen de la cisterna y el tanque elevado que requerirán las instalaciones utilizando el RNE III.3 Instalaciones Sanitarias, IS010.

REFLEXIONES El desarrollo de la practica fue de gran necesidad para el aprendizaje correcto del calculo de la dotación diaria y uso de la normativa. Se ubicaron las distintas tablas a usar tanto para la dotación como número de aparatos dependiendo del uso de la edificación.

7


EV1

8

DOTACIÓN DIARIA, VOLUMEN DE CISTERNA Y TANQUE ELEVADO


EV -1

9


EV2

10

MEMORIA DESCRIPTIVA


OBJETIVO El trabajo consistió en realizar la memoria descriptiva de una vivienda multifamiliar de 5 pisos y sotano que usariamos más adelante para desarrollar distintos encargos, como la red de agua y desague. Con esta primera aproximación, tendriamos los calculos e información necesaria a utilizar.

REFLEXIONES Se unificó todos los datos del proyecto y cálculos aprendidos en clase hasta el momento como, dotación diaria, cisterna y tanque elevado. Además, de repasar las normativas aplicadas en cuanto a instalaciones sanitarias y reglas debido a la ubicación del proyecto.

11


EV2

MEMORIA DESCRIPTIVA

TABLA DE CONTENIDO

1CAPÍTULO I: INTRODUCCIÓN Y ANTECEDENTES ............ 1 1.1

Datos Generales .................................................................... 1

1.2

Objeto del Proyecto .............................................................. 1

1.3

Situación y Emplazamiento .................................................. 1

1.4

Topografía ............................................................................ 2

1.5

Accesos ................................................................................ 2

1.6

Alturas .................................................................................. 2

1.7

Descripción Funcional por Niveles ....................................... 2 1.7.1Planta 1................................................................................. 3 1.7.2Planta 2................................................................................. 3 1.7.3Planta 3................................................................................. 3 1.7.4Planta 4................................................................................. 3 1.7.5Planta 5................................................................................. 3 1.7.6Planta del Sótano .................................................................. 3

1.8

Cuadro de Superficies ........................................................... 4

1.9

Número de Usuarios de la Edificación (Aforo) ..................... 4

2CAPÍTULO II: NORMATIVA TÉCNICA .................................. 5 2.1

Justificación del cumplimiento de la Normativa Técnica ...... 5

2.2

TITULO I: GENERALIDADES .......................................... 5 2.2.1Norma G.010 Consideraciones Básicas ................................ 5 2.2.2Norma G.020 Principios Generales....................................... 5 2.2.3Norma G.030 Derechos y Responsabilidades ....................... 5 2.2.4Norma G.050 Seguridad Durante la Construcción ................ 6

2.3

TITULO II: HABILITACIONES URBANAS...................... 6 2.3.1Norma GH.020 Componentes de Diseño Urbano ................. 6

2.4

12

Tipos de Habilitaciones ........................................................ 6


EV -2

2.4.1Norma TH.010 Habilitaciones Residenciales ........................ 6 2.5

Obras de Saneamiento .......................................................... 6 2.5.1Norma OS.010 Captación y Conducción de Agua para consumo

humano ……………………………………………………………….6 2.5.2Norma OS.020 Plantas de Tratamiento de Agua para consumo humano ……………………………………………………………….7 2.5.3Norma OS.030 Almacenamiento de Agua para consumo humano 7 2.5.4Norma OS.040 Estaciones de Bombeo de Agua para consumo humano ……………………………………………………………….7 2.5.5Norma OS.050 Redes de Distribución de Agua para consumo humano ……………………………………………………………….7 2.5.6Norma OS.100 Consideraciones Básicas de Diseño de Infraestructura Sanitaria ....................................................................... 7 2.6

TÍTULO III: EDIFICACIONES ........................................... 7 2.6.1Norma GE.010 Alcances y Contenidos ................................. 8 2.6.2Norma GE.020 Componentes y Características de los Proyectos 8 2.6.3Norma GE.030 Calidad en la Construcción .......................... 8 2.6.4Norma GE.040 Uso y Mantenimiento................................... 8

2.7

Arquitectura.......................................................................... 8 2.7.1Norma A.010 Consideraciones generales de Diseño ............. 8 2.7.2Norma A.020 Vivienda ......................................................... 8 2.7.3Norma A.120 Accesibilidad para personas con discapacidad y de

las personas adultas mayores ................................................................ 9 2.7.4Norma A.130 Requisitos de Seguridad ................................. 9 2.8

Instalaciones Sanitarias ......................................................... 9 2.8.1Norma IS.010 Instalaciones Sanitarias para edificaciones .... 9 2.8.2Norma IS.020 Tanques Sépticos ........................................... 9

13


MEMORIA DESCRIPTIVA

3CAPÍTULO III: MEMORIA CONSTRUCTIVA ........................ 10 3.1 Instalaciones ......................................................................... 10 3.1.1Instalaciones de Saneamiento ............................................... 10 CAPÍTULO IV: MEMORIA DE CÁLCULO DE INSTALACIONES SANITARIAS ..................................................................................... 11

14

4.1

Datos de Diseño ................................................................. 11

4.2

Cálculos de los componentes del sistema ............................ 11


EV -2

En la siguiente tabla se detallan los parámetros urbanísticos más importantes que se deben de tener en cuenta a la hora de realizar el proyecto. PARÁMETROS NORMATIVOS AL ÁREA DEL LOTE ZONIFICACIÓN

Zona urbana RDM (Residencial de densidad media)

SECTOR DE ÍNDICE DE USOS

B

USOS PERMISIBLES

Vivienda

USOS COMPATIBLES

Uso Residencial

LOTE NORMATIVO MÍNIMO

150 m2

ÁREA LIBRE

30% mínimo

ALTURA MÁXIMA

10 pisos

RETIRO FRONTAL

4.28 m Frente a Jr. Juan Fanning y 2.53 m Frente a Jr. Soldado Cabada

FRENTE GRÁFICO DEL LOTE

35.51 m Frente a Jr. Juan Fanning y 49.96 m Frente a Jr. Soldado Cabada

ESTACIONAMIENTO

1 cada 2 viviendas Tabla 1 Parámetros urbanísticos del terreno

1.4

Topografía

El lote no presenta desniveles apreciables en el nivel de la calle. 1.5

Accesos

La edificación “Vivienda multifamiliar” tendrá un ingreso vehicular por Jr. Juan Fanning y un ingreso peatonal por Jr. Soldado Cabada. 1.6

Alturas

Respetando los límites dictados por los parámetros urbanísticos, los cuales permiten tener una altura de 10 pisos, el proyecto a tratar consta de 5 pisos con una altura entre pisos de 3 metros y altura total de 18 metros.

15


MEMORIA DESCRIPTIVA

16


NIVELES 1. SÓTANO 1 2. PLANTA 1 3. PLANTA 2 4. PLANTA 3 5. PLANTA 4 6. PLANTA 5 TOTAL 1.9

m2 CONST. 1526.41 1187.45 1160.17 894.33 944.23 894.33 6606.92

EV -2

Número de Usuarios de la Edificación (Aforo)

Respetando los límites dictados por el CENEPRED en las Normas de Inspecciones Técnicas de Seguridad en Edificaciones, en el Anexo 6, se realizó el cálculo del aforo público y de empleados. Ambiente

m2/persona

NIVEL 1 Cafetería 9.3 Viviendas Gimnasio 4.6 TOTAL NIVEL 2 Cafetería 9.3 Viviendas TOTAL NIVEL 3 Viviendas TOTAL NIVEL 4 Viviendas TOTAL NIVEL 5 Viviendas TOTAL TOTAL DEL AFORO DE LA EDIFICACIÓN

m2

Aforo PÚBLICO

Aforo EMPLEADOS

131.22 80.51

14 17 18 49

14 14

60.29 -

6 13 19

6 6

-

28 28

0

-

13 13

0

-

19 19 128

0 20

17


MEMORIA DESCRIPTIVA

18


EV -2

19


MEMORIA DESCRIPTIVA

20


EV -2

21


MEMORIA DESCRIPTIVA

CAPÍTULO III: MEMORIA CONSTRUCTIVA En el presente documento se efectuará una descripción y justificación de cada una de las soluciones propuestas para llevar a término la construcción de las instalaciones sanitarias de una vivienda multifamiliar del proyecto. 3. 8

Instalaciones

3.8.1 Instalaciones de Saneamiento El saneamiento horizontal de la edificación se resuelve mediante tubos de PVC con los diámetros indicados en los planos. Su pendiente no será inferior al 1%. Los desagües de los aparatos sanitarios se realizarán en PVC de los diámetros indicados en los planos. Todos los aparatos contarán con sifón individual y rebosadero. El trazado de la red horizontal de saneamiento se ejecuta para conseguir una circulación natural y no expuesta a obstrucciones. Como norma general, se evitan los cambios bruscos de dirección y pendiente, y los codos de 90º. En los cambios de dirección de más de 45º de desviación se prevé un registro. Las tuberías atravesarán perpendicularmente los muros y llevarán pasamuros. La conexión con el alcantarillado urbano se hará a través de un pozo de acometida preexistente, donde verterá la red general de saneamiento, según puede observarse gráficamente. Para el cálculo del diámetro de las tuberías de agua se utilizarán las unidades de gasto y se empleará el método de HUNTER. Materiales Toda la red se ejecutará con tubería de PVC. Red de saneamiento y pequeña evacuación Para la determinación de los diámetros de tubería de PVC en aguas sanitarias partimos de un coeficiente que denominamos unidad de descarga (UD), dado en función de los diferentes aparatos. Una vez sumadas las unidades de descarga, calculamos el diámetro del colector de PVC correspondiente según el Anexo nº8 del RNE.

22


EV -2

CAPÍTULO IV: MEMORIA DE CÁLCULO DE INSTALACIONES SANITARIAS Se refiere a las instalaciones sanitarias de agua y desagüe para una vivienda multifamiliar. 4.1

Datos de Diseño

Todo el diseño de las instalaciones nuevas se realizará conforme al Reglamento Nacional de Edificaciones (R.N.E.) IS.010 vigente. 4.2

Cálculos de los componentes del sistema ▪ Cálculo de la Dotación de Agua Fría

Según los planos de Arquitectura, en la edificación se ha proyectado un edificio multifamiliar que contiene: 1 departamento de 4 dormitorios, 7 departamentos de 3 dormitorios, 11 departamentos de 2 dormitorios, 3 departamentos de 1 dormitorio, 1 cafetería y 1 gimnasio. Por tanto, la dotación diaria estimada se presenta en el siguiente cuadro. CÁLCULO DE DOTACIÓN DE AGUA DIARIA ESPACIO

Medida

Dotación L/m2

Total

Dpto. de 3 dormitorios

7u

1200

8400

Dpto. de 2 dormitorios

11u

850

9350

Dpto. de 1 dormitorio

3u

500

1500

Dpto. de 4 dormitorios

1u

1350

1350

Área verde

575.92 m2

2

1151.84

Cafetería

186.39 m2

40

7455.6

Gimnasio

80.39 m2

30

2411.7

Estacionamientos

1526.41 m2

2

3052.82

TOTAL en litros

34671.96

23


MEMORIA DESCRIPTIVA

Los parámetros de diseño a utilizar en el presente estudio son los indicados en el “Reglamento Nacional de Edificaciones IS.010” de Instalaciones Sanitarias del Reglamento Nacional de Construcciones.

x

Cálculo del Volumen mínimo de la Cisterna

CÁLCULO DEL VOLUMEN MÍNIMO DE CISTERNA VolCist-mínimo = ¾ x Dotación diaria de la Vivienda Multifamiliar VolCist-mínimo = ¾ x 34.67 VolCist-mínimo = 27.00 x

m3

Cálculo de dimensiones de la cisterna

CÁLCULO DE DIMENSIONES DE CISTERNA H = 1.7

largo x ancho = 15.88

hf = 2

largo=5.64

dimensiones del agua

1.7 x 5.64 x 2.82

27.03m3

dimensiones físicas

2 x 5.64 x 2.82

31.81 m3

x

ancho= 2.82

Cálculo del Volumen mínimo del Tanque Elevado

CÁLCULO DEL VOLUMEN MÍNIMO DE TANQUE ELEVADO VolTanque-mínimo = 1/3 x Dotación diaria de la Vivienda Multifamiliar VolTanque-mínimo = 1/3 x 34.67 VolTanque-mínimo = x

11.57

m3

Cálculo de dimensiones del Tanque Elevado

CÁLCULO DE DIMENSIONES DEL TANQUE ELEVADO H = 1.5 hf = 1.8 dimensiones del agua dimensiones físicas

largo x ancho = 7.71 largo=2.5 1.5 x 2.5 x 3.09 1.8 x 2.5 x 3.09

ancho= 3.09 11.59 m3 13.91 m3 12

24


EV -2

x

Cálculo de las redes interiores de agua potable y desagüe

El cálculo de las redes interiores de agua potable y desagüe se realizó con los gastos probables, obtenidos según el número de unidades de gasto de los aparatos sanitarios a servir de acuerdo al método de HUNTER. En el Reglamento Nacional de Edificaciones, en su Título III, IS-0.10 Instalaciones Sanitarias para Edificaciones, en sus Anexos 1, 3, 8 y 9. En los siguientes cuadros se presentan las unidades Hunter de demanda y descarga de agua. NÚMERO DE INSTALACIONES SANITARIAS Y UNIDADES HUNTER Gasto Aparatos N° U.H. U.H. U.H. Edificación probable Sanitarios Aparatos p/Aparato Totales Total (l/s) Inodoro 68 6 408 Tina 43 2 86 Vivienda 674 Multifamiliar Lavadero 24 3 72 6.22 Lavatorio

108

1

108 TOTAL

674

En los cuadros anteriores se indica el gasto probable de 6.22 l/s aplicado con el método Hunter. Con ello se calcula que el diámetro del tubo de impulsión es de 2 1/2 pulgadas y el de succión de 3 pulgadas en función del gasto de bombeo.

13 25


EV3

LABORATORIO 1 RED DE AGUA FRÍA Y CALIENTE VIVIENDA UNIFAMILIAR

26


OBJETIVO Recopilar los datos en un informe sobre la clase de laboratorio virtual acerca de las redes de agua fría y agua caliente, en el que se observaron los materiales, herramientas, recomendaciones y pruebas para la instalación correcta del mismo.

REFLEXIONES Este trabajo fue de gran ayuda ya que se pudo reconocer los materiales y herramientas correctas a utilizar para cada instalación junto con sus recomendaciones en cuanto a calidad. Además, la cantidad y resultado de la prueba adecuada para confirmar una correcta instalación de la red de agua fría y caliente en su totalidad.

27


EV3

LABORATORIO 1

TABLA DE CONTENIDO

1 OBJETIVOS GENERALES

1

2 HERRAMIENTAS

2

2.1.

Cortador de tubo

2

2.2.

Pegamento

2

2.3.

Niple

3

2.4.

Formador de empaques

3

2.5.

Llave Stilson o llave francesa

4

3 MATERIALES

4

3​.1.

4

3​.2

AGUA FRÍA 3​.1.1 Tubo PVC

4

3​.1.2 Polipropileno

4

AGUA CALIENTE 2.2.1 Tubo CPVC

3​.3

3​.4

28

ACCESORIOS

5 5 5

3​.3.1 De presión

6

3​.3.2 Con unión roscada

6

VÁLVULAS

6

3​.4.1 Válvula esférica

6

3​.4.2 ​ Válvula de compuerta

6

3​.4.3 ​ Válvula check

7

4 FABRICACIÓN DE LLAVE

7

5 PRUEBA HIDRÁULICA

8

6 RECOMENDACIONES Y CONCLUSIONES

9

6​.1

9

RECOMENDACIONES 6​.1.1 ​ Tuberías y conexiones a presión de PVC

9

6​.1.2 ​ Productos con unión roscada

9

6​.1.3 ​ Válvula Check

9


EV -3

29


LABORATORIO 1 2.3

NIPLE Son tubos pequeños cortados, pueden ser hechos a mano, cortando un tubo de PVC (a presión) o prefabricados (roscado).

NIPLE ROSCADO

2.4

NIPLE A PRESIÓN

FORMADOR DE EMPAQUES Adhesivo líquido con mayor viscosidad lo que permite lograr mayor resistencia. Además, sella empaquetaduras tanto en frío como en caliente.

3

30


EV -3

31


LABORATORIO 1

32


EV -3

33


LABORATORIO 1

34


EV -3

35


LABORATORIO 1

36


EV -3

11

37


EV4

PRÁCTICA DE AULA RED DE AGUA FRÍA Y CALIENTE VIVIENDA UNIFAMILIAR

38


OBJETIVO Diseñar la red de agua caliente y agua fría en una vivienda unifamiliar, agregando sus accesorios desde la red pública, cisterna, conexiones a aparatos sanitarios, terma y tanque elevado con sus respectivos diámetros.

REFLEXIONES En esta segunda práctica de aula se comprobó los temas aprendidos en cuanto al diseño y calculo de dotación, con un mayor diseño general y el metrado de un baño específico. Se completó satisfactoriamente la segunda parte, y a pesar de no completar la primera asignatura se logró con un resultado satisfactorio. Además, se corrigieron los temas faltantes para esta entrega.

39


EV4

PRÁCTICA DE AULA: RED DE AGUA FRÍA Y CALIENTE VIVIENDA UNIFAMILIAR

PREGUNTA 1:

L

E

Y

E

SIMBOLOGIA

1.- REALICE EL DISEÑO DE LA RED DE AGUA FRIA Y CALIENTE 2.- COLOQUE LOS DIAMETROS DE LA TUBERIA 3.- UBIQUE LA CISTERNA Y EL TANQUE ELEVADO 4.- UBIQUE LA VALVULA DE PIE 5.- UBIQUE LA BOMBA DE AGUA 6.- UBIQUE EL CALENTADOR DE AGUA 7.- VALVULA CHECK 8.- LLAVES COMPUERTAS O VALVULAS ESFERICAS 9.- MEDIDOR DE AGUA 10.- DOTACION DIARIA 11.- UNIDADES HUNTER

N

BOMBA

VALVULA ESFERICA

VALVULA CHECK

VALVULA FLOTADOR Ø1/2"

Ø1"

Ø3/4"

Ø 1 1/4"

DIAMETRO DE TUBERIAS TUBERIA DE AGUA FRIA TUBERIA DE AGUA CALIENTE REDUCCION

TH

CALENTADOR

MEDIDOR

CTO. SERV.



BAÑO SERV.

PATIO DE SERVICIO LAVANDERIA

JARDÌN

TERRAZA

BAÑO DORMITORIO

COMEDOR

COCINA 

10

9

8

7

6

5

4

3

8

7

6

5

4

3

2

DORMITORIO

11

SALA vestidor

12

1

16

15

14

13

BAÑO



HALL 

DORMITORIO

BAÑO

HALL DE DISTRIBUCIÓN

vestidor



GARAJE

Ø3/4"

INGRESO DORMITORIO

2

1

PLANTA 1°PISO esc. 1/50

40

D

DESCRIPCION

PLANTA 2°PISO

PLANTA TECHO

esc. 1/50

esc. 1/50

A


EV -4

PREGUNTA 2:

RALICE EL SIGUIENTE METRADO

METRADO 1/2"

MATERIALES CODOS FG BRONCE PESADO CODOS TEES PVC UNIONES UNIVERSALES VALCULAS ESFÉRICAS

3 4 2 0 0

REDUCCIÓN DE 3/4" A 1/2"

AF PVC

3/4"

AC CPVC 1/2"

0 6 0 2 1

2 11 1 2 1

1

TUBERIA

2.57 0.16 0.55 0.16 0.15 0.16 1.1

3.28 1.33 0.16 0.3 0.3

TOTAL

4.85

5.37

INODORO LAVATORIO LAVADERO DUCHA TINA

EQUIPOS

UNIDADES HUNTER U.G CANT. 1.5 1 2 1 3 0 2 1 2 0 TOTAL U.G GASTO PROBABLE

3.17 1.06 0.27 0.27 0.27 2.19 0.3 0.3 0.27 0.55 0.27 2 10.92

SUB TOTAL 1,5 2 2 5.5 0,24

41


EV5

RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

42


OBJETIVO Con las pautas aprendidas en clase, realizar un diseño de la red total de agua fría y agua caliente de una vivienda multifamiliar.

REFLEXIONES Al ser el primer trabajo de diseño en grupo, se logro llegar al objetivo propuesto, con todos los requerimientos a desarrollar. La uniformidad era un tema escencial, ya que habían algunos departamentos parecidos o iguales. Además, gracias a la crítca se llego a un buen resultado y ahora en esta entrega actual se corrigió el elemento faltante que se tuvo en la entrega.

43


EV5

RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR A

B

C

8.58

8.50

8.50

6.50

1

B

6.50

2

3

6.50

Ø2 1/2"

Ø1/2"

Ø1/2"

Ø2 1/2" Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

4 Ø1/2"

Ø2 1/2"

6.50

Ø1/2"

5.00

5

6

8.57

A

44

8.53

B

8.47

C


EV -5 D

A

E

8.50

F

G

8.50

7.39

1 Ø2 1/2"

Ø2 1/2"

Ø3"

6.50

31.81 M3 Ø2 1/2"

B' Ø2 1/2"

6.50

2

Ø2 1/2"

6.50

3

Ø2 1/2"

4

Ø2 1/2"

6.50

Ø2 1/2"

5.00

5

6

N

8.50

D

A'

8.50

SÓTANO

7.51 0

E

F

1

2

3

G

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR PLANTA SOTANO

G-3

A-01

45


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

8.58

8.50

A

8.50

B

C

6.50

1

Ø3/4"

B

Ø3/4"

Ø1"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1"

Ø3/4" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2" Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4" Ø1/2"

2

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1" Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1" Ø1"

Ø1"

Ø1/2" Ø1"

Ø1"

Ø1"

TH

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø1"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

6.50

Ø1" Ø1/2"

Ø1/2"

Ø1/2"

Ø1" Ø1"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

3

Ø1/2"

Ø1" Ø1-1/2"

Ø1-1/2"

Ø1-1/4"

Ø1-1/2"

Ø1-1/4"

Ø1-1/4"

Ø1-1/4"

Ø1-1/4" Ø3/4"

Ø1" Ø1"

Ø1"

Ø1"

6.50

Ø1"

Ø1/2"

Ø1"

Ø1"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

Ø1"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1"

Ø3/4"

Ø1/2"

TH

Ø1"

Ø1/2"

4

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø1/2"

Ø1/2" Ø1"

Ø1/2"

Ø1/2" Ø1/2"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4" Ø1/2" Ø3/4" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø3/4" Ø3/4"

Ø1/2"

Ø1/2" Ø3/4"

Ø1/2"

Ø3/4" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø3/4" Ø3/4"

Ø3/4"

Ø3/4"

6.50

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

5

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

5.00

Ø1/2"

6 Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

8.57

A

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

8.53

B

8.47

C

JR. SOLDADO CAB

46


EV -5

8.50

D

8.50

7.39

E

A

F

G

1 Ø2 1/2"

Ø2 1/2"

Ø2 1/2"

6.50

Ø3/4"

B'

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

2

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

6.50

Ø3/4"

Ø1/2" Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

3 Ø1"

Ø1"

Ø1"

Ø1"

Ø1"

Ø1"

Ø1" Ø3/4" Ø1" Ø1-1/4"

Ø1/2"

Ø3/4"

Ø1-1/4" Ø1"

Ø1"

Ø1"

Ø1/2"

6.50

Ø1/2"

Ø1"

Ø1/2"

Ø1"

Ø1"

Ø1"

Ø1" Ø3/4" Ø1/2"

Ø1"

Ø1/2"

Ø1"

Ø1" Ø1"

Ø1"

Ø1/2" Ø1"

Ø1"

Ø3/4"

Ø1/2"

Ø1/2"

TH

Ø3/4"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

Ø3/4" Ø1/2"

Ø3/4"

Ø1"

4

Ø3/4" Ø1/2"

Ø1/2"

Ø1" Ø1/2"

Ø3/4"

TH Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2" Ø1/2"

Ø1"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1"

Ø3/4"

Ø1"

Ø1/2" Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2" Ø3/4"

Ø1/2" Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

6.50

Ø1" Ø1"

Ø1/2" Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

5.00

5

6 Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

N PLANTA 1 0

8.50

D

A'

8.50

E

1

2

3

7.51

F

G

BADA

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR PRIMERA PLANTA

G-3

A-02

47


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

A

B 8.58

C 8.50

8.50

6.50

1

B

Ø3/4"

Ø3/4" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2" Ø1"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2"

Ø1"

Ø1/2" Ø3/4"

2

Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø3/4"

Ø1"

Ø1" Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

TH

Ø3/4"

Ø1"

Ø1"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1"

Ø3/4" Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1"

6.50

Ø3/4"

Ø1"

3 Ø1"

Ø1 1/4"

Ø1 1/4"

6.50

Ø1 1/4"

Ø3/4"

Ø3/4" Ø3/4" Ø3/4" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

4

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

6.50

Ø3/4"

Ø1/2" Ø1/2" Ø1/2" Ø1/2"

5

5.00

Ø1/2"

6

8.50

8.58

A

48

B

8.50

C


EV -5

D

E

A

F

8.50

G 7.39

8.50

6.50

1

B'

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø3/4" Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2" Ø1/2"

Ø1"

Ø3/4"

Ø1/2"

Ø3/4"

2

Ø1/2" Ø3/4"

Ø1" Ø3/4" Ø1/2"

Ø1"

Ø1" Ø3/4"

Ø1/2"

TH

Ø3/4"

Ø1/2" Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

Ø1"

Ø1" Ø1/2"

Ø1" Ø3/4"

Ø1"

Ø1"

6.50

Ø1"

Ø3/4"

Ø1"

Ø1"

Ø1 1/4"

3 Ø1"

Ø1 1/4"

Ø1 1/4"

6.50

Ø1 1/4"

Ø1"

Ø1"

Ø1"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4" Ø1"

Ø1"

Ø3/4"

TH

Ø1"

Ø3/4"

Ø1/2"

Ø3/4" Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

Ø1/2"

4

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

6.50

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4" Ø3/4"

Ø3/4"

5.00

5

6

N

8.50

D

A'

8.50

7.51

PLANTA 2 E

F

G

0

1

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

2

3

EDIFICIO MULTIFAMILIAR SEGUNDA PLANTA

G-3

A-03

49


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

A

B

C

8.58

8.50

8.50

6.50

1

B

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2"

Ø1"

Ø1/2" Ø3/4"

Ø1/2" Ø1/2"

2

Ø1/2" Ø1/2"

Ø3/4"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

TH

Ø1/2"

Ø3/4" Ø3/4"

Ø3/4" Ø3/4"

Ø1"

Ø3/4"

Ø1"

Ø1"

6.50

Ø3/4"

3 Ø1"

Ø1 1/4"

6.50

Ø1 1/4"

Ø1" Ø1 1/4"

Ø1"

Ø3/4"

Ø1 1/4"

Ø3/4"

Ø1/2" Ø3/4"

Ø3/4"

Ø1"

Ø1/2"

TH

4

Ø1/2"

Ø1/2" Ø1/2" Ø1/2"

Ø1/2" Ø3/4"

Ø1"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1"

6.50

Ø3/4"

Ø1"

Ø1"

Ø3/4" Ø3/4" Ø3/4"

Ø1/2" Ø3/4"

Ø3/4"

Ø1"

Ø1/2"

TH

5

Ø1/2"

Ø1/2" Ø1/2" Ø1/2"

Ø1/2" Ø3/4"

Ø1"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

5.00

Ø3/4"

6

8.57

A

50

8.50

B

8.50

C


EV -5

D

E

A

F

8.50

G 7.39

8.50

6.50

1

B'

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4" Ø1/2"

Ø1/2"

Ø1"

Ø1"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2" Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

2

Ø3/4"

Ø1" Ø3/4" Ø1/2" Ø1" Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

TH

Ø3/4"

Ø1"

Ø1/2"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø3/4"

6.50

Ø1"

Ø1"

Ø1"

3 Ø1"

6.50

Ø1 1/4"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1"

Ø1" Ø3/4"

Ø3/4"

Ø1" Ø3/4"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

TH

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1"

Ø1" Ø1/2"

TH

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2" Ø3/4" Ø1"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4" Ø1"

Ø1/2" Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

6.50

Ø3/4"

4

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø1"

Ø1"

Ø3/4"

5.00

5

6

N

8.50

D

A'

8.50

E

7.51

F

PLANTA 3 G

0

1

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

2

3

EDIFICIO MULTIFAMILIAR TERCERA PLANTA

G-3

A-04 51


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

A

B 8.58

C 8.50

8.50

6.50

1

B

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2"

Ø1"

Ø1/2" Ø3/4"

Ø1/2" Ø1/2"

2

Ø1/2" Ø1/2"

Ø3/4"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

TH

Ø1/2"

Ø3/4" Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø1" Ø1"

Ø1"

6.50

Ø3/4"

Ø1"

3 Ø1"

Ø1 1/4"

6.50

Ø1 1/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

4

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

6.50

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

5.00

5

6

8.58

A

52

8.50

B

8.50

C


EV -5

D

E

A

F

8.50

G

8.50

7.39

6.50

1

B'

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4" Ø1/2"

Ø1/2"

Ø1"

Ø1"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2" Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

2

Ø3/4"

Ø1" Ø3/4" Ø1/2" Ø1" Ø3/4"

Ø1/2" Ø1/2"

Ø1"

Ø3/4"

Ø1/2" Ø1" Ø1/2"

Ø1/2"

TH

Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø3/4"

6.50

Ø1"

Ø1"

Ø1" Ø1 1/4"

3 Ø1"

Ø1 1/4"

6.50

Ø1 1/4"

Ø1"

Ø1"

Ø1" Ø3/4"

Ø1"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

TH

Ø1"

Ø3/4"

Ø3/4"

Ø1" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

6.50

Ø1/2" Ø1/2"

4

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4" Ø3/4"

Ø3/4"

5.00

5

6

N

8.50

D

A'

7.51

8.50

E

F

PLANTA 4 G

0

1

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

2

3

EDIFICIO MULTIFAMILIAR CUARTA

PLANTA

G-3

A-05

53


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

A

B

C

8.58

8.50

8.50

6.50

1

B

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2"

Ø1"

Ø1/2" Ø3/4"

Ø1/2" Ø1/2"

2

Ø1/2" Ø1/2"

Ø3/4"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø1/2"

Ø1/2"

Ø1"

Ø1"

Ø3/4"

TH

Ø1/2"

Ø3/4"

Ø3/4" Ø3/4"

Ø1"

Ø3/4"

Ø1"

Ø1"

6.50

Ø3/4"

Ø1"

3 Ø1"

Ø1 1/4"

Ø1 1/4"

6.50

Ø1 1/4"

Ø3/4"

Ø1 1/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø1/2"

Ø3/4" Ø3/4"

Ø1/2"

Ø3/4"

TH

4

Ø1 1/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2" Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø3/4"

Ø3/4"

6.50

Ø3/4"

Ø3/4" Ø3/4" Ø3/4"

Ø3/4"

Ø3/4"

Ø3/4" Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4"

TH

5

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2" Ø3/4"

Ø3/4" Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø3/4"

Ø1/2" Ø1/2"

Ø3/4"

5.00

Ø3/4"

Ø3/4" Ø3/4"

6

8.57

A

54

8.50

B

8.50

C


EV -5

D

E

A

F

8.50

G 7.39

8.50

6.50

1

B'

Ø3/4"

Ø3/4"

Ø3/4"

Ø1/2" Ø1/2"

Ø3/4" Ø1"

"

Ø1/2"

Ø1/2"

Ø1"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2" Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

2

Ø3/4"

Ø1" Ø3/4" Ø1/2" Ø1" Ø3/4"

Ø1/2" Ø1/2"

Ø1"

Ø3/4"

Ø1/2" Ø1" Ø1/2"

Ø1/2"

TH

Ø3/4"

Ø1/2"

Ø1"

Ø1/2"

Ø1" Ø3/4"

Ø3/4"

6.50

Ø1"

Ø1"

Ø1" Ø1 1/4"

3 Ø1"

Ø1 1/4"

6.50

Ø1 1/4"

Ø3/4"

Ø1"

Ø1"

Ø1" Ø3/4"

Ø3/4"

Ø1" Ø3/4" Ø3/4"

Ø3/4"

TH

Ø1"

Ø3/4"

4

Ø1/2" Ø3/4"

Ø3/4"

Ø1" Ø1/2"

Ø1"

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø3/4" Ø1/2"

Ø1/2"

Ø1"

Ø1/2"

Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø1/2" Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

TH

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø3/4"

Ø1/2"

Ø1/2"

Ø1/2"

Ø3/4"

Ø3/4"

Ø1/2"

6.50

Ø3/4" Ø1/2"

Ø1/2"

Ø3/4" Ø3/4" Ø3/4" Ø3/4" Ø3/4" Ø3/4"

5

5.00

Ø3/4"

Ø3/4"

6

N

8.50

8.50

D

A'

E

7.51

F

PLANTA 5 G

0

1

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

2

3

EDIFICIO MULTIFAMILIAR QUINTA

PLANTA

G-3

A-06

55


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

A

B 8.58

C 8.50

8.50

6.50

1

B

2

6.50

Ø2 1/2"

Ø2 1/2"

Ø2 1/2"

3 Ø2 1/2"

Ø2 1/2"

6.50

Ø2 1/2"

6.50

4

5.00

5

6

8.57

A

56

8.50

B

8.50

C


EV -5

D

A

E

8.50

F

G 7.39

8.50

6.50

1

B'

6.50

2

6.50

3

6.50

4

5.00

5

6

N

8.50

D

A'

8.50

E

7.51

F

AZOTEA G

0

1

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

2

3

EDIFICIO MULTIFAMILIAR PLANTA

AZOTEA

G-3

A-07

57


RED DE AGUA FRÍA Y CALIENTE VIVIENDA MULTIFAMILIAR

TANQUE ELEVADO V=13.91 m3

DETALLE TANQUE ELEVADO

CISTERNA 31.81 M3

INSTALACIONES

CISTERNA

31.81 M3

UNIVERSIDAD DE LIM

FACULTAD DE INGENIERIA INSTALACIONES I

58


MA

A Y ARQUITECTURA

EV -5

L

E

Y

E

SIMBOLOGIA

N

D

A

DESCRIPCION BOMBA

VALVULA ESFERICA

VALVULA CHECK

VALVULA FLOTADOR Ø1/2"

Ø1"

Ø2 1/2"

Ø3/4"

Ø 1 1/4"

Ø 3"

DIAMETRO DE TUBERIAS TUBERIA DE AGUA FRIA TUBERIA DE AGUA CALIENTE REDUCCION

TH

CALENTADOR

MEDIDOR

GRIFO DE RIEGO

CRUCE DE TUBERIAS SIN CONEXIÓN

CODOS / TEES / UNION CRUZ

EDIFICIO MULTIFAMILIAR DETALLE CISTERNA Y TANQUE ELEVADO

D-01

59


EV6

LABORATORIO 2 RED DE DESAGÜE VIVIENDA UNIFAMILIAR

60


OBJETIVO Recopilar los datos en un informe sobre la clase de laboratorio virtual hecha en la Universidad de Lima acerca de la de desagüe, en el que se observaron materiales, herramientas, recomendaciones e instalaciones de los artefactos del modo adecuado.

REFLEXIONES Este segundo informe fue de gran ayuda, por lo que se pudo reconocer las herramientas y materiales adecuados para cada instalación a los distintos aparatos y su fácil recorrido para evitar daños o fugas proximas en los espacios.

61


EV6

LABORATORIO 2

TABLA DE CONTENIDO

62

1 OBJETIVOS GENERALES

1

2 MATERIALES

2

2.1.

YEE

2

2.2.

TEE

2

2.3.

SOMBRERO

2

2.4.

REDUCCIÓN

3

2.5.

DOBLE YEE

3

2.6.

TEE SANITARIA

3

2.7.

UNIONES

4

2.8.

CODOS DE 45°

4

2.9.

CODOS DE 90°

4

2.10.

CODO DE VENTILACIÓN

5

2.11.

TAPA DE REGISTRO

5

2.12.

REJILLAS PARA SUMIDEROS

5

2.13.

PEGAMENTOS

6

3 PROCESO CONSTRUCTIVO

7

3​.1.

CAJA DE REGISTRO

7

3​.1.

MONTANTE

9

4 INSTALACIONES

11

5 PRUEBAS ​

15

5.1

PRUEBA DE ESTANQUEIDAD

15

5​.2

PRUEBA DE PENDIENTE

16

6 RECOMENDACIONES Y CONCLUSIONES

17

6​.1

RECOMENDACIONES

17

6​.2

CONCLUSIONES

18


EV -6

63


LABORATORIO 2

64


EV -6

65


LABORATORIO 2 2.10 CODO DE VENTILACIÓN Conecta el inodoro a la tubería de ventilación.

2.11 TAPA DE REGISTRO Existen de 2” y de 4”. De bronce cromado.

2.12 REJILLA PARA SUMIDEROS Existen de 2” y de 4”. De bronce.

5

66


EV -6

67


LABORATORIO 2

68


EV -6

69


LABORATORIO 2

Según la Norma E070, dentro del muro portante de soga están prohibidos los tubos mayores a 55mm. Es decir, que como máximo deberían de colocarse tuberías de 2”. Las tuberías de 4” tienen el ancho del muro y al ser casi exacto puede dañar y debilitar la estructura lo que impide que el tubo pueda atravesarlo.

En una vivienda unifamiliar normalmente se tiene una distribución distinta en cada nivel. Por ello, muchas veces se atraviesa las montantes por medio de un muro. Según la norma, una tubería de 4” si se podría colocar en muros portantes de cabeza, ya que estos son de 23 cm de ancho, superando el ancho de la tubería. Pero se deben colocar cada 2 hileras mechas o chicote para asegurar el muro.

10

70


EV -6

71


LABORATORIO 2

72


EV -6

73


LABORATORIO 2

74


EV -6

75


LABORATORIO 2

76


EV -6

6.2

CONCLUSIONES ● Es de suma importancia tener conocimiento de los materiales y accesorios necesarios para el correcto funcionamiento de una red de desagüe. ● Se deben realizar todas las pruebas necesarias antes de terminar la instalación, para evitar picar el piso en caso de una fuga en la red. La prueba de la pendiente es sumamente importante, ya que confirmamos el correcto flujo en caso de objetos sólidos y evitamos la estanqueidad en la tubería con un futuro daño en la red de la vivienda. ● El diseño de la red sanitaria de desagüe debe realizarse teniendo en cuenta todos los aparatos sanitarios que se utilizarán en la obra para que las conexiones sean más precisas.

18

77


EV7

PRÁCTICA DE AULA RED DE DESAGÜE VIVIENDA UNIFAMILIAR

78


OBJETIVO Diseñar la red de desagüe en un vivienda unifamiliar, con sus debidos accesorios, lognitudes y diámetros para un fácil flujo y una ventilación adecuada.

REFLEXIONES En esta última practica, se comprobó los temas aprendidos con respecto al diseño de la red de desagüe, calculo de la caja de registro, pendiente de las tuberías y una correcta instalación de las mismas. Se corrigieron algunos elementos luego de la entrega del examen para observar con mejor claridad en esta segunda entrega.

79


EV7

PRÁCTICA DE AULA: RED DE DESAGÜE

Diseñar la red de desagüe en la vivienda unifamiliar teniendo en cuenta lo siguiente: 1.

Salidas de desagüe

(1/2P)

2.

Salidas de ventilación

(1/2P)

3.

Registro roscado

(1/2P)

4.

Sumideros

(1/2P)

5.

Montantes

(1/2P)

6.

Cajas de registro

(1P)

7.

Cota de tapa

sum.Ø2" Ø2" S=2%

LAVANDERIA V3 Sube ventilación Ø2"

sum.Ø2"

RRØ2"

L=3m

Ø2" S=2%

8.

Cota de fondo

(1P)

Pendiente

(1/2P)

10. Sentido del flujo

(1/2P)

11. Longitud

(1P)

12. Diámetros de tuberías

(1P)

13. Diseño de red

(12p)

V2 Sube ventilación Ø2"

Ø2" S=2%

Ø2" S=2%

(1/2P)

9.

JARDIN

TH

C.R. Nº1 0.25 x 0.50 m CT = + 0.20 CLL = +0.14 CF = -0.60

Ø2" S=2% RRØ2" sum.Ø2"

Ø2" S=2%

COCINA

TERRAZA

NPT + .20m

Ø4" S=1% L=10.2m

SALA

COMEDOR M2 Sube Montante Ø4"

Ø4" S=1%

14

16

15

12

13

11

9

10

L=10.2m

2

1

4

3

6

7

5

8

RECIBO

NPT + .20m

M1 Sube Montante Ø4"

RRØ4"

BAÑO 1

Ø4" S=1%

C.R. Nº2 0.25 x 0.50 m CT = +0.20 CLL = +0.10 CF = -0.60

ESTUDIO

Ø4" S=1% Ø2" S=2% V1 Sube ventilación Ø2"

JARDIN

GARAJE

Ø4" S=1% L=6.2m

C.R. Nº3 0.30 x 0.60 m CT = + 0.20 CLL = -0.59 CF = -0.80

PLANTA DE PRIMER PISO 80

ESC: 1/50


EV -7

LEYENDA Caja de registro Sumideros Trampa p TECHO

NPT + .2.95m

Registros

sum.Ø2"

sum.Ø4"

sum.Ø2" RRØ2"

RRØ4"

Accesorios Red de desagüe DORMITORIO 3

Flecha sentido del flujo Montante Tubería ventilación

WC

ESTAR TV

NPT + 3.00m

closet

M2 Sube Montante Ø4"

RRØ4" sum.Ø2"

sum.Ø4"

Ø4" S=1%

BAÑO 3

Ø2" S=2%

14

16

15

13

12

11

9

10

DORMITORIO 2 NPT + 3.00m

1

2

4

3

6

7

5

8

HALL

NPT + 3.00m M1 Sube Montante Ø4"

sum.Ø4"

BAÑO 2

RRØ4" sum.Ø2" Ø4" S=1% Ø2" S=2% V1 Sube ventilación Ø2"

DORMITORIO 1 NPT + 3.00m

TECHO N .T.T +

4.40ml

PLANTA DE SEGUNDO PISO 81


EV8

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

82


OBJETIVO Desarrollar la red de desagüe en el mismo edificio multifamiliar empleado, con todos sus accesorios y accesos de ventilación para caada departamento.

REFLEXIONES Para este último trabajo de diseño grupal, se tomaron en cuenta todas las pautas del trabajo anterior y se empleo una mayor homogeneidad en los niveles, ya que requeía una mayor conexión vertical debido a la ventilación de cada uno. Se llegó al resultado esperado. Además, se corrigieron detalles que fueron observados y criticados luego de la entrega, como asuntos de ploteo y mejor visibilidad.

83


EV8

PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

2 Ø2" S=2%

L= 8.75m

Ø2" S=2%

Ø2" S=2%

sum.Ø2"

C.R. Nº1 0.25 x 0.50 m CT = - 3.00 CLL = -3.18 CF = -0.60

sum.Ø2"

3

SM2 Sube Montante Ø4"

Ø4" S=1%

POZO NEGRO

% S=2 2" Ø

Ø4" S=1%

C.R. Nº6 0.45 x 0.60 m CT = - 3.00 CLL = -4.00 CF = -1.00

%

Ø4" S=1%

Ø4" S=1%

S=2

Ø2" S=2%

Ø2" S=2%

sum.Ø2"

2"

Ø2" S=2%

Ø

Ø2" S=2%

L= 14.96m

Ø4" S=1%

Ø4" S=1% L= 14.96m

Ø

2"

S=2

%

4

2"

Ø

2"

Ø

%

S=2

%

S=2

S=2

%

5 2"

sum.Ø2"

Ø

sum.Ø2"

sum.Ø2"

6

A

8 84

B

C

D


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1 Ø2 1/2"

Ø3"

CISTERNA 31.81 M3

B'

sum.Ø4" Ø2" S=2%

Ø2" S=2%

sum.Ø2"

C.T: -3.00 C.F: -3.25

CANALETA

REBOSE Ø4"

Ø2" S=2%

C.R. Nº2 0.25 x 0.50 m CT = - 3.00 CLL = -3.43 CF = -0.60 Ø2" S=2%

L= 8.50m Ø2" S=2%

2

Ø4" S=1%

L= 12.25m

Ø2" S=2%

Ø2" S=2%

C.R. Nº3 0.25 x 0.50 m CT =- 3.00 CLL = -3.60 CF = -0.60

sum.Ø2" sum.Ø2"

Ø4" S=1% L= 10.78m

Ø

2"

S=2

%

sum.Ø2"

3

L= 10.78m Ø4" S=1%

C.R. Nº5 0.45 x 0.60 m CT = - 3.00 CLL = -3.85 CF = -1.00

sum.Ø2"

S=2 2"

sum.Ø2"

Ø

S=2

%

%

2"

Ø

Ø4" S=1% L= 13.8m

Ø4" S=1%

Ø4" S=1%

L= 13.8m

C.R. Nº4 0.30 x 0.60 m CT =- 3.00 CLL = -3.71 CF = -0.80

4

2"

Ø

2"

Ø

%

S=2

%

S=2

5 sum.Ø2"

sum.Ø2"

sum.Ø2"

LEYENDA

Caja de registro 6

Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

RRØ2"

RRØ4"

Accesorios Red de desagüe Flecha sentido del flujo Montante

A'

E

F

Tubería ventilación

G

Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR SOTANO

NIVEL -3.00M

G-3

IS-01 85


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V6 Sube ventilación Ø2"

V5 Sube ventilación Ø2" Ø

S=2

Ø

%

Ø2" S=2%

2"

2" S=2

2"

%

Ø S=2 %

Ø2" S=2%

RRØ4"

Ø4" S=1%

Ø4" S=1%

%

2

RRØ4"

sum.Ø2"

4"

S=1

sum.Ø2"

Ø

4"

Ø

%

S=1

Ø

2"

RRØ2" Ø2" S=2%

%

% S=2

S=1 4"

S=2 %

Ø

2"

Ø4" S=1%

Ø

V7 Sube ventilación Ø2"

Ø4" S=1%

RRØ4"

SM3 Sube Montante Ø4"

Ø 4" S=1 %

Ø4" S=1%

Ø4" S=1%

sum.Ø2" Ø4" S=1%

Ø2" S=2%

Ø2" S=2%

L= 7.18m

RRØ2"

Ø4" S=1%

3

Ø2" S=2%

Ø

2"

S=2

%

V9 Sube ventilación Ø2"

C.R. Nº3 0.25 x 0.50 m CT = +- 0.00 CLL = -0.31 CF = -0.60

L= 3.50m Ø4" S=1%

%

SM2 Sube Montante Ø4"

L= 7.05m Ø4" S=1%

2%

S=1

Ø

Ø2" S=2%

4"

S=1

1%

S=

%

S=

4"

Ø

Ø4"

2"

Ø

C.R. Nº4 0.25 x 0.50 m CT = +- 0.00 CLL = -0.35 CF = -0.60

5.6

1m

L=

7.

02

m

Ø

4"

S=1

Ø4"

%

S=1

%

RRØ2"

L=

V2 Sube ventilación Ø2"

4"

Ø 1%

S=

SV10 Sube ventilación Ø2"

Ø

2"

4"

Ø

SM1 Sube Montante Ø4"

S=1

Ø4"

%

S=1

%

Ø2" S=2% RRØ2"

RRØ4" RRØ2"

Ø4" S=1%

Ø4" S=1%

2" Ø

1%

S=

L= 6.66m

4"

%

Ø4" S=1% Ø4" S=1%

Ø

S=2

Ø4"

Ø2" S=2%

Ø2" S=2% Ø2" S=2% V1 Sube ventilación Ø2"

Ø4"

Ø2" S=2%

Ø4" S=1%

2%

S=

4

Ø2" S=2% Ø2"

V3 Sube ventilación Ø2"

Ø4" RRØ4"

sum.Ø2"

V4 Sube ventilación Ø2"

C.R. Nº5 0.25 x 0.50 m CT = +- 0.00 CLL = -0.42 CF = -0.60

L= 10.86 m

Ø2" S=2%

Ø2" S=2% RRØ2"

L= 5.78 m

Ø4" S=1% SV11 Sube ventilación Ø2" Ø4" S=1%

RRØ2"

SM7 Sube Montante Ø4"

S=1 %

Ø2" S=2%

Ø 4"

5

C.R. Nº6 0.25 x 0.50 m CT = +- 0.00 CLL = -0.48 CF = -0.60

Ø4" S=1%

Ø4" S=1%

Ø4" S=1% Ø4" S=1%

L= 8.62 m

Ø4" S=1%

L= 8.62 m

Ø4" S=1%

6

C.R. Nº7 0.25 x 0.50 m CT = +- 0.00 CLL = -0.57 CF = -0.60

A

B

C

D

JR. SOLDADO CABADA

86


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1

B' V2 Sube ventilación Ø2"

2

2% " S=

Ø2

SM4 Sube Montante Ø4"

1%

Ø4"

S=

2%

" S=

Ø2

1%

RRØ2"

" S=

Ø4"

S=1

%

Ø4

1%

%

m

Ø4" S=1

L= 9.17

" S=

Ø4

1%

" S=

Ø4

m

L= 9.17

Ø4" S=1%

1%

" S=

Ø4

3 C.R. Nº2 0.25 x 0.50 m CT = +- 0.00 CLL = -0.24 CF = -0.60

1%

" S=

Ø4

L= 9.17m L= 14.83m L= 9.17

Ø4" S=1%

m Ø4" S=1%

SV13 Sube ventilación Ø2" L= 14.83m Ø4" S=1%

Ø4" S=1%

C.R. Nº1 0.25 x 0.50 m CT = +- 0.00 CLL = -0.09 CF = -0.60

4"

Ø %

S=1

%

S=1 S=1

RRØ4"

V19 Sube ventilación Ø2"

Ø4" S=1%

Ø2" S=2%

1%

4" S=1 Ø

4"

%

S=2

V5 Sube ventilación Ø2"

4"

Ø

S=

Ø

%

2"

Ø

RRØ2"

%

Ø

S=1

2%

S=

Ø4" S=1%

Ø2" S=2%

2"

Ø

Ø2" S=2%

1%

S=

Ø4" S=1%

4"

Ø

sum.Ø2"

sum.Ø2"

V12 Sube ventilación Ø2"

RRØ4"

RRØ4" 2" %

S=2

Ø2" S=2%

Ø

%

S=2

Ø2" S=2%

V20 Sube ventilación Ø2"

2"

Ø

SM6 Sube Montante Ø4"

4

Ø2" S=2%

Ø4" S=1%

V18 Sube ventilación Ø2"

RRØ4"

4"

%

Ø

4"

Ø2" S=2%

SM5 Sube Montante Ø4"

RRØ2"

V21 Sube ventilación Ø2"

5

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

RRØ2"

RRØ4"

Accesorios Red de desagüe

A'

Flecha sentido del flujo E

F

G

Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR PRIMER NIVEL +-0.00M

G-3

IS-02 87


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V5 Sube ventilación Ø2"

V6 Sube ventilación Ø2"

% S=2 Ø

Ø

Ø4" S=1%

Ø4"

S=

RRØ4"

Ø2" S=2% RRØ2"

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

sum.Ø2"

1%

2

V8 Sube ventilación Ø2"

2"

2"

S=2

%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

RRØ4"

Ø4" S=1% Ø4"

S=

1%

Ø2" S=2%

Ø2" S=2% RRØ2"

Ø4" S=1% Ø2" S=2%

V7 Sube ventilación Ø2"

Ø4" S=1%

sum.Ø2"

Ø4" S=1%

SM3 Sube Montante Ø4"

RRØ2"

3

V9 Sube ventilación Ø2"

SM2 Sube Montante Ø4"

V2 Sube ventilación Ø2"

Ø4" S=1%

Ø2" S=2%

Ø4" S=1%

Ø4" S=1%

2"

Ø

V3 Sube ventilación Ø2"

RRØ4"

Ø4" S=1%

sum.Ø2"

RRØ2"

Ø4" S=1%

2"

Ø

4"

Ø

Ø4" S=1%

2%

S=

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

%

S=2

V1 Sube ventilación Ø2"

SV10 Sube ventilación Ø2"

RRØ4"

V4 Sube ventilación Ø2"

%

S=1

Ø2" S=2%

S=1

2%

4"

S=

4

Ø

2"

SM1 Sube Montante Ø4"

%

Ø

Ø

2"

sum.Ø2"

Ø2" S=2%

SV11 Sube ventilación Ø2"

4"

Ø %

S=1

Ø2" S=2% Ø

2"

RRØ2"

S=2

%

Ø4" S=1%

SM7 Sube Montante Ø4"

5

6

A

88

B

C

D

S=

2%

Ø4" S=1% RRØ4"


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1

Ø2" S=2%

Ø

%

%

=2

=2

S 2"

S 2"

Ø RRØ4"

Ø2" S=2%

Ø2" S=2%

RRØ4"

1%

S=

Ø

4"

S=

sum.Ø4"

Ø4" S=1%

Ø4" S=1%

1%

RRØ2"

Ø4" S=1%

Ø2" S=2%

B'

V16 Sube ventilación Ø2"

V15 Sube ventilación Ø2"

V14 Sube ventilación Ø2"

2

Ø

4"

sum.Ø2"

sum.Ø2"

Ø4" S=1% Ø2" S=2%

RRØ2"

V17 Sube ventilación Ø2"

Ø4" S=1%

SM4 Sube Montante Ø4"

RRØ2"

3

SV13 Sube ventilación Ø2"

RRØ2" Ø2" S=2%

RRØ2"

V18 Sube ventilación Ø2"

4

Ø4" S=1%

SM5 Sube Montante Ø4"

sum.Ø2"

2"

Ø

4"

Ø

Ø2" S=2%

2%

S=

V19 Sube ventilación Ø2"

RRØ2"

Ø2" S=2%

Ø2" S=2%

%

S=1

sum.Ø2"

Ø2" S=2%

%

1% S= 4" Ø

4"

S=

2%

RRØ4"

2"

4" Ø

V20 Sube ventilación Ø2"

Ø

S=

1%

Ø

SM6 Sube Montante Ø4"

Ø2" S=2%

Ø4" S=1%

Ø2" S=2%

%

Ø2" S=2%

Ø2" S=2%

S=1

1%

2%

Ø4" S=1%

S=

RRØ4"

S=

2"

Ø

Ø4" S=1%

sum.Ø2" SV12 Sube ventilación Ø2"

4"

Ø

Ø4" S=1%

V21 Sube ventilación Ø2"

5

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

A'

RRØ2"

RRØ4"

Accesorios E

F

G

Red de desagüe Flecha sentido del flujo Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR SEGUNDO NIVEL +3.00M

G-3

IS-03 89


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V5 Sube ventilación Ø2"

V6 Sube ventilación Ø2"

S=

%

RRØ4"

Ø2" S=2% Ø2" S=2%

RRØ2"

Ø2" S=2%

Ø4" S=1%

sum.Ø2"

1%

2

S=2 Ø

Ø

Ø4" S=1%

Ø4"

V8 Sube ventilación Ø2"

2"

2"

S=2

%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

RRØ4"

Ø4" S=1% S=

1%

Ø2" S=2%

Ø4" S=1%

Ø4"

sum.Ø2"

Ø2" S=2% RRØ2"

Ø4" S=1% Ø2" S=2%

V7 Sube ventilación Ø2"

Ø4" S=1%

SM3 Sube Montante Ø4"

RRØ2"

3

V9 Sube ventilación Ø2"

SM2 Sube Montante Ø4"

Ø2" S=2%

V2 Sube ventilación Ø2"

RRØ2" Ø2" S=2% SM1 Sube Montante Ø4"

SV10 Sube ventilación Ø2"

Ø4" S=1%

4

RRØ2"

RRØ4"

Ø4" S=1% Ø2" S=2% Ø2" S=2% V1 Sube ventilación Ø2"

V3 Sube ventilación Ø2"

Ø4" S=1% RRØ4"

sum.Ø2"

V4 Sube ventilación Ø2"

Ø4" S=1%

V23 Sube ventilación Ø2"

SV11 Sube ventilación Ø2"

RRØ2" 2" Ø Ø 2"

Ø4" S=1%

2"

Ø %

S=2

Ø2" S=2% Ø4" S=1%

Ø2" S=2% V22 Sube ventilación Ø2"

S=2 %

% S=2

SM7 Sube Montante Ø4" RRØ2"

5

Ø2" S=2%

Ø4" S=1%

RRØ4"

V3 Sube ventilación Ø2" Ø2" S=2% Ø4" S=1% Ø4" S=1%

RRØ4"

sum.Ø2"

V25 Sube ventilación Ø2"

Ø4" S=1%

6

A

90

B

C

D


TODESK STUDENT VERSION

G

1

V15 Sube ventilación Ø2"

Ø2" S=2%

Ø S 2"

%

%

=2

=2

S 2" RRØ4"

Ø2" S=2%

Ø2" S=2%

RRØ4"

Ø

4"

S=

1%

sum.Ø4"

Ø4" S=1%

Ø4" S=1%

S=

sum.Ø2"

1%

RRØ2"

Ø4" S=1%

Ø2" S=2%

B'

V16 Sube ventilación Ø2"

Ø

V14 Sube ventilación Ø2"

Ø

4"

2

sum.Ø2"

Ø4" S=1% Ø2" S=2%

RRØ2"

V17 Sube ventilación Ø2"

Ø4" S=1%

SM4 Sube Montante Ø4"

RRØ2"

3

SV13 Sube ventilación Ø2"

RRØ2"

2"

Ø 2%

S= Ø4" S=1%

RRØ2" Ø2" S=2%

RRØ2"

V18 Sube ventilación Ø2"

2" 2%

S=

sum.Ø2"

Ø2" S=2%

2% S= 2" Ø

1% S= 4" Ø 1%

S= 4"

RRØ4"

Ø2" S=2%

Ø2" S=2%

Ø

1%

Ø2" S=2%

Ø2" S=2%

V20 Sube ventilación Ø2"

Ø4" S=1%

RRØ4"

S=

Ø4" S=1%

sum.Ø2"

SV12 Sube ventilación Ø2"

4"

2%

Ø2" S=2%

Ø

S=

V19 Sube ventilación Ø2"

RRØ2"

Ø2" S=2%

Ø2" S=2%

2"

Ø2" S=2%

4

Ø4" S=1%

SM5 Sube Montante Ø4"

Ø

RRØ4"

Ø4" S=1%

Ø

F

N

E

A

EV -8

V21 Sube ventilación Ø2"

5

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

A'

RRØ2"

RRØ4"

Accesorios E

F

G

Red de desagüe Flecha sentido del flujo Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR TERCER NIVEL +6.00M

G-3

IS-04 91


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V5 Sube ventilación Ø2"

V6 Sube ventilación Ø2"

S=

RRØ4"

Ø2" S=2% Ø2" S=2%

RRØ2"

Ø2" S=2%

Ø4" S=1%

sum.Ø2"

1%

2

S=2 % Ø

Ø

Ø4" S=1%

Ø4"

V8 Sube ventilación Ø2"

2"

2"

S=2

%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

RRØ4"

Ø4" S=1%

Ø4"

S=

1%

Ø2" S=2%

Ø4" S=1%

sum.Ø2"

Ø2" S=2% RRØ2"

Ø4" S=1% Ø2" S=2%

V7 Sube ventilación Ø2"

Ø4" S=1%

SM3 Sube Montante Ø4"

RRØ2"

3

V9 Sube ventilación Ø2"

SM2 Sube Montante Ø4"

V2 Sube ventilación Ø2"

Ø4" S=1%

Ø2" S=2% RRØ4"

Ø4" S=1%

sum.Ø2" RRØ2" 4"

2"

Ø

Ø

S=1

2%

S=

V4 Sube ventilación Ø2"

%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

%

S=2

V3 Sube ventilación Ø2"

Ø4" S=1% Ø4" S=1%

Ø2" S=2%

Ø4" S=1%

2"

Ø

V1 Sube ventilación Ø2"

SV10 Sube ventilación Ø2"

RRØ4" Ø4" S=1%

4

S=1

2%

4"

S=

Ø

2"

%

Ø

SM1 Sube Montante Ø4"

Ø

2"

sum.Ø2"

Ø2" S=2%

V23 Sube ventilación Ø2"

S=1

%

SV11 Sube ventilación Ø2"

Ø 4"

SM7 Sube Montante Ø4"

5

RRØ4" Ø4" S=1%

Ø 2"

Ø4" S=1%

S=2 %

Ø 4"

Ø2" S=2%

Ø4" S=1%

S=1 %

Ø2" S=2%

V25 Sube ventilación Ø2"

Ø

Ø4" S=1%

2"

Ø 4"

S=2

%

S=1 %

V22 Sube ventilación Ø2"

RRØ4"

6

A

92

B

C

D

S=

2%

Ø4" S=1% RRØ4"


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1

V15 Sube ventilación Ø2"

S 2"

Ø2" S=2%

Ø

%

%

=2

=2

S 2" RRØ4"

Ø2" S=2%

Ø2" S=2%

RRØ4"

Ø

4"

S=

1%

sum.Ø4"

Ø4" S=1%

Ø4" S=1%

S=

sum.Ø2"

1%

RRØ2"

Ø4" S=1%

Ø2" S=2%

B'

V16 Sube ventilación Ø2"

Ø

V14 Sube ventilación Ø2"

Ø

4"

2

sum.Ø2"

Ø4" S=1% Ø2" S=2%

RRØ2"

V17 Sube ventilación Ø2"

Ø4" S=1%

SM4 Sube Montante Ø4"

RRØ2"

3

SV13 Sube ventilación Ø2"

RRØ2" Ø2" S=2%

RRØ2"

V18 Sube ventilación Ø2"

2"

Ø

4"

Ø

Ø2" S=2%

2%

S=

Ø2" S=2%

%

S=1

sum.Ø2"

Ø2" S=2%

1% S= 4" Ø

4"

V20 Sube ventilación Ø2"

2"

S=

2%

RRØ4"

Ø

Ø

4"

S=

1%

Ø

Ø2" S=2%

SM6 Sube Montante Ø4"

Ø2" S=2%

Ø4" S=1%

Ø2" S=2%

Ø2" S=2%

S=1

1%

2%

Ø4" S=1%

S=

RRØ4"

S=

2"

Ø

Ø4" S=1%

sum.Ø2" SV12 Sube ventilación Ø2"

4"

Ø

Ø4" S=1%

%

V19 Sube ventilación Ø2"

RRØ2"

Ø2" S=2%

4

Ø4" S=1%

SM5 Sube Montante Ø4"

sum.Ø2"

V21 Sube ventilación Ø2"

5

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

A'

RRØ2"

RRØ4"

Accesorios E

F

G

Red de desagüe Flecha sentido del flujo Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR CUARTA NIVEL +9.00M

G-3

IS-05 93


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V5 Sube ventilación Ø2"

V6 Sube ventilación Ø2"

S=

RRØ4"

Ø2" S=2% Ø2" S=2%

RRØ2"

Ø2" S=2%

Ø4" S=1%

sum.Ø2"

1%

2

S=2 % Ø

Ø

Ø4" S=1%

Ø4"

V8 Sube ventilación Ø2"

2"

2"

S=2

%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

RRØ4"

Ø4" S=1%

S=

1%

Ø2" S=2%

Ø4" S=1%

Ø4"

sum.Ø2"

Ø2" S=2% RRØ2"

Ø4" S=1% Ø2" S=2%

V7 Sube ventilación Ø2"

Ø4" S=1%

SM3 Sube Montante Ø4"

RRØ2"

3

V9 Sube ventilación Ø2"

SM2 Sube Montante Ø4"

V2 Sube ventilación Ø2"

RRØ2" Ø2" S=2% SM1 Sube Montante Ø4"

SV10 Sube ventilación Ø2"

Ø4" S=1%

4

RRØ2"

RRØ4"

Ø4" S=1% Ø2" S=2% Ø2" S=2% V1 Sube ventilación Ø2"

V3 Sube ventilación Ø2"

R

Ø2" S=2%

Ø4" S=1% RRØ4"

sum.Ø2"

V4 Sube ventilación Ø2"

Ø4" S=1%

Ø4"

RRØ4"

V23 Sube ventilación Ø2"

SV11 Sube ventilación Ø2"

RRØ2"

2"

Ø 2"

S=2

SM7 Sube Montante Ø4"

Ø

RRØ2" Ø4" S=1%

2" Ø

5

%

%

S=2

Ø2" S=2%

% S=2 Ø2" S=2% Ø4" S=1%

Ø2" S=2% V22 Sube ventilación Ø2"

Ø4" S=1%

RRØ4"

V3 Sube ventilación Ø2" Ø2" S=2% Ø4" S=1% Ø4" S=1%

RRØ4"

sum.Ø2"

V25 Sube ventilación Ø2"

Ø

2"

S= 2%

Ø4" S=1%

Ø2" S=2%

6

A

94

B

C

D

RR


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1

V15 Sube ventilación Ø2"

S 2"

Ø2" S=2%

Ø

%

%

=2

=2

S 2" RRØ4"

Ø2" S=2%

Ø2" S=2%

RRØ4"

Ø

4"

S=

1%

sum.Ø4"

Ø4" S=1%

Ø4" S=1%

S=

sum.Ø2"

1%

RRØ2"

Ø4" S=1%

Ø2" S=2%

B'

V16 Sube ventilación Ø2"

Ø

V14 Sube ventilación Ø2"

Ø

4"

2

sum.Ø2"

Ø4" S=1% Ø2" S=2%

RRØ2"

V17 Sube ventilación Ø2"

Ø4" S=1%

SM4 Sube Montante Ø4"

RRØ2"

3

SV13 Sube ventilación Ø2"

RRØ2" Ø2" S=2%

RRØ2"

V18 Sube ventilación Ø2"

2" 2%

S=

RRØ4"

% 2"

V19 Sube ventilación Ø2"

RRØ2"

Ø2" S=2%

% =2

4

Ø4" S=1%

SM5 Sube Montante Ø4"

Ø

sum.Ø2"

Ø2" S=2%

S

sum.Ø2"

4"

Ø

Ø

2% S= 2" Ø

1% S= 4" Ø 1%

S= 4"

RRØ4"

Ø2" S=2%

Ø2" S=2%

Ø

1%

Ø4" S=1%

Ø2" S=2%

V20 Sube ventilación Ø2"

S=

Ø4" S=1%

SM6 Sube Montante Ø4"

Ø2" S=2%

Ø2" S=2%

Ø2" S=2%

Ø4" S=1%

RRØ4"

4"

1%

Ø

S=

Ø2" S=2% sum.Ø2" SV12 Sube ventilación Ø2"

" S=1%

V21 Sube ventilación Ø2"

5 Ø2" S=2%

RØ2"

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

A'

RRØ2"

RRØ4"

Accesorios E

F

G

Red de desagüe Flecha sentido del flujo Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR QUINTO

NIVEL +12.00

G-3

IS-06 95


PRODUCED BY AN AUT

RED DE DESAGÜE VIVIENDA MULTIFAMILIAR

A

B

C

D

1

B

V5 Sube ventilación Ø2"

V6 Sube ventilación Ø2"

V8 Sube ventilación Ø2"

2 V7 Sube ventilación Ø2"

Ø

4"

S=1

%

SM3 Sube Montante Ø4"

sum.Ø4"

CANALETA

REBOSE Ø4"

3

V9 Sube ventilación Ø2"

SM2 Sube Montante Ø4"

V2 Sube ventilación Ø2"

SM1 Sube Montante Ø4"

SV10 Sube ventilación Ø2"

4 V3 Sube ventilación Ø2" V1 Sube ventilación Ø2" V4 Sube ventilación Ø2"

V23 Sube ventilación Ø2"

SV11 Sube ventilación Ø2"

SM7 Sube Montante Ø4"

5 V24 V3 Sube ventilación Ø2" V22 Sube ventilación Ø2" V25 Sube ventilación Ø2"

6

A

96

B

C

D


TODESK STUDENT VERSION

F

N

E

A

EV -8

G

1

V15 Sube ventilación Ø2"

B'

V16 Sube ventilación Ø2"

V14 Sube ventilación Ø2"

2 V17 Sube ventilación Ø2"

SM4 Sube Montante Ø4"

3

SV13 Sube ventilación Ø2"

V18 Sube ventilación Ø2"

4

SM5 Sube Montante Ø4" V19 Sube ventilación Ø2"

SV12 Sube ventilación Ø2"

SM6 Sube Montante Ø4"

V20 Sube ventilación Ø2"

V21 Sube ventilación Ø2"

5

LEYENDA 6

Caja de registro Sumideros sum.Ø2"

sum.Ø4"

Trampa p sum.Ø2"

Registros

A'

RRØ2"

RRØ4"

Accesorios E

F

G

Red de desagüe Flecha sentido del flujo Montante Tubería ventilación Reducción de 4" a 2" 0

1

2

3

4

5

UNIVERSIDAD DE LIMA FACULTAD DE INGENIERIA Y ARQUITECTURA INSTALACIONES I

EDIFICIO MULTIFAMILIAR AZOTEA NIVEL +15.00M

G-3

IS-07 97


CV

CAMILA HEREDIA SOTO

EDUCACIÓN 2006-2012 Primaria Colegio FAP J. Quiñones 2013-2017 Secundaria Colegio FAP J. Quiñones 2018-Actual Pre-grado Universidad de Lima

IDIOMA Castellano

(Natal)

Inglés Alemán

PROGRAMA Autocad Revit Estudiante de la carrera de Arquitectura, soy una persona con la capacidad para trabajar en equipo, perseverante y tolerante para lograr buenos resultados en diversas situaciones. Me reconozco por ser creativa, responsable y comprometida. Resalto por tener un alto nivel de cooperación y precaución para lograr mis objetivos propuestos. Me fascina el arte como la danza, el cine y la fotografía. He tenido la oportunidad de conocer otro continente y apreciar culturas y edificaciones diferentes y poder aprender nuevos métodos y formas de observar al mundo.

Photoshop Illustrator Sketchup MS Office TwinMotion

INTERESES Danza - Fotografía - Viaje - Arte

RECONOCIMIENTOS Proyecto de Arquitectura I

CONTACTO 73706893

2018-1 Dibujo Final seleccionado para exposición Proyecto de Arquitectura IV 2020-1 Proyecto Final seleccionado para exposición

camiheredia1705@gmail.com +51 986 664 800 camiheredia123 camiheredia1705

98

LABORAL 2019-2020 Retail Part-time Quicksilver Jockey Plaza


INFORMACIÓN DEL CURSO

IC

NOMBRE DEL CURSO:

INSTALACIONES I SECCIÓN:

521 DOCENTE:

Jose Luis Reyes Ñique SUMILLA: Instalaciones 1 es una asignatura de carácter teórico práctico obligatoria destinada a desarrollar la capacidad de definir, desarrollar, representar, coordinar, y supervisar los sistemas de instalaciones sanitarias y gas de un proyecto de edificación según la normativa vigente, así como desarrollar la capacidad de trabajo en equipo con compromiso ético y de calidad.

OBJETIVO GENERAL: Desarrollar la capacidad de definir, desarrollar, representar, coordinar y supervisar las instalaciones sanitarias y de gas de un proyecto de edificación, tomando en cuenta los estándares de calidad para ejercer el rol de coordinador principal de proyectos, así como conocer las consideraciones necesarias para su correcta aplicación y compatibilización durante el proceso de diseño arquitectónico, optimizando el funcionamiento y seguridad de la edificación y de los usuarios.

OBJETIVOS ESPECÍFICOS: 1. Comprender el proceso de diseño, construcción, operación y mantenimiento de las instalaciones sanitarias y de gas para proyectos de edificación, desarrollando el pensamiento crítico para enmarcarse dentro de los requerimientos arquitectónicos y regulatorios aplicables, y de sostenibilidad a través del desarrollo de un trabajo escalonado y progresivo que va integrando los diseños de los componentes básicos de las instalaciones sanitarias para una edificación multifamiliar. 2. Desarrollar un enfoque crítico y creativo para el procesamiento de la información mínima necesaria para el diseño, construcción, operación y mantenimiento de las instalaciones sanitarias y de gas para proyectos de edificación, reconociendo los requerimientos básicos para su integración y compatibilización con el diseño arquitectónico, estructural, eléctrico y demás instalaciones complementarias a través de la revisión de estudios de casos aplicativos. 3. Desarrollar las habilidades para desarrollarse y la capacidad de trabajar en equipo, planificando gestionando adecuadamente la participación de sus integrantes, demostrando capacidad de autocrítica y compromiso ético.

99


Cuenta de perfil issuu: https://issuu.com/camiheredia1705


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.