The Examiners’ Answers for CIMA Masters Gateway Assessment SECTION A Answer to Question One Requirement (a) Direct labour cost: Introduction stage The learning curve applies throughout this stage, therefore: Y = ax
b
Y = $100,000 x 10
-0.4150
= $38,459
Therefore total direct labour cost = 10 x $38,459 = $384,590 Growth stage The learning curve continues for another 20 batches so the direct labour cost of these 20 batches is: Y = ax
b
Y = $100,000 x 30
-0.4150
= $24,378
Total direct labour cost for first 30 batches = 30 x $24,378 = $731,340 Less: Total direct labour cost for first 10 batches = 10 x $38,459 = $384,590 Therefore total direct labour cost for these 20 batches = $346,750 The direct labour cost of each of the other 10 batches in this stage is the same as that of the thirtieth batch: