The Examiners’ Answers CIMA Masters Gateway Assessment SECTION A Answer to Question One Requirement (a) The average time per unit for 200 units is: Y = ax

b

Y = 20 x 200

-0.4150

Y = 2.219 hours Total time for 200 units = 200 x 2.219 hours = 443.8 hours The average time per unit for 199 units is: Y = ax

b

Y = 20 x 199

-0.4150

Y = 2.223 hours Total time for 199 units = 199 x 2.223 hours = 442.4 hours th

Time for 200 unit = 1.4 hours Total time for 500 units = (300 x 1.4 hours) + 443.8 hours = 863.8 hours

Requirement (b) $ Sales revenue (500 x $85) Direct materials (500 x $34) Variable overhead (500 x $18) Direct labour (863.8 hours x $12)

17,000 9,000 10,366

CONTRIBUTION November 2011

$ 42,500

36,366 6,134

1

Examiner's Answers CMGA