P1 – performance operations - the examiner’s answers - September 2010

Page 1

Operational Level Paper

P1 –Performance Operations Examiner’s Answers SECTION A Answer to Question One 1.1

The correct answer is A.

1.2

(102 + 67 - 54) = 115 days The correct answer is B.

1.3

$19,615/$219,615 = 8.9% The correct answer is D.

1.4

If the maximin rule is applied, the highest of the worst profit for each of the three projects is $450,000 i.e. project C. The correct answer is C.